Paper | Title | Other Keywords | Page | |||||
---|---|---|---|---|---|---|---|---|
MOXKI03 | Status of the SNS - Machine and Science | target, beam-losses, injection, beam-transport | 7 | |||||
|
Funding: ORNL/SNS is managed by UT-Battelle, LLC, for the U. S. Department of Energy under contract DE-AC05-00OR22725. |
The Spallation Neutron Source (SNS) will be the world's leading pulsed neutron source, with design beam power capability of 1.4 MW. The SNS Construction Project was completed in June 2006. The accelerator complex was successfully commissioned during the construction phase of the project in seven discrete commissioning runs. The facility is now in the first of a three year performance ramp-up phase, in which the beam power, reliability and operating time will be increased to the baseline design values of 1.4 MW, 90% and 5000 hours respectively. Meanwhile, neutron scattering instruments are being constructed and commissioned in preparation for full user operations in 2009. The progress toward bringing the SNS to its full capabilities will be presented. |
|
Slides
|
|
|
||
MOYKI03 | Energy Recovery Linacs | electron, emittance, gun, beam-losses | 22 | |||||
|
Energy recovey linacs have made great strides in the past decade and are now poised to revolutionize light sources, lepton-hadron colliders, electron coolers, high-power FELs, Compton sources and THz radiators. The status and direction of ERLS will be discussed.
|
|
|
Slides
|
|
|
||
MOZBKI02 | The BEPC II: Status and Early Commissioning | injection, luminosity, electron, quadrupole | 53 | |||||
|
BEPCII is the upgrade project of Beijing Electron Positron Collider (BEPC). The installation of its storage ring components except the superconducting (SC) insertion magnets was completed in early November, 2006. While the improvement of the cryogenic system for SC magnets is in progress, the commissioning of the synchrotron radiation (SR) mode for the so called back-up scheme with conventional magnets adopted in the interaction region (IR), started on Nov. 13, 2006. The first electron beam was stored on Nov. 18 and later beam was provided to SR users for about 1 month starting from Dec. 25, 2006. The commissioning of the collision mode including the electron and positrion rings started in Feb. 2007. The first beam collision was realized on Mar. 25. Then optimization of the beam parameters was done. On May 14, a 100mA to 100mA beam collision was achieved with 20 bunches for each beam. The luminosity estimated from the measured beam-beam parameters has reached that of BEPC. From May 25 the machine turns to the second run of the SR mode. This paper provides an overview of the construction and introduce the commissioning results of the backup scheme of BEPCII.
|
|
|
Slides
|
|
|
||
MOZBKI03 | The JLab 12 GeV Energy Upgrade of CEBAF for QCD and Hadronic Physics | controls, beam-transport, electron, emittance | 58 | |||||
|
Funding: Authored by Jefferson Science Associates, LLC under U. S. DOE Contract No. DE-AC05-06OR23177 |
CEBAF is a 5-pass, recirculating cw electron linac operating at ~6 GeV. The 12-GeV Upgrade is a $300M project anticipated to receive Critical Decision 2 approval in late summer of 2007 and begin construction activities in 2008; funding for the project is provided by the DOE Office of Nuclear Physics which will double the beam energy. The new energy reach will permit significant extensions in research into non-perturbative aspects of QCD. Areas of interest are Generalized Parton Distributions (GPDs), measurements at high-xBjorken, and the use of hybrid mesons to explore the nature of quark confinement. The upgrade includes: doubling the accelerating voltages of the linacs by adding 10 new high-performance cryomodules plus the requisite expansion of the 2K cryogenics plant and rf power systems, upgrading the beam transport system from 6 GeV to 12 GeV capability through extensive re-use of existing hardware, adding one recirculation arc, adding a new experimental area and the beamline to it, building new experimental equipment for the GPD, high-xBjorken, and hybrid mesons programs. The presentation will touch on the science and give some details of the accelerator plans. |
|
Slides
|
|
|
||
MOZAAB02 | MAX-IV Design: Pushing the Envelope | dipole, emittance, injection, lattice | 74 | |||||
|
The proposed MAX IV facility is meant as a successor to the existing MAX-lab. The acceleraor part will consist of three storage rings, two new ones operated at 3 and 1.5 GeV respectively and the existing MAX III ring. The two new rings have identical lattices and are placed on top of each other. Both these rings have a very small emittances, 0.86 and 0.4 nm rad respectively, and offer sychrotron radiation of very high mean brilliance. As an injector, a 3 GeV linear accelerator is planned. The design philosophy and the special technical solutions called for are presented in this paper.
|
|
|
Slides
|
|
|
||
MOOBAB02 | Progress Toward an ERL Extension to CESR | emittance, ion, optics, electron | 107 | |||||
|
Funding: Supported by Cornell University and NSF grant PHY 0131508 |
The status of plans for an Energy-Recovery Linac (ERL) X-ray facility at Cornell University is described. Currently, Cornell operates the Cornell High Energy Synchrotron Source (CHESS) at the CESR ring and the ERL is planned to be an extension to the CESR ring with the addition of a 5-GeV superconducting c.w. linac. Topics covered in this paper include the full layout on the Cornell campus, the different operation modes of the accelerator, methods to limit emittance growth, control of beam-ion effects and ways to limit transverse instabilities. As an upgrade of the CESR ring, special attention is given to reuse of many of the existing components. The very small electron-beam emittances would produce an x-ray source that is highly superior than any existing storage-ring light source. The ERL includes 18 X-ray beamlines optimized for specific areas of research that are currently being defined by an international group of scientists. This planned upgrade illustrates how other existing storage rings could be upgraded to work as ERL light sources with vastly improved beam qualities and with limited dark time for x-ray users. |
|
Slides
|
|
|
||
MOZAC03 | The LANSCE Accelerator: A Powerful Tool for Science and Applications | proton, isotope-production, scattering, storage-ring | 120 | |||||
|
The Los Alamos Neutron Science Center (LANSCE) accelerator was built over 30 years ago. It consists of a 800-MeV proton linac, a proton storage ring, and facilities for isotope production, proton radiography, ultra-cold neutrons, weapons neutron research and for various sciences such as materials, biological and nanotechnology using neutron scattering. For national security, it plays a vital role in stockpile stewardship by providing important data on dynamic events during weapons detonation using proton radiography. The aging components of LANSCE will be refurbished and modernized in the next few years and the LANSCE will continue serving as a prominent facility for both science and national security in the years ahead. After SNS comes on line, it will play a complementary role and will also serve as a staging facility for some experiments to be carried out at SNS. Interesting science being conducted at LANSCE and the plans for the refurbishment and future enhancement of the facility will be presented.
|
|
|
Slides
|
|
|
||
MOZBC03 | Applications for Energy Recovering Free Electron Lasers | laser, electron, free-electron-laser, controls | 132 | |||||
|
The availability of high-power, high-brilliance sources of tunable photons from energy-recovered Free Electron Lasers is opening up whole new fields of application of accelerators in industry. This talk will review some of the ideas that are already being put into production, and some of the newer ideas that are still under development.
|
|
|
Slides
|
|
|
||
MOOBC01 | Electron Accelerator Options for Photo-Detection of Fissile Materials | photon, electron, target, laser | 137 | |||||
|
Funding: Work supported by DNDO of US Government |
For national security, it is important to detect the presence of Special Nuclear Materials (SNM), especially Highly-Enriched Uranium (HEU). Generally used methods for such detection include interrogation by photons and neutrons. For example, photofission in HEU can be initiated with 14-MeV photons. The resulting delayed neutrons and photons from the fission fragments are clear signatures of the presence of HEU. One can generate high-energy photons using electron accelerators via various mechanisms. In this paper, we will describe two of them, namely electron bremsstrahlung and Compton-backscattered photons. We focus on these two mechanisms because they cover a wide range of accelerator requirements. Electron bremsstrahlung can be generated using a compact low-energy electron linac while the generation of Compton-backscattered photons requires a high-energy electron accelerator of a few hundred MeV. We review these two options, describe their accelerator requirements, and compare their relative merits. |
|
Slides
|
|
|
||
MOPAN005 | Injector Improvements at the Brazilian Synchrotron Light Source | injection, synchrotron, storage-ring, booster | 152 | |||||
|
We present the results of hardware, software and operational improvements implemented at the injector complex of the 1.37 GeV electron storage ring of the Brazilian Synchrotron Light Source (LNLS) with the aim of improving injector stability and reliability, thus reducing the injection time. The improvements include changes to the 120 MeV injector LINAC RF system and high power modulators, injection automation and the implementation of a new procedure for reusing the current at the end of each user's shifts before injection by ramping the energy back down to 500 MeV (the injection energy) without dumping the beam. All of these changes allowed us to significantly reduce the overall time from the end of a shift to the delivery of beam in the following shift with a positive impact on the reduction of injection thermal transients for the storage ring and beamlines. Further improvements are expected in the near future as a result of planned changes to the injection timing system and of the installation of a recently assembled upgrade of the 500 MeV booster synchrotron RF system
|
|
|
|||||
MOPAN007 | A Non-intercepting Beam Current Monitor for the ISAC-II SC-linac | ion, pick-up, vacuum, impedance | 155 | |||||
|
A personnel protection system will monitor the ion beam current into the experimental hall from the ISAC-II SC-linac. It will use continuous self-test and redundancy and have an accuracy of ±10% from 1 to 200enA. The system, based on an Atlas design, will use capacitive pickups with rf resonators and buffer amplifiers. Ion charge, velocity and bunch width will affect the sensitivity so periodic calibration with dc Faraday cups will be needed. The signal from each 13cm long, 5cm diameter pickup tube will pass through a vacuum feedthrough to a helical resonator. An AD8075 IC with an input impedance of 87kΩ at 35MHz will allow a high coil tap. The ISAC beam, bunched at 11.8MHz, is injected into the ISAC-II SC-linac via a 25m long transfer line. Monitors will be placed in the transfer line and downstream of the linac before the experimental hall. A 35MHz and a 70MHz coil (3 and 6 harmonic) have loaded Q's of 600. A test in the transfer line of the 35MHz coil gave a sensitivity 0.09mV/enA from the unity gain buffer using 20Ne+5 ions at 1.5MeV/u. The background was equivalent to 1enA. The 70MHz coil gave 0.04mV/enA using 22Ne+4 ions. System design and test data will be presented.
|
|
|
|||||
MOPAN008 | A Single Bunch Selector for the Next Low β Continuous Wave Heavy Ion Beam | heavy-ion, ion, simulation, insertion | 158 | |||||
|
Funding: Eurisol Project supported by the European Commission under contract N? 515768 RIDS |
The Eurisol heavy ion post-accelerator and the Spiral2 deuton/ion MEBT should transport a continuous wave (cw) beam from respectively a 88.05 MHz RFQ (β respectively 0.036 and 0.04) to a drift-tube linac. A high frequency chopper is being studied to select only 1 bunch over N, 10 < N < 10000 as asked by the physicists. It requires pulses higher than 3 kV, rising in less than 7 ns at a repetition rate up to 8.8 MHz. These figures are at the border of what can be provided by the travelling wave fast choppers and the capacitive-type chopping technologies. We have reviewed the current fast and slow chopping structures and their associated pulse generator. Some preliminary RF simulations to adapt the present chopping devices to our requirements are presented. The main limitations of these technologies when applied to isolate bunches in ion cw accelerators are also shown. Our first studies and results to solve the arising problems are discussed. |
|
|||||
MOPAN015 | Compact Waveguide Distribution with Asymmetric Shunt Tees for the European XFEL | klystron, coupling, controls, simulation | 176 | |||||
|
In the European X-ray FEL 32 superconducting cavities (4 cryomodules with 8 cavities per module) are connected to one 10 MW multibeam klystron through a waveguide distribution system. The XFEL tunnel has limited space for the waveguide system and therefore a new more compact waveguide distribution has been developed. The waveguide distribution is based on a binary cell which consists of two circulators connected to a shunt tee with integrated phase shifters. Four binary cells are combined by three asymmetric pretunable shunt tees. The asymmetric shunt tees allow to change the RF power for each pair of cavities and to reach the maximum cryomodule gradient. In this paper we will present the status of the waveguide distribution system and report on the development of the different new waveguide components.
|
|
|
|||||
MOPAN019 | Performance of the New Master Oscillator and Phase Reference System at FLASH | controls, monitoring, free-electron-laser, klystron | 188 | |||||
|
The master oscillator and phase reference system at FLASH must provide several rf reference frequencies to widely spread locations with low phase noise and small long term phase drifts. The phase noise requirements of the 1300 MHz reference is of the order of 0.1 deg. while short and medium term phase stability is of of the order of 0.1 deg. and 1 deg. respectively. The frequency distribution system employs a temperature stabilized coaxial line for rf power distribution and a fiber optic system for the monitoring of phase drifts. Presented are the the concept, design and performance measured in the accelerator environment.
|
|
|
|||||
MOPAN031 | Design Study of a Very Large Aperture Eddy Current Septum for J-PARC | septum, injection, beam-transport, extraction | 224 | |||||
|
An eddy current septum is selected as a backup of injection septum. Due to the high beam intensity and low beam energy, the injection beam size is very large. To accommodate the large size beam, large aperture septum is required. Large end field and large eddy current loss result in degradation of gap field. The paper discusses the eddy current loss effects on field distribution and introduces some correction methods.
|
|
|
|||||
MOPAN037 | Acceleration of Cold Emission Beam from Carbon Nanotube Cathode in KEKB/PF Linac | gun, cathode, emittance, acceleration | 236 | |||||
|
An electron gun with carbon nanotube cathode has been installed in the KEKB/PF linac, and the beam acceleration tests up to 2.5GeV have been performed successfully. The results and performance are presented in details.
|
|
|
|||||
MOPAN038 | Electric Power Compensation of the Large Scale Accelerator using SMES | power-supply, synchrotron, proton, quadrupole | 239 | |||||
|
Power supply for the large scale accelerator magnets draws a large amount of power from the utility network. For example, the peak active power and the dissipation power of J-PARC 50GeV synchrotron magnet power are estimated to be about 135MW and 37MW, respectively. Super Conducting Magnetic Energy Storage (SMES) is one of candidates to compensate these large load and line voltage fluctuation. Study on circuit configuration of the power supply with SMES has been continued. Present status of the R & D for the SMES system and small case experiment result will be discussed.
|
|
|
|||||
MOPAN039 | Development of Hybrid Type Carbon Stripper Foils with High Durability at >1800K for RCS of J-PARC | injection, proton, ion, laser | 242 | |||||
|
The Japan Proton Accelerator Research Complex (J-PARC) requires thick carbon stripper foils (250-500 ug/cm2) to strip electrons from the H- beam supplied by the linac before injection into the RCS of J-PARC. For this high-intensity H- beam and circulating bunch beam, which gives much damage to conventional carbon stripper foils. Thus carbon stripper foils with high durability at 1800K produced by energy deposition in the foil are indispensable for this accelerator. Recently, we have successfully developed hybrid type thick boron mixed carbon stripper foils (HBC-foil). Namely, the lifetime measurement of the foils was tested by using a 3.2 MeV, Ne+ DC beams of 2.5 uA, in which a significant amount of energy was deposited in the foils. The maximum lifetime was found to be extremely long, 30-and 250-times longer than those of Diamond and commercially available best carbon foils, respectively. The foils were also found to be free from any shrinkage, and to show an extremely low thickness reduction rate even at a high temperature of 1800K during long beam irradiation. In this conference the foil preparation procedures and lifetime measurements with a 3.2 MeV, Ne+ is presented.
|
|
|
|||||
MOPAN040 | Comparative Study on Lifetime of Stripper Foil using 650keV H- Ion Beam | target, ion, ion-source, synchrotron | 245 | |||||
|
Funding: This work is supported by the Japan Society for the Promotion of Science, under contract No. 18540303. |
Thick carbon stripper foils of >300 μg/cm2 will be used as a stripping of H-ion beam for 3GeV Rapid Cycling Synchrotron (3GeV-RCS) of the J-PARC. The carbon foils with long lifetime even at >1800 K are required. For this purpose, we have developed a new irradiation system for the lifetime measurement using high current pulsed and dc H- beams of the KEK Cockcroft-Walton accelerator. These high power 650keV H- Ion beams can simulate the high energy deposition in carbon stripper foils at the J-PARC RCS. An automatic data acquisition system is also developed for recording the data of foil temperature and irradiated beam current. The Hybrid Boron mixed Carbon (HBC) stripper foils, which are developed at KEK are irradiated by high current H- ion beam up to 2000 K. A few SNS-diamond and commercially available carbon (CM) foils are also tested for comparing with HBC-foils. The results of the lifetime measurement of HBC and SNS-diamond including CM stripper foils are reported. |
|
|||||
MOPAN044 | Development of Commissioning Software System for J-PARC LINAC | controls, quadrupole, lattice, alignment | 257 | |||||
|
Beam commissioning of J-PARC LINAC has been performed since November 2006. A commissioning software framework and a database system have been developed for the commissioning. We first discuss the LINAC control system, and then our commissioning software framework. Then, we discuss our strategy of comparing online/offline data and models in our system with monitors, magnets, and the RF system. Commissioning tools developed during the commissioning will be presented in detail.
|
|
|
|||||
MOPAN059 | PEFP Monitoring System Through an Analog Input to Ethernet Converter | power-supply, controls, monitoring, proton | 287 | |||||
|
Funding: This work was supported by the 21C Frontier R&D program sponsored by Ministry of Science and Technology, Korean Government. |
Proton Engineering Frontier Project (PEFP) has above 40 magnet power supplies for the 20MeV proton linac. Because some power supplies have analog interfaces, we chose ATEC (Analog Input To Ethernet Converter) to monitor their output currents and voltage by supporting the protocol conversion function. Software components of the Experimental Physics and Industrial Control System (EPICS) have been ported to a VME single board computer based on a PowerPC microprocessor (MPC7410). This paper presents the software component and processing of analog input values between EPICS on the PowerPC based board and ATEC operating as Server Mode. |
|
|||||
MOPAN061 | Compact Output Filter for Switching Frequency Elimination at the PLC Linac New Magnet Power Supply | power-supply, controls, damping, feedback | 293 | |||||
|
Funding: This work is supported by the Ministry of Science and Technology, Korea. |
At 2006, PLS Linac magnet power supply (MPS) has been upgraded for the stable beam injection and 4th generation light source research. New MPS are developed new compact MPS of 16-bit resolution and 20ppm stability using four-quadrant switching scheme with 50kHz MOSFET switching device, and consists of main power board, control power board, regulator board and CPU board. Size of each board is only 100mm width and 240mm depth. Output of MPS is 10V, ±10A for the bipolar and 50V, 50A for the unipolar magnet. Main board is consisted four-quadrant FET switch, driver and output filter. Output filter must be perfectly eliminating switch frequency and compact size. In this paper, we report on development and characteristics of compact output filter of the new MPS for PAL linac. |
|
|||||
MOPAN066 | First Tests of a Precision Beam Phase Measurement System in CTF3 | pick-up, luminosity, extraction, collider | 302 | |||||
|
Funding: This work is supported by the Commission of the European Communities under the 6th Framework Programme -Structuring the European Research Area-, contract number RIDS-011899. |
High precision beam phase measurements will be vital for synchronization of main and drive beams in CLIC. Development work is underway with the aim to demonstrate 0.1 degree resolution for a wideband 30GHz measurement. In order to be able to test this with a beam exhibiting much higher phase jitter, two prototypes have been built so that the difference in their outputs can be measured. Results of measurements made with bunch trains in CTF3 are presented. |
|
|||||
MOPAN090 | Logging of Operation Data at TLS | injection, booster, feedback, kicker | 371 | |||||
|
The Taiwan Light Source had been Top-Up operation in October 2005 and the beam current had increased to 300mA in early 2006. For normal operation, there are some important parameters of Top-up operation, such as beam stability, filling pattern and injection efficiency etc. These data have to be recorded and to be reference for the accelerator operating. Therefore, a LabVIEW-based data logging system had been developed. The system handles communication with other instruments via Ethernet and IEEE-488 interconnections. In this report, the design concept and the current status are described. The planned improvements are carried out in the future.
|
|
|
|||||
MOPAN103 | New Control System for the 50 MeV Linear Accelerator of TLS | controls, gun, booster, vacuum | 404 | |||||
|
The preinjector of the Taiwan Light Source(TLS) is consist of a 140 kV themionic gun and a 50 MeV traveling wave type linear accelerator system. In order to improve performance, to decouple the vacuum interlock logic from the linac control system, and to provide a better control functionality for top-up operation and to avoid obsolescence, linac control system have been renew. One VME crate system is dedicated for linac control, new hardware equips with high resolution of analog interface to provide better control. Vacuum interlock logic will be done be a dedicated programmable logic controller(PLC). The remained linac devices have sequential control needed will be done by another PLC, such as door access interlock, klystron warm up, gun warm up, trig interlock, gun high voltage interlock, klystron modulator high voltage interlock, water flow interlock. Both interlock and sequence control PLC will control by the VME crate. All the other functions without interlock or sequence requirement will control by the VME crate directly. New control system expects to provide better control functionality, better performance, easy for maintenance, and useful easy to add new hardware equipments.
|
|
|
|||||
MOPAN115 | Aluminum Coating in the Undulator Vacuum Chamber for the LINAC Coherence Light Source | cathode, vacuum, undulator, power-supply | 437 | |||||
|
Funding: Work supported by DOE under contract Nos. DE-AC02-06CH11357 and DE-AC03-76SF00515. |
A prototype vacuum chamber is under development at the Advanced Photon Source for use in the Linac Coherent Light Source at Stanford Linear Accelerator Center. The chamber will be fabricated from the austenite stainless steels. The chamber requires a continuous aluminum coating on the inner surface in order to reduce the wakefield losses to a level within the resistivity budget. The method being presented here is unique in that it can be applied to a fully fabricated chamber 5 mm high, 11.5 mm wide, and 3460 mm long. In existing methods the chamber aperture has been much larger than is used here. This paper describes a method applicable for these smaller cross sections. This process uses a pair of small electrodes, centered in the aperture, where they are attached to a high frequency AC power supply. In this configuration each electrode is connected to the opposite polarity of the other. The chamber cavity is filled with argon gas to facilitate the formation of a glow discharge causing the aluminum electrodes to sputter onto the chamber walls. This paper presents the laboratory test results from small samples up to the full-sized assemblies. |
|
|||||
MOPAS019 | Focusing Solenoid for the Front End of a Linear RF Accelerator | focusing, dipole, quadrupole, proton | 473 | |||||
|
Following a design study, a prototype of a focusing solenoid for use in a superconducting RF linac has been built and is being tested at FNAL. The solenoid cold mass is comprised of the main coil, two bucking coils, and a soft steel flux return. It is mounted inside a dedicated cryostat with a 20 mm diameter warm bore. At the maximum current of 250 A, the magnetic field reaches 7.2 T in the center of the solenoid and is less than 0.01 T at a distance of 200 mm from the center. The flange-to-flange length of the system is 270 mm. This report discusses the main design features of the solenoid and first test results.
|
|
|
|||||
MOPAS022 | Controls, LLRF, and Instrumentation Systems for ILC Test Facilities at Fermilab | controls, instrumentation, single-bunch, klystron | 479 | |||||
|
Funding: Work supported by the U. S. Department of Energy under contract No. DE-AC02-76CH03000. |
The major controls and instrumentation systems for the ILC test areas and the NML test accelerator at Fermilab are discussed. The test areas include 3 separate areas for Vertical Superconducting RF Cavity Testing, Horizontal Cavity Testing, and NML RF and beam test area. A common control infrastructure for the test areas including a controls framework, electronic logbook and cavity database will be provided, while supporting components supplied by collaborators with diverse areas of expertise (EPICS, DOOCS, LabVIEW, and Matlab). The discussions on the instrumentation systems are focused on overview and requirements. |
|
|||||
MOPAS048 | Quantitative Evaluation of Magnet Hysteresis Effects at LANSCE with Respect to Magnet Power Supply Specifications | power-supply, controls, feedback, quadrupole | 542 | |||||
|
Funding: Work supported by US Department of Energy. |
The proton beam in the LANSCE accelerator is guided and focused almost exclusively by electromagnets. Magnet hysteresis has had significant impacts on the tuning of the LANSCE accelerator.* Magnet hysteresis can also have an impact on Magnet Power Supply (MPS) control, regulation and repeatability requirements. To date, MPS performance requirements have been driven by the requirements on the magnetic fields as determined by the accelerator physicists. Taking hysteresis effects into account can significantly change MPS requirements, as some requirements become more stringent and some are found to be overspecified. Overspecification of MPS requirements can result in significant increases in MPS cost. Conversely, the use of appropriate MPS requirements can result in significant cost savings. The LANSCE accelerator's more than three decades of operation provide a wide variety of magnet power supply technologies and operational experience. We will survey the LANSCE magnet power supply history and determine how performance specifications can be refined to both reduce costs and improve the operators abilities to control the magnetic fields.
*R. McCrady, "Mitigation Of Magnet Hysteresis Effects at LANSCE", LINAC 2006, August, 2006. |
|
|||||
MOPAS049 | Ceramic-Supported Traveling-Wave Structures for SNS Fast Beam Chopper | simulation, coupling, storage-ring, extraction | 545 | |||||
|
The current structure for the fast 2.5-MeV beam chopper for the Spallation Neutron Source (SNS) project was originally developed* to provide rise and fall times around 1 ns. The structure is based on the meander-folded notched strip line with low-dielectric-constant supports and metal separators. Since then the requirements of the chopper rise-time has been significantly relaxed, up to 10 ns, as a result of beam dynamics simulations and to simplify the voltage pulse generators. In addition, initial runs with the beam showed that this structure was prone to damage when accidental beam spills occurred. We suggest alternative meander structures for the SNS chopper that employ high-dielectric-constant substrate (e.g., alumina). Time-domain simulations show their electromagnetic performance to be well within the requirements, while their resistance to beam spills and thermal properties are expected to be much better and fabrication significantly simpler.
|
* S. S. Kurennoy and J. F. Power, EPAC 2000 (Vienna, Austria, 2000), 336. |
|
|||||
MOPAS050 | Active Damping of the e-p Instability at the LANL PSR | damping, feedback, electron, proton | 548 | |||||
|
Funding: This work was supported by the United States Department of Energy under contracts DE-AC52-06NA25396 and W-7405-ENG-36. |
A prototype of an analog, transverse (vertical) feedback system for active damping of the two-stream (e-p) instability has been developed and successfully tested at the Los Alamos National Laboratory Proton Storage Ring (PSR). This system was able to improve the instability threshold by approximately 30% (as measured by the change in RF buncher voltage at instability threshold). Evidence obtained from these tests suggests that further improvement in performance is limited by beam leakage into the gap at lower RF buncher voltage and the onset of instability in the horizontal plane, which had no feedback. Here we describe the present system configuration, system optimization, results of several recent experimental tests, and results from studies of factors limiting its performance. |
|
|||||
MOPAS052 | The LANSCE Control System Current State and Upgrade Outlook | controls, instrumentation, diagnostics, monitoring | 554 | |||||
|
The LANSCE (Los Alamos Neutron Science Center) runs its LINAC control system based on 30(+) year old technology. While some peripheral upgrades have been made over the years, the control system will need some major improvements over the next five years in order to continue to support the user facility's mission. The proposed multi-million dollar LANSCE-R (Refurbishment) project creates a unique opportunity to upgrade the existing control system. We intend to use the EPICS (Experimental Physics and Industrial Control System) control system with the following goals for effective control at modest cost: (1) Replacing our VMS basedμVAX's; (2) Replacing the RICE (Remote Instrumentation and Control Equipment) subsystem with Programmable Logic Controllers (PLCs) to handle regular data acquisition and control, and custom hardware to handle "flavored" data acquisition; (3) Replacing the Master Timer subsystem with a modern event system; (4) Converting Fortran programs running on VAX/VMS computers to Java Programs running on Linux-based desktop PCs. The boundary condition, as usual, is that we must implement these major changes on a running accelerator.
|
|
|
|||||
MOPAS053 | LANSCE Vacuum System Improvements for Higher Reliability and Availability | vacuum, ion, proton, storage-ring | 557 | |||||
|
The Los Alamos Neutron Science Center (LANSCE) accelerator, an 800-MeV proton linac with a storage ring, has been operated over 30 years since early 1970s. Due to the aging and radiation damage of equipment, cables and connectors, the number of troubles is increasing. In order to reduce the time for unscheduled maintenance, we have implemented a system to catch a symptom of degrading vacuum and send an email automatically. We have been testing this system since July 2006. This paper describes this alert system and our experience. In addition, we will describe our plan for modernizing the vacuum system in the next few years.
|
|
|
|||||
MOPAS073 | 700 MHz Low-Loss Electrically-Controlled Fast Ferroelectric Phase Shifter For ERL Application | electron, controls, impedance, resonance | 599 | |||||
|
Funding: Research supported by the Department of Energy, Division of High Energy Physics |
A fast, electrically-controlled phase shifter is described with parameters suitable for operation with the SC acceleration structure of the electron cooling system of Relativistic Heavy Ion Collider (RHIC) at BNL. The phase shifter is a key element of the external RF vector modulator that is capable of fast tuning of the cavities against microphonics, Lorentz force and beam instabilities in a way that can possibly lead to an order of magnitude reduction in the required RF power. The phase shifter is based on a shortened low-impendence coaxial line with ferroelectric rings. The dielectric constant of the ferroelectric rings is altered by applying a 4.2 kV voltage that provides an RF phase shift from 0 to 180 deg. |
|
|||||
MOPAS078 | Digital RF Control for Spallation Neutron Source Accumulator Ring | controls, beam-loading, feedback, simulation | 611 | |||||
|
Funding: SNS is managed by UT-Battelle, LLC, under contract DE-AC05-00OR22725 for the U. S. Department of Energy. |
The proposed upgrade plan for RF control of the Spallation Neutron Source (SNS) accumulator ring requires that the new digital field control module (FCM) support both the conventional narrow-band feed forward control and a new beam-based feed forward control. Both are necessary for compensating the heavy beam loading in SNS ring. The ring FCM also has the integrated control and monitoring features for the cavity bias, cavity resonance, and tetrode grid boost. A user-friendly Epics GUI for all these FCM functionalities is also a part of the requirement. The ring FCM under development is being implemented on the hardware of the proven FCM of SNS Linac. Both the controller architecture and the design code of the digital hardware for the Linac system will be largely reused in the ring system. |
|
|||||
MOPAS079 | Spallation Neutron Source (SNS) High Pulse Repetition Rate Considerations | target, klystron, controls, proton | 614 | |||||
|
Funding: SNS is managed by UT-Battelle, LLC, under contract DE-AC05-00OR22725 for the U. S. Department of Energy. |
Increasing the pulse repetition rate (PRR) of the SNS Linac to its designed maximum of 60 Hz to provide 1.4 MW of beam on target is in progress. Operation above 60 Hz in the future to provide beam to a second target is also being considered. Increasing the PRR to 80 Hz would allow the additional pulses to be diverted to a second target. This paper discusses the impact of increasing the PRR on the SNS infrastructure including Radio Frequency (RF) systems and structures, the ion source, cryogenics, controls and the target. |
|
|||||
MOPAS085 | The SNS Insulating Vacuum Design for the Superconducting Linac | vacuum, controls, radiation, monitoring | 629 | |||||
|
Funding: SNS is managed by UT-Battelle, LLC, under contract DE-AC05-00OR22725 for the U. S. Department of Energy |
The superconducting linac of the Spallation Neutron Source (SNS) has 23 cryomodules each of which incorporate either 3 or 4 niobium cavities. These cavities are submerged in a bath of liquid helium and maintained at an operating temperature of ~ 2K. This bath is surrounded by heat shields and a multilayer blanket within the cryomodule shell. The pressure in this area needs to be maintained at <5·10-5 torr to limit heat leak due to gas convection. Some cryomodules have developed helium leaks into this vacuum cavity and now need to be actively pumped. This paper provides an overview of the Insulating Vacuum System (IVS) that has been installed for this purpose. |
|
|||||
MOPAS097 | Unique features in magnet designs for R&D Energy Recovery Linac at BNL | dipole, emittance, quadrupole, electron | 655 | |||||
|
Funding: Work supported by U. S. DOE under contract No DE-AC02-98CH1-886 |
In this paper we describe unique features of magnets for R&D ERL, which is under construction in Collider-Accelerator Department, BNL. The R&D ERL serves as a test-bed future BNL ERLs, such as electron-cooler-ERL for RHIC and 20 GeV ERL for future electron-hadron, eRHIC. We present selected designs of various dipole and quadrupole magnets, which are used in Z-bend merging systems and the returning loop, 3-D simulations of the fields in these magnets, particle tracking and analysis of magnet's influence on the beam parameters. We discuss an uncommon method of setting requirements on the quality of magnetic field and transferring them into measurable parameters as well as into manufacturing tolerances. We compare selected simulation with results magnetic measurements. |
|
|||||
TUXKI02 | Recommendations from the International Scoping Study for a Neutrino Factory | target, proton, factory, acceleration | 681 | |||||
|
The International Scoping Study (ISS), a one-year review set up at the behest of CCLRC, aimed to lay the foundation for a planned international design study (IDS) for a neutrino factory or superbeam facility over the next three to five years. A team of experienced accelerator physicists were asked to examine the accelerator work carried out to date, identify a fully self-consistent and viable scenario, and specify areas for immediate study and R&D. The ISS Report, published in late 2006, makes recommendations for all parts of a Neutrino Factory complex, from the proton driver, through muon production and acceleration to the final decay ring, which directs the neutrino beams through the earth to far detectors. The paper describes these proposals, explaining the reasoning behind them, and outlines the work currently being undertaken in preparation for the IDS.
|
|
|
Slides
|
|
|
||
TUOBAB01 | Beam Dynamics of the 250 MeV Injector Test Facility | emittance, simulation, space-charge, electron | 785 | |||||
|
The PSI-FEL/LEG project aims for the development of a pulsed high-brightness, high-current electron source which is one of the cornerstones for a cost-efficient high-power laser-like X-ray light-source. Creating an ultra low emittance beam is a great challenge, transporting i.e. accelerating and compressing is equally difficult. We present a 3D start-to-end simulation of our planned 250 MeV injector test facility. The injector consists of a 2 cell standing wave l-band cavity followed by a ballistic bunching section. The following L-band and S-band structures accelerate the electron beam up to the final energy of 250 MeV. An X-band RF structure prepares the beam for the following bunch compressor in which the target current of 350 ampere is reached. The target value of the slice emittance is 0.10 [mm mrad] therefore precise beam dynamics simulations are needed. For the 3D simulations we use IMPACT-T, a time domain parallel particle tracking code in which the self fields are treated using electrostatic approximation . We discuss various issues such as projected and slice emittance preservation and shade light on some of the differences between an envelope and the 3D model.
|
|
|
Slides
|
|
|
||
TUOBAB02 | Experimental Characterization of the Transverse Phase Space of a 60-MeV Electron Beam through a Compressor Chicane | electron, synchrotron, synchrotron-radiation, simulation | 788 | |||||
|
Funding: U. S. DOE of Sciences |
Space charge and coherent synchrotron radiation may deteriorate electron beam quality when the beam passes through a magnetic bunch compressor. This paper presents the transverse phase-space tomographic measurements for a compressed beam at 60 MeV, around which energy the first stage of magnetic bunch compression takes place in most advanced linacs. Transverse phase-space bifurcation of a compressed beam is observed at that energy, but the degree of the space charge-induced bifurcation is appreciably lower than the one observed at 12 MeV. The Trafic4 simulation confirms the observation.
The paper was published at PRST-AB, November 2006 |
|
Slides
|
|
|
||
TUZBAB02 | The Extreme Value Theory to Estimate Beam Losses in High Power Linacs | beam-losses, quadrupole, simulation, beam-transport | 815 | |||||
|
The influence of random perturbations of high intensity accelerator elements on the beam losses is considered. This influence is analyzed with the help of the Extreme Value Theory (EVT) to allow loss estimates for a very low fraction of the beam. Many fields of modern science and engineering have to deal with events which are rare but have significant consequences. EVT is considered to provide the basis for the statistical modeling of such extremes events (extreme variations of financial market for insurance companies or extreme wind speed for electric companies). To illustrate the application of this theory to beam losses estimates, the SPIRAL2 driver is used. This 5 mA deuteron accelerator is simulated from the output of the source to the target with high resolution PIC modelisations (up to 1.3 million macro-particles) using realistic external fields.
|
|
|
Slides
|
|
|
||
TUXC03 | Design and Status of the XFEL RF System | klystron, electron, controls, linear-collider | 841 | |||||
|
The RF system of the European XFEL under construction at present at DESY in Hamburg, Germany, consists of 27 RF stations. At a later point of time the number might be increased to 31. The RF system provides RF power at 1.3GHz for the superconducting cavities of the main linear accelerator, the cavities of the injector and the RF gun. Each station consists of a 10MW multiple beam klystron, a HV pulse modulator, HV pulse cables, a pulse transformer, an interlock system, a low level RF system, a waveguide distribution system and a number of auxiliary power supplies. This paper describes the layout of the RF system and summarizes the design and status of the main high power components.
|
|
|
Slides
|
|
|
||
TUYC02 | High Gradient Induction Accelerator | induction, proton, electron, vacuum | 857 | |||||
|
Funding: This work was performed under the auspices of the U. S. Department of Energy by the University of California, Lawrence Livermore National Laboratory under Contract No. W-7405-Eng-48. |
Progress in the development of compact induction accelerators employing advanced vacuum insulators and dielectrics will be described. These machines will have average accelerating gradients at least an order of magnitude higher than existing machines and can be used for a variety of applications including flash x-ray radiography and medical treatments. Research describing an extreme variant of this technology aimed at proton therapy for cancer will be described. |
|
Slides
|
|
|
||
TUZAC01 | The ILC Control System Design | controls, feedback, monitoring, linear-collider | 868 | |||||
|
Funding: Work supported in the U. S. by the U. S. Department of Energy under contract Nos. DE-AC02-06CH11357, DE-AC02-76CH03000, and DE-AC02-76SF00515. |
The scale and performance parameters of the ILC require new thinking in regards to control system design. This design work has begun quite early in comparison to most accelerator projects, with the goal of uniquely high overall accelerator availability. Among the design challenges are high control system availability, timing reference distribution, standardization of interfaces, operability, and maintainability. We present the current state of the design and take a prospective look at ongoing research and development projects. |
|
Slides
|
|
|
||
TUZAC02 | Modern Accelerator Control Systems | controls, positron, injection, electron | 873 | |||||
|
Discussion of modern approaches to accelerator control systems including software and hardware implications, in view of maintaining reliability under changing requirements.
|
|
|
Slides
|
|
|
||
TUOCC01 | Software Tools for Commissioning of the Spallation Neutron Source Linac | acceleration, proton, quadrupole, optics | 883 | |||||
|
Funding: ORNL/SNS is managed by UT-Battelle, LLC, for the U. S. Department of Energy under contract DE-AC05-00OR22725. |
The Accelerator Physics group at the Spallation Neutron Source (SNS) has developed numerous codes to assist in the beam commissioning, tuning, and operation of the SNS Linac. These codes have been key to meeting the beam commissioning milestones. For example, a recently developed code provides for rapid retuning of the superconducting Linac in case of RF stations going offline or coming online. Highlights of these "physics applications" will be presented. |
|
Slides
|
|
|
||
TUPMN018 | Dark Current Transport in the FLASH Linac | gun, simulation, electron, undulator | 956 | |||||
|
The free electron laser facility FLASH at DESY Hamburg operates a low-emittance photoinjector and several acceleration modules with superconducting cavities to produce a high quality electron beam of up to 700 MeV. Since few months, the accelerator is routinely operated with its design RF pulse length of 800 μs instead of the prior length of 70-200 μs. As a result, the activation of components due to dark current emitted by the gun has reached critical proportions. To improve the understanding of dark current transport through the linac, simulations have been conducted with the Astra tracking code. The generated phase space distributions are compared against a detailed 3-dimensional aperture model of the machine with the newly developed ApertureLib toolkit. The results are in agreement with direct measurements of the dark current and with the observed activities.
|
|
|
|||||
TUPMN029 | Linac Upgrading Program for the Fermi Project : Status and Perspectives | laser, electron, undulator, controls | 977 | |||||
|
FERMI@ELETTRA is a soft X-ray forth generation light source under development at the ELETTRA laboratory. It will be based on the existing 1.0 GeV Linac, revised and upgraded to fulfil the stringent requirements expected from the machine. The overall time schedule of the project is very tight and ambitious, foreseeing to supply 10 nm photons to users within 2010. Here the machine upgrading program and the ongoing activities are presented and discussed.
|
|
|
|||||
TUPMN036 | Laser and RF Synchronization Measurements at SPARC | laser, feedback, gun, emittance | 992 | |||||
|
Funding: Work supported by the EU Commission in the sixth framework programme, contract no. 011935 - EUROFEL. |
The SPARC project consists in a 150 MeV B-band, high-brilliance linac followed by 6 undulators for FEL radiation production at 530 nm. The linac assembly has been recently completed. During year 2006 a first experimental phase aimed at characterizing the beam emittance in the first 2m drift downstream the RF gun has been carried out. The low level RF control electronics to monitor and synchronize the RF phase in the gun and the laser shot on the photocathode has been commissioned and extensively tested during the emittance measurement campaign. The laser synchronization has been monitored by measuring the phase of the free oscillation of an RF cavity impulsively excited by the signal of a fast photodiode illuminated by the laser shot. Phase stability measurements are reported, both with and without feedback correction of the slow drifts. A fast intra-pulse phase feedback system to reduce the phase noise produced by the RF power station has been also positively tested. |
|
|||||
TUPMN039 | Status of the SPARC-X Project | emittance, radiation, undulator, brightness | 1001 | |||||
|
SPARC-X is a two branch project consisting in the SPARC test facility dedicated to the development and test of critical subsystems such as high brightness photoinjector and a modular expandable undulator for SASE-FEL experiments at 500 nm with seeding, and the SPARX facility aiming at generation of high brightness coherent radiation in the 3-13 nm range, based on the achieved expertise. The projects are supported by MIUR (Research Department of Italian Government) and Regione Lazio. SPARC has completed the commissioning phase of the photoinjector in November 2006. The achieved experimental results are here summarized together with the status of the second phase commissioning plans. The SPARX project is based on the generation of ultrahigh peak brightness electron beams at the energy of 1 and 2 GeV generating radiation in the 3-13 nm range. The construction is at the moment planned in two steps starting with a 1 GeV Linac. The project layout including both RF-compression and magnetic chicane techniques has been studied and compared, together with the feasibility of a mixed s-band and x-band linac option.
|
|
|
|||||
TUPMN044 | Status of R&D Efforts Toward the ERL-based Future Light Source in Japan | laser, gun, synchrotron, radiation | 1016 | |||||
|
Energy Recovery Linacs (ERL), based on superconducting accelerators, are one of the most promising synchrotron light sources in future. The KEK and the JAEA, in collaboration with the ISSP, the UVSOR, and the SPring-8, are considering to realize together the ERL-based next-generation light source in Japan. To establish key technologies for that, active R&D efforts started. The R&D program includes the developments of ultra-low-emittance photocathode guns and of superconducting cavities, as well as experimental proofs of accelerator-physics issues at the ERL test facility, which will be built at the KEK campus. We are currently working on constructing a prototype photocathode gun, on designing superconducing cavities, and on designing a prototype ERL. The current plan of the prototype ERL comprises a full injector linac, one or two cryomodules for the main linac, and the beam return loop, which can be operated at beam energies from 60 to 160 MeV. The up-to-date R&D status will be reported.
|
|
|
|||||
TUPMN046 | Quadrupole HOM Damping with Eccentric-fluted Beam Pipes | quadrupole, dipole, damping, ion | 1022 | |||||
|
HOM damping is important for superconducting cavities, especially for high current CW machines such as ERLs. The lower Q-values of HOMs lead to the lower requirement of a refrigerator system and the higher beam current against HOM BBU. Enlarged beam pipes, which have lower cutoff frequencies, are effective to damp HOMs of monopole and dipole, but insufficient for HOMs of quadrupole which have high cutoff frequencies. An eccentric-flute is proposed to damp the HOMs of quadrupole. The eccentric-flute is formed by displacing the flute from the center of the beam pipe and/or by jackknifing around the midpoint of the flute to couple two degenerate modes. The eccentric-flute acts as a mode converter from quadrupole to dipole of the lower cutoff frequency so that the RF power can propagate through the beam pipe. The result of calculation with MAFIA and measurement of a cold model with the eccentric-flute are presented.
|
|
|
|||||
TUPMN054 | Design of a Source to Supply Ultra-fast Electron and X-Ray Pulses | electron, laser, gun, scattering | 1046 | |||||
|
In this paper we report the preliminary design and considerations on a multi-discipline ultra-fast source, which is capable of providing the user community with femtosecond electron bunch and light pulses with the wavelength ranging from IR to X-ray. The facility is based on photocathode RF gun driven by a Ti:Sapphire laser system. The low emittance subpicosecond electron bunch at the gun exit can be used in femtosecond electron diffraction setup to visualize the ultrafast structural dynamics. After acceleration and compression, the electron beam with the energy of 50 MeV is further used to provide high peak brightness X-ray by inverse Compton scattering with TW laser. We also consider the possibility and reliability of storing the electron beam in a compact storage ring and the laser pulse in a super-cavity. Operating in this scheme may increase the average flux of the X-ray photons by orders of magnitude.
|
|
|
|||||
TUPMN073 | First Operation of a Thermionic Cathode RF Gun at NSRRC | gun, cathode, electron, brightness | 1088 | |||||
|
An injector system that based on rf gun technology is being constructed at NSRRC. This will be a 100 MeV beam injector that consists of an rf linac with a thermionic cathode rf gun as electron source. The superior performance and special configuration of the thermionic rf gun system made it an attractive option as a reliable pre-injector booster synchrotron. In cooperation with an alpha-magnet as low energy bunch compressor, ultra-fast electron beam pulses as short as 100 fs can be generated from the thermionic cathode rf gun for generation of intense coherent short wavelength radiations, production of femto-second electron and wavelength tunable ultra-fast X-ray pulses. First operation of the thermionic rf gun will be presented.
|
|
|
|||||
TUPMN083 | Electron Beam Dynamics in 4GLS | electron, laser, sextupole, insertion | 1103 | |||||
|
Funding: Some of the work reported in this paper is supported by the EuroFEL programme. |
Studies of the electron beam dynamics for the 4GLS design are presented. 4GLS will provide three different electron bunch trains to a variety of user synchrotron sources. The 1 kHz XUV-FEL and 100 mA High Average Current branches share a common 540 MeV linac, whilst the 13 MHz IR-FEL must be well-synchronised to them. An overview of the injector designs, electron transport, and energy recovery is given, including ongoing studies of coherent synchrotron radiation, beam break-up and wakefields. This work is being pursued for the forthcoming Technical Design Report due in 2008. |
|
|||||
TUPMN084 | The Status of the Daresbury Energy Recovery Linac Prototype | gun, laser, electron, diagnostics | 1106 | |||||
|
As part of the UK's R&D programme to develop an advanced energy recovery linac-based light source (4GLS); a 35 MeV technology demonstrator called the Energy Recovery Linac Prototype (ERLP) has been constructed. It is based on a combination of a DC photocathode electron gun, a superconducting injector linac and main linac operating in energy recovery mode, driving an IR-FEL. The priorities for this machine are to gain experience of operating a photoinjector gun and superconducting linacs; to produce and maintain high-brightness electron beams; achieving energy recovery from an FEL-disrupted beam and studying important synchronisation issues. The current status of this project is presented, including construction and commissioning progress, including plans for the future exploitation of this scientific and technical R&D facility.
|
|
|
|||||
TUPMN086 | Operation of the Diamond Light Source Injector | booster, storage-ring, injection, single-bunch | 1112 | |||||
|
The Diamond Light source injector consists of a 100 MeV pre-injector linac and a 3 GeV full energy booster. The injection system has been reliably providing beam to the storage ring since September 2006 in both multibunch and single bunch mode, at 5 Hz repetition rate. All user operation at present is carried out in multibunch mode, with an injection efficiency up to 95%. Single bunch and hybrid modes are being developed now for users later this year. Differences in operation between multibunch and single bunch mode are largely restricted to the linac, although a small correction in booster sextupole ramp is needed for single bunch operation. Single bunch purity has been measured in the storage ring to be greater than 99.9%. The timing system can be controlled to allow a wide range of filling patterns, including complete ring fill in both single and multibunch mode, and hybrid fills with individual single bunches placed in gaps between continuous bunch trains. Top-up operation is envisaged for user operation in the future, and trials are underway to ensure safe and efficient running in this mode.
|
|
|
|||||
TUPMN089 | Configuration, Optics, and Performance of a 7-GeV Energy Recovery Linac Upgrade for the Advanced Photon Source | emittance, undulator, storage-ring, photon | 1121 | |||||
|
Funding: Work supported by the U. S. Department of Energy, Office of Science, Basic Energy Sciences, under Contract No. DE-AC02-06CH11357. |
The Advanced Photon Source (APS) is a 7-GeV storage ring light source that has been in operation for over a decade. In order to make revolutionary improvements in the performance of the existing APS ring, we are exploring the addition of a 7-GeV energy recovery linac (ERL) to the APS complex. In this paper, we show the possible configuration of such a system, taking into account details of the APS site and the requirement that stored beam capability be preserved. We exhibit a possible configuration for the single-pass, 7-GeV linac. We discuss optical solutions for transport from 10 MeV to 7 GeV and back, including a large turn-around arc that would support 48 additional user beamlines. Tracking results are shown that include incoherent and coherent synchrotron radiation, resulting in predictions of the beamline performance. |
|
|||||
TUPMN099 | An Energy Recovery Linac Upgrade for the Advanced Photon Source Located in the Storage Ring Infield | injection, storage-ring, emittance, dipole | 1145 | |||||
|
Funding: Work supported by the U. S. Department of Energy, Office of Science, Office of Basic Energy Sciences, under Contract No. DE-AC02-06CH11357. |
In the recent past, the Advanced Photon Source (APS) was asked by the U. S. Department of Energy to explore a revolutionary upgrade based on emerging energy recovery linac (ERL) technology. In an ERL, the energy of the 7-GeV, 100-mA beam is recovered after the beam passes through user beamlines by decelerating the beam back through the same superconducting linac cavities that accelerated it. The main constraint on this upgrade is that the existing APS beamlines not be disturbed. This requires that the APS storage ring be used as a single-pass transport line in the overall ERL beamline layout. A natural place to locate the ERL is inside the existing APS storage ring infield'' area, which has unoccupied space south of the existing APS injector complex. Other important constraints include minimal disturbance of existing building structures and injector beamlines. The existing injector complex would be preserved so that existing operation can be continued through and even possibly beyond ERL commissioning. In this paper, we describe a layout that satisfies these constraints. We also estimate the amount of emittance increase the beam will experience before ring injection. |
|
|||||
TUPMN100 | LCLS Undulator Production | undulator, factory, extraction, photon | 1148 | |||||
|
Funding: Work supported by the U. S. Dept. of Energy, under contract numbers DE-AC02-06CH11357 and DE AC03-76SF00515. |
Design and construction of the undulators for the Linac Coherent Light Source (LCLS) is the responsibility of Argonne National Laboratory. A prototype undulator* was constructed in-house and was extensively tested. The device was tunable to well within the LCLS requirements and was stable over a period of several years. Experience constructing the prototype undulator led us to conclude that with appropriate engineering design and detailed assembly procedures, precision undulators can be constructed by qualified vendors without previous undulator-construction experience. Our detailed technological knowledge and experience were transferred to the successful bidders who have produced outstanding undulators. Our production concept for the 40 3.4 m long, fixed-gap, planar-hybrid undulators with a 30 mm period is presented. Manufacturing, quality assurance, and acceptance testing details are also presented.
*LCLS Prototype Undulator Report, Argonne National Laboratory Report ANL/APS/TB-48, January 2004, R. Dejus, Editor. |
|
|||||
TUPMN102 | Electromagnetic Design of the RF Cavity Beam Position Monitor for the LCLS | dipole, coupling, simulation, impedance | 1153 | |||||
|
Funding: Work supported by the U. S. Department of Energy under Contract Nos DE-AC02-06CH11357 and DE-AC03-76SF00515. |
A high-resolution X-band cavity beam position monitor (BPM) has been developed for the LCLS in order to achieve micron-level accuracy of the beam position using a dipole mode cavity and a monopole mode reference cavity. The rf properties of the BPM will be discussed in this paper including output power, tuning, and issues of manufacturing. In addition, methods will be presented for improving the isolation of the output ports to differentiate between horizontal/vertical beam motion and to reject extraneous modes from affecting the output signal. The predicted simulation results will be compared to data collected from low-power experimental tests. |
|
|||||
TUPMS019 | Ion Effects and Ion Elimination in the Cornell ERL | ion, electron, emittance, simulation | 1218 | |||||
|
Funding: Supported by Cornell University and NSF grant PHY 0131508 |
In an energy recovery linac (ERL) where beam-loss has to be minimal, and where beam positions and emittances have to be very stable in time, optic errors and beam instabilities due to ion effects have to be avoided. Here we explain why ion clearing electrodes are the least unattractive way of eliminating ions in an ERL and we present calculations of the remnant ion density and its effect on the beam. We also show a design of the clearing electrodes that should be distributed around the accelerator and illustrate their wake-field properties. |
|
|||||
TUPMS022 | Beam Breakup Simulations for the Cornell X-ray ERL | simulation, quadrupole, lattice, electron | 1227 | |||||
|
Funding: Supported by Cornell University and NSF grant PHY 0131508 |
Multi-pass, multi-bunch beam-breakup (BBU) can limit the current in linac-based recirculating accelerators. We have therefore made the computation of the transverse and longitudinal BBU-threshold current available in Cornell's main optics design and beam simulation library BMAD. The coupling of horizontal and vertical motion as well as time of flight effects are automatically contained. Subsequently we present a detailed simulation study of transverse and longitudinal BBU in the proposed 5GeV Energy Recovery Linac light source at Cornell University, including the use of frequency randomization, polarized cavities and optical manipulations to improve the threshold current. |
|
|||||
TUPMS041 | The Wisconsin VUV/Soft X-ray Free Electron Laser Project | laser, electron, scattering, photon | 1278 | |||||
|
Funding: Work supported by the University of Wisconsin - Madison. SRC is supported by the U. S. National Science Foundation under Award No. DMR-0537588. |
The University of Wisconsin-Madison and its partners are developing a design for an FEL operating in the UV to soft x-ray range that will be proposed as a new multidisciplinary user facility. Key features of this facility include seeded, fully coherent output with tunable photon energy and polarization over the range 5 eV to 1240 eV, and simultaneous, independent operation of multiple beamlines. The different beamlines will support a wide range of science from femto-chemistry requiring ultrashort pulses with kHz repetition rates to photoemission and spectroscopy requiring high average flux and narrow bandwidth at MHz rates. The facility will take advantage of the flexibility, stability, and high average pulse rates available from a CW superconducting linac driven by a photoinjector. This unique facility is expected to enable new science through ultra-high resolution in the time and frequency domains, as well as coherent imaging and nano-fabrication. This project is being developed through collaboration between the UW Synchrotron Radiation Center and MIT. We present an overview of the facility, including the motivating science, and its laser, accelerator, and experimental systems. |
|
|||||
TUPMS042 | A Superconducting Linac Driver for the Wisconsin Free Electron Laser | laser, electron, gun, cathode | 1281 | |||||
|
Funding: Work supported by the University of Wisconsin - Madison. SRC is supported by the U. S. National Science Foundation under Award No. DMR-0537588. |
We present an initial design of the driver for the Wisconsin VUV/Soft Xray FEL facility, which will provide high intensity coherent photons from 5 eV to 1.2 keV. It uses a 2.5 GeV, L-band CW superconducting linac with a 1.7 GeV tap-off to feed the lower energy FELs. In order to support multiple high rep-rate FELs, the average design current is 1 mA. Sub-nanocoulomb bunches with normalized transverse emittances of order 1 micron are generated in a photoinjector for beamlines operating at repetition rates from kHz to MHz. Multi-stage bunch compression provides 1 kA peak current to the FELs, with low energy spread and a suitable current profile. Compressed bunch lengths of several hundred femtoseconds will allow generation of photon pulses in the range 10 to 100 fs using cascaded FELs. Consideration has been given to removing the residual energy chirp from the beam, and minimizing the effects of space charge, coherent synchrotron radiation, and microbunching instabilities. A beam switchyard using RF separators and fast kickers delivers the desired electron bunches to each of the FELs. Details of the design will be presented, including those areas requiring the most development work. |
|
|||||
TUPMS044 | Design of a 980 MeV Energy Recovery Linac | recirculation, quadrupole, synchrotron, synchrotron-radiation | 1287 | |||||
|
Funding: This research was supported by National Science Foundation grant no. DMR-0537588. |
A 980-MeV energy recovery linac with radiofrequency (rf) of 1.5 GHz is designed. Electrons are accelerated by two passages through a 480-MeV superconducting linac, and decelerated by two subsequent passages. Recirculation is accomplished with six 60-degree bending magnets. The threshold current for beam breakup instability exceeds 100 mA. Gaussian bunches with normalized transverse emittances of 0.1 mm-mrad and rms length of 1.85 ps may be compressed by a factor of 180 (to a bunch length of 10 fs) with only a slight increase in transverse normalized emittance. Bunch charges up to 8 pC may be compressed at 980 MeV without excessive degradation from coherent synchrotron radiation, allowing operation with beam currents up to 12 mA. |
|
|||||
TUPMS049 | Initial Commissioning Experience with the LCLS Injector | gun, laser, cathode, emittance | 1302 | |||||
|
Funding: U. S. Department of Energy contract #DE-AC02-76SF00515. |
The Linac Coherent Light Source (LCLS) is a SASE x-ray Free-Electron Laser (FEL) project presently under construction at SLAC. The injector section, from drive-laser and RF photocathode gun through the first bunch compressor chicane, was installed during the Fall of 2006. Initial system commissioning with an electron beam takes place in the Spring and Summer of 2007. The second phase of construction, including the second bunch compressor and the FEL undulator, will begin later, in the Fall of 2007. We report here on experience gained during the first phase of machine commissioning, including RF photocathode gun, linac booster section, energy spectrometers, S-band and X-band RF systems, the first bunch compressor stage, and the various beam diagnostics. |
|
|||||
TUPMS059 | LCLS Undulator Tuning And Fiducialization | undulator, alignment, electron, free-electron-laser | 1320 | |||||
|
Funding: Work supported in part by the DOE Contract DE-AC02-76SF00515. |
The LCLS x-ray free electron laser project at SLAC requires 40 undulators: 33 in the beamline, 6 spares, and one reference undulator. A new facility was constructed at SLAC for tuning and fiducializing the undulators. The throughput of the facility must be approximately one undulator per week. Much effort has gone into automating the undulator tuning. Because of tight alignment tolerances, accurate techniques were developed to fiducialize the undulators. The new facility, the tuning techniques, and the fiducialization techniques will be discussed. |
|
|||||
TUPMS076 | Status of R&D Energy Recovery Linac at Brookhaven National Laboratory | gun, controls, diagnostics, power-supply | 1347 | |||||
|
Funding: Work performed under the auspices of the U. S. Department of Energy and partially funded by the US Department of Defence. |
In this paper we present status and plans for the 20-MeV R&D energy recovery linac, which is under construction at Collider Accelerator Department at BNL. The facility is based on high current (up to 0.5 A of average current) super-conducting 2.5 MeV RF gun, single-mode super-conducting 5-cell RF linac and about 20-m long return loop with very flexible lattice. The R&D ERL, which is planned for commissioning in 2008, aims to address many outstanding questions relevant for high current, high brightness energy-recovery linacs. |
|
|||||
TUPMS081 | Design considerations of the NSLS-II Injection Linac | injection, booster, emittance, single-bunch | 1359 | |||||
|
The NSLS-II injector consists of a 3 GeV booster injected by a 200MeV linac. Specifications of the linac are derived from Booster and Storage ring beam requirements. Linac design considerations are presented to meet these specifications.
|
|
|
|||||
TUPMS085 | Photoemission Tests of a Pb/Nb Superconducting Photoinjector | laser, cathode, electron, optics | 1365 | |||||
|
Funding: This work has been partially supported by the EU Commission, contract no. 011935 EUROFEL-DS5, US DOE under contract number DE-AC02-98CH10886. |
We report recent progress in the development of a hybrid lead/niobium superconducting (SC) injector. The goal of this effort is to produce an all-SC injector with the SCRF properties of a niobium cavity along with the superior quantum efficiency (QE) of a lead photocathode. Two prototype hybrid injectors have been constructed, one utilizing a cavity with a removable cathode plug, and a second consisting of an all-niobium cavity arc-deposited with lead in the cathode region. We present the results of QE measurements on these cavities, along with tests of the effect of the laser on the cavity RF performance. |
|
|||||
TUPAN003 | Beam Quality and Operational Experience with the Superconducting LINAC at the ISAC II RIB facility | emittance, ion, diagnostics, acceleration | 1392 | |||||
|
The ISAC II superconducting LINAC is now in the operational phase. The linac was commissioned with stable beams from an off-line source. The commissioning not only proved the integrity of the infrastructure but benchmarked the beam quality and rf cavity performance. Measurements of the transverse and longitudinal emittance are consistent with little or no emittance growth through the acceleration. Transmission near 100% has been achieved though some solenoid steering is evident due to misalignment. The misalignment problem is being evaluated using the beam as diagnostic tool while applying corrections based on the beam measurements. The effectiveness of the corrections will be reported. The machine has been demonstrated to be easy to tune, reliable in restoring beam and flexible enough to accommodate different tuning strategies; software routines have been developed in order to facilitate the tuning process. In this paper the operational routine for tuning and beam delivery will be presented as well as the beam characteristics drawn from the commissioning studies.
|
|
|
|||||
TUPAN017 | Development of a Coupled CH Structure for the GSI Proton Injector | proton, coupling, klystron, simulation | 1428 | |||||
|
Funding: CARE (contract No RIICT-2003-506-395), GSI, BMBF |
The FAIR facility, under development at GSI, needs a new dedicated proton injector for the production of intense antiprotons secondary beams. This injector will accelerate protons from 3 to 70 MeV at a current of 70 mA, and due to the high voltage gain and shunt impedance will be based on CH cavities powered by a 2.5 MW, 325 MHz klystron. An innovative coupling cell containing one drift tube of length N-beta λ was developed to combine multicell drift tube modules of the CH-type (H210 mode).. In order to study this innovative coupling mechanism a scaled model of the second resonator of GSI Proton injector is under production at IAP. The according full scale prototype, 3 meter long coupled X MV resonator from MeV to MeV is under construction and will be power tested with a 2.5 MW klystron at GSI at the end of 2008. This paper describes in detail the coupled structure together with a general overview of the R&D results achieved on the CH-DTL's cavity. |
|
|||||
TUPAN019 | The Superconducting Linac Approach for IFMIF | simulation, coupling, rfq, focusing | 1434 | |||||
|
The International Fusion Material Irradiation Facility (IFMIF) which is under design will be a high flux source of fast neutrons for the development of new materials needed for future fusion reactors. IFMIF will deliver 250 mA of 40 MeV deuterons. The duty cycle is 100% and the beam power on the lithium target is 10 MW. The beam will be accelerated by two 175 MHz linacs in parallel operation. Beside the room temperature Alvarez solution an alternative design using superconducting CH-structures has been proposed. In this paper we present the superconducting approach for IFMIF with the emphasis on the beam dynamics simulations. The simulations have been performed using the LORASR code. A new space charge routing has been added to the code to increase the number of macro particles to more than 1 million. Additionally a new routine allows the simulation of randomly distributed RF and alignment errors. The optimized linac layout including error and loss studies will be presented.
|
|
|
|||||
TUPAN020 | A RFQ-Decelerator for HITRAP | rfq, ion, emittance, vacuum | 1437 | |||||
|
The HITRAP linac at GSI will decelerate ions from 5 MeV/u to 6 keV/u for experiments with the large GSI Penning trap. The ions are decelerated at first in the existing experimental storage ring (ESR) down to an energy of 5 MeV/u and will be injected into a new Decelerator-Linac consisting of a IH-structure, which decelerates down to 500keV/u, and a 4-Rod RFQ , decelerating to 5 keV/u. The properties of the RFQ decelerator and the status of the project will be discussed.
|
|
|
|||||
TUPAN021 | RFQ and IH Accelerators for the new EBIS Injector at BNL | rfq, ion, emittance, heavy-ion | 1439 | |||||
|
The new EBIS preinjector at BNL will accelerate ions from the EBIS source with specific mass to charge ratio of up to 6.25, from 17 keV/u to 2000 keV/u to inject into the Booster synchrotron, expanding experimental possibilities for RHIC and NASA experiments. The properties of the RFQ and IH accelerators and the status of the project will be discussed.
|
|
|
|||||
TUPAN039 | Profile Measurement and Transverse Matching in J-PARC Linac | beam-losses, electron, simulation, scattering | 1472 | |||||
|
Beam commissioning of J-PARC linac has been performed since November 2006. In the beam commissioning, transverse matching has been performed by measurement of beam profiles and emittance with wire scanners. In this presentation, detail of wire scanners and the method of matching are described.
|
|
|
|||||
TUPAN043 | RF Amplitude and Phase Tuning of J-PARC DTL | beam-transport, monitoring, injection, controls | 1481 | |||||
|
The beam commissioning of J-PARC linac has been started in November 2006. In the beam commissioning, the tuning of the RF phase and amplitude for its DTL (Drift Tube Linac) has been performed with a phase-scan method. Detailed results of the RF tuning are presented with a brief discription of the tuning procedure.
|
|
|
|||||
TUPAN056 | Fabrication Status of ACS Accelerating Modules of J-PARC Linac | coupling, target, impedance, vacuum | 1514 | |||||
|
An ACS (Annular Coupled Structure) cavity has been developed for the J-PARC Linac from 190-MeV to 400-MeV. We fabricated a buncher module with two 5-cell accelerating tanks and one 5-cell bridge tank as the first module. The buncher module is shorter than accelerating module that consists of two 17-cell accelerating tanks and one 9-cell bridge tank. The first buncher module achieved the stable operation of 50 Hz, 600 us, 600 kW in the high-power test, which corresponds to the E0 value of 4.8 MV/m. The second buncher module and three accelerating modules are under fabrication continuously. These results of the frequency tuning and assembling are presented in detail.
|
|
|
|||||
TUPAN058 | High Power Conditioning of the DTL for J-PARC | vacuum, klystron, acceleration, pick-up | 1517 | |||||
|
For the J-PARC, DTL (Drift Tube Linac) is used to accelerate an H- ion beam from 3MeV to 50MeV. The DTL consists of 3 tanks and the all tanks were installed in the accelerator tunnel for J-PARC. After the installation, the high power conditioning has been started in Oct. 2006. The required rf power levels for beam acceleration are about 1.08MW, 1.2MW and 1.03MW (the pulse length is 600μsec and the pulse repetition is 25Hz) for the 1st, 2nd and 3rd tanks, respectively. As a result of the conditioning, we have been achieved that the rf power levels are about 1.3MW, 1.45MW and 1.23MW of 1.2 times required power levels (the pulse length is 650μsec and the pulse repetition is 25Hz). In this paper, the results of the high power conditioning of the DTL tanks are described.
|
|
|
|||||
TUPAN059 | The Precise Survey and the Alignment Results of the J-PARC Linac | survey, alignment, beam-transport, laser | 1520 | |||||
|
J-PARC linear accelerator components have been installed and the beam commissioning has been started in Nov. 2006. A total length is more than 400 m including the beam transport line to the 3GeV RCS(Rapid Cycling Synchrotron). Precise alignment of the accelerator components is essential for high quality beam acceleration. After the completion of the linac building, floor elevation was surveyed periodically for more than one year to adjust the beam height from the ion source to the RCS. Before the beam commissioning, a metrological survey has been done. The reference points on the tunnel wall were set up to form a survey network to reduce the survey error less than 1mm in the entire linac. Based on the survey results, the linac components were re-aligned finely to satisfy the requirement. In this paper, the results of the floor elevation and the final alignment are described.
|
|
|
|||||
TUPAN060 | The DTL/SDTL Alignment of the J-PARC Linac | alignment, laser, target, survey | 1523 | |||||
|
J-PARC linear accelerator components have been installed and the beam commissioning has been started in Nov. 2006. The length of the linear section is about 300 m which consists of the ion source, the radio frequency quadropole linac(RFQ), the drift tube linac(DTL), separated type DTL(SDTL), and the beam transport line. Precise alignment of the accelerator components is essential for high quality beam acceleration. The required alignment error in the J-PARC linac is 0.1mm in transverse direction. In the DTL/SDTL section, the fine alignment was carried out by using an optical alignment telescope along with the cavity installation. The relay targets were placed at short intervals for smooth connection between neighboring components. After the installation, the DTL/SDTL positions were confirmed by measuring the reference base by using a laser tracker. In this paper, the alignment procedure for the DTL/SDTL section and the results by the laser tracker measurements are described.
|
|
|
|||||
TUPAN062 | RF Amplitude and Phase Tuning of J-PARC SDTL | klystron, feedback, simulation | 1529 | |||||
|
In the beam commissioning of J-PARC Linac, RF phase and amplitude of SDTL (Separate-type Drift Tube Linac) cavities have been tuned with a phase-scan method based on the beam-energy measurement. The output beam energy is measured with two FCTs (Fast Current Transformer) using the TOF (Time-Of-Flight) method. The detailed results of RF tuning for SDTL cavity is presented.
|
|
|
|||||
TUPAN063 | High Power Test of MA Cavity for J-PARC RCS | impedance, synchrotron, acceleration, power-supply | 1532 | |||||
|
We have been testing the RF cavities for the J-PARC RCS, we can operate the cavities without sever problems. Before some MA cores were damaged, then we found such cores have low ribbon resistance. After that we have tested the cavities loaded with improved ribbon resistance.
|
|
|
|||||
TUPAN076 | Conceptual Design of the Beam Line for the PEFP User Facility | proton, target, quadrupole, optics | 1547 | |||||
|
Funding: The work was supported by the 21C Frontier R&D program in Ministry of Science and Technology of the Korean Government |
The Proton Engineering Frontier Project (PEFP) will supply 20-MeV and 100-MeV proton beams from a 100 MeV proton linear accelerator for beam applications. The extracted 20 MeV or 100 MeV proton beams will be simultaneously distributed into the five targets through a dipole magnet equipped with a controllable AC power supply. The most important design criterion is the flexibility of the irradiation conditions in order to meet various user requirements in many application fields. For this purpose, we have designed the beamlines to the targets for wide or focused beams, external or in-vacuum beams, and horizontal or vertical beams. This work includes details of the conceptual design of the beamlines. |
|
|||||
TUPAN077 | Error Analysis of the PEFP 100 MeV Linac | controls, proton, quadrupole, simulation | 1550 | |||||
|
Funding: This work was supported by the 21C Frontier R&D program in Mnistry of Science and Technology of the Korean Government. |
The 100 MeV Linac of the Proton Engineering Frontier Project (PEFP) consists of an ion source, a low energy beam transport (LEBT), a 3 MeV radio frequency quadrupole (RFQ), and an 100 MeV drift tube linac (DTL). The DTL is separated into two parts. The first part includes 4 tanks which accelerate 20 mA proton beams up to 20 MeV. The medium energy beam transport (MEBT) follows the 20 MeV accelerator in order to match proton beams into the next linac as well as to extract and supply 20 MeV proton beams to the user facilities. The second part of the DTL consists of 7 tanks to accelerate proton beams to 100 MeV. This work focuses on the error analysis of the designed 100 MeV linac in order to obtain the tolerance limit in the fabrication and alignment processes of the linac as well as to study the steering magnets which control the beam fluctuations and reduce the potential beam loss. |
|
|||||
TUPAN078 | Design and Fabrication of the PEFP DTL II | vacuum, proton, pick-up, alignment | 1553 | |||||
|
Funding: This work is supported by the 21C Frontier R&D program in the Ministry of Science and Technology of the Korean government |
The PEFP DTL II which accelerates a proton beam from the energy of 20MeV Beam to 100MeV is now under fabrication. The DTL II which has some similar specifications with the DTL I which accelerates the proton beam to the energy of 20MeV is made of seamless carbon steel with Cu electroplating inside. The DTL tank is divided into 3 sections whose length is about 2.2m. We verified the mechanical and thermal stability using ANSYS code, and we established the fabrication process of the drift tube. The DTL II is now being fabricated. |
|
|||||
TUPAN083 | Space-Charge Neutralization in Ion Undulator Linear Accelerator | ion, simulation, undulator, acceleration | 1565 | |||||
|
RF undulator accelerator (UNDULAC-RF) is suggested as an initial part of high intensity ion linac*. Such accelerator can be realized in periodical IH structure where a field has no spatial harmonics in synchronism with the beam. Ion beam is accelerated by the combined field of two non-synchronous harmonics. Accelerating force value is proportional to squared particle charge. Transmission coefficient and accelerating gradient for low velocity ions with the identical sign of charge are the same as in RFQ. The limit beam current can be larger in this type accelerator. Its value was calculated earlier in paper **. But the beam intensity can be substantially increased in UNDULAC by using space charge neutralization of positive and negative charged ions. In UNDULAC positive and negative ions can be accelerated simultaneously within the same bunch. The process of acceleration and focusing of oppositely charged ions with the identical charge-to-mass ratio is discussed in this paper.
|
* E. S. Masunov, Technical Physics, V. 46, 11, 2001, pp. 1433-1436.**E. S. Masunov, S. M. Polozov, NIM., A 558, 2006, pp. 184-187. |
|
|||||
TUPAN084 | Using Smooth Approximation for Beam Dynamics Investigation in Superconducting Linac | ion, acceleration, focusing, proton | 1568 | |||||
|
The superconducting linac consists of some different classes of the identical cavities. The each cavity based on a superconducting structure with a high accelerating gradient. The distance between the cavities is equal to acceleration structure period L. By specific phasing of the RF cavities one can provide a stable particle motion in the whole accelerator. The ion dynamics in such periodic structure is complicated. The reference particle coordinate and momentum can be represented as a sum of a smooth motion term and a fast oscillation term, a period of which is equal to L. Three dimensional equation of motion for ion beam in the Hamiltonian form is derived in the smooth approximation for superconducting linac. The longitudinal acceptance and maximum energy width in a bunch are found by means of the effective potential function. The general conditions applicability of a smooth approximation to given electrodynamic problem is formulated. The nonlinear ion beam dynamics is investigated in such accelerated structure.
|
|
|
|||||
TUPAN093 | Simulation of the CERN PS Booster Performance with 160 MeV H- Injection from Linac4 | injection, simulation, emittance, space-charge | 1595 | |||||
|
The ultimate luminosity (2.3 x 1034 cm-2 s-1) in the LHC can only be reached or even exceeded if a major upgrade of the CERN proton injector complex takes place. The first identified bottleneck towards higher brightness beams is the 50 MeV proton injection of Linac2 into the PS booster (PSB). Doubling the intensity in the PSB can be achieved with a new linac (Linac4) which increases the injection energy to 160 MeV. Linac4 will provide H- ions and charge-exchange injection will be used in the PSB instead of using the present multi-turn proton injection scheme. The code ACCSIM is used to study the H- injection process and to determine if the requested intensities can be reached within the specified emittance budgets. The results are then compared with ORBIT simulations. In the longitudinal plane we use ESME to study various capture schemes.
|
|
|
|||||
TUPAN109 | 160 MeV H- Injection into the CERN PSB | injection, dipole, septum, emittance | 1628 | |||||
|
The H- beam from the proposed LINAC4 will be injected into the four existing rings of the PS Booster at 160 MeV. A substantial upgrade of the injection region is required, including the modification of beam distribution system and the construction of a new H- injection system. This paper discusses beam dynamics and hardware requirements and presents the results of optimisation studies of the injection process for different beam characteristics and scenarios. The resulting conceptual design of the injection region is presented, together with the main hardware modifications and performance specifications.
|
|
|
|||||
TUPAN111 | Status Report on the RAL Front End Test Stand | rfq, ion, ion-source, emittance | 1634 | |||||
|
High power proton accelerators (HPPAs) with beam powers in the several megawatt range have many applications including drivers for spallation neutron sources, neutrino factories, waste transmuters and tritium production facilities. The UK's commitment to the development of the next generation of HPPAs is demonstrated by a test stand being constructed in collaboration between RAL, Imperial College London and the University of Warwick. The aim of the RAL Front End Test Stand is to demonstrate that chopped low energy beams of high quality can be produced and is intended to allow generic experiments exploring a variety of operational regimes. This paper describes the status of the RAL Front End Test Stand which consists of five main components: a 60 mA H- ion source, a low energy beam transport, a 324 MHz Radio Frequency Quadrupole accelerator, a high speed beam chopper and a comprehensive suite of diagnostics. The aim is to demonstrate production of a 60 mA, 2 ms, 50 pps, chopped H- beam at 3 MeV.
|
|
|
|||||
TUPAN112 | Slow-Wave Chopper Structures for Next Generation High Power Proton Drivers | proton, vacuum, coupling, beam-losses | 1637 | |||||
|
Funding: Work supported by CCLRC/RAL/ASTeC and the European Community Research Infrastructure Activity under the FP6 "Structuring the European Research Area" programme (CARE, contract No. RII3-CT-50295) |
A description is given of slow-wave chopper structures for the 3.0 MeV, 60 mA, H- MEBT lines of the CERN Linac 4 and RAL Front-End Test Stands (FETS). Transmission line properties and transverse E-field uniformity for the original European Spallation Source (ESS) designs* have been refined by modelling static, and time dependent electromagnetic fields in the 3D CST 'EM Studio', and 'Microwave Studio' codes**. In addition, the original compact, radiation hard, vacuum compatible designs have been simplified and reconfigured to be compatible with standard NC machining practice. Transmission line properties in the frequency and time domain, together with E-field uniformity in the axial and transverse planes, are presented.
* M. A. Clarke-Gayther, 'Slow-wave electrode structures for the ESS 2.5 MeV fast chopper', Proc. of the 2003 Particle Accelerator Conference (PAC), Portland, Oregon, USA, p. 1473-1475.** www.cst.com |
|
|||||
TUPAN114 | RF Design Options for a 180 MeV H- Linac for Megawatt Beam Facilities | proton, impedance, quadrupole, factory | 1643 | |||||
|
Future projects like a neutrino factory or an advanced spallation neutron source require high power proton accelerators capable of producing beams in the multi-MW range. The quality of the beam delivered to the target is very much dictated by the accelerator front end and by the lower energy linac. Prompted by the Front End Test Stand (FETS) under construction at RAL, a new 180 MeV H- linac is being considered as a possible replacement for the aging current 70 MeV ISIS injector, and the same linac has also been included in designs for the proton driver for a possible UK Neutrino Factory. In this paper, different RF design options are analysed and a general layout for the new linac is presented based on two accelerating structures to raise the beam energy from 3 to 180 MeV: a 324 MHz Drift Tube Linac (DTL) making use of commercial Toshiba klystrons, followed by Side Coupled Linac (SCL) with a triple frequency jump at the transition between the two structures.
|
|
|
|||||
TUPAN115 | Comparative Study of Beam Dynamics in LINAC4 using CERN and RAL MEBT (Medium Energy Beam Transport) Lines | emittance, quadrupole, simulation, beam-transport | 1646 | |||||
|
Funding: We acknowledge the support of the European Community-Research Infrastructure Activity under the FP6 "Structuring the European Research Area" program (CARE, Contract No. RII3-CT-2003-506395). |
CERN and RAL are working in parallel to develop Front Ends for future particle accelerators. At CERN the Front End will be part of LINAC4, a potential replacement for the Linac2 accelerator, whilst at RAL the Front End is intended to demonstrate that a high current, high quality chopped beam is achievable and that the design could be used as part of a Proton Driver for a future Neutrino Factory. The two Front End designs have many similarities and basically consist of four main components: an H- ion source, a Low Energy Beam Transport (LEBT) matching into a Radio-Frequency Quadrupole (RFQ) and a Medium Energy Beam Transport (MEBT) line with a fast beam chopper. The beam choppers are different in the two designs and it is important to compare the effectiveness of the two methods of operation. This paper describes a simulation study of high intensity beam dynamics and beam transport when the RAL and CERN MEBT designs are each fed into the same CERN structure for LINAC4. |
|
|||||
TUPAS004 | A Driver LINAC for the Advanced Exotic Beam Laboratory: Physics Design and Beam Dynamics Simulations | simulation, beam-losses, emittance, lattice | 1661 | |||||
|
Funding: This work was supported by the U. S. Department of Energy, Office of Nuclear Physics, under Contract No. DE-AC-02-06CH11357 |
The Advanced Exotic Beam Laboratory (AEBL) being developed at ANL consists of an 833 MV heavy-ion driver linac capable of producing uranium ions up to 200 MeV/u and protons to 580 MeV with 400 kW beam power. We have designed all accelerator components including a two charge state LEBT, an RFQ, a MEBT, a superconducting linac, a stripper section and beam switchyard. We present the results of an optimized linac design and end-to-end simulations which include possible machine errors. |
|
|||||
TUPAS005 | Accelerators for the Advanced Exotic Beam Facility in the U. S. | ion, target, heavy-ion, acceleration | 1664 | |||||
|
Funding: This work was supported by the U. S. Department of Energy, Office of Nuclear Physics, under Contract No. DE-AC-02-06CH11357 |
The Office of Science of the Department of Energy is currently considering options for an advanced radioactive beam facility in the U. S. The U. S. facility will complement capabilities both existing and planned elsewhere. As envisioned at ANL, the facility, called the Advanced Exotic Beam Laboratory (AEBL), would consist of a heavy-ion driver linac, a post-accelerator and experimental areas. The proposed design of the AEBL driver linac is a cw, fully superconducting, 833 MV linac capable of accelerating uranium ions up to 200 MeV/u and protons to 580 MeV with 400 kW beam power. An extensive research and development effort has resolved many technical issues related to the construction of the driver linac and other systems required for AEBL. This paper presents the status of planning, some options for such a facility, as well as, progress in related R&D. |
|
|||||
TUPAS018 | A Conceptual Design of an Internal Injection Absorber of 8 GeV H- Injection into the Fermilab Main Injector | injection, proton, dipole, simulation | 1694 | |||||
|
Funding: Work supported by Universities Research Association, Inc. under contract No. DE-AC02-76CH03000 with the U. S. Dept. of Energy. |
A 8 GeV H- superconducting linac has been proposed as an alternative injector for the Main Injector to support a 2 MW Neutrino program. An injection absorber is required to accept protons generated after the secondary stripping foil which will intercept the un-stripped H- and H0 particles after the MI primary foil injection point. The motivations underlying the choice of a compact internal absorber over an external absorber will be discussed. We show that using a high-Z material (tungsten) for the inner shielding allows the construction a compact absorber that can take a very intense beam and fits within the existing enclosure. The absorber requirements and a shielding design and the results of energy deposition calculations are presented. |
|
|||||
TUPAS020 | An 8 GeV H- Multi-turn Injection System for the Fermilab Main Injector | injection, simulation, proton, dipole | 1700 | |||||
|
Funding: Work supported by Universities Research Association, Inc. under contract No. DE-AC02-76CH03000 with the U. S. Dept. of Energy. |
The technique for H- charge exchange for multi-turn injection utilizing stripping foils in the energy range of a few hundred MeV has been used at many labs for decades and most recently up to 1 GeV at the SNS. Utilization the beam from the proposed Proton Driver* would permit the extension of this technique up to 8 GeV. The injection layout and required accelerator modifications are discussed. Results from transverse and longitudinal simulations are presented.
* W. G. Foster and J. A. MacLachlan, "A Multi-mission 8 GeV Injector Linac as a Fermilab Booster Replacement", Proc. Of LINAC-2002, Gyeongju, Korea, p.86. |
|
|||||
TUPAS041 | Injection Parameters Optimization for the Fermilab Booster | injection, space-charge, booster, beam-losses | 1736 | |||||
|
The maximal capacitance for the Booster to deliver the 8-GeV beam to downstream accelerators is limited by the beam loss. Most of losses happen at injection due to space charge effect being the strongest at the injection energy. Optimizing the RF voltage ramp in the presence of the space charge effect to capture more beam and simultaneously keep small beam emittance has been numerically investigated using 3-D STRUCT code. The results of simulations agree well with the measurements in the machine. Possibilities, such as beam painting and using the second rf harmonic at injection, for further reductions of beam loss in order to reach the maximum beam intensity delivered from the Booster have been investigated.
|
|
|
|||||
TUPAS053 | Beam Dynamics Studies for the Reacceleration of Low Energy RIBs at the NSCL | rfq, emittance, simulation, target | 1769 | |||||
|
Funding: This work is supported by the U. S. Department of Energy |
Rare Isotope Beams (RIBs) are created at the National Superconducting Cyclotron Laboratory (NSCL) by the in-flight particle fragmentation method. A novel system is proposed to stop the RIBS in a helium filled gas system followed by reacceleration that will provide opportunities for an experimental program ranging from low-energy Coulomb excitation to transfer reaction studies of astrophysical reactions. The beam from the gas stopper will first be brought into a Electron Beam Ion Trap (EBIT) charge breeder on a high voltage platform to increase its charge state and then accelerated initially up to about 3 MeV/u by a system consisting of an external multi-harmonic buncher and a radio frequency quadrupole (RFQ) followed a superconducting linac. The superconducting linac will use quarter-wave resonators with bopt of 0.047 and 0.085 for acceleration and superconducting solenoid magnets for transverse focusing. The paper will discuss the accelerator system design and present the end-to-end beam dynamics simulations. |
|
|||||
TUPAS054 | Design Studies of the Reaccelerator RFQ at NSCL | rfq, emittance, focusing, quadrupole | 1772 | |||||
|
Rare Isotope Beams (RIBs) are created at the National Superconducting Cyclotron Laboratory (NSCL) by the in-flight particle fragmentation method. A novel system is proposed to stop the RIBS in a helium filled gas system followed by a reacceleration that will provide opportunities for an experimental program ranging from low-energy Coulomb excitation and to transfer reaction studies of astrophysical reactions. The beam from the gas stopper will first be brought into a Electron Beam Ion Trap (EBIT) charge breeder on a high voltage platform to increase its charge state and then accelerated initially up to about 3 MeV/u by a system consisting of an external multi-harmonic buncher and a Radio Frequency Quadrupole (RFQ) followed a superconducting linac. The planned RFQ will operate in the cw mode at a frequency of 80.5MHz to accelerate ion beams from ~12 keV/u to ≥ 300keV/u. An external multi-harmonic buncher will be used to produce a small longitudinal emittance beam out of the RFQ. In this paper, we will describe the design of the RFQ, present the beam dynamics simulation results, and also discuss the impact of the external buncher harmonics on the output beam properties.
|
|
|
|||||
TUPAS055 | End-to-End Beam Dynamics Simulations of the ISF Driver Linac | simulation, emittance, ion, alignment | 1775 | |||||
|
A proposed Isotope Science Facility (ISF), a major upgrade from the Coupled Cyclotron Facility at the National Superconducting Cyclotron Laboratory (NSCL), will provide the nuclear science community with world-class beams of rare isotopes. The ISF driver linac will consist of a front-end and three acceleration segments of superconducting cavities separated by two charge-stripping sections, and will be capable of delivering primary beams ranging from protons to uranium with variable energies of ≥200 MeV/nucleon. The results of end-to-end beam simulation studies including physical misalignments, dynamic rf amplitude and phase errors, and variations in the stripping foil thickness, will be performed to evaluate the driver linac overall performances and beam loss, even for the challenging case of the uranium beam with multiple charge states using the newly-developed RIAPMTQ/IMPACT codes. The paper will discuss ISF beam dynamics issues and present the end-to-end beam simulation results.
|
|
|
|||||
TUPAS062 | The LANSCE Refurbishment (LANSCE-R) Project | proton, controls, target, klystron | 1796 | |||||
|
Funding: Work performed under the auspices of the U. S. Department of Energy |
At the core of the Los Alamos Neutron Science Center (LANSCE) accelerator lies an 800-MeV proton linac that drives user facilities for isotope production, proton radiography, ultra-cold neutrons, weapons neutron research and for various sciences using neutron scattering. LANSCE is in the planning phase of a refurbishment project that will sustain reliable facility operations well into the next decade. The general goals for LANSCE-R are to (1) preserve dependable operation of the linac and (2) increase the cost effectiveness of operations. Requirements can be met for overall beam intensity, availability, and reliability with long-term sustainability and minimal disruption to scheduled user programs. The baseline refurbishment project consists of replacing the 201 MHz RF systems, upgrading a substantial fraction of the 805 MHz RF systems, updating the control system, and replacing or improving a variety of diagnostics and accelerator subsystems. The plans for the various LANSCE-R improvements will be presented and the preliminary cost and schedule estimates will be discussed. |
|
|||||
TUPAS063 | A New Bunching Scheme for Increasing the LANSCE WNR Peak Beam Current | simulation, ion, ion-source, bunching | 1799 | |||||
|
Funding: This work is supported by the U. S. Department of Energy, Contract DE-AC52-06NA25396. |
The LANSCE linac simultaneously provides both H+ and H- beams to several user facilities. The Weapons Neutron Research (WNR) user facility is configured to accept the H- beam with a typical pulse pattern of one linac micro-pulse every 1.8 microseconds. To produce this pulse spacing a slow-wave chopper located in the 750 keV injector beam transport is employed to intensity modulate the beam. The beam is subsequently bunched at both 16.77 MHz and 201.25 MHz prior to entering the 100 MeV drift tube linac. One downside of the chopping process is that the majority of the beam produced by the ion source during the WNR macro-pulses is discarded. By applying a longitudinal bunching action immediately following the ion source, simulations have shown that some of this discarded beam can be used to increase the charge in these micro-pulses. Recently, we began an effort to develop this buncher by superimposing 16.77 MHz RF voltage on one of the HVDC electrodes in the 80 kV column located inside H- Cockcroft-Walton dome. This paper describes the beam dynamics simulations, design and implementation of the rf hardware and the results of tests performed with the system. |
|
|||||
TUPAS073 | New Design of the SNS MEBT Chopper Deflector | power-supply, beam-transport, extraction, target | 1817 | |||||
|
Funding: SNS is managed by UT-Battelle, LLC, under contract DE-AC05-00OR22725 for the U. S. Department of Energy. |
The chopper system for the Spallation Neutron Source (SNS) provides a gap in the beam for clean extraction from the accumulator ring. It consists of a pre-chopper in the low energy beam transport and a faster chopper in the medium energy beam transport (MEBT). The original "meander line" design of the MEBT chopper deflector was successfully tested with low power beam during the SNS linac commissioning but turned out to be unsuitable for high power beam operation due to poor cooling of the copper strip line through the dielectric substrate. We developed a new deflecting structure, with higher deflection efficiency and with rise and fall time easily customizable to match the available high voltage pulse generator. In this paper we describe design, implementation and beam tests results of the new MEBT chopper deflector. |
|
|||||
TUPAS074 | Performance of the SNS Front End and Linac | beam-losses, quadrupole, radiation, target | 1820 | |||||
|
Funding: SNS is managed by UT-Battelle, LLC, under contract DE-AC05-00OR22725 for the U. S. Department of Energy. |
The Spallation Neutron Source accelerator systems will deliver a 1.0 GeV, 1.4 MW proton beam to a liquid mercury target for neutron scattering research. The accelerator complex consists of an H- injector, capable of producing one-ms-long pulses at 60 Hz repetition rate with 38 mA peak current, a 1 GeV linear accelerator, an accumulator ring and associated transport lines. The 2.5 MeV beam from the Front End is accelerated to 86 MeV in the Drift Tube Linac, then to 185 MeV in a Coupled-Cavity Linac and finally to 1 GeV in the Superconducting Linac. With the completion of beam commissioning, the accelerator complex began operation in June 2006 and beam power is being gradually ramped up toward the design goal. Operational experience with the injector and linac will be presented including chopper performance, transverse emittance evolution along the linac, and the results of a beam loss study. |
|
|||||
TUPAS081 | A 25-keV, 30-milliamp Hydrogen-ion Injector for a 200-MHz, 750-keV Radio Frequency Quadrupole (RFQ) | rfq, proton, plasma, ion | 1838 | |||||
|
A four-bar, 200-MHz, 750-keV RFQ is being developed by Linac Systems. The RFQ design requires injection of a 25-keV, approximate 25-mA proton beam to produce a 20-mA 750-keV output beam bunched at 200 MHz. The injector is comprised of a microwave proton source and single einzel lens low-energy beam transport (LEBT) system. For an ideally matched injector beam, the RFQ design predicts > 90% beam transmission. Such a transmission has not yet been measured in the laboratory using a microwave proton source and a single einzel lens LEBT. PBGUNS* simulations are being performed to elucidate the injector performance. Model assumptions and various designs will be presented. Predicted injector phase-space distributions at the RFQ match point will be compared to the RFQ acceptance parameters. *Steve Bell, Thunderbird Simulations, www.thunderbirdsimulations.com.
|
|
|
|||||
WEXKI03 | Survey of Advanced Dielectric Wakefield Accelerators | electron, acceleration, gun, simulation | 1899 | |||||
|
Funding: Work supported by the US Department of Energy under contract # DE-AC02-06CH11357. |
There has been continued interest in the development of dielectric-loaded wakefield structures that can be used to accelerate particle beams. The present search for materials able to withstand very intense RF fields has renewed this interest. Recent experiments at the Argonne Wakefield Accelerator have generated short RF pulses with accelerating fields in excess of 80 MV/m. These experiments used ceramic-lined cylindrical waveguides, operating at frequencies between 10 and 15 GHz. Other important experiments, at different RF frequencies and using planar or cylindrical geometries, have been carried out at various other facilities. A number of new experiments are planned in the near future to explore the capabilities of this class of structures. This presentation will provide an up-to-date survey of the activities in this area of research. |
|
Slides
|
|
|
||
WEOAAB02 | The Optimized Bunch Compressor for the International Linear Collider | wiggler, damping, emittance, linear-collider | 1958 | |||||
|
The International Linear Collider (ILC) utilizes a two stage Bunch Compressor (BC) that compresses the RMS bunch length from 9 mm to 200 to 300 micrometers before sending the electron beam to the Main Linac. This paper reports on the new design of the optimized BC wiggler. It was reduced in length by more than 30 %. The introduction of nonzero dispersion slope in the BC wigglers enabled them to generate the required compression while having a small SR emittance growth, a tunability range of over a factor of 2 in each wiggler, and less than 3 % RMS energy spread throughout the entire system.
|
|
|
Slides
|
|
|
||
WEYAB01 | Overview of Industrialization Strategies for ILC | linear-collider, superconducting-RF, collider, electron | 1961 | |||||
|
ILC is by far the largest and most challenging application of superconducting RF accelerator technology. Starting from the experience with TESLA and XFEL I will describe the level of industrial competence in the three global regions (Asia, America and Europe). In particular I will refer to the state of the art of cavity fabrication, module assembly and auxiliary components as well as to the synergy with the XFEL project. I will use the fabrication experience with SC magnets for LHC at CERN as benchmark for industrialization strategies for ILC.
|
|
|
|||||
WEYAB02 | Availability and Reliability Issues for ILC | simulation, power-supply, luminosity, klystron | 1966 | |||||
|
Funding: Work supported by the U. S. Department of Energy under contract number DE-AC03-76SF00515. |
The International Linear Collider will be the largest most complicated accelerator ever built. For this reason extensive work is being done early in the design phase to ensure that it will be reliable enough. This includes gathering failure mode data from existing accelerators and simulating the failures and repair times of the ILC. This simulation has been written in a general fashion using MATLAB and could be used for other accelerators. Results from the simulation tool have been used in making some of the major ILC design decisions and an unavailability budget has been developed. |
|
Slides
|
|
|
||
WEOBAB02 | Studies of Emittance Bumps and Adaptive Alignment method for ILC Main Linac | emittance, alignment, feedback, linear-collider | 1973 | |||||
|
Funding: U. S. Department of Energy |
International Linear Collider (ILC) is a proposed electron-positron accelerator requiring very small spot-size at the interaction point, and thus necessitates very tight tolerances on beamline elements. For static tuning of the machine a few methods like dispersion-free steering (DFS) or kick minimization (KM) techniques was proposed. The further suppression of emittance growth can be achieved by using close orbit emittance bumps. Stability of ILC is determined by the stability of the site, additional noises of beamline component, energy and kicker jitter and performance of the train-to-train and intra-train feedback. We discuss the performances of the Adaptive Alignment technique, which keeps accelerator dynamically aligned in presence of ground motion an technical noises. This presentation is an overview of two posters THPMN107 and THPMN108, presented at PAC07. |
|
Slides
|
|
|
||
WEZAB02 | Results on CLIC Proof of Principle from CTF3 | collider, extraction, injection, beam-loading | 1979 | |||||
|
The CLIC Test Facility CTF3, built at CERN by an international collaboration, aims at demonstrating the feasibility of the CLIC scheme of Multi-TeV electron-positron collider by 2010. In its final configuration CTF3 will consist of a 150 MeV drive beam linac followed by a 42 m long delay loop and an 84 m combiner ring. The installation includes a two-beam test stand and a test decelerator. The linac and delay loop have been already commissioned, while the combiner ring will be completed by the first half of 2007. High gradient testing of accelerating structures is also under way. The status of the facility, the experimental results obtained and the future plans will be presented.
|
|
|
Slides
|
|
|
||
WEZAB03 | Main Linac Issues and Evolving Test Facilities | 1984 | ||||||
|
This talk will focus on ILC Main Linac issues and how they can be addressed via various existing test facilities or by those planned or under construciton. The talk will focus on ILC main linac component test facilities in the U. S. Facilities described will include Vertical test setups to test bare SCRF cavities to demonstrate maximum achievable accelerating gradient. Horzontal testing of cavities equipped with tuners and couplers and the ILC RF unit test facility at Fermilab. Test facilities existing or under construction at DESY and KEK will also be described for context.
|
|
|
Slides
|
|
|
||
WEOCAB01 | Design of the Beam Delivery System for the International Linear Collider | collimation, extraction, diagnostics, betatron | 1985 | |||||
|
The beam delivery system for the linear collider focuses beams to nanometer sizes at the interaction point, collimates the beam halo to provide acceptable background in the detector and has a provision for state-of-the art beam instrumentation in order to reach the physics goals. The beam delivery system of the International Linear Collider has undergone several configuration changes recently. This paper describes the design details and status of the baseline configuration considered for the reference design.
|
|
|
Slides
|
|
|
||
WEOCC03 | Halo Estimates and Simulations for Linear Colliders | scattering, simulation, electron, photon | 2041 | |||||
|
Funding: This work is supported by the Commission of the European Communities under the 6th Framework Programme "Structuring the European Research Area", contract number RIDS-011899. |
Halo simulations and estimates are important for the design of future linear accelerators. We present simulations performed for the ILC and CLIC and compare these with semi-analytical estimates and other simulations. |
|
Slides
|
|
|
||
WEPMN002 | Tuner Control in TRIUMF ISAC 2 Superconducting RF System | feedback, controls, coupling, superconducting-RF | 2047 | |||||
|
The TRIUMF ISAC 2 superconducting RF system operates on self-excited, phase locking mode. A mechanical tuner is used to minimize the required RF power. The tuner derives the tuning information from the phase shift around the self-excited loop. Its accuracy is however reduced by phase drift in the amplifier due to thermal effects. Cross correlation between the In-phase and the Quadrature-phase errors is used to detect this drift. A Kalman filter is used to combine these information to control the movement of the tuner.
|
|
|
|||||
WEPMN006 | Status of the Superconducting CH-structure | cryogenics, simulation, proton, site | 2056 | |||||
|
Funding: GSI, BMBF 06F134I, EU 516520-FI6W, RII-CT-2003-506395, EFDA/99-507ERB5005-CT990061 |
The superconducting CH-structure is the first multi-cell cavity for the acceleration of low and medium energy ions and protons. A superconducting prototype cavity has been built and several cold tests have been performed at the IAP in Frankfurt. After the detection of a field emission centre the cavity will be treated by buffered chemical polishing and high pressure rinsing. Additionally the cavity is being prepared for tests in a horizontal cryostat with slow and fast tuner system. We present the status of these developments and the test results which have been gained recently. |
|
|||||
WEPMN009 | Vibration Stability Studies of a Superconducting Accelerating Module Quadrupole Operating at 4.5K | quadrupole, cryogenics, vacuum, damping | 2065 | |||||
|
Funding: Work supported by the Commission of the European Communities under the 6th Framework Program Structuring the European Research Area, contract number RIDS-011899. |
The European X-ray Free Electron Laser (XFEL) and the International Linear Collider (ILC) superconducting accelerating modules, containing a string of Niobium (Nb) cavities and a quadrupole, will operate at 2K. In this paper, we will report on the vibration stability studies of a high gradient XFEL/ILC type III superconducting accelerating module quadrupole operating at 4.5K. Measurements are performed via geophones affixed on the cold mass in both horizontal and vertical directions. This data will be compared with piezoelectric accelerometers for the same module. The goal is to study the stability of the cold quadrupole and to compare the results with room temperature conditions. |
|
|||||
WEPMN010 | Linearization of Downconversion for IQ Detection Purposes | controls, radio-frequency, simulation | 2068 | |||||
|
Funding: We acknowledge the support of the European Community-Research Infrastructure Activity under the FP6 ''Structuring the European Research Area'' program (CARE, contract number RII3-CT-2003-506395). |
Measurements of effective Radio Frequency (RF) field parameters (amplitude and phase) are tasks of great importance in high-energy accelerators*. The RF signal is downconverted in frequency to intermediate frequency (IF) but keeping the information about amplitude and phase. The IF signal is then sampled in ADC and processed in digital IQ detector computing the I and Q components**. The downconverter is a nonlinear device thus not only the fundamental frequency but also its harmonics are present and sampled by ADC. For a typical downconverter (used in FLASH LLRF system) the higher order harmonics levels depend on RF signal level and are about 40dBm lower than the fundamental frequency component. These harmonics can produce errors in IQ detector of up to few percent in amplitude and few degree in phase. These errors depends not only on nonlinearity of downconverter but also on the IQ detection scheme*** (IF and sampling rate SR). The paper presents the optimization of the IQ detection scheme (choosing the IF and SR) taking into account the nonlinear characteristics of the downconverter.
*Grelick A. et all:A High-Resolution , Proc. LINAC 2004,715-718**Grecki M. et all:Estimation of IQ , Proc. MIXDES 2005,783-788***Simrock S. et all:Considerations , Proc. EPAC 2006,1462-1464 |
|
|||||
WEPMN013 | Testing of 10 MW Multibeam Klystrons for the European X-ray FEL at DESY | klystron, power-supply, gun, cathode | 2077 | |||||
|
For the European XFEL project multibeam klystrons, which can produce RF power of 10 MW, at an RF frequency of 1.3 GHz, 1.5ms pulse length and 10Hz repetition rate, were chosen as RF power sources. So far three companies have produced this kind of new klystron. At DESY we installed a new test stand dedicated for testing this new type of RF power source. So far we have tested several tubes from Thales, Toshiba and CPI in our test stand. In this paper we give an overview of the test facilities and we summarize the current test results of the L-band multibeam klystrons (MBK).
|
|
|
|||||
WEPMN017 | RF System for the Elettra New Full Energy Booster Injector | booster, storage-ring, synchrotron, extraction | 2083 | |||||
|
The Elettra new full energy injector will be based on a 100 MeV linac and a 2.5 GeV booster synchrotron and it will replace the existing 1.2 linac injector. This paper presents the design, construction and the test results of the RF system for the booster synchrotron. The analysis of the foreseen operating scenario is also described. The system must be as simple and reliable as possible, taking into consideration the high availability required for the possible top-up mode of operation. It has also to be consistent with the other upgrades of the facility, as the upgrade of the storage ring RF system. The booster RF system will use a 500 MHz 5-cell copper cavity powered by a 60 kW klystron based power plant. The low level electronics has been in-house developed, starting from the system in operation in the storage ring, increasing the performances and developing the new features required by the use of a five-cell cavity, instead of a single cell one, and by the ramped operation. The commissioning of the new injector is scheduled to start in summer 2007, while the first Elettra operation for users with the new full energy injector is expected for the first quarter of 2008.
|
|
|
|||||
WEPMN018 | High Precision Measurements of Linac Coupled Cells | coupling, booster, proton | 2086 | |||||
|
Funding: Istituto Nazionale di Fisica Nucleare, Rome, Italy. Italian Ministry of Research. |
For an assembled structure (module, tank) of a Linac, the single cells, when coupled, loose their individuality and in cooperation contribute to the generation of the structure modes (resonant frequencies) Fm. On the other end these modes are the only measurable quantities. The system of the coupled cells can be modelled, in a narrow frequency band, as a lumped constant circuit. The modes are solution of an equation obtained equating to zero the determinant relevant to the lumped circuit. This is an algebraic equation of the same order as the number N of cells. A plausible question can be posed: is it possible from a manipulation of the measurable quantities (Fm) to draw the lumped circuit parameters, namely coupling constants and single cell resonant frequencies? The answer is positive if a certain degree of symmetry is satisfied. The coefficients of above mentioned equation can be easily related to the measured modes Fm. By varying, by means of tuners, the tune of a single cell of a small unknown amount, any couple of equation coefficient moves on a straight line. Therefore, we have N(N-1) known straight line coefficients which may give the unknowns with extremely high accuracy. |
|
|||||
WEPMN020 | Improved Design of the ILC Blade-Tuner for Large Scale Production | simulation | 2089 | |||||
|
The ILC superconducting linacs ask for the use of a compact and cost effective tuner design with no interference with the cavity end group area. The integration of the piezo-assisted fast tuning option made the Blade-Tuner, successfully tested at DESY on the superstructures, the most viable candidate to be included into the ILC BCD. In the perspective of large scale production and on the basis of the experience acquired so far, two alternative prototypes have been recently designed and built. They mainly differ for the materials adopted (titanium or stainless steel) and have been optimized to minimize material and construction cost, while fulfilling the reviewed performances required for the high gradient cavity operation up to 35 MV/m or even higher. In this paper we discuss the rationales that brought us to the current solutions, together with a critical comparison of the two systems behavior and cost.
|
|
|
|||||
WEPMN022 | High Gradient Tests of C-band Accelerating System for Japanese XFEL Project | klystron, power-supply, vacuum, collider | 2095 | |||||
|
The C-band (5712 MHz) choke-mode type accelerating structure will be used for SCSS. Since the C-band accelerator generates higher accelerating gradient than traditional S-band accelerator, it makes the machine size compact and the cost low. In order to confirm the performance of the C-band accelerating system for the 8 GeV XFEL machine, the system including the same accelerating structure and RF system have been installed in the SCSS prototype accelerator. In the prototype machine, four 1.8 m long C-band accelerating structures are used to accelerate electron up to 250 MeV. From November 2005, we have operated the C-band accelerator in the prototype machine with no serious problem. After the RF conditioning, accelerating gradient up to 35 MV/m was achieved. Since a lot of C-band accelerator units, about 70 klystrons and 130 accelerating structures, will be used for 8 GeV XFEL machine, it is necessary to investigate the damage due to the beam operation. Therefore, we plan to observe the inside of the accelerating structure and pulse compressor in early 2007. In this paper, we will report on the achieved performance and the inside observation of the C-band accelerator.
|
|
|
|||||
WEPMN024 | RF Feedback Control Systems of the J-PARC Linac | feedback, controls, beam-loading, proton | 2101 | |||||
|
The commissioning of the J-PARC 181MeV proton linac was started from October of 2006. The RF sources of the linac consist of 4 solid-state amplifiers and 20 klystrons. In each RF source, the RF fields are controlled by a digital RF feedback system installed in a compact PCI (cPCI) to realize the accelerating field stability of ±1% in amplitude and ±1 degree in phase. In this paper the performance of the RF feedback control systems will be reported in detail.
|
|
|
|||||
WEPMN026 | Test Operation of Ball-Screw-Type Tuner for Low-Loss High-Gradient Superconducting Cavity in a Cryomodule | resonance, controls, damping, linear-collider | 2104 | |||||
|
We are constructing a Superconducting RF Test Facility (STF) at KEK as an R&D for ILC accelerator. In STF, four Low-Loss (LL) type 9-cell cavities will be installed into a cryomodule. We are developing ball-screw-type tuner for these cavities aiming at the accelerating gradient of 45 MV/m. At the end of 2006, we installed one LL 9-cell cavity dressed with the ball-screw tuner into the cryomodule. It will be operated without beam in 2007. This paper describes the results of the first operation of the ball-screw tuner for LL 9-cell cavity in the cryomodule of STF.
|
|
|
|||||
WEPMN029 | Status of the Low-Level RF System at KEK-STF | feedback, controls, linear-collider, klystron | 2113 | |||||
|
RF field stabilities of less than 0.3%, 0.3deg. are required at STF llrf system. In order to satisfy these requirements, digital FB system using a FPGA is adopted. The FB system consists of a FPGA (VirtexIIPro30) with ten 16-bit ADCs and two 14-bit DACs. The rf (1.3 GHz) probe signals are downconverted to the IF (10 MHz) and directly acquired at ADCs. Total 8 cavities will be installed at STF-Phase 1 in 2007 and vector sum control of 8 cavity signals will be carried out. The performance of the FB system is examined with electric cavity simulators prior to the rf operation.
|
|
|
|||||
WEPMN036 | High Field Performance in Reduced Cross-sectional X-Band Waveguides Made of Different Materials | laser, simulation, acceleration | 2119 | |||||
|
To study the characteristics of different materials on high-field rf breakdown we designed a simplified waveguide, where the field of 200MV/m is realized at rf power of 100MW. The geometry is transformed from the WR90, where the height and the width are reduced from 10.16 mm to 1mm and from 22.86mm to 14mm, respectively. This paper reports on the high-gradient testing of copper and stainless-steel waveguides. We have observed rf breakdowns by bursts of x-rays, flashes of visible lights and acoustic signals. Frequent breakdowns are observed at about 100MV/m level in copper case and the study on the stainless-steel waveguide will be performed to be compared to that of copper case.
|
|
|
|||||
WEPMN038 | Development of the Beam Chopper Timing System for Multi-Turn Injection to the J-PARC RCS | injection, controls, extraction, synchrotron | 2125 | |||||
|
Multi-turn injection using charge exchange is employed for the J-PARC Rapid Cycling Synchrotron (RCS). To improve the bunching factor of the beam in the ring, the momentum offset injection scheme is used. In each turn, the bunch trains from the linac are injected into the RF buckets with a momentum offset. The bunch train is called the "intermediate pulse". The intermediate pulses are generated in the low energy section of the linac by the RF chopper and pre-chopper. Since the pulse must be synchronized to the RF voltage in the ring, the timing signals for the choppers are generated by the low-level RF (LLRF) system of the RCS and the signals are sent to the chopper control. The RF chopper and the pre-choppers require different pulse widths. Thanks to the direct digital synthesis (DDS) in the LLRF system, precise zero-cross signals for the reference of the chopper pulses are generated without difficulties. The cable route from the RCS LLRF system to the linac chopper control system is more than one kilometer. Thus, the chopper pulses are sent via optical cables. We developed the chopper timing module. We describe the details of the hardware and the preliminary test results.
|
|
|
|||||
WEPMN039 | Performance of J-PARC Linac RF System | controls, klystron, feedback, beam-loading | 2128 | |||||
|
High power operation of all the RF systems of J-PARC linac was started for the cavity conditioning in October 2006. Twenty 324-MHz klystrons have powered the accelerating cavities successfully, and the beam commissioning was started in November 2006. The performance of the RF drive and control system will be presented.
|
|
|
|||||
WEPMN041 | Reduction of RF Skin Loss with Thin Foils | impedance, resonance, electromagnetic-fields, controls | 2134 | |||||
|
Reduction of RF power loss caused by skin effect has been studied. Some measurement results on a coaxial cavity with thin foils are described. Application to another type of RF devices will be discussed.
|
|
|
|||||
WEPMN043 | The Modulator Stability System for the BEPCII Klystron | klystron, feedback, target, controls | 2137 | |||||
|
The stability of the modulator high voltage output pulse is the important target for the klystron. The stability of the BEPCII modulator is demanded less than 0.15%. To achieve this target, we use thyristor voltage regulator having feedback function to stabilize the DC high voltage of the modulator and the De-Qing circuit to stabilize the charging voltage. This paper describe the modulator stability system and the stabilization measurement .
|
|
|
|||||
WEPMN055 | PEFP HOM Coupler Design | damping, simulation, controls, coupling | 2161 | |||||
|
Funding: This work was supported by the 21C Frontier R&D program of Korea Ministry of Science and Technology. |
A new type of coaxial higher-order mode (HOM) coupler with one hook and two stubs has been designed for PEFP SRF cavities to satisfy the HOM damping requirements of the superconducting RF (SRF) linac of the Proton Engineering Frontier Project (PEFP), and to overcome the notch frequency shift and feed-through tip melting issues. This paper has presents details on the PEFP HOM coupler?s structure, structure optimization, filter characteristics, electro-magnetic field distribution and a coupler installation tool. |
|
|||||
WEPMN056 | PEFP Low-beta SRF Cavity Design | electron, coupling, simulation, proton | 2164 | |||||
|
Funding: This work was supported by the 21C Frontier R&D program of Korea Ministry of Science and Technology. |
An elliptical superconducting RF cavity of 700 MHz with βg=0.42 has been designed for the Linac of Proton Engineering Frontier Project (PEFP). A double-ring stiffening structure is used for a low-beta cavity for a Lorentz force detuning. The results of the electron multipacting analysis of the cavity are presented. A HOM analysis shows that the HOM coupler's Qext is lower than 3·10+5, thus reducing the influence of dangerous modes on the beam instabilities and the HOM-induced power. |
|
|||||
WEPMN060 | Fabrication of ICHIRO Nine-cell Cavities in PAL for STF of KEK | electron, superconductivity, focusing, cryogenics | 2173 | |||||
|
Funding: Korea Ministry of Science & Technology |
Pohang Accelerator Laboratory has studied SRF cavity and set up SRF test laboratory from January 2006. The first activity for SRF research was to develop SRF 3rd harmonic cavity for Pohang Light Source, which was designed, fabricated and tested in 2006. The cryostat are under design. The fabrication of ICHIRO cavity, which is ILC ACD cavity, is PAL's second activity related to SRF. Deep drawing, trimming and welding by electron beam for a 9-cell ICHIRO cavity were done in PAL. The polishing processes for the RF surface including electropolishing were done in KEK under the collaboration between two institutes. This will be tested with real beam in STF-1 of KEK in second half period of 2007. This paper reports the results of fabrication of ICHIRO single- and nine-cell cavities performed in PAL. |
|
|||||
WEPMN061 | Design of Cooling System for Resonance Control of the PEFP DTL | controls, resonance, proton, simulation | 2176 | |||||
|
Funding: Supported by the 21st PEFP (KAERI) and MOST in Korea |
The temperature-controlled cooling water system was designed to obtain the resonance frequency stabilization of the normal conducting drift tube linac (DTL) for the PEFP 100 MeV proton accelerator. The primary sizing of individual closed-loop low conductivity cooling water pumping skids for each DTL system was conducted with a simulation of thermo-hydraulic network model. The temperature control schemes incorporating the process dynamic model of heat exchangers were examined to regulate the input water temperatures into the DTL during the steady state operation. The closed water circuits to achieve system performance and stability for low and full duty operation modes were discussed, and numerical results were also presented. |
|
|||||
WEPMN066 | Progress Towards Development of a Superconducting Traveling Wave Accelerating Structure | feedback, acceleration, coupling, collider | 2182 | |||||
|
In the ILC project the required accelerating gradient is higher than 35 MeV/m. For current technology the maximum acceleration gradient in SC structures is limited mainly by the value of the surface RF magnetic field. In order to increase the gradient, the RF magnetic field is distributed homogeneously over the cavity surface (low-loss structure), and coupling to the beam is improved by introducing aperture ?noses? (re-entrant structure). These features allow gradients in excess of 50 MeV/m to be obtained for a singe-cell cavity. Further improvement of the coupling to the beam may be achieved by using a TW SC structure with small phase advance per cell. Calculations show that an additional gradient increase by up to 40% is possible if a p/2 TW SC structure is employed. However, a TW SC structure requires a SC feedback waveguide to return the few GW of circulating RF power from the structure output back to the structure input. We describe a single-cell test TW SC structure with a feedback waveguide. The test cavity is designed to demonstrate the possibility of achieving a significantly higher gradient than existing SC structures.
|
|
|
|||||
WEPMN070 | High Power Test of an X-band Slotted-Iris Accelerator Structure at NLCTA | damping, vacuum, controls, higher-order-mode | 2191 | |||||
|
The CLIC study group at CERN has built two X-band HDS (Hybrid Damped Structure) accelerating structures for high-power testing in NLCTA at SLAC. These accelerating structures are novel with respect to their rf-design and their fabrication technique. The eleven-cell constant impedance structures, one made out of copper and one out of molybdenum, are assembled from clamped high-speed milled quadrants. They feature the same heavy higher-order-mode damping as nominal CLIC structures achieved by slotted irises and radial damping waveguides for each cell. The X-band accelerators are exactly scaled versions of structures tested at 30 GHz in the CLIC test facility, CTF3. The results of the X-band tests are presented and compared to those at 30 GHz to determine frequency scaling, and are compared to the extensive copper data from the NLC structure development program to determine material dependence and make a basic validation of the HDS design.
|
|
|
|||||
WEPMN071 | High RF Power Production for CLIC | damping, impedance, extraction, simulation | 2194 | |||||
|
The CLIC Power Extraction and Transfer Structure (PETS) is a passive microwave device in which bunches of the drive beam interact with the impedance of the periodically loaded waveguide and excite preferentially the synchronous mode. The RF power produced (several hundred MW) is collected at the downstream end of the structure by means of the Power Extractor and delivered to the main linac structure. The PETS geometry is a result of multiple compromises between beam stability and main linac RF power needs. Another requirement is to provide local RF power termination in case of accelerating structure failure (ON/OFF capability). Surface electric and magnetic fields, power extraction method, HOM damping, ON/OFF capability and fabrication technology were all evaluated to provide a reliable design.
|
|
|
|||||
WEPMN078 | RF Cavity Development for FFAG Application on ERLP at Daresbury | impedance, klystron, electron, extraction | 2209 | |||||
|
Funding for a non-scaling, Fixed Field Alternating Gradient (FFAG) facility has been approved for installation on the Energy Recovery Linac Prototype (ERLP) at Daresbury. The RF system specification for this project requires the development of a high efficiency, 1.3 GHz, normal conducting accelerating structure, capable of delivering the required accelerating voltage, whilst adhering to stringent space limitations imposed by the extremely compact nature of the FFAG ring. We have optimised a cavity design, providing the necessary acceleration and minimising the RF power requirements to match with commercially available power sources.
|
|
|
|||||
WEPMN080 | Development of Circuits and System Models for the Synchronization of the ILC Crab Cavities | controls, beam-loading, target, kaon | 2215 | |||||
|
Funding: The Commission of the European Communities under the 6th Framework Programme (Structuring the European Research Area) The UK particle physics and astromony research council. |
The ILC reference design report (RDR) recommends a 14 mrad crossing angle for the positron and electron beams at the IP. A matched pair of crab cavity systems are required in the beam delivery system to align both bunches at the IP. The use of a multi-cell, 3.9GHz dipole mode superconducting cavity, derived from the Fermilab CKM cavity. Dipole-mode cavities phased for crab rotation are shifted by 90 degrees with respect to similar cavities phased for deflection. Uncorrelated phase errors of 0.086 degrees (equivalent to 61fs) for the two cavity systems, gives an average of 180nm for the relative deflection of the bunch centers. For a horizontal bunch size of 655nm, a deflection of 180nm reduces the ILC luminosity by 2%. The crab cavity systems are to be placed ~28m apart and their synchronization to within 61fs is on the limit of what is presently achievable. This paper describes the design and testing of circuits and control algorithms under development at the Cockcroft Institute in the UK for proof of principle experiments planned on the ERLP at Daresbury and on the ILCTA test beamline at FNAL. Simulation results for measurement and control systems are also given. |
|
|||||
WEPMN082 | Global Scattering Matrix Technique Applied to the Calculation of Higher Order Modes for ILC Superconducting Cavities | scattering, simulation, dipole, electromagnetic-fields | 2218 | |||||
|
A cascaded scattering matrix approach is used to determine the electromagnetic (e.m.) field in the main ILC cavities. This approach is used to compute higher order e.m. modes in the baseline configuration, and high gradient alternative configurations. We present results on three designs: TESLA, Cornell University's re-entrant and, KEK's "Ichiro". This approach allows realistic experimental errors to be incorporated in the studies in an efficient manner and allows several cavities to be modelled en masse. Simulations are presented on the wake-fields in super-structures and segments of entire modules. Details on trapped eigen-modes and means to avoid them are delineated. The influence of cell misalignments and cavity perturbations on the modes are also presented.
|
|
|
|||||
WEPMN090 | Recent RF Results from the MuCool Test Area | resonance, background, coupling, radiation | 2239 | |||||
|
Funding: Supported by the USDOE Office of High Energy Physics |
The MuCool Experiment has been continuing to take data with 805 and 201 MHz cavities in the MuCool Test Area. The system uses rf power sources from the Fermilab Linac. Although the experimental program is primarily aimed at the Muon Ionization Cooling Experiment (MICE), we have been studying the dependence of rf limits on frequency, cavity material, high magnetic fields, gas pressure, coatings, etc. with the general aim of understanding the basic mechanisms involved. The 201 MHz cavity, essentially a prototype for the MICE experiment, was made using cleaning techniques similar to those employed for superconducting cavities and operates at its design field with very little conditioning. |
|
|||||
WEPMN091 | Beam Test of a Grid-less Multi-Harmonic Buncher | ion, bunching, pick-up, simulation | 2242 | |||||
|
Funding: This work was supported by the U. S. Department of Energy, Office of Nuclear Physics, under Contract No. DE-AC-02-06CH11357. |
The Argonne Tandem Linear Accelerator System (ATLAS) is the first superconducting heavy-ion linac in the world. Currently ATLAS is being upgraded with the Californium Rare Ion Breeder Upgrade (CARIBU). The latter is a funded project to expand the range of short-lived, neutron-rich rare isotope beams available for nuclear physics research at ATLAS. To avoid beam losses associated with the existing gridded multi-harmonic buncher, we have developed and built a grid-less four-harmonic buncher with fundamental frequency of 12.125 MHz. In this paper, we are going to report the ATLAS beam performance with the new buncher. |
|
|||||
WEPMN092 | Capture Cavity II Results at FNAL | resonance, controls, electron, feedback | 2245 | |||||
|
Funding: FRA |
As part of the research and development towards the International Linear Collider (ILC), several test facilities have been developed at Fermilab. This paper presents the latest LLRF results obtained with Capture Cavity II at these test facilities. The main focus will be on controls and RF operations using the SIMCON based LLRF system. Details about hardware upgrades and overall system performance will be also explained. Finally, design considerations and objectives for the future test facility at the New Muon Laboratory (NML) will be presented. |
|
|||||
WEPMN093 | Multipactor Simulations in Superconducting Cavities | simulation, RF-structure, electron, radio-frequency | 2248 | |||||
|
The multipactor (MP) is a well-known phenomenon. The existence of resonant trajectories can lead to electron avalanche under certain field level and surface conditions. In this paper we describe features of the extension of Analyst software - PT3P code developed for MP simulations in a real 3D RF structures, such as cavities, couplers, RF windows etc. Also we present the results of MP simulations in HOM couplers of TESLA, SNS β=0.61 and β=0.81 and FNAL 3-rd harmonic cavities. We discuss the comparison of simulations with experimental results.
|
|
|
|||||
WEPMN099 | Production of 325 MHz Single Spoke Resonators at FNAL | vacuum, target, proton, linear-collider | 2262 | |||||
|
Funding: US Department of Energy |
The High Intensity Neutrino Source (HINS) project represents the current effort at Fermi National Accelerator Laboratory to produce an 8-GeV proton linac based on about 400 independently phased superconducting resonators. Eighteen β=0.21 single spoke resonators, operating at 325 MHz, comprise the first stage of the linac cold section. We are presenting the production status of the first two of these resonators and the performance of the tuning mechanism prototype. In particular, we will report on the construction phases, the pre-weld tuning process and the comparison of low power RF measurements with calculations made using Microwave Studio*.
* CST MICROWAVE STUDIO (CST MWS), http://www.cst.com/ |
|
|||||
WEPMN102 | A 96 Channel Receiver for the ILCTA LLRF System at Fermilab | controls, impedance, target, insertion | 2271 | |||||
|
The present configuration of an ILC Main Linac RF station has 26 nine cell cavities driven from one klystron. With the addition of waveguide power coupler monitors, 96 RF signals will be downconverted and processed. A downconverter chassis is being developed that contains 12 eight channel analog modules and a single upconverter module. This chassis will first be deployed for testing a cryomodule composed of eight cavities located at New Muon Laboratory (NML) - Fermilab. Critical parts of the design for LLRF applications are identified and a detailed description of the circuit with various characteristic measurements is presented. The board is composed of an input band-pass filter centered at 1.3GHz, followed by a mixer, which downconverts the cavity probe signal to a proposed 13 MHz intermediate frequency. Cables with 8 channels per connector and good isolation between channels are being used to interconnect each downconverter module with a digital board. As mixers and power splitters are the most sensitive parts for noise, nonlinearities and cross-talk issues, special attention is given to these parts in the design of the LO port multiplication and distribution.
|
|
|
|||||
WEPMN104 | Mechanical Stability Study of Type IV Cryomodule (ILC Prototype) | quadrupole, vacuum, alignment, simulation | 2277 | |||||
|
An ANSYS modal and harmonic finite element analysis (FEA) was performed in order to investigate cryomodule design mechanical stability for the proposed International Linear Collider (ILC). The current cryomodule, designated Type IV or T4CM, closely follows the Type III TESLA Test Facility (TTF) version used at DESY, with the exception of a proposed location of the superconducting (SC) quadrupole at the center. This analysis considered the stringent stability criteria established for the ILC, where vertical motion for the SC quad is limited to the micron range, at a few Hz. Model validation was achieved through Type II cryomodule vibration measurement studies performed at DESY. The effect of support location, support stiffness and other important parameters were considered in a parametric sensitivity study. FEA results, fast motion investigations and stabilization techniques are discussed.
|
Operated by Universities Research Association, Inc., under Contract No. DE-AC02-76CH03000 with the U. S. Department of Energy#mcgee@fnal.gov |
|
|||||
WEPMN110 | Fabrication and Test of the First Normal-Conducting Crossbar H-type Accelerating Cavity at Fermilab for HINS | focusing, vacuum, lattice, radio-frequency | 2292 | |||||
|
Funding: This work was supported by the U. S. Department of Energy under contract number DE-AC02-76CH03000 |
The proposed High Intensity Neutrino Source at Fermilab is based on an 8 GeV linear proton accelerator which consists of a normal-conducting and a superconducting section. The normal-conducting (warm) section is composed of an ion source, a radio frequency quadrupole, a medium energy beam transport and 16 normal-conducting crossbar H-type cavities that accelerate the beam from 2.5 MeV to 10 MeV (from β=0.0744 to β=0.1422). These warm cavities are separated by superconducting solenoids enclosed in individual cryostats. Beyond 10 MeV, the design uses superconducting spoke resonators to accelerate the beam up to 8 GeV. In this paper, we illustrate the completion of the first normal-conducting crossbar h-type cavity (β=0.0744) explaining in detail the mechanical engineering aspects related to the machining and brazing processes. The radio-frequency measurements and tuning performed at Fermilab on the resonator and the comparisons with the former simulations are also discussed. |
|
|||||
WEPMN116 | Plans for Precision RF Controls for FERMI@ELETTRA | controls, klystron, feedback, beam-loading | 2310 | |||||
|
FERMI@ELETTRA is a 4th generation light source under construction at Sincrotrone Trieste. It will be operated as a seeded FEL driven by a warm S-band linac presently serving as the injector for the ELETTRA storage ring. Operation as an FEL driver places much more stringent specifications on control of the amplititude and phase of the RF stations than in its present operation. This paper describes a conceptual design of an upgrade to the RF controls to achieve these specifications. The system consists of a stabilized distribution of the master oscillator signal providing a reference to local digital RF controllers . The RF reference distribution system takes advantage of recent breakthroughs in optical techniques where stabilized fiber lasers are used to provide a very accurate control of RF phases over long distances. The RF controller is based on recent improvements on modern digital systems, using a 14-bit high speed digitizer in combination with an FPGA and high speed DAC. This paper also presents experimental results of early tests performed as a feasibility study of the system.
|
|
|
|||||
WEPMS002 | Polyhedral Cavity Structure for Linac Colliders | collider, coupling, higher-order-mode, emittance | 2325 | |||||
|
Funding: DOE grant #DE-FG02-06ER41405 |
A polyhedral superconducting cavity is being developed for possible use in linac colliders. In side view it has the contour of a Tesla-type multi-cell string. The surfaces of the cavity are formed by bonding flat foils to solid copper wedge-shaped segments, so that the end view is a polyhedron of such segments. Several features of this structure make it interesting for linac colliders: the cavity segments are totally open for cleaning, polishing, and inspection until the final assembly step; narrow slot gaps at the boundaries between segments strongly suppress all deflecting modes without penalty to the accelerating mode; the solid copper substrate accommodates cooling channels and eliminates the need for an immersion cryostat; and the open geometry makes it possible to utilize advanced superconductors (e.g. multi-layer Nb/Nb3Sn, YBCO, MgB2) on the cavity surface, opening the possibility of higher gradients. |
|
|||||
WEPMS003 | Design of Half-Reentrant SRF Cavities for Heavy Ion Linacs | cryogenics, ion, superconductivity, heavy-ion | 2328 | |||||
|
Funding: DOE #DE-FG02-06ER41411 |
The Spallation Neutron Source (Oak Ridge), the proposed 8 GeV Proton Driver (Fermilab), and the proposed Rare Isotope Accelerator use multicell elliptical SRF cavities to provide much of the accelerating voltage. This makes the elliptical cavity segment the most expensive part of the linac. A new type of accelerating structure called a half-reentrant elliptical cavity can potentially improve upon existing elliptical designs by reducing the cryogenic load by as much as 30% for the same accelerating voltage. Alternatively, with the same peak surface magnetic field as traditional elliptical cavities, it is anticipated that half-reentrant designs could operate at up to 25% higher accelerating gradient. With a half-reentrant shape, liquids can drain easily during chemical etching and high pressure rinsing, which allows standard multicell processing techniques to be used. A half-reentrant cavity for β = v/c = 1, suitable for the proposed ILC, has been designed and fabricated, with RF tests in progress*. In this paper, we present electromagnetic designs for three half-reentrant cell shapes suitable for an ion or proton linac (β = 0.47, 0.61 and 0.81, f = 805 or 1300 MHz).
* M. Meidlinger et al., in Proc. XXIII Int. Linac Conf., Knoxville, TN, Aug 2006 |
|
|||||
WEPMS013 | High Power Tests of First Input Couplers for Cornell ERL Injector Cavities | vacuum, coupling, superconductivity, impedance | 2355 | |||||
|
Funding: Work is supported by the National Science Foundation grant PHY 0131508 |
First RF power couplers for the ERL injector, currently under construction at Cornell University, have been fabricated. The couplers were assembled in pairs in the liquid nitrogen cryostat, built for their tests. A 15 kW CW IOT transmitter was available for coupler tests. A resonant ring was used for additional increase of the power. The couplers were successfully tested up to the goal power level of 50 kW CW. However, the first pair of couplers showed excessive temperature rise in some points. Therefore, minor changes in the design have been done to improve cooling. |
|
|||||
WEPMS015 | An Improved SF6 System for the FXR Induction Linac Blumlein Switches | induction, pulsed-power, electron, controls | 2361 | |||||
|
Funding: This work was performed under the auspices of the US Department of Energy by the University of California, Lawrence Livermore National Laboratory, under Contract W-7405-Eng-48. |
The now-mature FXR (Flash X-Ray) radiographic facility at Lawrence Livermore National Laboratory will be briefly described with emphasis on its pulsed power system. The heart of each accelerating cell's pulse-forming Blumlein is it's sulfur hexafluoride-based triggered closing switch. FXR's recent upgrade to a recirculating SF6 gas reclamation system will be described and the resulting accelerator performance and reliability improvements documented. This was accompanied by a detailed switch breakdown study on FXR's Test Stand* and the recent analysis of the resulting statistics will be shown.
* W. DeHope, D. Goerz, R. Kihara, M. Ong, G. Vogtlin, J. Zentler, "An Induction Linac Test Stand", 21st Particle Accelerator Conference, Knoxville, TN, May 20, 2005 |
|
|||||
WEPMS022 | Gain Scheduled Neural Network Tuned PI Feedback Control System for the LANSCE Accelerator | controls, feedback | 2379 | |||||
|
The current LANSCE LLRF system is an analog proportional/integral (PI) feedback control system that achieves amplitude and phase errors within 1% and 1 degree. The feedback system receives the cavity amplitude and phase, and the crosstalk between the amplitude and phase is significant. In this note, we propose an In-phase (I) and Quadrature (Q) based feedback control system which easily decouples the crosstalk of I and Q channels. For LANSCE-R, the current RF amplifier chain has to be preserved, so the controller output I/Q is transferred back to amplitude/phase values which drive the RF amplifier chain. The resultant feedback system reduces transient peaks of the RF and hence reduces the degradation of the RF amplifier chain. Self-tuning is performed every clock cycle. This feature of the feedback controller can reduce the beam loading transient drastically. The proposed control system is implemented with the Altera Stratix II FPGA. The proposed control system will first be tested on the low power test-stand to determine the robustness of the algorithm and will then be tested on a LANSCE Drift Tube Linac (DTL) tank.
|
|
|
|||||
WEPMS023 | Progress on New High Power RF System for LANSCE DTL | power-supply, impedance, controls, injection | 2382 | |||||
|
Funding: Work supported by the United States Department of Energy, National Nuclear Security Agency, under contract DE-AC52-06NA25396 |
A new 200 MHz RF system is being developed for the LANSCE proton drift tube linac (DTL). A planned upgrade will replace parts of the DTL RF system with new generation components. When installed for the LANSCE-R project, the new system will reduce the total number of electron power tubes from twenty-four to seven in the DTL plant. The 3.4 MW final power amplifier will use a Thales TH628 Diacrode. This state-of-the-art device eliminates the large anode modulator of the present triode system, and will be driven by a new tetrode intermediate power amplifier. In this mode of operation, this intermediate stage will provide 150 kW of peak power. The first DTL tank requires up to 400 kW of RF power, which will be provided by the same tetrode driver amplifier. A prototype system is being constructed to test components, using some of the infrastructure from previous RF projects. High voltage DC power became available through innovative re-engineering of an installed system. A summary of the design and construction of the intermediate power amplifier will be presented and test results will be summarized. |
|
|||||
WEPMS027 | The Klystron RF Systems for the Indiana University LENS Accelerator | controls, klystron, cathode, power-supply | 2394 | |||||
|
Funding: This work supported by the Indiana University Cyclotron Facility. |
This paper describes the Klystron RF systems for the Indiana University Low Energy Neutron Source (LENS) accelerator 425 MHz Radio Frequency Quadrupole (RFQ) and Drift Tube Linac (DTL) systems. Of interest in the power conditioning system is the design of the totem-pole grid-catch modulator for the mod-anode klystrons. This topology provides a fast rise and fall and closed loop regulation for the klystron mod-anode to cathode voltage, which minimizes RF amplitude and phase droop while maximizing efficiency. Another advantage is that short pulse high rep-rate operation is viable within the average power capabilities of the klystron. The 425 MHz, 1.25 MW klystron amplifier chain will also be detailed. Of final interest, is the digital low level RF system. This provides vector control of the cavity field using direct conversion, non-I/Q sampling architecture, at a sampling rate of 132 MHz with a 12-bit ADC. Four input and two output channels are integrated into a 6U VME module, with all DSP functions performed in Xilinx Spartan-3 field-programmable gate arrays. The design and implementation of these systems, coupled with LENS operational results, will be presented. |
|
|||||
WEPMS029 | LANSCE RF System Refurbishment | klystron, controls, power-supply, proton | 2400 | |||||
|
The Los Alamos Neutron Science Center (LANSCE) is in the planning phase of a refurbishment project that will sustain reliable facility operations well into the next decade. The LANSCE accelerator was constructed in the late 1960s and early 1970s and is a national user facility that provides pulsed protons and spallation neutrons for defense and civilian research and applications. The refurbishment will focus on systems that are approaching 'end of life' and systems where modern upgrades hold the promise for significant operating cost savings. The current baseline consists of replacing all the 201 MHz RF systems, upgrading a substantial fraction of the 805 MHz RF systems to high efficiency klystrons, replacing the high voltage systems, and replacing the low level RF cavity field control systems. System designs will be presented. The performance improvements will be described and the preliminary cost and schedule estimates will be discussed.
|
|
|
|||||
WEPMS033 | LANSCE 201 MHz and 805 MHz RF System Experience | klystron, vacuum, cathode, acceleration | 2412 | |||||
|
Funding: Work supported by the United States Department of Energy, National Nuclear Security Agency, under contract DE-AC52-06NA25396 |
The LANSCE RF system consists of four RF stations at 201 MHz and 44 klystrons at 805 MHz. In the LANSCE accelerator, the beam source is injected into the RF system at 0.75 MeV. The beam is then accelerated to 100 MeV in four drift tube linac (DTL) tanks, driven at 201.25 MHz. Each 201 MHz RF system consists of a train of amplifiers, including a solid state amplifier, a tetrode, and then at triode. After the DTL, the beam is accelerated from 100 MeV to 800 MeV in the forty-four coupled cavity linac (CCL) tanks at 805 MHz. The machine operates with a normal RF pulse width of 835 microseconds at a repetition rate up to 120 Hz, and sometimes operates with a pulse width up to 1.2 microseconds for single pulses. This RF system has been operating for about 37 years. This paper summarizes the recent operational experience. The reliability of the 805 MHz and 201 MHz RF systems is discussed, and a summary the lifetime data of the 805 MHz klystrons and 201 MHz triodes is presented. |
|
|||||
WEPMS034 | Mitigation of Electric Breakdown in an RF Photoinjector by Removal of Tuning Rods in High-Field Regions | gun, electron, cathode, coupling | 2415 | |||||
|
Funding: United States Department of Energy |
The pi-mode resonant frequency of the 1.6 cell SLAC/BNL/UCLA style RF photoinjector electron gun is conventionally tuned using cylindrical copper tuning pieces that extend into the full-cell cavity through holes in the side of the gun. This design begins to fail in many versions of this popular gun design at higher voltage levels, when the cavity undergoes electric breakdown in the vicinity of the tuners. In order to remove the tuners from the region of high electric field, mitigating this problem, the full cell geometry must be changed significantly. We report on a method of accomplishing this, in which we use a mechanical device of custom design to stretch the cavity structure of an existing photoinjector in order to tune the resonant frequency up by over 2 MHz. We present results of testing the modified photoinjector in an RF test bed with both copper and magnesium cathodes, succeeding in putting approximately 8 - 10 MW of RF power into the gun. This is an improvement over the 4 MW routinely achieved in a similar gun using conventional tuning methods installed at the UCLA Neptune laboratory. |
|
|||||
WEPMS036 | LCLS LLRF Upgrades to the SLAC Linac | klystron, controls, feedback, laser | 2421 | |||||
|
Funding: DOE |
The Linac Coherent Light Source at SLAC will be the brightest X-ray laser in the world when it comes on line. In order to achieve the brightness a 100fS length electron bunch is passed through an undulator. To creat the 100fS bunch, a 10pS electron bunch, created from a photo cathode in an RF gun, is run off crest on the RF to set up a position to energy correlation. The bunch is then compressed chicanes. The stability of the RF system is critical in setting up the position to energy correlation. Specifications derived from simulations require the RF system to be stable to below 100fS in several critical injector stations and the last kilometer of linac. The SLAC linac RF system is being upgraded to meet these requirements. |
|
|||||
WEPMS037 | RF Distribution Optimization in the Main Linacs of the ILC | controls, damping, coupling, linear-collider | 2424 | |||||
|
Funding: Work supported by the U. S. Department of Energy under contract DE-AC02-76SF00515. |
The nominal design gradient for the ILC is 31.5 MV/m, but the L-band superconducting cavities built to date have demonstrated a range in sustainable gradient extending below this goal, limited by Q-dropoff and quenching. An economically feasible cavity acceptance rate will include in the linacs a certain percentage of sub-performing cavities. We examine how, with a customizable RF distribution scheme, one can most efficiently distribute power from one klystron amongst 24 nine-cell cavities. The nominal cavity fills to the design gradient at the time the beam arrives, after which the beamloading voltage exactly cancels any further rise, yielding constant gradient during the bunch train. Along with adjustable RF power, we assume adjustable cavity coupling, or loaded quality factor, so that the gradient can be leveled in non-nominal cavities, to avoid quench-inducing overshoots. We explore these and related issues for the ILC linac high-power RF. |
|
|||||
WEPMS041 | Multipacting Simulations of TTF-III Coupler Components | simulation, electron, pick-up, vacuum | 2436 | |||||
|
Funding: This work was supported by US DOE contract No. DE-AC02-76SF00515. This work was performed under the auspices of the US DOE by the University of California, LLNL under Contract No. W-7405-Eng-48. |
The TTF-III coupler adopted for the ILC baseline cavity design has shown a tendency to have long initial high power processing times. A possible cause for the long processing times is believed to be multipacting in various regions of the coupler. To understand performance limitations during high power processing, SLAC has built a flexible high-power coupler test stand. The plan is to test individual sections of the coupler, which includes the cold and warm coaxes, the cold and warm bellows, and the cold window, using the test stand to identify problematic regions. To provide insights for the high power test, detailed numerical simulations of multipacting for these sections will be performed using the 3D multipacting code Track3P. The simulation results will be compared with measurement data. |
|
|||||
WEPMS043 | An RF Waveguide Distribution System for the ILC Test Accelerator at NML | coupling, klystron, linear-collider, collider | 2442 | |||||
|
Funding: Work supported by the U. S. Department of Energy under contract DE-AC02-76SF00515. |
An ILC R&D facility is being constructed in the NML building at Fermilab which, in addition to an injector and beam dump with spectrometer, will contain up to three cryomodules worth of ILC-type superconducting 9-cell cavities, 24 in all. This linac will be powered by a single klystron. As part of SLAC?s contribution to this project, we will provide a distribution network in WR650 waveguide to the various cavity couplers. In addition to commercial waveguide components and circulators and loads developed for TESLA, this sytem will include adjustable tap-offs, and customized hybrids. In one configuration, the circulators will be removed to test pair-wise cancellation of cavity reflections through hybrids. The system will be pressurized with nitrogen to 3 bar absolute to avoid the need for SF6 at windows or circulator. The full distribution for the first cryomodule will be delivered and installed later this year. We describe the design of the system and completed RF testing. |
|
|||||
WEPMS045 | Power Modulators for FERMI Linac's Klystrons. | klystron, controls, induction, vacuum | 2448 | |||||
|
The conventional line type modulators used for ELETTRA will have to be replaced for FERMI due to the increase in the pulse repetition frequency (PRF) from 10 to 50 Hz. The requirements for the FERMI modulator are as follows. The klystron used is a Thales TH2132 with a microperviance of 1.9-2.1 uA/V**(3/2). The peak voltage from the modulator is 320 kV, and the current is 350 A. The pulse width is 4.5 us, with a PRF of 50 Hz. Flat top should be better than ?0.5 % of the peak voltage. Prototypes for an upgraded line type modulator and a solid state induction type modulator[1] are in fabrication. The solid state design uses eight induction cells, each cell driven by two parallel Insulated Gate Bipolar Transistors (IGBT). Each IGBT will power a METGLAS 2605CO core with 4 kV and 3 kA for up to 5 us. A single turn is passed through the aperture of each of the cells, inductively adding the pulse voltages. The output from the modulator is then fed to a conventional pulse transformer to reach the 320 kV requirement. This paper presents the system design of both modulator types as well as details of the IGBT drivers, control electronics, IGBT and klystron protection and test data.
|
1. "NLC Hybrdi Solid State Induction Modulator" R. L. Cassel, etal, Lubeck, Germany, Linac 2004. |
|
|||||
WEPMS057 | Innovative Modular, Multiple Power Levels, 325 MHz Spokes Cavities Power Couplers | vacuum, proton, simulation, electron | 2475 | |||||
|
Funding: Footnotes: The project was funded by the US Department of Energy under contract DE-FG02-05ER84346 |
In order to increase the protons energy up to 8 GeV in a driver Linac, the particles must be accelerated through various stages and three different power levels (25kW, 100kW and 210kW) are required for the 325 MHz Fermilab Proton Driver couplers. The problem identified by the project is that no High RF power coupler for these cavities has ever been produced using US industrial capabilities. AMAC proposed a novel resolution by development of innovative modular, multiple power levels, 325 MHz spoke cavities power couplers, which to meet three type cavities with one coupler design. The simulation and concept design are presented. The results of HFSS, MAFIA, ANSYS, and Multipacting are also discussed. |
|
|||||
WEPMS059 | Performance of the First Refurbished CEBAF Cryomodule | vacuum, target, radiation, electron | 2478 | |||||
|
Funding: U. S. DOE Contract No. DE-AC05-06OR23177. This manuscript has been authored by Jefferson Science Associates, LLC under U. S. DOE Contract No. DE-AC05-06OR23177. |
The Thomas Jefferson National Accelerator Facility has begun a cryomodule refurbishment project. The goal of this project is robust 6 GeV, 5 pass operation of the Continuous Electron Beam Accelerator Facility (CEBAF). The scope of the project includes removing, refurbishing and replacing 10 CEBAF cryomodules at a rate of three per year. Refurbishment includes reprocessing of SRF cavities to eliminate field emission and increase the nominal gradient from the original 5 MV/m to 12.5 MV/m. New "dogleg" couplers between the cavity and helium vessel flanges will intercept secondary electrons that produce arcing on the 2 K ceramic window in the Fundamental Power Coupler (FPC). Modification of the Qext of the FPC will allow higher gradient operations. Other changes include new ceramic RF windows for the air to vacuum interface of the FPC and improvements to the mechanical tuners. Any damaged or worn components will be replaced as well. Currently, the first of the refurbished cryomodules has been installed and tested both in the Cryomodule Test Facility and in place in the North Linac of CEBAF. This paper will summarize the results of these tests. |
|
|||||
WEPMS060 | A Digital Self Excited Loop for Accelerating Cavity Field Control | controls, feedback, resonance, electron | 2481 | |||||
|
Funding: Notice: Authored by Jefferson Science Associates, LLC under U. S. DOE Contract No. DE-AC05-06OR23177. |
We have developed a digital process that emulates an analog oscillator and ultimately a self excited loop (SEL) for field control. The SEL, in its analog form, has been used for many years for accelerating cavity field control. In essence the SEL uses the cavity as a resonant circuit much like a resonant ?tank? circuit is used to build an oscillator. An oscillating resonant circuit can be forced to oscillate at different, but close, frequencies to resonance by applying a phase shift in the feedback path. This allows the circuit to be phased locked to a master reference, which is crucial for multiple cavity accelerators. For phase and amplitude control the SEL must be forced to the master reference frequency, and feedback provided for in both dimensions. The novelty of this design is in the way digital signal processing (DSP) is structured to emulate an analog system. While the digital signal processing elements are not new, to our knowledge this is the first time that the digital SEL concept has been designed and demonstrated. This paper reports on the progress of the design and implementation of the digital SEL for field control of superconducting accelerating cavities. |
|
|||||
WEPMS065 | CEBAF New Digital LLRF System Extended Functionality | controls, resonance, vacuum, ion | 2490 | |||||
|
Funding: JSA/DOE Contract - DE-AC05-06OR23177 |
The new digital LLRF system for the CEBAF 12GeV accelerator will perform a variety of tasks, beyond field control.* In this paper we present the superconducting cavity resonance control system designed to minimize RF power during gradient ramp and to minimize RF power during steady state operation. Based on the calculated detuning angle, which represents the difference between reference and cavity resonance frequency, the cavity length will be adjusted with a mechanical tuner. The tuner has two mechanical driving devices, a stepper motor and a piezo-tuner, to yield a combination of coarse and fine control. Although LLRF piezo processing speed can achieve 10 kHz bandwidth, only 10 Hz speed is needed for 12 GeV upgrade. There will be a number of additional functions within the LLRF system; heater controls to maintain cryomodule's heat load balance, ceramic window temperature monitoring, waveguide vacuum interlocks, ARC detector interlock and quench detection. The additional functions will be divided between the digital board, incorporating an Altera FPGA and an embedded EPICS IOC. This paper will also address hardware evolution and test results performed with different SC cavities.
*RF Control Requirements for the CEBAF Energy Upgrade Cavities, C. Hovater, J. Delayen, L. Merminga, T. Powers, C. Reece, Proceedings 2000 Linear Accelerator Conference, Monterey, CA , August 2000 |
|
|||||
WEPMS068 | JLab High-Current CW Cryomodules for ERL and FEL Applications | damping, simulation, vacuum, insertion | 2493 | |||||
|
Funding: Authored by Jefferson Science Associates, LLC under U. S. DOE Contract No. DE-AC05-06OR23177, and by The Office of Naval Research under contract to the Dept. of Energy. |
We describe the developments underway at JLab to develop new CW cryomodules capable of transporting up to Ampere-levels of beam currents for use in ERLs and FELs. Goals include an efficient cell shape, high packing factor for efficient real-estate gradient and very strong HOM damping to push BBU thresholds up by two or more orders of magnitude compared to existing designs. Cavity shape, HOM damping and ancillary components are optimized for this application. Designs are being developed for low-frequency (750 MHz), Ampere-class compact FELs and for high-frequency (1.5 GHz), 100 mA configurations. These designs and concepts can easily be scaled to other frequencies. We present the results of conceptual design studies, simulations and prototype measurements. These modules are being developed for the next generation ERL based high power FELs but may be useful for other applications such as high energy light sources, electron cooling, electron-ion colliders, industrial processing etc. |
|
|||||
WEPMS072 | Status and Performance of the Spallation Neutron Source Superconducting Linac | radiation, vacuum, higher-order-mode, cryogenics | 2502 | |||||
|
Funding: SNS is managed by UT-Battelle, LLC, under contract DE-AC05-00OR22725 for the U. S. Department of Energy |
The Superconducting Linac at SNS has been operating with beam for almost two years. As the first operational pulsed superconducting linac, many of the aspect of its performance were unknown and unpredictable. A lot of experience has been gathered during the commissioning of its components, during the beam turn on and during operation at increasingly higher beam power. Some cryomodules have been cold for well over two years and have been extensively tested. The operation has been consistently conducted at 4.4 K and 10 and 15 pulses per second, with some cryomodules tested at 30 and 60 pps and some tests performed at 2 K. Careful balance between safe operational limits and the study of conditions, parameters and components that create physical limits has been achieved. This paper presents the experience and the performance of the superconducting cavities and of the associated systems with and without beam. |
|
|||||
WEPMS074 | Design and High Power Processing of RFQ Input Power Couplers | vacuum, coupling, rfq, klystron | 2505 | |||||
|
Funding: This work was supported by SNS through UT-Battelle, LLC, under contract DE-AC05-00OR22725 for the U. S. Department of Energy. |
A RF power coupling system has been developed for future upgrade of input coupling of the RFQ in the SNS linac. The design employs two coaxial loop couplers for 402.5 MHz operation. Each loop is fed through a coaxial ceramic window that is connected to an output of a magic-T waveguide hybrid through a coaxial to waveguide transition. The coaxial loop couplers are designed, manufactured, and high power processed. Two couplers will be used in parallel to power the accelerating structure with up to total 800 kW peak power at 8% duty cycle. RF and mechanical properties of the couplers are discussed. Result of high power RF conditioning that is performed in the RF test facility of the SNS is presented. |
|
|||||
WEPMS075 | Development and Testing of High Power RF Vector Modulators | controls, impedance, klystron, simulation | 2508 | |||||
|
Funding: This work was supported by SNS through UT-Battelle, LLC, under contract DE-AC05-00OR22725 for the U. S. Department of Energy. |
High power vector modulators can allow a fan-out RF power distribution system that can power many accelerating cavities from a single high-power klystron amplifier. The configuration enables independent control of amplitudes and phases of RF voltages at the cavities. A vector modulator employs either one or two hybrids with two fast phase shifters. Prototype high power RF vector modulators employing a hybrid and two fast ferrite phase shifters in coaxial TEM transmission lines for 402.5 MHz and 805 MHz are built and tested. RF properties of the design and result of high power testing are presented. |
|
|||||
WEPMS076 | Status of the SNS Cryomodule Test | electron, cryogenics, vacuum, radiation | 2511 | |||||
|
Funding: SNS is managed by UT-Battelle, LLC, under contract DE-AC05-00OR22725 for the U. S. Department of Energy |
The cryomodule tests are on going to have better understandings of physics as a whole and eventually to provide safe and reliable operation for neutron production. Some features are revealed to be interesting issues and need more attentions than expected, such as operating condition, collective effects between cavities, HOM coupler issues, end-group stability, cavity-coupler interactions, and vacuum/gas physics, waiting for more investigations. Up to now SNS cryomodules were mainly tested at 4.4 K, 10 pulse per second (pps) and 30 pps/60 pps tests are under progress. This paper presents the experiences and the observations during tests of cryomodules. |
|
|||||
WEPMS080 | SRF Cavity Transient Beam Loading Detection - Simulation and Measurement | simulation, beam-loading, accumulation, controls | 2517 | |||||
|
Funding: SNS is managed by UT-Battelle, LLC, under contract DE-AC05-00OR22725 for the U. S. Department of Energy. |
Beam phase measurement based on detection of transient beam loading signal in a Superconducting (SC) cavity is utilized to setup the cavity synchronous phase. It has the potential to become a fast tune-up technique for a high intensity SC electron linac, as cavity phase could be determined precisely with only a few beam pulses. The paper introduces a transient detector study in the Spallation Neutron Source (SNS) proton linac, and discusses one of the major challenges - stochastic noise in the cavity RF system, which deteriorates the precision and increases the time needed for phase measurement with this technique. We analyze the influence of RF noise to the phase measurement in a simulation study with a beam-cavity model. Beam signal measurement with the cavity Low Level RF (LLRF) system and the initial experiment of prototype detectors are briefly introduced. |
|
|||||
WEPMS084 | A Solid State Driven, Parasitic Oscillation Suppressed, 17 GHz High Gain TW Klystron for Stable Operation with High Gradient Linac Structures | klystron, resonance, coupling, space-charge | 2529 | |||||
|
Funding: Work performed under the auspices of the U. S. Department of Energy SBIR Grant No. DE-FG02-04ER83973. |
The gain of a high power TW relativistic klystron can be increased substantially with the use of a varying phase velocity, large beam aperture, lengthened output structure, designed for asynchronous interaction to control space charge fields and provide near-adiabatic bunch compression during the power extraction process. While this technique enables the replacement of a pulsed vacuum tube driver system with a small, inexpensive solid state RF source, lengthening the output circuit increases the number (and reduces the separation) of the longitudinal mode resonances in the TM01 operating band. Thus, the probability of exciting parasitic oscillations is increased, especially when the klystron is operated into a mismatched load or a high Q structure. The prevention of such oscillations, even when in close proximity to the operating frequency, using a technique that is unaffected by the phase or amplitude of reflected signals is described; and test results are presented of a solid state driven, 76dB gain 17GHz TW relativistic klystron, recently installed in the linac test facility at the MIT Plasma Science and Fusion Center. |
|
|||||
WEPMS085 | A 17 GHz High Gradient Linac having Stainless Steel Surfaces in the High Intensity Magnetic and Electric Field Regions of the Structure | feedback, coupling, linear-collider, collider | 2532 | |||||
|
Funding: Work performed under the auspices of the U. S. Department of Energy SBIR Grant No. DE-FG02-05ER84362. |
To avoid surface erosion damage and to assist in understanding RF breakdown limitations imposed on high gradient linac operation, a gradient hardened structure is being fabricated having high temperature brazed and machined stainless steel surfaces located in the high E-field region of the beam apertures and in the high H-field regions of the racetrack shaped coupling cavities. The microwave design parameters and physical dimensions of this 17GHz, 2pi/3 mode, 22-cavity structure were established specifically to allow comparison of its high gradient performance to that of a similar all-copper structure tested under identical conditions, using an existing 4X power amplifying, RF recirculating dual ring system. Use of the 6X thicker skin depth material, the resulting de-Q-ing effects and the minimal reduction of beam energy (2%) associated with the strategically located lossy surfaces are discussed; fabrication techniques are described; and design parameters of the gradient hardened linac and the 17GHz power amplifying system are presented. |
|
|||||
WEPMS088 | Challenges Encountered during the Processing of the BNL ERL 5 Cell Accelerating Cavity | electron, vacuum, radiation, site | 2541 | |||||
|
Funding: Work done under the auspices of the US DOE |
One of the key components for the Energy Recovery Linac being built by the Electron cooling group in the Collider Accelerator Department is the 5 cell accelerating cavity which is designed to accelerate 2 MeV electrons from the gun up to 15-20 MeV, allow them to make one pass through the ring and then decelerate them back down to 2 MeV prior to sending them to the dump. This cavity was designed by BNL and fabricated by AES in Medford, NY. Following fabrication it was sent to Thomas Jefferson Lab in VA for chemical processing, testing and assembly into a string assembly suitable for shipment back to BNL and integration into the ERL. The steps involved in this processing sequence will be reviewed and the deviations from processing of similar SRF cavities will be discussed. The lessons learned from this process are documented to help future projects where the scope is different from that normally encountered. |
|
|||||
WEPMS090 | High Average Current Low Emittance Beam Employing CW Normal Conducting Gun | emittance, gun, electron, cathode | 2547 | |||||
|
CW normal conducting guns usually do not achieve very high field gradient and waste much RF power at high field gradient compared to superconducting cavities. But they have less trapped modes and wakefields compared to the superconducting cavities due to their low Q. The external bucking coil can also be applied very close to the cathode to improve the beam quality. By using a low frequency gun with a recessed cathode and a carefully designed beam line we can get a high average current and a high quality beam with acceptable RF power loss on the cavity wall. This paper shows that the CW normal conducting gun can be a backup solution for those projects which need high peak and average current, low emittance electron beams such as the Relativistic Heavy Ion Collider (RHIC) e-cooling project and Energy Recovery Linac (ERL) project.
|
|
|
|||||
WEPMS092 | A Simplified Approach to Analyze and Model Inductive Voltage Adder | impedance, simulation, kicker, pulsed-power | 2553 | |||||
|
Funding: Work performed under auspices of U. S. Departemnt of Energy. |
We have recently developed a simplified model and a set of simple formulas for inductive voltage adder design. This model reveals the relationship of output waveform parameters and hardware designs. A computer simulation has demonstrated that parameter estimation based on this approach is accurate as compared to an actual circuit. This approach can be used in early stages of project development to assist feasibility study, geometry selection in engineering design, and parameter selection of critical components. In this paper, we give the deduction of a simplified model. Among the estimation formulas we present are those for pulse rise time, system impedance, and number of stages. Examples are used to illustrate the advantage of this approach. This approach is also applicable to induction LINAC design. |
|
|||||
THXKI02 | Room Temperature Structure Development for High-Current Applications | rfq, proton, focusing, quadrupole | 2564 | |||||
|
A lot of new high current accelerators use both room temperature and superconducting structures. While it is clear that low beam current, low duty cycle accelerator should push for superconducting cavities, high current CW applications still prefers room temperature structure. This mainly depends on the accelerator constrains and objectives. This talk will present an overview of the worldwide activities and recent developments of room temperature structures for high-current applications.
|
|
|
Slides
|
|
|
||
THOAKI02 | The Cornell ERL Superconducting 2-Cell Injector Cavity String and Test Cryomodule | alignment, emittance, cryogenics, damping | 2572 | |||||
|
Funding: Work supported by NSF. |
Cornell University is developing and fabricating a SRF injector cryomodule for the acceleration of the high current (100 mA) beam in the Cornell ERL prototype and ERL light source. Major challenges include emittance preservation of the low energy, ultra low emittance beam, cw cavity operation, and strong HOM damping with efficient HOM power extraction. Prototypes have been completed for the 2-cell niobium cavity with helium vessel, coaxial blade tuner with piezo fine tuners, twin high power input couplers, and beam line HOM absorbers loaded with ferrites and ceramics. Axial symmetry of HOM absorbers, together with two symmetrically placed input couplers per cavity, avoids transverse on-axis fields, which would cause emittance growth. A one-cavity cryostat has been designed following concepts of the TTF cryostat, and is presently under fabrication and assembly. The cryostat design has been optimized for precise cavity alignment, good magnetic shielding, and high dynamic cryogenic loads from the RF cavities, input couplers, and HOM loads. In this paper we report on the status of the assembly and first test of the one-cavity test cryostat. |
|
Slides
|
|
|
||
THOAKI03 | Revision of Accelerating and Damping Structures for KEK STF 45 MV/m Accelerator Modules | damping, coupling, simulation, higher-order-mode | 2575 | |||||
|
KEK is constructing its superconducting RF test facility and installing 1.3 GHz superconducting accelerator structures. Learning from experience with our first 45MV/m 9-cell structures, we have revised accelerating structures as well as higher order mode dampers for improved performance. Problems found in the earlier structures are discussed and solutions are presented. New experimental results will be also reported.
|
|
|
Slides
|
|
|
||
THOAKI04 | Status of the Cryomodules for the SPIRAL 2 Superconducting LINAC | vacuum, heavy-ion, coupling, cryogenics | 2578 | |||||
|
The SPIRAL 2 superconducting linac is composed of 2 cryomodule families. The first family in the low energy section, called cryomodules A, is composed of 12 cryomodules housing a single cavity at β=0.07. The second family in the high energy section, called cryomodules B, is composed of 7 cryomodules housing 2 cavities at β=0.12. The frequency of these QWR resonators is 88.050 MHz, and the design goal for the accelerating field Eacc is 6.5 MV/m. This paper describes the present status of the cryomodules development.
|
|
|
Slides
|
|
|
||
THYKI02 | Laser Stripping of H- beams: Theory and Experiments | laser, ion, proton, electron | 2582 | |||||
|
Funding: Research sponsored by LDRD Program of Oak Ridge National Laboratory, managed by UT-Battelle, LLC, for the U. S. Department of Energy under Contract No. DE-AC05-00OR22725. |
Thin carbon foils are used as strippers for charge exchange injection into high intensity proton rings. However, the stripping foils become radioactive and produce uncontrolled beam loss, which is one of the main factors limiting beam power in high intensity proton rings. Recently, we presented a scheme for laser stripping an H- beam for the Spallation Neutron Source ring. First, H- atoms are converted to H0 by a magnetic field, then H0 atoms are excited from the ground state to the upper levels by a laser, and the excited states are converted to protons by a magnetic field. In this paper we report on the first successful proof-of-principle demonstration of this scheme to give high efficiency (around 90%) conversion of H- beam into protons at SNS in Oak Ridge. The experimental setup is described, and comparison of the experimental data with simulations is presented. In addition, future plans on building a practical laser stripping device are discussed. |
|
Slides
|
|
|
||
THXAB01 | Commissioning and Early Experiments with ISAC II | ion, emittance, vacuum, acceleration | 2593 | |||||
|
The first phase of the ISAC-II superconducting accelerator has recently been commissioned. The heavy ion linac adds 20MV to the 1.5MeV/u beam injected from the ISAC post accelerator. The linac is composed of five cryomodules; each cryomodule housing four 106 MHz quarter wave resonators and one 9T superconducting solenoid. On-line performance has confirmed cw operation at a peak surface field in excess of 35MV/m. The talk will describe the very successful commissioning and the early operation with both stable and radioactive beams.
|
|
|
Slides
|
|
|
||
THXAB03 | Commissioning of the Spallation Neutron Source Accelerator Systems | injection, target, coupling, beam-losses | 2603 | |||||
|
Funding: ORNL/SNS is managed by UT-Battelle, LLC, for the U. S. Department of Energy under contract DE-AC05-00OR22725. |
The Spallation Neutron Source accelerator complex consists of a 2.5 MeV H- front-end injector system, a 186 MeV normal-conducting linear accelerator, a 1 GeV superconducting linear accelerator, an accumulator ring, and associated beam transport lines. The linac was commissioned in five discrete runs, starting in 2002 and completed in 2005. The accumulator ring and associated beam transport lines were commissioned in two runs in February and April 2006. With the completed commissioning of the SNS accelerator, the facility has begun initial low-power operations. In the course of beam commissioning, most beam performance parameters and beam intensity goals have been achieved at low duty factor. A number of beam dynamics measurements have been performed, including emittance evolution, transverse coupling in the ring, beam instability thresholds, and beam distributions on the target. The commissioning results, achieved beam performance and initial operating experience of the SNS will be presented. |
|
Slides
|
|
|
||
THOAAB01 | Longitudinal Beam Parameters Study in the SNS Linac | electron, simulation, emittance, ion | 2608 | |||||
|
Funding: SNS is managed by UT-Battelle, LLC, under contract DE-AC05-00OR22725 for the U. S. Department of Energy. |
SNS Linac utilizes several accelerating structures operating at two frequencies. CCL and SCL operate at 805 MHz while 402.5 MHz is used for RFQ and DTL. Beam transfer from the previous part of the accelerator to the subsequent one requires careful longitudinal matching to improve beam transmission and to minimize beam losses. Longitudinal beam parameters have been investigated with the help of three Bunch Shape Monitors installed in the intersegments of the first CCL Module. The results of bunch shape observations for different accelerator settings are presented. Longitudinal beam emittance has been measured and optimized. Longitudinal beam halo has been evaluated as well. |
|
Slides
|
|
|
||
THYAB01 | Muon Accelerators | acceleration, emittance, factory, proton | 2614 | |||||
|
Funding: The work is supported by the UK Neutrino Factory/Particle Physics and Astronomy Research Council (PPARC) under Contract No. 2054. |
Accelerator of muon has to have very large acceptance and very quick acceleration. Recent study shows that FFAGs (in particular non-scaling) are one of the most promising candidates for muon accelerators as building block for a neutrino factory. There are, however, some unresolved problems which should be studied in more detail. We will talk about mostly beam dynamics issues of the muon accelerators, not only FFAG, but other candidates such as linac and RLA and compare their performance. |
|
Slides
|
|
|
||
THYAB02 | Commissioning of the J-PARC Linac | rfq, klystron, acceleration, proton | 2619 | |||||
|
The J-PARC (Japan Proton Accelerator Research Complex?is a joint project between the Japan Atomic Energy Agency (JAEA) and the High Energy Accelerator Research Organization (KEK) to construct and operate the high-intensity proton accelerator facility. The J-PARC comprises a 400 MeV linac, a 3 GeV rapid-cycling synchrotron (RCS), a 50 GeV main ring synchrotron (MR) and experimental facilities. The energy of the linac is reduced to 181 MeV for the time being, and it will be increased to 400 MeV in the near future. The 3 MeV RFQ, which is a front end of the linac, has been beam commissioned since November 2006, and we will continue to work on the rest of the linac such as a 50 MeV DTL and a 181 MeV Separated-type DTL. The results and status of the J-PARC linac beam commissioning will be presented.
|
|
|
Slides
|
|
|
||
THXC02 | Diagnostics for Commissioning LCLS | emittance, diagnostics, monitoring, radiation | 2635 | |||||
|
The fist stage of commissioning of the Linac Coherent Light Source at SLAC has begun in April of this year with succesful transport of the beam from the new RF photoinjector throught to the first bunch compressor. Construction and installation is continuing and will culminate with first FEL light in 2009. The LCLS provides several diagnostic challenges for providing precision, single-pulse readback of beam size and position in order to tune for very low 1 micron emittances. Ultra-short subpicosecond bunches call for special techniques of bunch length measurement including coherent radiation monitoring and the transverse deflecting cavity. The latter is also used to measure time dependant emittance and energy spread of slices along the bunch, which are critical to the lasing process within the FEL.
|
|
|
Slides
|
|
|
||
THOAC03 | Measurement of the Beam's Trajectory Using the Higher Order Modes it Generates in a Superconducting Accelerating Cavity | dipole, higher-order-mode, coupling, electron | 2642 | |||||
|
Funding: US DOE Contract #DE-AC02-76SF00515 |
It is well known that an electron beam excites Higher Order Modes (HOMs) as it passes through an accelerating cavity~[panofsky68]. The properties of the excited signal depend not only on the cavity geometry, but on the charge and trajectory of the beam. It is, therefore, possible to use these signals as a monitor of the beam's position. Electronics were installed on all forty cavities present in the FLASH~[flashref] linac in DESY. These electronics filter out a mode known to have a strong dependence on the beam's position, and mix this down to a frequency suitable for digitisation. An analysis technique based on Singular Value Decomposition (SVD) was developed to calculate the beam's trajectory from the output of the electronics. The entire system has been integrated into the FLASH control system. |
|
Slides
|
|
|
||
THOAC04 | RMS Emittance Measurements Using Optical Transition Radiation Interferometry at the Jefferson Lab FEL | electron, emittance, radiation, diagnostics | 2645 | |||||
|
Funding: Office of Naval Research Joint Technology Office |
Optical Transition Radiation Interferometry (OTRI) has proven to be effective tool for measuring rms beam divergence. We present rms emittance measurement results of the 115 MeV energy recovery linac at the Thomas Jefferson National Laboratories Free electron Laser using OTRI. OTRI data from both near field beam images and far field angular distribution images give evidence of two spatial and angular distributions within the beam. Using the unique features of OTRI we segregate the two distributions of the beam and estimate separate rms emittance values for each component. |
|
Slides
|
|
|
||
THIAKI04 | Recent Activities in Accelerator Construction and STF Cryomodule | synchrotron, vacuum, proton, power-supply | 2677 | |||||
|
Hitachi has been involved with construction of various accelerator systems for over forty years, from small apparatuses for laboratory use to the large systems for national projects. Our recent results are: SRC (Superconducting Ring Cyclotron) sector magnets of RIKEN RI Beam Factory, J-PARC (Japan Proton Accelerator Research Complex) magnets and power-supplies in JAEA, etc. And also, we have been developed capacities on manufacturing superconducting and cryogenic equipments. These are the key technologies in fundamental science researches. For these two years, we have been practically participated to construct STF (Superconducting RF Test Facility) cryomodule as an R&D equipment for the future ILC. Its two 6-meter long cryostats are designed to contain maximum eight 9-cell cavities in total. After the high-accuracy manufacturing of large vacuum vessels and cryogenic components, we assembled the entire cryomodules with specially designed jigs. Cavities and some related parts were installed by KEK. Through this work, we shared the valuable experience of manufacturing and assembling process. This paper describes our recent activities in accelerator construction and STF cryomodule.
|
|
|
Slides
|
|
|
||
THIAKI05 | European Industries Potential Capabilities on Superconducting RF Accelerator Modules | superconducting-RF, synchrotron, vacuum, RF-structure | 2680 | |||||
|
European Industry has been supporting accelerator projects in the past and will be supporting future projects. Larger numbers of superconducting accelerator modules with guaranteed performance parameters have been supplied for example for LEP at CERN and superconducting cavities have been supplied also with guarantees for CEBAF at Jefferson Lab, the proton linear accelerator for the Spallation Neutron Source, Oak Ridge, and for the rf system for LHC. A significant number of cavities have been supplied in support of the TTF/ILC activities. With a view to the future European X-FEL linear accelerator it is expected that turn-key accelerator modules will be requested from industry. A review of the European Industries supplies in the past and present will be given to show their capabilities for the future ILC.
|
|
|
Slides
|
|
|
||
THIBKI02 | Power Couplers for the ILC | vacuum, electron, controls, pulsed-power | 2685 | |||||
|
Power couplers are critically important components in all superconducting accelerators. Power couplers provide the vacuum and thermal interface between the superconducting cavity and the room temperature waveguide components and transmit microwaves generated by the high power klystron or IOT. Power couplers must be extraordinarily clean and reliable. CPI power couplers are manufactured to our customer?s specifications using processes which are standard to the electron device industry as well as processes which have been developed specifically for power couplers. We have developed the capability of electroplating high-RRR copper. Our high-RRR copper plating has been qualified by Cornell and DESY. We have developed the capability of applying TiN coatings to ceramic windows for multipactor suppression. Using these processes, CPI has manufactured over 50 power couplers of various designs with an additional 50 power couplers to be built this year. Our talk will focus on power couplers for the ILC. In particular, we will discuss some of the challenges to be faced during the manufacture of tens of thousands of power couplers for the ILC.
|
|
|
Slides
|
|
|
||
THIBKI03 | Klystron Development by TETD | klystron, electron, proton, controls | 2688 | |||||
|
TETD (Toshiba Electron Tubes & Devices Co., LTD.) has been developing vacuum microwave devices such as klystrons, gyrotrons and input couplers in collaboration with some Japanese research institutes. This article describes recent development status of klystrons and input couplers for high-power RF accelerator systems including a 324-MHz and a 972-MHz klystrons for JARC, 1.3-GHz vertical and horizontal MBKs for DESY and a 1.3-GHz TTF-type input coupler for European XFEL. As an application to fusion experimental devices, development of a 5-GHz, 500-kW CW klystron for KSTAR and a 170-GHz quasi-CW gyrotron for ITER are also presented.
|
|
|
Slides
|
|
|
||
THICKI05 | European Industries Potential Capabilities on Cryogenics for the Future IlC | cryogenics, damping, positron, collider | 2704 | |||||
|
Following the construction of LHC, the European industries have demonstrated there ability to construct complete helium and nitrogen refrigeration systems both for the needs of the huge accelerator and the associated detectors. Eight 18 kW at 4.5 K and 2.4 kW at 1.8 K helium refrigeration systems have been constructed. Each refrigeration system is connected to 3 km of the 27 km long accelerator thanks to interconnecting valve boxes and high performances helium transfer lines. This is the biggest refrigeration system ever constructed in the world. The demand for cryogenics for the future ILC project is comparable in terms of equipment sizes but even bigger in terms of number of units required. The present refrigeration system scenario of ILC includes ten 22 kW at 4.5 K refrigerators and twelve 4.1 kW at 2 K refrigerators. In the present paper, this scenario will be presented and compared to the realizations done by the European Cryogenic Industries. Contact : Pascale.dauguet@airliquide.com
|
|
|
Slides
|
|
|
||
THPMN003 | Commissioning of the 100 keV Beam Stage of the Injector Linac of the IFUSP Microtron | microtron, cathode, alignment, emittance | 2710 | |||||
|
Funding: Work supported by FAPESP and CNPq |
The injector linac consists of a beam conforming stage, with chopper and buncher systems, and two acceleration structures, the first one with variable β, and the second one divided into two parts with different β. There are two 3-mm diameter collimators, the first at the entrance to the first chopper cavity and the second at the entrance to the first acceleration structure. The beam focalization is made by solenoids, and correcting coils are provided for steering. In this work we describe the commissioning of the optical lattice of the conforming beam stage. The first beam images are shown. |
|
|||||
THPMN014 | Commissioning of the Linac for the Heidelberg Heavy Ion Cancer Therapy Centre (HIT) | rfq, ion, synchrotron, diagnostics | 2734 | |||||
|
A clinical facility for cancer therapy using energetic proton and ion beams (C, He and O) is under construction and will be installed at the Radiologische Universitätsklinik in Heidelberg, Germany. It consists of two ECR ion sources, a 7 MeV/u linac injector, and a 6.5 Tm synchrotron to accelerate the ions to final energies of 50-430 MeV/u. The linac comprises a 400 keV/u RFQ and a 7 MeV/u IH-DTL operating at 216.8 MHz. The commissioning of the linac with beam was performed in three steps for the LEBT, the RFQ, and the IH-DTL. For this purpose a versatile beam diagnostic test bench has been used consisting of a slit-grid emittance measurement device, transverse pick-ups providing for time of flight energy measurements, SEM-profile grids, and different devices for beam current measurements. In this contribution the procedure and the results of the successful commissioning in the year 2006 of the linear accelerator are reported.
|
|
|
|||||
THPMN022 | Going Towards the Dual Energy X-Ray Radiographic System for Material Recognition Purposes | electron, controls, focusing, target | 2754 | |||||
|
Non Destructive Testing (NDT) has become the most used technique to inspect objects in order to find manufacturing defects (quality control), investigate contents (custom control), detect damages (structural control). However, the mono-energetic NDT can only discover a density variation in the analyzed sample but in most cases no hypothesis can be done on its composition; a complete inspection of an object would require the recognition of the material composing the analyzed sample and this can be achieved by means of the dual energy x-ray radiography. In this context, the INFN Gruppo Collegato di Messina is implementing the radio-tomographic system of the Universita di Messina, based on a 5 MeV electron linac, to the aim to provide dual energy x-ray beams for material recognition purposes. A wide study has been performed to provide different electron energies acting on the linac parameters. According to a theoretical study on the x-ray transmission for two properly chosen x-ray energies, preliminary tests have been performed to evaluate the complementarity of the images obtained with the dual energy technique. Work is still in progress to improve the dual energy system.
|
|
|
|||||
THPMN023 | Study of an Electron Linac Driven X-Ray Radio-Tomographic System Response as a Function of the Electron Beam Current | electron, photon, target, simulation | 2757 | |||||
|
At the Dipartimento di Fisica, Universita di Messina, a high energy x-ray radio-tomography system driven by a 5 MeV electron linac, has been recently assembled. It has been tested and has already provided good results in inspecting heavy materials. In order to achieve good radiographic results, especially when inspecting heavy or thick materials, an enhancement of the x-ray dose at the sample position can be required and most of times this is associated to an enhancement of the grey level in the acquired image according to a linear function. Nevertheless, in the hypothesis to work at the maximum magnetron power, a variation of the x-ray dose, obtained changing the electron beam current, is associated to a variation of the electron beam energy. As a consequence, the x-ray energy spectrum varies thus influencing the response of the radio-tomographic system. This does not allow a linear correspondence between the x-ray fluence (or the electron beam current) and the image grey level. By means of MCNP-4C2 simulations, the influence of electron beam energy variations on the produced bremsstrahlung spectrum has been studied and the theoretical results have been experimentally confirmed.
|
|
|
|||||
THPMN026 | C-band Linac in SCSS Prototype Accelerator of the Japanese X-FEL Project | klystron, acceleration, power-supply, electron | 2766 | |||||
|
Funding: RIKEN-JASRI Joint-Project for SPring-8 XFEL |
C-band (5712-MHz) linac is used as the main accelerator of the Japanese X-FEL facility in SPring-8. Since the C-band linac has high acceleration gradient, our 8-GeV accelerator is compact rather than a conventional S-band accelerator. The system consists of following components; two choke-mode-type 1.8-m accelerating structures, an rf pulse compressor (SLED), a 50-MW klystron, a 100-MW compact modulator, and an rf digital control system. We will use 60 to 70 units for the X-FEL accelerator. Since November 2005, we have operated two C-band units in the 250-MeV FEL prototype accelerator (SCSS). After rf conditioning, the accelerating gradient was achieved to 35-MV/m. We successfully accelerated the electron beam by this gradient of electrical field. In this presentation, we will report the detail of each component and its operation status of the SCSS prototype accelerator. |
|
|||||
THPMN027 | Status of C-band Accelerator Module in the KEKB Injector Linac | acceleration, positron, electron, klystron | 2769 | |||||
|
For future upgrade of the KEKB injector linac, components of C-band accelerator module have been developed since 2002. A prototype C-band accelerator module composed of a 50-MW klystron, an RF-pulse compressor and four 1-m long accelerating sections, has been constructed in the present S-band injector linac. It has been operated for 14 months. In a recent beam-acceleration study, it has achieved an energy gain of 151 MeV, which corresponds to an average acceleration field of 39 MV/m.
|
|
|
|||||
THPMN030 | Enhancement of the Positron Intensity by a Tungsten Single Crystal Target at the KEKB Injector Linac | target, positron, electron, vacuum | 2778 | |||||
|
Funding: This work was supported by the Grant-in-Aid of Ministry of Education, Culture, Sports, Science and Technology of Japan and by the grant of Ministry of Education and Science of the Russian Federation. |
A new tungsten single-crystalline positron target has been successfully employed for generation of the intense positron beam at the KEKB injector linac in September 2006. The target is composed of a tungsten single-crystal with a thickness of 10.5 mm. The positron production target is bombarded at an incident electron energy of 4 GeV, and the produced positrons are collected and accelerated up to the final injection energy of 3.5 GeV in the succeeding sections. A conventional tungsten plate with a thickness of 14 mm has been used previously, and the conversion efficiency (Ne+/Ne-), the ratio between the number of positrons (Ne+) captured in the positron capture section and the number of the incident electrons (Ne-), was 0.20 on average. By replacing the tungsten plate with the tungsten crystal, it increased to 0.25 on average. The increase of the conversion efficiency has boosted the positron intensity to its maximum since the beginning of KEKB operation in 1999. Now this new positron source is stably operating and is contributing to increasing the integrated luminosity of the KEKB B-factory. |
|
|||||
THPMN031 | Experiment of X-Ray Source by 9.4 GHz X-Band Linac for Nondestractive Testing System | electron, gun, target, power-supply | 2781 | |||||
|
We are developing a compact X-ray source for Nondestractive Testing (NDT) system. We aim to develop a portable X-ray NDT system by 950 keV X-band linac to realize in-site inspection. Our system has 20 kV electron gun, and accelerate electron beam to 950 keV with 9.4 GHz X-band linac. RF source of this system is 250kW magnetron. Our target spot size and spatial resolution are 1mm. We adopted APS (Alternative Periodic Structure) tube of pi/2 mode for easy manufacturing. It is difficult to realize a high-shunt-impedance for low-energy-cells, which attributes to manufacturing problems. Instead, we use three pi-mode cavities there. Further, we choose the low power magnetron for small cooling system and the low voltage electron gun for small power supply. For the stability of the X-ray yield the system include the Auto Frequency Control (AFC), which detect and tune the frequency shift at the magnetron. We have also performed X-ray generation calculation by the Monte Carlo code of GEANT and EGS to confirm the X-ray source size. We are going to construct the whole system and verify it experimentally. Updated results are presented at the spot.
|
|
|
|||||
THPMN035 | Pinpoint keV/MeV X-ray Sources for X-ray Drug Delivery System | radiation, electron, laser, scattering | 2793 | |||||
|
X-ray Drug Delivery System (DDS) is the most advanced radiation therapy coming after IMRT (Intensity Modulated Radiation Therapy) and IGRT (Image Guided). DDS uses advanced nano-scaled polymers which contain and deliver drug or contrast agent to cancers without side effects. Several X-ray DDS poses high-Z atoms like Pt and Au to absorb X-rays effectively and used as contrast agent for inspection. Moreover, they have radiation enhancement effect by emission of Auger electron and successive characteristic X-rays. The enhancement factor off Pt and Au is more than five. This can be used for therapy. This new modality must be very important for inspection and therapy of deep cancers. We are making use of our Compton scattering monochromatic keV X-ray source and MeV linac aspinpoint keV/MeV X-ray sources for the purpose. Physical analysis and evaluation of the contrast efficiency and radiation enhancement of the X-ray DDS are under way. Furthermore, a new compact X-band linac with a multi-beam klystron for a pinpoint X-ray source is proposed and designed. Updated research status and result are presented.
|
|
|
|||||
THPMN036 | Simulation Study on Attosecond Electron Bunch Generation | emittance, electron, gun, space-charge | 2796 | |||||
|
Pulse radiolysis, a stroboscopic method with an ultrashort electron bunch and an ultrashort light, is essential for the observation of ultrafast reactions. The time resolution of pulse radiolysis depends on the electron bunch length. In Osaka University, a 98-fs electron bunch was generated by using a photocathode electron linac for a development of femtosecond pulse radiolysis*. Furthermore, a sub-femtosecond/attosecond pulse radiolysis will be proposed to study the ionization and thermalization processes in attosecond time region. In order to realize such a high time resolution, the possibility of attosecond electron bunch generation based on the photocathode RF gun linac and a magnetic bunch compressor was studied. In the simulation, the bunch length growth due to charge, emittance, accelerating phase and magnetic fields were investigated to generate an attosecond electron bunch.
|
* J. Yang, T. Kondoh, K. Kan, T. Kozawa, Y. Yoshida and S. Tagawa: Nucl. Instrum. Methods Phys. Res., Sect. A 556 (2006) 52-56 |
|
|||||
THPMN047 | Commissioning Scenario for L-band Electron Accelerator by PARMELA Code | simulation, bunching, electron, focusing | 2820 | |||||
|
Funding: Work supported by KAPRA and PAL |
An intense L-band electron accelerator is now being installed at PAL (Pohang Accelerator Laboratory) for initial tests. It is capable of producing 10-MeV electron beams with average 30 kW. This accelerator has a diode-type E-gun, a pre-buncher cavity, and an accelerating column with the built-in bunching section. We conduct simulational study for the commissioning scenario by the PARMELA code. At first, we observe the beam position and the beam current when the beam line is misaligned under no fields. Next, turning on focusing solenoids we observe the beam position change to check the alignments of the solenoids. Finally, varying RF power and phase of the pre-buncher we observe beam energy and beam power to obtain the optimum pre-buncher condition. In this paper, we present simulational results for each step. We also present commissioning strategies based on these results. |
|
|||||
THPMN048 | Cold Test on C-band Standing-wave Accelerator | coupling, bunching, electron, resonance | 2823 | |||||
|
Funding: Work supported by PAL. |
For a compact X-ray source, we designed a C-band standing-wave electron accelerator. It is capable of producing 4-MeV electron beams with 50-mA peak beam current. As an RF source, we use 5-GHz magnetron with duty factor of 0.08%. The accelerating structure is bi-periodic and on-axis coupled structure, operated with π/2-mode standing waves. Each cavity in the bunching and normal cell is designed by the MWS code and measured with aluminium prototype cavity. As per the dispersion relation derived from the measurement results, calibration factor obtained for the actual copper cavity. |
|
|||||
THPMN049 | Current Status of Intense L-band Electron Accelerator for Irradiation Source | klystron, electron, power-supply, controls | 2826 | |||||
|
Funding: Work supported by KAPRA. |
An intense L-band electron accelerator is designed and under development for CESC (Cheorwon Electron-beam Service Center) irradiation applications. It is capable of producing 10-MeV electron beams with average 30 kW. For an RF source, a Thales klystron is used with 1.3 GHz, pulsed 25 MW, and average 60 kW. The accelerator column, fabricated by IHEP in China, is operated with 2π/3 mode traveling-wave under the fully-beam-loaded condition. The modulator was fabricated with inverter power supplies. The klystron was assembled to the klystron tank with pulse transformer. The high-voltage pulse test was conducted for the klystron tube. In this paper, we present design details of the accelerator and current status. |
|
|||||
THPMN058 | Beam Dynamics Studies in the CLIC Injector Linac | positron, emittance, electron, quadrupole | 2838 | |||||
|
The CLIC Injector Linac has to accelerate both electron and positron main beams from 200 MeV up to 2.42 GeV prior to their injection into the pre-damping rings. Its 26 accelerating structures operate at 1.875 GHz, with a loaded gradient of 17 MV/m. A FODO lattice that wraps the accelerating structures at the beginning of the linac, followed by a succession of triplet lattices between the accelerating structures, is proposed. The large transverse emittance (9200 mm.mrad), bunch length (5 mm) and energy spread (7 MeV) of the positron beam set constraints on the linac in order to reach acceptable characteristics at 2.42 GeV for the injection into the pre-damping ring. The use of a bunch compressor at the entrance of the linac is an option in order to achieve good performance in both the longitudinal and transverse phase spaces. Tracking studies of both electron and positron beams in the linac have been performed and are presented.
|
|
|
|||||
THPMN059 | Feedback Studies | feedback, luminosity, emittance, ground-motion | 2841 | |||||
|
Funding: Supported by the European Community under the 6th Framework Programme "Structuring the European Research Area". |
Dynamic imperfections in future linear colliders can lead to a significant luminosity loss. We discuss different orbit feedback strategies in the main linac that can mitigate the emittance dilution and compare their efficiency. We also address the impact of ground motion in the beam delivery system and the potential cures. |
|
|||||
THPMN061 | Bunch Compressor for Beam-Based Alignment | emittance, alignment, simulation, quadrupole | 2844 | |||||
|
Funding: Supported by the European Community under the 6th Framework Programme "Structuring the European Research Area". |
Misalignments in the main linac of future linear colliders can lead to significant emittance growth. Beam-based alignment algorithms, such as Dispersion Free Steering (DFS), are necessary to mitigate these effects. We study how to use the Bunch Compressor to create the off-energy beams necessary for DFS and discuss the effectiveness of this method. |
|
|||||
THPMN062 | Dynamic Effects During Beam-Based Alignment | emittance, alignment, quadrupole, simulation | 2847 | |||||
|
Funding: Supported by the European Community under the 6th Framework Programme "Structuring the European Research Area". |
Complex beam-based alignment procedures are needed in future linear colliders to reduce the negative effects of static imperfections in the main linac on the beam emittance. The efficiency of these procedures could be affected by dynamic imperfections during their application. In this paper we study the resulting emittance growth. |
|
|||||
THPMN063 | CTF3 Combiner Ring Commissioning | optics, injection, quadrupole, collider | 2850 | |||||
|
CLIC Test Facility 3 (CTF3) has the objective to demonstrate the remaining feasibility issues of the CLIC two-beam technology for a future multi-TeV linear collider. One key issue is the efficient generation of a very high current 'drive beam' that serves as the power source for the acceleration of the main beam to high energy. This large current beam is produced by interleaving bunches in a combiner ring using transverse deflecting RF cavities. The 84 m long CTF3 combiner ring and the connecting transfer line have been recently installed and put into operation. The latest commissioning results will be presented.
|
|
|
|||||
THPMN083 | Spin Tracking at the International Linear Collider | polarization, damping, positron, simulation | 2901 | |||||
|
Funding: This work is supported in part by the Commission of the European Communities under the 6th Framework Programme "Structuring the European Research Area", contract number RIDS-011899. |
Polarized electron and positron beams are foreseen for the future International Linear Collider (ILC), with polarized electrons already included in the baseline design and polarized positrons seen as a highly-desirable upgrade. High precision physics requires the polarization of both beams to be known with a relative uncertainty of approximately 0.5% or better. Therefore all possible depolarization effects that could operate between the polarized sources and the interaction regions have to be carefully modelled. The "heLiCal" collaboration aims to provide a full "cradle-to-grave" analysis of all depolarization effects at the ILC, and to develop software tools to carry out appropriate computer simulations. In this paper we report on the first phase of our work which includes extensive simulations of the ILC spin-dynamics and a detailed study of beam-beam depolarization effects at the interaction point(s). |
|
|||||
THPMN088 | C-Band High Power RF Generation and Extraction Using a Dielectric Loaded Waveguide | acceleration, insertion, extraction, vacuum | 2912 | |||||
|
Funding: Department of Energy |
We report on the fabrication, simulation, and high-power testing of a C-band RF power extractor recently conducted at the Argonne Wakefield Accelerator (AWA) facility. Dielectric loaded accelerating (DLA) structures can be used for high-power RF generation [*,**] when a high-current electron beam passes through a DLA structure and loses energy into the modes of the structure due to self-wakefields. The AWA generates high charge (up to 100nC), short bunch length (1.5mm~2.5mm) electron beams, which is ideal for high-power RF generation. The generated RF power can be subsequently extracted with a properly designed extraction coupler in order to accelerate a second beam, or for other high power purposes. In this paper, the detailed design of a 7.8 GHz DLA power extractor, MAFIA simulations, and results of the high-power test are presented. Simulation predictions of an 79 MW, 2.2 ns long RF pulse (generated by a single 100 nC electron bunch) and a longer RF pulse of the same power (obtained from a 35 nC periodic bunch train) will be compared to experimental results.
* W. Gai, et al, Experimental Demonstration of Two Beam Acceleration Using Dielectric Step-up Transformer, PAC01, pp.1880-1882.** D. Yu, et al, 21GHz Ceramic RF Power Extractor, AAC02, pp.484-505. |
|
|||||
THPMN102 | A Muon Beam for Cooling Experiments | proton, target, emittance, lattice | 2948 | |||||
|
Funding: Work supported by the US Department of Energy |
Within the framework of the Fermilab Muon Collider Task Force, the possibility of developing a dedicated muon test beam for cooling experiments has been investigated. Cooling experiments can be performed in a very low intensity muon beam by tracking single particles through the cooling device. With sufficient muon intensity and large enough cooling decrement, a cooling demonstration experiment may also be performed without resolving single particle trajectories, but rather by measuring the average size and position of the beam. This allows simpler, and thus cheaper, detectors and readout electronics to be used. This paper discusses muon production using 400MeV protons from the linac, decay channel and beamline design, as well as the instrumentation required for such an experiment, in particular as applied to testing the Helical Cooling Channel (HCC) proposed by Muons Inc. |
|
|||||
THPMN104 | Recent Studies of Dispersion Matched Steering for the ILC Bunch Compressor and Main Linac | emittance, quadrupole, injection, alignment | 2954 | |||||
|
Beam Based Alignment techniques are expected to play a critical role to the emittance preservation for the ILC. The Dispersion Free Steering (DFS) method is studied in detail in the 2nd statge of the bunch Compressor and in the beginning of the curved Main Linac. It is shown than in absence of cavity tilts (rotations on the YZ plane), DMS provides a unique and stable solution with negligible emittance growth. If cavity tilts are about 200 to 300 micro-radiant, the DMS solution is no longer unique and significant emittance occurs as well. While within the ILC budget, other dynamical effects, such a large beam jitter or sudden ground motion will cause severe performance degradation. A Variant of the DFS algorithm can be used to re-aling cavity supports, leading to better LET performance. In presence of perturbations (klystron jitter, ground motion,.. ) such DFS solutions are easier to maintain and improved if they are stable and unique. Therefore, it is suggested to consider using movers on quadrupole/BPM and, a bit more controversial, for the support system of the r.f. cavities, especially at low energy, where spurious dispersion due to cavity tilts are large.
|
|
|
|||||
THPMN107 | Study of Emittance Bumps in The ILC Main Linac | emittance, alignment, simulation, quadrupole | 2960 | |||||
|
Funding: U. S. Department of Energy |
This paper reports the studies of using global emittance tuning bumps to limit the emittance growth to very small values in the main linac of the proposed International Linear Collider (ILC) machine. Simulation studies indicate that closed-orbit emittance bumps, when used after local or quasi-local beam based alignment techniques, can be utilized to further suppress the emittance growth in the ILC main linac. A series of simulations are performed to find the optimal number of bumps and their locations. A more general method of optimizing the emittance bumps in the ILC main linac is also discussed. |
|
|||||
THPMN108 | Study of Adaptive Alignment as Beam Based Alignment in ILC Main Linac in the Presence of Ground Motion | emittance, alignment, ground-motion, lattice | 2963 | |||||
|
Funding: U. S. Department of Energy |
The proposed International Linear Collider (ILC) machine requires extremely small transverse emittances of the beam to achieve desired luminosity. A very precise alignment of the beamline elements, both in main linac and in beam delivery system, is required to limit the emittance growth. However, ground motion (GM) and technical noise continuously misaligns the elements and hence spoils the effect of alignment. It is thus very important to understand and analyze the effect of GM on the performance of ILC. Also, it is imperative to find an effective dynamic alignment procedure to preserve the transverse emittances in the presence of GM. In this paper we study the effect of GM and technical noise on the proposed ILC main linac. Initial alignment of the Linac is performed through one-to-one and dispersion free steering (DFS). We then study "Adaptive Alignment" method to mitigate the effects of GM and technical noise. |
|
|||||
THPMN109 | Status of the ILC Main Linac Lattice Design | lattice, synchrotron, quadrupole, synchrotron-radiation | 2966 | |||||
|
The report describes the present design of the ILC Main Linac lattice. The topics covered include basic element layout, optical functions, and issues centered around the linac following of the Earth's curvature. Also discussed are beam parameter measurements and instrumentation requirements.
|
|
|
|||||
THPMS005 | Observation of Wakefields in a 17 GHz Metallic Photonic Bandgap (PBG) Structure | higher-order-mode, vacuum, radiation, damping | 3002 | |||||
|
Funding: Work supported by the Department of Energy, High Energy Physics, under contract DE-FG02-91ER40648. |
Results are reported on experimental wakefield measurements made on a 6 cell, 17 GHz metallic PBG accelerator structure. Wakefields were observed using a variety of detectors and methods. The PBG structure is open, containing no outer wall, and radiation has been observed through a window in the surrounding vacuum vessel. The input and output ports have also been used with windows to observe radiation coupling out of the ports. Estimations of radiation are made using HFSS and an EFIE code. Measurements have been made using video diode detectors, wavemeters, heterodyne receivers, and a bolometer. Plans are discussed for future experiments with injected power and longer structures. |
|
|||||
THPMS013 | Comparison of Tracking Codes for the International Linear Collider | emittance, simulation, lattice, linear-collider | 3020 | |||||
|
Funding: Supported by the US Department of Energy, the US National Science Foundation and the Commission of the European Communities under the 6th Framework Programme "Structuring the European Research Area". |
In an effort to compare beam dynamics and create a benchmark'' for Dispersion Free Steering (DFS) a comparison was made between different International Linear Collider (ILC) simulation programs while performing DFS. This study consisted of three parts. First, a simple betatron oscillation was tracked through each code. Secondly, a set of component misalignments and corrector settings generated from one program was read into the other to confirm similar emittance dilution. Thirdly, given the same set of component misalignments DFS was performed independently in each program and the resulting emittance dilution was compared. Performance was found to agree exceptionally well in all three studies. |
|
|||||
THPMS017 | Design of Muon Accelerators for an Advanced Muon Facility | rfq, acceleration, proton, target | 3032 | |||||
|
Muon beams are produced at Muon Facilities all over the world. They are commonly used in condensed matter physics with mSR (Muon Spin Rotation / Relaxation / Resonance) spectroscopy. Up to today, the applications of mSR are limited by the large sizes of the muon beams (typically 10 cm2). We carried out design works of an Advanced Muon Facility at LANSCE that produces a 'muonμbeam'. The muonμbeam improves beam brightness by three orders of magnitude from that at conventional Muon Facilities and would revolutionize not only material research using mSR spectroscopy but also numerous applications in nano-technology, high-pressure science and bioscience. The designed facility mainly consists of a large acceptance muon channel 'LA Omega' followed by novel muon linear accelerators. This equipment is capable of producing the world?s most intense muon beam of ~109 muon/s at LANSCE. The intense muon beam of LA Omega will be cooled and accelerated with the muon linear accelerators to produce a 50-keV and a separate 10-MeV muonμbeam. The unique time structure of the muon beam produced by the LANSCE linear accelerator optimally matches the muon accelerator.
|
|
|
|||||
THPMS031 | Plasma Wakefield Acceleration Utilizing Multiple Electron Bunches | plasma, electron, single-bunch, acceleration | 3070 | |||||
|
Funding: DoE contract # DE-FG02-92-ER40745 |
We investigate various plasma wakefield accelerator schemes that rely on multiple electron bunches to drive a large amplitude plasma wave, which are followed by a witness bunch at a phase where it will sample the high acceleration gradient and gain energy. Experimental verifications of various two bunch schemes are available in the literature; here we provide analytical calculations and numerical simulations of the wakefield dependency and the transformer ratio when M drive bunches and one witness bunch are fed into a high density plasma, where M is between 2 and 10. This is a favorable setup since the bunches can be adjusted such that the transformer ratio and the efficiency of the accelerator are enhanced compared to single bunch schemes. The possibility of a five bunch ILC afterburner to accelerate a witness bunch from 100 GeV to 500 GeV is also examined. |
|
|||||
THPMS054 | Study of Lattice Beams and their Limitations | cathode, emittance, space-charge, single-bunch | 3112 | |||||
|
Funding: Work supported by U. S. Dept. of Energy contract DE-AC02-76SF00515. |
Luminosity considerations for microscale accelerators intended for high-energy physics place a high premium on the bunch repetition rate and phase space density at the interaction point. The NLC Test Accelerator (NLCTA) at SLAC was built to address such beam dynamics issues for the Next Linear Collider and beyond. Because an S-Band RF gun has been installed together with a low-energy, high-resolving power spectrometer (LES), it is useful to explore alternatives to conventional scenarios with it. We consider possibilities that can be tested with minimal modification to this system e.g. cases that involve producing multiple bunches from the cathode in different formats such as a 2D planar matrix or 3D tensor beam made of smaller bunches or bunchlets that replace the usual, single higher charge bunches. Thus, we study configurations of interacting bunchlets nij or nijk coming from the cathode and passing through the emittance compensating solenoids that can be matched to the linac or focussed on the LES focal plane at 6 MeV. Parmela calculations have been done that show no significant space charge effects or emittance increases for pC bunchlet charges. |
|
|||||
THPMS055 | Beam Dynamics Measurements for the SLAC Laser Acceleration Experiment | gun, laser, emittance, electron | 3115 | |||||
|
Funding: Work supported by U. S. Dept. of Energy contract DE-AC02-76SF00515. |
The NLC Test Accelerator (NLCTA) at SLAC was built to address various beam dynamics issues for the Next Linear Collider. An S-Band RF gun has been installed with diagnostics and a low energy spectrometer (LES) at 6 MeV together with a large-angle extraction line at 60 MeV. This is followed by a matching section, buncher and final focus for the laser acceleration experiment, E163. The laser-electron interaction area is followed by a broad range (2\%), high resolving power (104) spectrometer (HES) for electron bunch analysis. Emittance compensating solenoids and the LES are used to tune for best operating point and match to the linac. Optical symmetries in the design of the 25.5° extraction line provide 1:1 phase space transfer without use of sextupoles for a large, 6D phase space volume and range of input conditions. Spot sizes of a few microns at the IP (or HES object) allow tests of microscale structures as well as high resolving power at the image of the HES. Tolerances, tuning sensitivities and diagnostics are discussed together with the latest commissioning results and their comparison to design expectations. |
|
|||||
THPMS060 | Transport Optics Design and Multi-particle Tracking for the ILC Positron Source | positron, target, optics, electron | 3124 | |||||
|
Funding: U. S. DOE Contract DE-AC02-76SF00515 |
Undulator-based positron source is adopted as the International Linear Collider baseline design. Complete optics to transport the positron beam having large angular divergence and large energy spread from a thin Ti target to the entrance of the 5 GeV damping ring injection line is developed. Start-to-end multi-particle tracking through the beamline is performed including the optical matching device, capture accelerator system, transport system, superconducting booster linac, spin rotators, and energy compressor. Positron capture efficiency of different schemes (immersed vs shielded target, and flux concentrator vs quarter wave transformation for the optics matching system) is compared. For the scheme of a shielded target and quarter wave transformation, the simulation shows that 15.1% of the positrons from the target are captured within the damping ring 6-D acceptance at the entrance of the damping ring injection line. |
|
|||||
THPMS061 | Design of a High-current Injector and Transport Optics for the ILC Electron Source | electron, gun, booster, bunching | 3127 | |||||
|
Funding: U. S. DOE Contract DE-AC02-76SF00515 |
A train of 2-nsμbunches are generated in the DC-gun based injector in the ILC e- source; a bunching system with extremely high bunching efficiency to compress bunch down to 20 ps FWHM is designed. Complete optics to transport the electron beam to the 5-GeV damping ring injection line is developed. Start-to-end multi-particle tracking through the beamline is performed including the bunching system, pre-acceleration, chicane, 5-GeV SC booster linac, spin rotators and energy compressor. It shows more than 95% of electrons from the DC-gun are captured within the 6-D damping ring acceptance at the entrance of damping ring injection line. The field and alignment errors, and orbit correction are analyzed. |
|
|||||
THPMS074 | High Transformer Ratios in Collinear Wakefield Accelerators | laser, gun, simulation, target | 3154 | |||||
|
Funding: DOE SBIR Phase II, DE-FG02-02ER83418. |
Based on our previous experiment that successfully demonstrated wakefield transformer ratio enhancement in a 13.625 GHz dielectric-loaded collinear wakefield accelerator using the ramped bunch train technique, we present here a redesigned experimental scheme for even higher enhancement of the efficiency of this accelerator. Design of a collinear wakefield device with a transformer ratio R>>2, is presented. Using a ramped bunch train (RBT) rather than a single drive bunch, the enhanced transformer ratio (ETR) technique is able to increase the transformer ratio R above the ordinary limit of 2. To match the wavelength of the fundamental mode of the wakefield with the bunch length (σz=2 mm) of the new Argonne Wakefield Accelerator (AWA) drive gun, where the experiment will be performed, a 26.625 GHz dielectric based accelerating structure is required. This transformer ratio enhancement technique based on our dielectric-loaded waveguide design will result in a compact, high efficiency accelerating structure for future wakefield accelerators. |
|
|||||
THPMS079 | Nonlinear Permittivity Effects in Dielectric Accelerating Structures | controls, acceleration, diagnostics, simulation | 3169 | |||||
|
Funding: Work supported by the US Department of Energy |
New low loss ferroelectric ceramic materials* possessing large variations in the permittivity as a function of the electric field present interesting and potentially useful applications for dielectric loaded accelerating structures, both wakefield-based and driven by an external rf source. We will consider X-band cylindrical dielectric structures and report numerical results on frequency multiplication, wave steepening and shock formation, and the effect of nonlinearities on the mode structure of these devices. We will examine applications of nonlinear dielectric devices to high gradient acceleration, rf sources, and beam diagnostics.
* ''Fast Switching Ferroelectric Materials for Accelerator Applications'', A. Kanareykin et al., Proceedings of Advanced Accelerator Concepts 2006 (in press) |
|
|||||
THPMS087 | Low Emittance Electron Beams for the RHIC Electron Cooler | emittance, electron, cathode, space-charge | 3187 | |||||
|
Funding: Work performed under the United Staes Department of Energy Contract No. DE-AC02-98CH1-886. |
An electron cooler, based on an Energy Recovery Linac (ERL) is under development for the Relativistic Heavy Ion Collider (RHIC) at Brookhaven National Laboratory. This will be the first electron cooler operating at high energy with bunched beams. In order to achieve sufficient cooling of the ion beams the electron have to have a charge of 5 nC and a normalized emittance less than 4 mm mrad. This paper presents the progress in optimizing the injector and the emittance improvements from shaping the charge distribution in the bunch. |
|
|||||
THPMS094 | Acceleration of Electrons with the Racetrack Non-Scaling FFAG for e-RHIC | betatron, acceleration, electron, lattice | 3205 | |||||
|
Funding: Supported by the U. S. Department of Energy under Contract No. DE-AC02-98CH10886 |
Acceleration of electrons up to 10 GeV for a future electron-ion collider eRHIC (Relativistic Heavy Ion Collider) could be performed with the energy recovery linac with multiple passes. An energy recovery scheme is required if a superconducting linac is used for acceleration. We report on an attempt to make a combination of a multi-pass linac with non-scaling Fixed Field Alternating Gradient (NS-FFAG) arcs. Two NS-FFAG arcs would allow electrons to pass through the same structure with different energies. The beam will be accelerated by the superconducting linac at the top of the sine function, and returned to the front of the linac by the non-scaling FFAG. This process is repeated until the total energy of 10 GeV is reached. After collisions the beam is brought back by the NS-FFAG and decelerated before being dumped. |
|
|||||
THPAN014 | Beam Dynamics of the 100 MeV Preinjector for the Spanish Synchrotron ALBA | gun, emittance, synchrotron, electron | 3253 | |||||
|
A turn key 100 MeV linac is under construction, in order to inject electrons into the booster synchrotron of ALBA [1]. The linac will deliver electron beams according to two operation modes: a single bunch mode (1 to 16 pulses - 0.25nC each) and a multi-bunch mode (112ns - 4nC). We have calculated the beam dynamics, using our in house code, PRODYN [2], from the gun to the end of the linac. The beam behaviour, such as the radial control, the bunching process, the energy spread and emittance are analysed.
|
[1] D. Einfeld, "Status of the ALBA project", EPAC 06, Scotland, Edinburgh, June 2006.[2] D. Tronc and A. Setty, "Electrons RF auto-focusing and capture in bunchers", Linear Accelerator Conference 1988, Virginia. |
|
|||||
THPAN020 | A Dispersionless Algorithm for Calculating Wake Potentials in 3D | background, simulation | 3268 | |||||
|
Funding: This work is supported in part by the EU under contract number RIDS-011899 (EUROTeV). |
Accurate computations of wake potentials are an important task in modern accelerator design. Short bunches used in high energy particle accelerators excite very high-frequency fields. The geometrical size of accelerating structures exceeds the wavelength of the excited fields by many orders of magnitude. The application of codes such as TBCI, MAFIA or tamBCI are limited due to numerical dispersion effects and memory needs. Recently new codes like PBCI have been developed to overcome these problems. In this work the utilization of dispersionless directions in the leap-frog update scheme on a Cartesian grid are proposed for accurate simulations. In conjunction with a conformal modelling technique which allows for the full Courant time step a moving window technique can be applied. This was previously implemented in a 2D code. In this publication an extension to arbitrary three dimensional problems are presented. |
|
|||||
THPAN022 | Conceptual Studies of the EUROTRANS Front-End | rfq, emittance, acceleration, beam-losses | 3274 | |||||
|
Funding: Work supported by European Commission (contract number: FI6W-CT-2004-516520) |
EUROTRANS (EUROpean Research Programme for the TRANSmutation of High Level Nuclear Waste in an Accelerator Driven System) is calling for an efficient high-current CW front-end accelerator system. A combination of RFQ, normal conducting CH- (Crossbar H-mode) and super-conducting CH-DTL which aims to work at 352MHz and accelerate a 30mA proton beam to 17MeV has been studied as a promising candidate. The preliminary conceptual study results are reported with respect to beam dynamics design. |
|
|||||
THPAN023 | MERLIN-Based Start-to-End Simulations of Luminosity Stability for the ILC | luminosity, simulation, ground-motion, emittance | 3277 | |||||
|
Funding: Supported by the Commission of the European Communities under the 6th Framework Programme "Structuring the European Research Area", contract number RIDS-011899. |
The International Linear Collider (ILC) requires the preservation of an ultra-small vertical emittance from the Damping Ring to the Interaction Point (IP) where the nanometre-sized beams are made to collide. It is well-known that ground motion and component vibration will need to be compensated by fast intra-train feedback systems and slower semi-continuous trajectory corrections. This complex system can in general only be modelled using simulation. In this paper, we report the progress and status of a full-featured so-called start-to-end simulation based on the MERLIN package of the ILC Low Emittance Transport (LET): Bunch compression, acceleration in the superconducting Main Linac, Beam Delivery System and finally collision at the IP. Realistic modelling of the beam-beam is included by using the code GUINEAPIG. Results based on several ground motion and vibration models and configurations of trajectory control are presented. |
|
|||||
THPAN025 | Evaluation of the Component Tolerances for the ILC Main Linac Assuming Global Linear Corrections | emittance, coupling, quadrupole, alignment | 3280 | |||||
|
Funding: This work is supported by the Commission of the European Communities under the 6th Framework Programme 'Structuring the European Research Area', contract number RIDS-011899. |
The small energy-spread, weak wakefields and relatively weak focusing in the ILC superconducting Main Linac result in little or no filamentation beam mismatch errors: linear correlations such as dispersion or cross-plane coupling from transverse misalignment or rotation errors of the quadrupoles respectively do not decohere as the beam is transported (accelerated) along the linac. Using correction available in the Beam Delivery System, the increase in projected emittance due to this linear correlations can to a large degree be corrected. In this paper we present component tolerances based on the assumption of a global correction at the end of the Main Linac. Some discussion on the impact of ground motion is also discussed. |
|
|||||
THPAN043 | Comparison of Trajectory Between Modeling and Experiment for J-PARC Linac | quadrupole, simulation, beam-transport, betatron | 3324 | |||||
|
In the beam commissioning of J-PARC (Japan Proton Accelerator Research Complex) linac, three simulations codes are used to model the accelerator. We have compared with the experimental results obtained in the beam commissioning to date, where a basic agreement has been confirmed between the modeling and the actual beam behavior.
|
|
|
|||||
THPAN045 | Explicit Time Domain Boundary Element Scheme for Dispersion-free Wake Field Calculation of Long Accelerator Structures | simulation, scattering, electromagnetic-fields, electron | 3330 | |||||
|
This paper introduces a new explicit scheme with a moving window option for wake field calculation of long accelerator structures. This scheme is based on a time domain boundary element method (TDBEM) which uses a retarded Kirchhoff boundary integral equation on interior region problems. As a corollary of this boundary integral equation, our approach allows a conformal modeling of a structure and time domain wake field simulation without numerical grid dispersion errors in all spatial directions. The implementation of a moving window technique in the framework of TDBEM is presented and it is shown that this moving window technique allows to significantly reduce memory requirement of the TDBEM scheme in the short range wake field calculation. Several numerical examples are demonstrated for the TESLA 9-cell cavity and tapered collimators. The results of the new TDBEM scheme are compared with that of finite difference codes.
|
|
|
|||||
THPAN057 | Error Analyses of the PEFP 20/100-MeV Beamlines | quadrupole, proton, dipole, lattice | 3357 | |||||
|
Funding: This work was supported by the 21C Frontier R&D program sponsored by Ministry of Science and Technology, Korean Government. |
The proton engineering frontier project (PEFP) 100-MeV proton linac has two main beamline systems to extract and deliver the proton beam to the user. The one is designed to extract 20-MeV proton beams at the medium energy transport system of the linac and to deliver them to five target stations through a beam switching system. The other is able to extract 100-MeV proton beams at the end of the linac and to deliver them to another five target stations trough a beam distribution system. We have completed the detailed beam optics designs of the beamline system and performed intensive error analyses to set the marginal limits of engineering errors of the beamline components by using a dedicated beam transport code. The paper presents the error analysis results of the PEFP beamline systems along with their characteristics and beam optics designs. |
|
|||||
THPAN070 | Advances in MAD-X using PTC | lattice, controls, survey | 3381 | |||||
|
For the last few years the MAD-X program makes use of the Polymorphic Tracking Code (PTC) to perform calculations related to beam dynamics in the nonlinear regime. An important new feature is the extension of the matching module to allow fitting of non-linear parameters to any order. Moreover, calculations can now be performed with parameter dependence defined in the MAD-X input. In addition, the user can access the PTC routines for the placement of a magnet with arbitrary position and orientation. This facilitates the design of non-standard lattices, in particular since a 3D visualization of a lattice is now available. For the LHC studies during commissioning it is of special interest that one has access to within the thick PTC elements which allows e.g. to find PTC Twiss parameters at any point in the ring. Lastly, the beam-beam element has been added to PTC to complete the set of elements available in MAD-X proper.
|
|
|
|||||
THPAN095 | Implementation and Performance of Parallelized Elegant | simulation, collective-effects, space-charge, damping | 3444 | |||||
|
Funding: Work supported by the U. S. Department of Energy, Office of Science, Basic Energy Sciences, under Contract No. DE-AC02-06CH11357. |
The program Elegant* is widely used for design and modeling of linacs for free-electron lasers and energy recovery linacs, as well as storage rings and other applications. As part of a multi-year effort, we have parallelized many aspects of the code, including single-particle dynamics, wakefields, and coherent synchrotron radiation. We report on the approach used for gradual parallelization, which proved very beneficial in getting parallel features into the hands of users quickly. We also report details of parallelization of collective effects. Finally, we discuss performance of the parallelized code in various applications.
*M. Borland, APS Light Source Note LS-287, September 2000. |
|
|||||
THPAN100 | Parallelization of TRACK for Large Scale Beam Dynamic Simulations in Linear Accelerator | simulation, space-charge, emittance, proton | 3459 | |||||
|
Funding: This work was supported by the U. S. Department of Energy, Office of Nuclear Physics, under Contract No. DE-AC-02-06CH11357. |
Large scale beam dynamics simulations are important to support the design and operations of an accelerator. From the beginning, the beam dynamics code TRACK was developed to make it useful in the three stages of a hadron (proton and heavy-ion) linac project, namely the design, commissioning and operation of the machine. In order to combine the unique features of TRACK with large scale and fast parallel computing we have recently developed a parallel version of the code*. We have successfully benchmarked the parallel TRACK on different platforms: BG/L and Jazz at ANL, Iceberg at ARSC, Lemieux at PSC and Seaborg at NERSC. We have performed large scale RFQ and end-to-end simulations of the FNAL proton driver where particles were simulated. The actual parallel version has the potential of simulating particles on 10 racks with 20,480 processors of BG/L at ANL, which will be available soon. After a brief description of the parallel TRACK, we'll present results from highlight applications.
* "Parallelization of a Beam Dynamics Code and First large Scale RFQ Simulations", J. Xu, B. Mustapha, V. N. Aseev and P. N. Ostroumov, accepted for publication in PRST-AB. |
|
|||||
THPAN101 | Parametric Modeling of Transverse Phase Space of an RF Photoinjector | gun, quadrupole, emittance, controls | 3462 | |||||
|
Funding: DOE PHASE II STTR - DE-FG02-04ER86225 |
High brightness electron beam sources such as rf photo-injectors as proposed for SASE FELs must consistently produce the desired beam quality. We report the results of a study in which a combined neural network (NN) and first-principles (FP) model is used to model the transverse phase space of the beam as a function of quadrupole magnet current, while beam charge, solenoid field, accelerator gradient, and linac voltage and phase are kept constant. The parametric transport matrix between the exit of the linac section and the spectrometer screen constitutes the FP component of the combined model. The NN block provides the parameters of the transport matrix as functions of quad current. Using real data from SLAC Gun Test Facility, we will highlight the significance of the constrained training of the NN block and show that the phase space of the beam is accurately modelled by the combined NN and FP model, while variations of beam matrix parameters with the quad current are correctly captured. We plan to extend the combined model in the future to capture the effects of variations in beam charge, solenoid field, and accelerator voltage and phase. |
|
|||||
THPAN112 | CHEF: A Status Report | optics, emittance, simulation, lattice | 3486 | |||||
|
Funding: Authored by Universities Research Association, Inc. under contract No. DE-AC02-76CH03000 with the U. S. Department of Energy. |
CHEF is both a framework and an interactive application emphasizing accelerator optics calculations. The framework supports, using a common infrastructure, multiple domains of applications: e.g. nonlinear analysis, perturbation theory, and tracking. Its underlying philosophy is to provide infrastructure with minimum hidden implicit assumptions, general enough to facilitate both routine and specialized computational tasks and to minimize duplication of necessary, complex bookkeeping tasks. CHEF was already described in recent conferences. In this paper we present a status report on the most recent developments, including issues related to its application to high energy linacs. |
|
|||||
THPAS002 | Evolution of Longitudinal Modulation in Electron Beams | simulation, electron, radiation, gun | 3510 | |||||
|
Electron beams with periodic longitudinal density modulations may produce terahertz radiation in a linear accelerator. Whether the radiation is desired or not, it would be useful to understand how the modulations of an electron bunch evolve as the beam is transported through a linac system. Recent studies (*) show that density modulated beams lose their density modulation in favor of energy modulation. Thus, it is instructive to simulate beams that have only density modulation and beams that have only energy modulation. The former is useful for learning how to keep the desired density modulation for beams intended to create terahertz radiation, the latter for learning how to suppress unwanted energy modulation, which may have originated as density modulation. In this study, simulations are performed using PARMELA and other software codes. The study investigates energy ranges that are higher than those studied in the authors previous work, and the study also focuses on the evolution of the beam in the electron gun. Parameters in the simulations are chosen to correspond to existing accelerator systems so that the results may be used to support an experimental study.
|
(*) Simulation of Longitudinally Modulated Electron Beams. C. P. Neuman and P. G. O'Shea. In 2006 Advanced Accelerator Concepts Workshop, AIP Conference Proceedings 877, edited by M. Conde and C. Eyberger, 621-627. Melville, NY, AIP (2006). |
|
|||||
THPAS007 | Parallel Beam Dynamics Simulation Tools for Future Light Source Linac Modeling | simulation, electron, space-charge, emittance | 3522 | |||||
|
Large-scale modeling on parallel computers is playing an increasingly important role in the design of future light sources. Such modeling provides a means to accurately and efficiently explore issues such as limits to beam brightness, emittance preservation, the growth of instabilities, etc. Recently the IMPACT codes suite was enhanced to be applicable to future light source design. Early simulations with IMPACT-Z were performed using up to 100M simulation particles for the main linac of a future light source. Combined with the time domain code IMPACT-T, it is now possible to perform large-scale start-to-end linac simulations for future sources, including the injector, main linac, chicanes, and transfer lines. In this paper we provide an overview of the IMPACT code suite, its key capabilities, and recent enhancements pertinent to accelerator modeling for future linac-based light sources.
|
|
|
|||||
THPAS015 | Three-Dimensional Integrated Green Functions for the Poisson Equation | space-charge, simulation, induction, accelerator-theory | 3546 | |||||
|
Funding: Supported by US DOE Office of Science: Offices of Nuclear Physics, grant DE-FG02-03ER83796; High Energy Physics; and Advanced Scientific Computing Research, SciDAC Accelerator Science and Technology. |
The standard implementation of using FFTs to solve the Poisson equation with open boundary conditions on a Cartesian grid loses accuracy when the change in G rho (the product of the Green function and the charge density) over a mesh cell becomes nonlinear; this is commonly encountered in high aspect ratio situations and results in poor efficiency due to the need for a very large number of grid points. A modification which solves this problem, the integrated Green function (IGF), has been implemented in two dimensions using linear basis functions and in three dimensions using constant basis functions. But, until recently, it has proved to be very difficult to implement IGF in three dimensions using linear basis functions. Recently significant progress has been made. We present both the implementation and test results for the three-dimensional extension. |
|
|||||
THPAS037 | Open Architecture Software Integration System (OASIS) for the Particle Beam Optics Laboratory (PBO Lab) | optics, target, quadrupole, simulation | 3579 | |||||
|
Funding: This work has been supported by the U. S. Department of Energy (DOE) Small Business Innovative Research (SBIR) program under grant number DE-FG02-04ER83961. |
The Particle Beam Optics Laboratory, or PBO Lab, is a suite of software applications developed to support beamline design, accelerator operations, and personnel training. The software provides an intuitive and easy-to-use graphic user interface (GUI) that works with a variety of particle optics codes. The PBO Lab GUI is largely responsible for the popularity of this software suite, which is now used at more than ninety institutions throughout the world. While PBO Lab greatly improves the human-machine interface for several popular optics programs, it has historically required a significant effort to incorporate additional optics codes into the software suite. The Open Architecture Software Integration System, or OASIS, provides an innovative framework that allows users to readily integrate their own optics programs into PBO Lab. This paper provides an overview of the OASIS framework and describes some of the new PBO Lab Modules that have been created using OASIS. |
|
|||||
THPAS043 | Controlling Coupler-kick Emittance Growth in the Cornell ERL Main Linac | emittance, simulation, lattice, controls | 3591 | |||||
|
Funding: Supported by Cornell University and NSF grant PHY 0131508 |
One of the main concerns in the design of a high energy Energy Recovery Linac x-ray source is the preservation of beam emittance. Discussed is one possible source of emittance dilution due to transverse electromagnetic fields in the accelerating cavities of the linac caused by the power coupler geometry. This has already been found to be a significant effect in Cornell's ERL injector cavities if only one coupler per cavity is chosen. Here we present results of simulations for Cornell's main ERL linac with three possible coupler configurations and compare them with regards to total normalized emittance growth after one complete pass through the linac. We explain why the sign of the phase between the transverse kick and the accelerating force alternates each cavity, which leads to a cancellation of the emittance growth to acceptable values. We also investigate the effect of cavity detuning on the coupler-kick effect. |
|
|||||
THPAS051 | The RIAPMTQ/IMPACT Beam-Dynamics Simulation Package | simulation, heavy-ion, beam-losses, rfq | 3606 | |||||
|
Funding: This work is supported by the U. S. Department of Energy, DOE contract number:W-7405-ENG-36 |
RIAPMTQ/IMPACT is a pair of linked beam-dynamics simulation codes that have been developed for end-to-end computer simulations of multiple-charge state heavy-ion linacs for future exotic-beam facilities. The simulations can extend from the low-energy beam transport after the ECR source to the end of the linac. The work has been performed by a collaboration including LANL, LBNL, ANL, MSU, and TechSource. The code RIAPMTQ simulates the linac front end including the LEBT, RFQ, and MEBT, and the code IMPACT simulates the main superconducting linac. The codes have been benchmarked for rms beam properties against previously existing codes at ANL and MSU. The codes allow high-statistics runs on parallel supercomputing platforms, such as NERSC at LBNL, as well as runs on desktop PC computers for low-statistics design work. We will show results from 10-million-particle simulations of RIA designs by ANL and MSU, carried out at the NERSC facility. These simulation codes will allow evaluations of candidate designs with respect to beam-dynamics performance including beam losses. |
|
|||||
THPAS060 | LCLS Beam Dynamics Studies with the 3-D Parallel Impact-T Code | space-charge, emittance, simulation, electron | 3624 | |||||
|
In 2007, the Linac Coherent Light Source (LCLS) will start to commission the photoinjector, the linacs (up to 250 MeV) and the first bunch compressor (BC1). In this paper, we report on the beam dynamics studies in this low-energy part of the machine with the parallel Impact-T code*, taking into account three-dimensional (3-D) space charge forces, linac wakefields, and coherent synchrotron radiation. We compare the IMPACT-T simulation results with PARMELA and discuss possible space charge effects in the linac and BC1 regions. We also plan to compare with experimental measurements when they become available.
|
* J. Qiang et al, Phys. Rev. ST Accel. Beams 9,044204 (2006). |
|
|||||
THPAS072 | Multipass Steering Protocols at Jefferson Lab | injection, quadrupole, controls, focusing | 3648 | |||||
|
Funding: Authored by Jefferson Science Associates, LLC under U. S. DOE Contract No. DE-AC05-06OR23177 |
The CEBAF recirculating accelerator consists of two CW superconducting RF linacs, through which an electron beam is accelerated for up to 5 passes. Focusing and steering elements affect each pass differently, requiring a multipass steering protocol to correct the orbits. Perturbations include lens misalignments (including long-term ground motion), BPM offsets, and focusing and steering from RF fields inside the cavities. A previous treatment of this problem assumed all perturbations were localized at the quadrupoles and the absence of x-y coupling. Having analyzed the problem and characterized the solutions, we developed an empirical iterative protocol to compare against previous results in the presence of skew fields and cross-plane coupling. We plan to characterize static and acceleration-dependent components of the beam line perturbations to allow systematic and rapid configuration of the accelerator at different linac energy gains. |
|
|||||
THPAS087 | ACCELVIEW: A Graphical Means for Driving Integrated Numerical Experiments | simulation, lattice, controls, quadrupole | 3687 | |||||
|
Funding: Work supported by the US Department of Energy. |
Many simulation efforts make use of integrated numerical experiments, where the inputs and outputs of several accelerator codes are tied together. This is usually accomplished by writing custom scripts that launch the underlying programs and perform data format translation. We present a way to simplify this process by using a graphical user interface that allows one to describe the data flow in the style of the LabVIEW and Simulink environments. A module to support a new accelerator code involves writing data translators to/from a common format (SDDS or HDF5), and a function to generate an input file based on a standard way of specifying an accelerator lattice (such as Accelerator Markup Language, or AML). |
|
|||||
THPAS096 | Optics of a Two-Pass ERL as an Electron Source for a Non-Magnetized RHIC-II Electron Cooler | electron, emittance, gun, simulation | 3708 | |||||
|
Funding: Work performed under the auspices of the U. S. Department of Energy contract No DE-AC02-98CH1-886 with support from the US Department of Defense. |
Non-magnetized electron cooling of RHIC requires an electron beam energy of 54.3 MeV, electron charge per bunch of 5 nC, normalized rms beam emittance of 4 mm-mrad, and rms energy spread of 3·10-4 *. In this paper we describe a lattice of a two-pass SCRF energy recovery linac (ERL) and results of a PARMELA simulation that provides electron beam parameters satisfying RHIC electron cooling requirements.
* A. Fedotov, Electron Cooling Studies for RHIC II http://www.bnl.gov/cad/ecooling/docs/PDF/Electron_Cooling.pdf |
|
|||||
THPAS097 | Merger System Optimization in BNL's High Current R&D ERL | electron, emittance, gun, space-charge | 3711 | |||||
|
Funding: Work performed under the auspices of the U. S. Department of Energy contract No DE-AC02-98CH1-886 with support from the US Department of Defense. |
A super-conducting RF R&D Energy recovery linac (ERL) is under construction at Brookhaven National Laboratory (BNL). This ERL will be used as a test facility to study issues relevant to high-current, high-brightness beams. One of the goals is to demonstrate an electron beam with high charge per bunch (~ 5 nC) and extremely low normalized emittance (~ 5 mm-mrad) at an energy of 20 MeV. In contrast with operational high-brightness linear electron accelerators, all presently operating ERLs have an order of magnitude larger emittances for the same charge per bunch. One reason for this emittance growth is that the merger system mixes transverse and longitudinal degrees of freedom, and consequently violates emittance compensation conditions. A merger system based on zigzag scheme* resolves this problem. In this paper we discuss performance of the present design of the BNL R&D ERL injector with a zigzag merger.
* V. N. Litvinenko, R. Hajima, and D. Kayran, Nucl. Instr. and Meth. A 557 (2006) 165. |
|
|||||
FRXC01 | SNS RF System Performance and Operation | klystron, controls, cathode, monitoring | 3792 | |||||
|
The Spallation Neutron Source (SNS) Linac and Accumulator Ring utilize 100 Radio-Frequency (RF) systems for acceleration and bunching of the proton beam. Several different types of gridded tubes and klystrons are operated at 1, 2, 402.5 and 805 MHz, at power levels ranging from a few kilowatts to several megawatts to drive several types of accelerating cavities, both normal- and super-conducting. The RF systems are standardized, especially in the Linac, to ease operation and maintenance. Phase and amplitude control is achieved with a digital low-level RF control system. The RF systems operate reliably and support production of a high-quality low-loss proton beam. Various modifications and upgrades have been made or are in progress to enhance system reliability and performance. Planning is well underway for a power upgrade that will require an additional 36 RF systems.
|
|
|
Slides
|
|
|
||
FROAC02 | RF Amplifier Choice for the ISAC Superconducting Linac | controls, diagnostics, power-supply, monitoring | 3798 | |||||
|
A superconducting linac is being commissioned at TRIUMF as an extension to the existing room temperature accelerator of exotic ions at ISAC. It will increase the isotope final energy from 1.5 to 6.5 MeV/u. Acceleration is accomplished in 40 bulk niobium quarter wave superconducting cavities operating at 106 and 141 MHz. Each cavity is energized from an independent RF amplifier with power rating up to 1 kW cw. Both vacuum tube and solid state amplifiers were considered as a viable option for the drivers. The paper compares many important parameters of these 2 amplifiers such as reliability, serviceability, capital and maintenance costs, as well as operating characteristics: gain linearity, phase noise, phase drift and others. Test results of prototypes of both types of amplifiers and 1 year operational experience of 20 tube amplifiers are discussed. Based on that the amplifier design requirements are formulated.
|
|
|
Slides
|
|
|
||
FROAC05 | Systems Design Concepts for Optical Synchronization in Accelerators | laser, controls, site | 3807 | |||||
|
Funding: This work is supported by the Director, Office of Science, High Energy Physics, U. S. Dept. of Energy under Contract no. DE-AC02-05CH1121 |
Development of accelerator-based light sources is expanding the size of femtosecond laser systems from tabletop devices up to kilometer-scale facilities. New optical techniques are needed to maintain temporal stability in these large systems. We present methods for distributing timing information over optical fiber using continuous optical waves, and how these can be employed in advanced accelerators requiring less than 100fs timing stability. Different techniques combine to form a tool set that can provide for synchronization down to a few femtoseconds. Practical examples are given for timing systems applicable to FELs now under construction, with experimental results to show these systems can be built with required performance. For example, have demonstrated 2km fiber links with 5fs timing stability over 24 hours, and synchronized femtosecond lasers separated by a fiber link with 20fs RMS relative jitter. |
|
|||||
FROAC06 | Survey of LLRF Development for the ILC | controls, klystron, feedback, linear-collider | 3810 | |||||
|
Funding: FRA |
The key to a successful LLRF design for the International Linear Collider (ILC) relies on a combined effort from the different laboratories involved in this global project. This paper covers the ILC LLRF design progress both long term and for current test facilities around the world. Much of the focus is towards the ILC Test Area and on inter-laboratories collaborations. The SIMCON controller board, originally developed at DESY has been successfully used at FNAL to control the superconducting capture cavity I and II. A joined effort is also underway to modify its hardware to improve its noise performance and upgrading the firmware to achieve a higher intermediate frequency operation. In parallel, several simulation models (U-Penn, FNAL) have been developed in addition to the Simulink based model from DESY. The motivation is to investigate such issues as variable gradients, low beam conditions and bunch compression. Finally, an active exchange of knowledge and expertise continues to occur during collaboration meetings and through mutual participation in accelerator tests and commissioning (Dec06/Jan07 at DESY). |
|
Slides
|
|
|
||
FROBC01 | 30 GHz High-Gradient Accelerating Structure Test Results | acceleration, electron | 3818 | |||||
|
The CLIC study is high power testing accelerating structures in a number of different materials and accelerating structure designs to understand the physics of breakdown, determine the appropriate scaling of performance and in particular to find ways to increase achievable accelerating gradient. The most recent 30 GHz structures which have been tested include damped structures in copper, molybdenum, titanium and aluminum. The results from these new structures are presented and compared to previous ones to determine dependencies of quantities such as achievable accelerating gradient, pulse length, power flow, conditioning rate and breakdown rate.
|
|
|
Slides
|
|
|
||
FROBC02 | RF Structures for Linac4 | coupling, klystron, alignment, quadrupole | 3821 | |||||
|
Linac4 is proposed to replace the existing proton linac at CERN (Linac2). Using an increased injection energy of 160 MeV instead of 50 MeV Linac4 is expected to double the beam intensity in the PS Booster and will thus be the first step towards higher brightness beams in the LHC. In this paper we re-assess the choice of RF structures for Linac4. Different accelerating structures for different energy ranges are compared in terms of RF efficiency, ease of construction and alignment, necessary infrastructure, and cost. Eventually we present the final choice of structures for Linac4.
|
|
|
Slides
|
|
|
||
FROBC03 | Efficient Accelerating Structures for Low-Energy Light Ions | focusing, rfq, quadrupole, impedance | 3824 | |||||
|
The radio-frequency quadrupole (RFQ) accelerator is the best structure immediately after an ion source for accelerating light-ion beams with considerable currents. On the other hand, the higher-energy part of the RFQ is known to be not a very efficient accelerator. We consider alternative room-temperature RF accelerating structures for the beam velocities in the range of a few percent of the speed of light - including H-mode cavities and drift-tube linacs - and compare them with respect to their efficiency, compactness, ease of fabrication, and overall cost. Options for the beam transverse focusing in such structures are discussed. Possible applications include a compact deuteron-beam accelerator up to the energy of a few MeV for homeland defense.
|
|
|
Slides
|
|
|
||
FRPMN010 | Emittance Measurements at the 100 keV Beam Stage of the Injector Linac of the IFUSP Microtron | emittance, microtron, cathode, acceleration | 3898 | |||||
|
Funding: Work supported by FAPESP and CNPq |
In this work we describe the determination of the beam emittance for the 100-keV injector of the IFUSP racetrack microtron. We measured the beam spot diameter at a fluorescent screen located 40 cm after a 3-mm diameter collimator (placed at the entrance to the first chopper cavity). A solenoid lens located upstream to the collimator was used to produce a beam waist at the fluorescent screen position. We used the collimator and the beam waist sizes to calculate the emittance for 80 and 90 keV beams. Results showed no dependence with energy, indicating that the collimator is limiting the beam emittance at 2.32(5) ??mm?mrad. |
|
|||||
FRPMN043 | Measurement of Beam Position Monitor Using HOM Couplers of Superconducting Cavities | pick-up, dipole, electron, monitoring | 4060 | |||||
|
The offset beam from the axis induces the HOMs in the cavities. These HOMs in superconducting cavities are usually damped by HOM couplers to suppress the beam instability. The induced HOM power is proportional to the beam offset and can be used to measure the beam position inside the cavity. The shifter magnet is installed to the JAEA superconducting ERL-FEL to vary the beam position. The HOM power from the HOM coupler with various beam position is measured. The result of the beam test is presented.
|
|
|
|||||
FRPMN045 | Beam Position Monitor and its Calibration in J-PARC LINAC | monitoring, quadrupole, pick-up, background | 4072 | |||||
|
The beam commissioning of J-PARC linac has been started in November 2006. Beam Position Monitors (BPMs) which have been calibrated on the bench setup with a scanning wire, utilize beam based calibration to relate the BPM center and the center of Q magnet. In this presentation, detail of installed BPM and the calibration methods are described.
|
|
|
|||||
FRPMN047 | Development of a Beam Induced Heat-Flow Monitor for the Beam Dump of the J-PARC RCS | proton, radiation, electron, controls | 4084 | |||||
|
A beam induced heat-flow monitor (BIHM) will be installed in front of the beam dump of the RCS (Rapid Cycling Synchrotron) at J-PARC (Japan Particle Accelerator Research Complex), where a power limitation of the beam dump is 4 kW. The purposes of this monitor are to observe a beam current injected into the beam dump and to generate an alarm signal for the main control system of the RCS. At the BIHM the beams penetrate a carbon plate of 1.5 mm in thickness, where the plate is supported by four rods on the monitor chamber. The heat generated by the interactions between the beam and the carbon plate propagates to the outer edge of the plate, and then to the monitor chamber through the four rods. By measuring the temperature differences between upstream and downstream ends of each rod, the total heat flow can be measured. The beam current can be determined by the measured heat flow with the help of the calculated stopping power of a proton in a carbon material. The design of the BIHM and test results of a prototype will be described.
|
|
|
|||||
FRPMN056 | Beam Current and Energy Measurement of the PEFP 20 MeV Accelerator | proton, rfq, controls, diagnostics | 4129 | |||||
|
Funding: This work is supported by the 21C Frontier R&D program in the Ministry of Science and Technology of the Korean government. |
The beam test of the Proton Engineering Frontier Project (PEFP) 20 MeV proton linear accelerator started again, after the upgrade of the RF control system, One of the important goals of the test is to increase the beam current to the design level. Tuned current transformers were installed along the DTL tanks to measure the beam current itself and possible beam loss along the accelerator. Because there were no empty drift tubes, the current transformers should be installed between DTL tanks. Therefore, the tuning plans were developed to obtain the desired beam properties with the limited number of beam diagnostic devices. Also two BPMs for the time of flight measurement and energy degrader were installed at the end of the 20 MeV accelerator to measure the beam energy. In this paper, the overall test results including beam current and energy measurement are presented. |
|
|||||
FRPMN060 | Beam Loss Simulation of SNS LINAC | simulation, radiation, beam-losses, monitoring | 4138 | |||||
|
Funding: SNS is managed by UT-Batelle, LLC, under contract DE-AC05-00OR22725 for the U. S. Department of Energy. |
We are developing a sophisticated system of beam loss pattern evaluation and residual radiation estimation. We have installed a number of Neutron Detectors and Ionization Chambers along LINAC. In this paper we present our implementation and simulation of the losses by inserting Faraday Cups, using Beam Stops and running Wire Scanners at different energies. The measured losses are simulated by 3-D transport codes (GEANT4, SHIELD, MCNPX). We compare two different sets of Beam Loss Monitors: Ionization Chambers (detecting X-ray and gamma radiation) and Photo-Multiplier Tubes with a neutron converter (detecting neutrons) and outline that such a combination is a better way to measure beam losses than relying on detectors of one type. We interpret the loss signal in terms of beam current lost in the SNS LINAC with accurate longitudinal loss distribution and plan to automate beam steering according to loss monitors readings by using vast Loss Pattern Database developed by simulating different loss scenarios with the transport codes. |
|
|||||
FRPMN063 | Superconducting RF Gun Cavities for large Bunch Charges | emittance, gun, focusing, cathode | 4150 | |||||
|
The first electron beam of the RF gun with a 3.5 cell superconducting cavity is expected in July 2007 in FZD. This cavity has been designed for small bunch charges. In the paper we present the design of a similar cavity and of 1.5 cell gun cavities for large bunch charges. For a charge of 2.5 nC, which is the design value of the BESSY-FEL, and a bunch length of 21 ps a projected transverse emittance less then 1 π mm mrad has been obtained (without thermal emittance).
|
|
|
|||||
FRPMN083 | RF Feed-Forward Control Experiments for the 50 MeV Linear Accelerator at TLS | controls, klystron, booster, synchrotron | 4258 | |||||
|
Performance of an electron linear accelerator is very important for synchrotron light source application. Its performance will decide the reproducibility of filling pattern in the booster synchrotron. The filling pattern of the booster synchrotron will affect filling pattern control of the storage ring. The RF feed-forward control can improve performance of linear accelerator deistically. Design consideration and details of the implementation will be summary in this report.
|
|
|
|||||
FRPMN090 | A Prototype Energy Spectrometer for the ILC at End Station A in SLAC | dipole, feedback, collider, linear-collider | 4285 | |||||
|
The main physics programme of the international linear collider requires a measurement of the beam energy with a relative precision on the order of 10-4 or better. To achieve this goal a magnetic spectrometer using high resolution beam position monitors (BPM) has been proposed. A prototype spectrometer chicane using 4 dipole magnets is currently under development at the End Station A in SLAC, intending to demonstrate the required stability of this method and investigate possible systematic effects and operational issues. This contribution reports on the successful commissioning of the beam position monitor system and the resolution and stability achieved. Also, the initial results from a run with a full spectrometer chicane are presented.
|
|
|
|||||
FRPMN091 | Simulation of HOM Wakefields in the Main ILC Cavities | simulation, dipole, emittance, damping | 4288 | |||||
|
We investigate the electromagnetic field (e.m.) excited by a train of multiple bunches in the main superconducting linacs of the ILC. These e.m. fields are represented as a wake-field. Detailed simulations are made for the modes which constitute the long-range wake-field in new high gradient cavity structures. In particular, we focus our study on the modes in re-entrant and low loss Ichiro cavities. Modes trapped within a limited number of cells can give rise to a significant diminution in the emittance of the beam and we pay particular attention to these modes. Beam tracking simulations on the resulting emittance dilution over the entire length of the linac are made in order to provide details on the damping which is necessary for modes with particularly large kick factors.
|
|
|
|||||
FRPMN102 | An Instrument Design for the Accurate Determination of the Electron Beam Location in the Linac Coherent Light Source Undulator | undulator, alignment, electron, vacuum | 4324 | |||||
|
Funding: Work supported by U. S. Department of Energy, under Contract Nos. DE-AC02-06CH11357 and DE-AC03-76SF00515. |
The Linac Coherent Light Source (LCLS), currently under design, requires accurate alignment between the electron beam and the undulator magnetic centerline. A Beam Finder Wire (BFW) instrument has been developed to provide beam location information that is used to move the undulators to their appropriate positions. A BFW instrument is mounted at each of the 33 magnets in the undulator section. Beam detection is achieved by electrons impacting two carbon fiber wires and then sensing the downstream radiation. The wires are mounted vertically and horizontally on a wire card similar to that of a traditional wire scanner instrument. The development of the BFW presents several design challenges due to the need for high accuracy of the wires' location and the need for removal of the wires during actual operation of the LCLS (30 microns repeatability is required for the wire locations). In this paper, we present the technical specification, design criteria, mechanical design, and results from prototype tests for the BFW. |
|
|||||
FRPMN111 | Design and Performance of the LCLS Cavity BPM System | undulator, dipole, coupling, alignment | 4366 | |||||
|
Funding: Work supported by U. S. Department of Energy under Contract Nos. DE-AC02-06CH11357 and DE-AC03-76SF00515 |
In this paper we present the design of the beam position monitor (BPM) system for the LCLS undulator, which features a high resolution X-band cavity BPM. Each BPM has a TM010 monopole reference cavity and a TM110 dipole cavity designed to operate at a center frequency of 11.384 GHz. The signal processing electronics features a low-noise single-stage three-channel heterodyne receiver that has selectable gain and a phase locking local oscillator. We will discuss the system specifications, design, and prototype test results. |
|
|||||
FRPMN114 | Feasibility of Near-field ODR Imaging of Multi-GeV Electron Beams at CEBAF | radiation, polarization, electron, target | 4381 | |||||
|
Funding: Work supported by U. S. Department of Energy, Office of Science, Office of Basic Energy Sciences, under Contract No. DE-AC02-06CH11357 and U. S. DOE Contract No. DE-AC05-06OR23177. |
We have evaluated the feasibility of using the optical diffraction radiation (ODR) generated as a 1- to 6-GeV CW electron beam passes nearby the edge of a single metal conducting plane as a nonintercepting (NI) relative beam size monitor for CEBAF. Previous experiments were successfully done using near-field imaging on the lower-current, 7-GeV beam at APS, and an analytical model was developed for near-field imaging. Calculations from this model indicate sufficient beam-size sensitivity in the ODR profiles for beam sizes in the 30-50 micron regime as found in the transport lines of CEBAF before the experimental targets. With anticipated beam currents of 100 microamps, the ODR signal from the charge integrated over the video field time should be ~500 times larger than in the APS case. These signal strengths will allow a series of experiments to be done on beam energy dependencies, impact parameters, polarization effects, and wavelength effects that should further elucidate the working regime of this technique and test the model. Plans for the diagnostics station that will also provide reference optical transition radiation (OTR) images will also be described. |
|
|||||
FRPMN118 | LCLS-S1 Optical Transition Radiation Monitor | undulator, radiation, diagnostics, target | 4396 | |||||
|
Funding: Work supported by the U. S. Department of Energy, under Contract Nos. DE-AC02-06CH11357 and DE-AC03-76SF00515. |
ANL has developed a high-resolution optical transition radiation (OTR) imaging monitor system for the LCLS injection linac at SLAC. The imaging station, OTR-S1, will be located at the S1 spectrometer with a beam energy of 135 MeV. The system will be used to acquire 2-D transverse beam distributions of the accelerated photocathode-gun-generated electron beam. We anticipate an average beam current of 0.2-1 nC and nominal beam spot size of σ-x 130 microns, σ-y 100 microns. The imaging system was designed for a field of view h/v: 10x7.5 mm. The spatial resolution of ~12 microns was verified over the central 5x4 mm region in the visible. A 12-bit digital camera acquires the image and a Mac-based digital frame capturing system was employed for the initial lab-based performance testing of the device. We are reporting on system development, image capture system, testing methodology, and test data analysis. Commissioning results will be reported as they become available. |
|
|||||
FRPMS032 | High-Order Modeling of an ERL for Electron Cooling in the RHIC Luminosity Upgrade using MaryLie/IMPACT | space-charge, electron, luminosity, simulation | 4000 | |||||
|
Funding: Work supported by the U. S. DOE Office of Science, Office of Nuclear Physics under grant DE-FG02-03ER83796. |
Plans for the RHIC luminosity upgrade call for an electron cooling system that will place substantial demands on the energy, current, brightness, and beam quality of the electron beam. In particular, the requirements demand a new level of fidelity in beam dynamics simulations. New developments in MaryLie/IMPACT have improved the space-charge computations for beams with large aspect ratios and the beam dynamic computations for rf cavities. We present the results of beam dynamics simulations that include the effects of space charge and nonlinearities, and aim to assess the tolerance for errors and nonlinearities on current designs for a super-conducting ERL. |
|
|||||
FRPMS042 | Electron Beam Diagnostics for Compact 1.2 GeV Booster Synchrotron | booster, synchrotron, diagnostics, storage-ring | 4051 | |||||
|
Funding: Supported by US DoE grant #DE-FG02-01ER41175. |
First operational experience has been gained with the linac and booster diagnostic system during the commissioning of the booster synchrotron at Duke University. Beam charge measurements are provided by Faraday cups, Integrated Current Transformers (ICT) and Modular Parametric Current Transformer (MPCT). Beam position monitoring is based on BPM system delivered from Bergoz company. Betatron tune measurements use synchrotron radiation (SR) and are different for two modes of operation: stored beam and energy ramping. Transverse profile and temporal beam structure monitoring employ insertable screens, CCD cameras, striplines and dissector. The diagnostics provided good understanding of electron beam behavior and allowed to adjust important beam parameters within design specifications. An overview of the diagnostic instrumentation of the Duke linac and booster synchrotron is given along with measurement examples and discussion of operational experience. |
|
|||||
FRPMS045 | Non-Destructive Single Shot Bunch Length Measurements for the CLIC Test Facility 3 | electron, klystron, pick-up, radiation | 4069 | |||||
|
Funding: DOE |
A non-destructive bunch length detector has been installed in the CLIC Test Facility (CTF3). Using a series of down-converting mixing stages and filters, the detector analyzes the power spectrum of the electromagnetic field picked-up by a single waveguide. This detector evolved from an earlier system which was regularly used for bunch length measurements in CTF2. Major improvements are increase of frequency reach from 90 GHz to 170 GHz, allowing for sub-pico second sensitivity, and single shot measurement capability using FFT analysis from large bandwidth waveform digitisers. The results of the commissioning of the detector in 2006 are presented. |
|
|||||
FRPMS051 | Proposed Beam Diagnostics Instrumentation for the LANSCE Refurbishment Project | instrumentation, simulation, bunching, beam-losses | 4099 | |||||
|
Funding: *Work supported by the U. S. Department of Energy. |
Presently, the Los Alamos National Laboratory is in the process of planning a refurbishment of various sub-systems within its Los Alamos Neutron Science Center accelerator facility. A part of this LANSCE facility refurbishment will include some replacement of and improvement to existing older beam diagnostics instrumentation. While plans are still being discussed, some instrumentation that is under improvement or replacement consideration are beam phase and position measurements within the 805-MHz side-coupled cavity linac, slower wire profile measurements, typically known as wire scanners, and possibly additional installation of fast ionization-chamber loss monitors. This paper will briefly describe the requirements for these beam measurements, what we have done thus far to answer these requirements, and some of the technical issues related to the implementation of these instrumentation. |
|
|||||
FRPMS052 | H+ and H- Beam Position and Current Jitter at LANSCE | isotope-production, quadrupole, kicker, feedback | 4105 | |||||
|
Funding: *Work supported by the U. S. Department of Energy. |
During the CY2005 and CY2006 Los Alamos Neutron Science Center (LANSCE) beam runs, six beam-development shifts were performed in order to acquire and analyze beam-current and beam-position jitter data for both the LANSCE H+ and H- beams. These data were acquired using three beam position monitors (BPMs) from the 100-MeV Isotope Production Facility (IPF) beam line and three BPMs from the Switchyard transport line at the end of the LANSCE 800-MeV linac. The two types of data acquired, intermacropulse and intramacropulse, were analyzed for statistical and frequency characteristics as well as various other correlations including comparing their phase-space characteristics in a coordinate system of transverse angle versus transverse position. This paper will briefly describe the measurements required to acquire these data, the analysis of these jitter data, and some interesting implications to beam operation. |
|
|||||
FRPMS053 | Electromagnetic Modeling of Beam Position and Phase Monitors for LANSCE Linac | coupling, pick-up, simulation, diagnostics | 4111 | |||||
|
Electromagnetic modeling has been used to compare pickup designs of the beam position and phase monitors (BPPM) for the Los Alamos Neutron Science Center (LANSCE) linac. This study is a part of the efforts to upgrade LANSCE beam diagnostics*. MAFIA 3-D time-domain simulations with an ultra-relativistic beam allow computing the signal amplitudes and phases on the BPPM electrodes for the given processing frequency, 402.5 MHz, as functions of the beam transverse position. An analytical model can be applied to extrapolate the simulation results to lower beam velocities. Based on modeling results, a BPPM design with 4 one-end-shorted electrodes each covering 60-degree subtended angle, similar to the SNS linac BPPM**, appears to provide the best combination of mechanical and diagnostics properties for the LANSCE side-coupled linac.
|
* J. D. Gilpatrick et al. These proceedings.** S. S. Kurennoy and R. E. Shafer, EPAC 2000 (Vienna, Austria, 2000), 1768. |
|
|||||
FRPMS055 | LANSCE Prototype Beam Position and Phase Monitor (BPPM) Mechanical Design | alignment, vacuum, isotope-production, pick-up | 4123 | |||||
|
Funding: Work supported by United States Department of Energy |
A prototype Beam Position and Phase Monitor (BPPM) beam line device is being designed to go in the LANSCE 805-MHz linac. The concept is to install two beam line devices in locations where their measurements can be compared with older existing Delta-T loop and wire scanner measurements. The plan is to install two devices so that transverse position, angular trajectory, as well as central beam phase and energy will be measured. The mechanical design will combine features from previous LANL designs that were done for the LANSCE Isotope Production Facility, LANSCE Switchyard project, and those done for the SNS linac. This paper will discuss the mechanical design and fabrication issues encountered during the course of developing the BPPM. |
|
|||||
FRPMS059 | Generation and Analysis of Subpicosecond Double Electron Bunch at the Brookhaven Accelerator Test Facility | electron, simulation, radiation, synchrotron | 4132 | |||||
|
Funding: U. S.DOE of Science |
Two compressed electron beam bunches from a single 60-MeV bunch have been generated in a reproducible manner during compression in the magnetic chicane - "dog leg" arrangement at ATF. Measurements indicate they have comparable bunch lengths (~100-200 fs) and are separated in energy by ~1.8 MeV with the higher-energy bunch preceding the lower-energy bunch by 0.5-1 ps. Some simulation results for analyzing the double-bunch formation process are also presented. |
|
|||||
FRPMS060 | Commissioning of the UCLA Neptune X-Band Deflecting Cavity and Applications to Current Profile Measurement of Ramped Electron Bunches | electron, sextupole, plasma, laser | 4135 | |||||
|
Funding: Department of Energy Grant # DE-FG02-92ER40693 |
A 9-cell standing wave deflecting cavity has recently been constructed and installed at the UCLA Neptune Laboratory for use as a temporal diagnostic for the 13 MeV, 300 to 700 pC electron bunches generated by the Neptune photoinjector beamline. The cavity is a center-fed Glid-Cop structure operating in at TM110-like deflecting mode at 9.59616 GHz with a pi phase advance per cell. At the maximum deflecting voltage of 500 kV, the theoretical resolution limit of the device is 50 fs, although with current beam parameters and a spot size of 460 microns RMS the effective resolution is approximately 400 fs. We discuss the operation and testing of the cavity as well as its intended application: measuring the temporal current profile of ramped electron bunches generated using the Neptune dogleg compressor, and we present the first measurements of the electron beam current profile obtained using the deflecting cavity. |
|
|||||
FRPMS067 | Energy Measurement in a Plasma Wakefield Accelerator | plasma, electron, acceleration, radiation | 4168 | |||||
|
Funding: DOE DE-AC02-76SF00515 (SLAC), DE-FG02-92-ER40745, DE-FG03-92ER40745, DE-FC02-01ER41179, DE-FG03-92ER40727, DE-FG02-03ER54721, DE-F52-03NA00065:A004, DE-AC-0376SF0098, NSF ECS-9632735, NSF-Phy-0321345 |
Particles are leaving the meter-long plasma wakefield accelerator with a large energy spread. To determine the spectrum of these particles, four diagnostics have been set up. These were used to determine energies of the particles that gain energy in the plasma, those that lose energy by driving the wake and the self-injected particles that are accelerated from rest. |
|
|||||
FRPMS073 | Picosecond Bunch Length and Energy-z Correlation Measurements at SLAC's A-Line and End Station A | synchrotron, feedback, simulation, electron | 4201 | |||||
|
Funding: US DOE Contract #DE-AC02-76FS00515 |
We report on measurements of picosecond bunch lengths and the energy-z correlation of the bunch with a high energy electron test beam to the A-line and End Station A (ESA) facilities at SLAC. The bunch length and the energy-z correlation of the bunch are measured at the end of the linac using a synchrotron light monitor diagnostic at a high dispersion point in the A-line and a transverse RF deflecting cavity at the end of the linac. Measurements of the bunch length in ESA were made using high frequency diodes (up to 100 GHz) and pyroelectric detectors at a ceramic gap in the beamline. Modelling of the beam's longitudinal phase space through the linac and A-line to ESA is done using the 2-dimensional tracking program LiTrack, and LiTrack simulation results are compared with data. High frequency diode and pyroelectric detectors are planned to be used as part of a bunch length feedback system for the LCLS FEL at SLAC. The LCLS also plans precise bunch length and energy-z correlation measurements using transverse RF deflecting cavities. |
|