Paper | Title | Other Keywords | Page | |||||
---|---|---|---|---|---|---|---|---|
MOXKI01 | LHC: Construction and Commissioning Status | dipole, quadrupole, injection, insertion | 1 | |||||
|
The LHC is now in its final phase of hardware commissioning. The whole ring is complete apart from a few elements in the matching regions yet to be installed. The first of the eight sectors has been cooled down and power tests to full energy are underway. Beam commissioning will start as soon as the last sector becomes available, hopefully before the end of 2007. The commissioning plan foresees a short "engineering" run with colliding beams at or near the injection energy of 450 GeV. This will be followed by a shutdown to finish installing the detectors and to commission the last sectors to full current. A review of the commissioning status to date will be given.
|
|
|
Slides
|
|
|
||
MOPAN085 | Completion of the Series Fabrication of the Main Superconducting Quadrupole Magnets of LHC | quadrupole, factory, dipole, insertion | 356 | |||||
|
By end of November 2006, the last cold mass of the main superconducting quadrupole cold masses were delivered by ACCEL Instruments to CERN. This comprised 360 cold masses for the arc regions of the machine and 32 special units dedicated to the dispersion suppressor regions. The latter ones contain the same main magnet but different types of correctors and are of increased length with respect to the regular arc ones. The end of the fabrication of these magnets coincided with the end of the main dipole deliveries allowing a parallel assembly into their cryostats and installation into the LHC tunnel. The positioning into the tunnel was optimized using the warm field measurements performed in the factory. On the other hand the correct slotting of the quadrupoles was complicated due to the multitude of variants and by the fact that a number of units needed to be replaced by spares which in some cases required a reshuffling of the positioning. The paper gives some final data about the successful fabrication at ACCEL Instruments and explains the issue of their best positions in the machine.
|
|
|
|||||
MOPAN091 | Design of Mechanical Structure and Cryostat for IASW Superconducting Wiggler at NSRRC | vacuum, wiggler, superconductivity, shielding | 374 | |||||
|
An in-achromatic superconducting wiggler (IASW) was successfully constructed and installed at the Taiwan Light Source (TLS) in January 2006. The cryostat with a 30 L liquid nitrogen aluminum reservoir shielding surrounds the helium vessel, which comprises the cold mass and 100 L liquid helium. The helium vessel is suspended by eight suspension links, which are thermally intercepted at 80 K and can be adjusted by applying tension, such that the center of the cold mass does not move during cooled to 4.2 K. A three-layered stainless tube was designed to prevent the transfer port from freezing and the steam- electricity separation system is designed to supply electricity and return the helium gas to prevent freezing of the power feedthrough.
|
|
|
|||||
MOPAN093 | Stability Improvement of the Cryogenic System at NSRRC | superconducting-magnet, resonance, electron, storage-ring | 380 | |||||
|
Negative gauge pressure appears in the helium suction line during the period of compressor starting up. The negative pressure induces the risk of air leakage into the cryogenic system and the damage to the burst disk of cryostat. A buffer tank is connected to the suction line to avoid the negative gauge pressure. Variation of nitrogen pressure changes the thermal-shielding temperature of the cavity cryostat and thus changes the length and frequency of the cavity. A phase separator with pressure control is installed before the cryostat to isolate the fluctuation of nitrogen pressure at the source side and prevent the trip of electron beam due to the frequency change or the overpressure at the cavity side. The stability improvement after usage of the phase separator shows that variation of the nitrogen pressure to the cavity cryostat is reduced from +0.6/-0.4 bar to ±0.08 bar and the drift of nitrogen pressure is eliminated. The stability after usage of the buffer tank shows that the negative gauge pressure is avoided in the suction line and the peak pressure was reduced from 1.4 bar to 1.2 bar.
|
|
|
|||||
MOPAN101 | Failure Analysis for Cryogenic System Operation at NSRRC | superconducting-magnet, controls, synchrotron, synchrotron-radiation | 398 | |||||
|
Two 450W cryogenic systems were installed on the year 2002 and 2006, respectively at NSRRC. So far, one 450W cryogenic system is cooling two superconducting magnets and one superconducting cavity. The new system will serve for five superconducting magnets on the year 2007. This paper presents the abnormal operation for the system, which induces the fluctuations for pressure, temperature, and flow rate, respectively. Solutions for these failures are shown and discussed.
|
|
|
|||||
MOPAS027 | Energy Deposition Studies of Block-Coil Quadrupoles for the LHC Luminosity Upgrade | quadrupole, luminosity, radiation, interaction-region | 491 | |||||
|
Funding: Work supported by the Director, Office of Science, U. S. Department of Energy under Contract DE-AC02-05CH11231. |
At the LHC upgrade luminosity of 1035 cm-2 s-1, collision product power in excess of a kW is deposited in the inner triplet quadrupoles. The quadrupole field sweeps secondary particles from pp-collisions into the superconducting coils, concentrating the power deposition at the magnetic mid-planes. The local peak power density can substantially exceed the conductor quench limits and reduce component lifetime. Under these conditions, block-coil geometries may result in overall improved performance by removing the superconductor from the magnetic mid-planes and/or allowing increased shielding at such locations. First realistic energy deposition simulations are performed for an interaction region based on block-coil quadrupoles with parameters suitable for the LHC upgrade. Results are presented on 3-D distributions of power density and accumulated dose in the inner triplet components as well as on dynamic heat loads on the cryogenic system. Optimization studies are performed on configuration and parameters of the beam pipe, cold bore and cooling channels. The feasibility of the proposed design is discussed. |
|
|||||
MOPAS043 | Instrumentation for the Cornell ERL Injector Test Cryostats | controls, vacuum, instrumentation, monitoring | 527 | |||||
|
Funding: Work is supported by the National Science Foundation grant PHY 0131508 |
Cornell is building a 1.3 GHz Injector Cryomodule for an ERL prototype. The cryomodule consists of five two-cell niobium cavities each cavity having two coaxial power input couplers. Cavity and coupler pairs will require acceptance testing at high power prior to assembly in the injector cryomodule. A liquid nitrogen cryostat for testing the couplers at high power has been built and the first input coupler test is complete. In addition, a Horizontal Test Cryostat (HTC) is being built to test input coupler pairs and cavities as a set. The first HTC test is scheduled for spring 2007. Details for instrumentation of the Coupler Test Cryostat (CTC) and HTC are presented. |
|
|||||
MOPAS082 | Status of the Spallation Neutron Source Superconducting RF Facilities | vacuum, controls, radiation, superconducting-RF | 623 | |||||
|
Funding: SNS is managed by UT-Battelle, LLC, under contract DE-AC05-00OR22725 for the U. S. Department of Energy |
The SNS project was completed with only limited SRF facilities installed as part of the project, namely a 5 MW, 805 MHz RF test stand, a fundamental power coupler processing system, a concrete test cave shell, and temporary cleaning/assembly facilities. A concerted effort has been initiated to install the infrastructure and equipment necessary to maintain and repair the superconducting Linac, and to support power upgrade R&D. Installation of a Class10/100/10,000 cleanroom and outfitting of the test cave with RF, vacuum, controls, personnel protection and cryogenics systems is underway. A horizontal cryostat, which can house a helium vessel/cavity and fundamental power coupler for full power, pulsed testing, is being procured. Equipment for cryomodule assembly/disassembly and cavity processing also is being designed. This effort, while derived from the experience of the SRF community, will provide a unique high power test capability as well as long term maintenance capabilities. This paper presents the current status and the future plans for the SNS SRF facilities. |
|
|||||
MOPAS093 | Vibration Measurements to Study the Effect of Cryogen Flow in a Superconducting Quadrupole | laser, quadrupole, superconducting-magnet, resonance | 643 | |||||
|
Funding: Work supported by the US Department of Energy under contract DE-AC02-98CH10886. |
The conceptual design of compact superconducting magnets for the International Linear Collider final focus is presently under development at BNL. A primary concern in using superconducting quadrupoles is the potential for inducing additional vibrations from cryogenic operation. We have employed a Laser Doppler Vibrometer system to measure the vibrations at resolutions ~1 nm (at frequencies above ~8 Hz) in a spare RHIC quadrupole coldmass under cryogenic conditions. Some preliminary results of these studies were presented at the Nanobeam 2005 workshop*. These results were limited in resolution due to a rather large motion of the laser head itself. As a first step towards improving the measurement quality, an actively stabilized isolation table was used to reduce the motion of the laser holder. The improved set-up will be described, and vibration spectra measured at cryogenic temperatures, both with and without helium flow, will be presented.
*A. Jain, et al., Nanobeam 2005, Kyoto, Japan, Oct.17-21, 2005; paper WG2d-05; available at http://wwwal.kuicr.kyoto-u.ac.jp/NanoBM . |
|
|||||
MOPAS095 | Study of the RHIC BPM SMA Connector Failure Problem | factory, superconducting-magnet, radiation | 649 | |||||
|
About 730 cryogenic beam position monitors (BPMs) are mounted on the RHIC CQS and triplet superconducting magnets. Semi-rigid coaxial cables bring the electrical signal from BPM feedthroughs to outside flanges at ambient temperature. Each year approximately 10 cables fail during RHIC operations. The connection usually fails at the warm end of the cable, either from solder joint failure or retraction of the center conductor in the SMA connector. Finite element analyses were performed to understand the solder joint failure mechanism. Results showed that (1) the SMA center conductor can separate from the mating connector due to the thermal retraction,(2) the maximum thermal stress at the warm end solder joint can exceed the material strength of the Pb37/Sn63 solder material, and (3) magnet ramping frequency (~10 Hz) during the machine startup can possibly resonate the coaxial cable and damage the solder joint. This failure problem can be resolved by repairing with silver bearing solder material (a higher strength material) and crimping the cable at the locations close to the SMA connector to prevent center conductor retraction.
|
|
|
|||||
TUPAN024 | HESR at FAIR: Status of Technical Planning | dipole, target, antiproton, electron | 1442 | |||||
|
The High-Energy Storage Ring (HESR) of the international Facility for Antiproton and Ion Research (FAIR) at GSI in Darmstadt is dedicated to Strong Interaction studies with antiprotons in the momentum range from 1.5 to 15 GeV/c. Powerful phase-space cooling is needed to reach demanding experimental requirements in terms of luminosity and beam quality. Status and details of technical planning including cryogenic concept will be presented.
|
|
|
|||||
TUPAN089 | The LHC Beampipe Waveguide Mode Reflectometer | quadrupole, pick-up, controls, scattering | 1583 | |||||
|
Several specially developed waveguide-mode reflectometers for obstacle detection in the LHC magnet beampipes have been intensively used for more than 18 months. This "Assembly" version is based on the synthetic pulse method using a modern vector network analyzer. It has mode selective excitation couplers and uses a specially developed waveguide mode dispersion compensation algorithm with external software. In addition there is a similar "in situ" version of the reflectometer which uses permanently installed microwave couplers at the end of each of the nearly 3 km long LHC arcs. A considerable number of unexpected objects have been found in the beampipes and subsequently removed. Operational statistics and lessons learned are presented and the overall performance is discussed.
|
|
|
|||||
TUPAN092 | Schedule evolution during the life-time of the LHC project | collider, hadron, civil-engineering, controls | 1592 | |||||
|
The Large Hadron Collider Project was approved by the CERN Council in December 1994. The CERN management opted from the beginning of the project for a very aggressive installation planning based on a just-in-time sequencing of all activities. This paper aims to draw how different factors (technical development, procurement, logistics and organization) have impacted on the schedule evolution through the lifetime of the project. It describes the cause effect analysis of the major rescheduling that occurred during the installation of the LHC and presents some general conclusions potentially applicable in other similar projects.
|
|
|
|||||
WEPMN004 | Operation of the SOLEIL RF Systems | feedback, injection, controls, booster | 2050 | |||||
|
The 352 MHz RF accelerating systems for the SOLEIL Booster (BO) and Storage Ring (SR) have been commissioned. In the BO, a 5-cell copper cavity of the CERN-LEP type is powered with a 35 kW solid state amplifier. In the SR, the required RF accelerating voltage (up to 4.4 MV) and power (650 kW at full beam current of 500 mA) will be provided by two cryomodules, each containing a pair of superconducting cavities, specifically designed for SOLEIL. The parasitic impedances of the high order modes are strongly attenuated by means of four coaxial couplers, located on the tube connecting the two cavities. The first cryomodule is operational, while the second one, which is being constructed by ACCEL (Germany), will be implemented beginning of 2008. Both cryomodules will be cooled down with liquid helium from a single 350 W liquefier and each cavity is powered with a 190 kW solid state amplifier. With the first cryomodule and two amplifiers in operation, the first year objective of storing 300 mA was successfully achieved. The RF system commissioning and operation results are reported.
|
|
|
|||||
WEPMN006 | Status of the Superconducting CH-structure | linac, simulation, proton, site | 2056 | |||||
|
Funding: GSI, BMBF 06F134I, EU 516520-FI6W, RII-CT-2003-506395, EFDA/99-507ERB5005-CT990061 |
The superconducting CH-structure is the first multi-cell cavity for the acceleration of low and medium energy ions and protons. A superconducting prototype cavity has been built and several cold tests have been performed at the IAP in Frankfurt. After the detection of a field emission centre the cavity will be treated by buffered chemical polishing and high pressure rinsing. Additionally the cavity is being prepared for tests in a horizontal cryostat with slow and fast tuner system. We present the status of these developments and the test results which have been gained recently. |
|
|||||
WEPMN009 | Vibration Stability Studies of a Superconducting Accelerating Module Quadrupole Operating at 4.5K | quadrupole, vacuum, damping, linac | 2065 | |||||
|
Funding: Work supported by the Commission of the European Communities under the 6th Framework Program Structuring the European Research Area, contract number RIDS-011899. |
The European X-ray Free Electron Laser (XFEL) and the International Linear Collider (ILC) superconducting accelerating modules, containing a string of Niobium (Nb) cavities and a quadrupole, will operate at 2K. In this paper, we will report on the vibration stability studies of a high gradient XFEL/ILC type III superconducting accelerating module quadrupole operating at 4.5K. Measurements are performed via geophones affixed on the cold mass in both horizontal and vertical directions. This data will be compared with piezoelectric accelerometers for the same module. The goal is to study the stability of the cold quadrupole and to compare the results with room temperature conditions. |
|
|||||
WEPMN037 | Manufacture and Assembly of the 6 Meter-Long Cryomodules for Superconducting RF Test Facility (STF) at KEK | vacuum, radiation, factory, insertion | 2122 | |||||
|
The Superconducting RF Test Facility (STF) has been developed at KEK as an R&D toward ILC (International Linear Collider). Hitachi carried out the fabrication of STF cryostat components and in si-tu assembly of cryomodules cooperated with KEK. Our objective is obtaining the manufacturing experience of long cryostats for superconducting cavities. STF cryomodules are designed on the basis of TESLA design. Those major components are : vacuum vessels, support posts, 80K radiation shields, 5K radiation shields, helium gas return pipe, cryogenic piping, cavity helium vessels, RF input couplers, various measurement equipments and sensors. Two units of 6-meter long cryostat are designed to contain maximum eight 9-cell cavities in total. At the first step of the cryomodules, two different types of cavities and some equipments have been carefully prepared and installed by KEK. This paper briefly presents the structural design of STF cryostat components, cryomodule assembly procedures with specially designed tooling, and a summary for the next step.
|
|
|
|||||
WEPMN060 | Fabrication of ICHIRO Nine-cell Cavities in PAL for STF of KEK | electron, superconductivity, focusing, linac | 2173 | |||||
|
Funding: Korea Ministry of Science & Technology |
Pohang Accelerator Laboratory has studied SRF cavity and set up SRF test laboratory from January 2006. The first activity for SRF research was to develop SRF 3rd harmonic cavity for Pohang Light Source, which was designed, fabricated and tested in 2006. The cryostat are under design. The fabrication of ICHIRO cavity, which is ILC ACD cavity, is PAL's second activity related to SRF. Deep drawing, trimming and welding by electron beam for a 9-cell ICHIRO cavity were done in PAL. The polishing processes for the RF surface including electropolishing were done in KEK under the collaboration between two institutes. This will be tested with real beam in STF-1 of KEK in second half period of 2007. This paper reports the results of fabrication of ICHIRO single- and nine-cell cavities performed in PAL. |
|
|||||
WEPMN087 | Variable CW RF Power Coupler for 345 MHz Superconducting Cavities | coupling, vacuum, simulation, beam-loading | 2230 | |||||
|
Funding: This work was supported by the U. S. Department of Energy, Office of Nuclear Physics, under Contract No. DE-AC-02-06CH11357. |
This paper reports the development of a 5-10 kW cw variable coupler for 345 MHz spoke-loaded superconducting (SC)cavities. The coupler inserts an 80K copper loop into a 5 cm diameter coupling port on several types of spoke-loaded cavity operating at 2 - 4K. The coupling loop can be moved during operation to vary the coupling over a range of 40 dB. The coupler is designed to facilitate high-pressure water rinsing and low-particulate clean assembly. Design details and operating characteristics are discussed. |
|
|||||
WEPMN096 | Status of the 3.9-GHz Superconducting RF Cavity Technology at Fermilab | superconducting-RF, controls, monitoring, vacuum | 2254 | |||||
|
Funding: This work supported by Universities Research Association Inc. under contract DE-AC02-76CH00300 with the U. S. DOE. |
Fermilab is involved in an effort to assemble 3.9 GHz superconducting RF cavities into a four cavity cryomodule for use at the DESY TTF/FLASH facility as a third harmonic structure. The design gradient of these cavities is 14 MV/m limited by thermal heat transfer. This effort involves design, fabrication, intermediate testing, assembly, and eventual delivery of the cryomodule. We report on all facets of this enterprise from design through future plans. Included will be test results of single 9-cell cavities, lessons learned, and current status. |
|
|||||
WEPMN101 | Coupling Interaction Between the Power Coupler and the Third Harmonic Superconducting Cavity | coupling, klystron, beam-loading, injection | 2268 | |||||
|
Funding: U. S. Department of Energy |
Fermilab has developed a third harmonic superconducting cavity operating at the frequency of 3.9 GHz to improve the beam performance for the FLASH user facility at DESY. It is interesting to investigate the coupling interaction between the SRF cavity and the power coupler with or without beam loading. The coupling of the power coupler to the cavity needs to be determined to minimize the power consumption and guarantee the best performance for a given beam current. In this paper, we build and analyze an equivalent circuit model containing a series of lumped elements to represent the resonant system. An analytic solution of the required power from the generator as a function of the system parameters has also been given based on a vector diagram. |
|
|||||
WEPMN103 | Mechanical Stability Study of Capture Cavity II at Fermilab | vacuum, resonance, superconducting-RF, monitoring | 2274 | |||||
|
Problematic resonant conditions at both 18 Hz and 180 Hz were encountered and identified early during the commissioning of Capture Cavity II (CC2) at Fermilab. CC2 consists of an external vacuum vessel and a superconducting high gradient (close to 25 MV/m) 9-cell 1.3 GHz niobium cavity, transported from DESY for use in the A0 Photoinjector at Fermilab. An ANSYS modal finite element analysis (FEA) was performed in order to isolate the source of the resonance and directed the effort towards stabilization. A novel idea was implemented, by using a fast piezoelectric tuner to excite (or shake) the cavity at different frequencies (from 10 Hz to 200 Hz) as a low-range sweep for analysis purposes. Both warm (300 K) and cold (1.8 K) accelerometer measurements at the cavity were taken as the resonant 'fix' was applied. FEA results, cultural and technical noise investigation, and stabilization techniques are discussed.
|
Operated by Universities Research Association, Inc., under Contract No. DE-AC02-76CH03000 with the U. S. Department of Energy#mcgee@fnal.gov |
|
|||||
WEPMN106 | Design and Commissioning of Fermilab's Vertical Test Stand for ILC SRF Cavities | radiation, shielding, controls, vacuum | 2283 | |||||
|
Funding: Operated by Universities Research Association, Inc. for the U. S. Department of Energy under contract DE-AC02-76CH03000 |
As part of a program to improve cavity performance reproducibility for the ILC, Fermilab is developing a facility for vertical testing of SRF cavities. It operates at a nominal temperature of 2K, using an existing cryoplant that can supply LHe in excess of 20g/sec and provides steady-state bath pumping capacity of 125W at 2K. The below-grade cryostat consists of a 4.9m long vacuum vessel and 4.5m long LHe vessel. The cryostat is equipped with external and internal magnetic shielding to reduce the ambient magnetic field to <10mG. Internal fixed and external movable radiation shielding ensures that radiation levels from heavily field-emitting cavities remain low. In the event that radiation levels exceed allowable limits, an integrated personnel safety system consisting of RF switches, interlocks, and area radiation monitors disables RF power to the cavity. In anticipation of increased throughput requirements that may be met with additional test stand installations, sub-systems have been designed to be easily upgradeable or to already meet these anticipated needs. Detailed facility designs, performance during system commissioning, and results from initial cavity tests are presented. |
|
|||||
WEPMS003 | Design of Half-Reentrant SRF Cavities for Heavy Ion Linacs | linac, ion, superconductivity, heavy-ion | 2328 | |||||
|
Funding: DOE #DE-FG02-06ER41411 |
The Spallation Neutron Source (Oak Ridge), the proposed 8 GeV Proton Driver (Fermilab), and the proposed Rare Isotope Accelerator use multicell elliptical SRF cavities to provide much of the accelerating voltage. This makes the elliptical cavity segment the most expensive part of the linac. A new type of accelerating structure called a half-reentrant elliptical cavity can potentially improve upon existing elliptical designs by reducing the cryogenic load by as much as 30% for the same accelerating voltage. Alternatively, with the same peak surface magnetic field as traditional elliptical cavities, it is anticipated that half-reentrant designs could operate at up to 25% higher accelerating gradient. With a half-reentrant shape, liquids can drain easily during chemical etching and high pressure rinsing, which allows standard multicell processing techniques to be used. A half-reentrant cavity for β = v/c = 1, suitable for the proposed ILC, has been designed and fabricated, with RF tests in progress*. In this paper, we present electromagnetic designs for three half-reentrant cell shapes suitable for an ion or proton linac (β = 0.47, 0.61 and 0.81, f = 805 or 1300 MHz).
* M. Meidlinger et al., in Proc. XXIII Int. Linac Conf., Knoxville, TN, Aug 2006 |
|
|||||
WEPMS018 | Superconducting Materials Testing with a High-Q Copper RF Cavity | klystron, superconductivity, monitoring, feedback | 2370 | |||||
|
Magnesium diboride (MgB2) has a transition temperature (Tc) of ~40 K, i.e., about 4 times higher than niobium (Nb) that has been used for recent accelerators. The studies in the last 3 years have shown that it could have about one order of magnitude less RF surface resistance (Rs) than Nb and much less power dependence compared to high-Tc materials such as YBCO up to ~400 Oe. The tests to check the RF critical magnetic field, an important parameter to determine the feasibility for accelerator application, are underway. We are planning to test different thickness films and with different coating methods. This paper describes the results obtained so far. One of the objectives is to verify Gurevich's theory of getting higher critical field than Nb by adding a very thin layer (less than penetration depth) to Nb. In addition, some CW tests on power dependence up to higher magnetic fields are planned and some results will be shown if available at the time of conference.
|
|
|
|||||
WEPMS021 | RF-loss Measurements in an Open Coaxial Resonator for Characterization of Copper Plating | simulation, coupling, pick-up | 2376 | |||||
|
Funding: Work supported by the Office of Naval Research and the High-Energy Laser Joint Technology Office. |
An experiment has been conducted to measure small differences in cavity Q caused by various cavity surface treatments. A requirement of the experiment was that it show little sensitivity to the reassembly with various test pieces. We chose a coaxial half-wave resonator, with an outer conductor extending significantly beyond the length of the inner conductor. The outer conductor acts as a cut-off tube, eliminating the need for electric termination and thus any RF-contacts that can influence the Q-measurements. The experiment is aimed at qualifying the performance of cyanide-copper plated GlidCop in comparison with that of a machined GlidCop surface. To maximize the sensitivity of the measurement we use a fixed outer conductor made of annealed OFE copper and only replace the inner conductor, which is mounted on a low-loss Teflon pedestal located in the low electric field region. The Q-values of machined GlidCop and cyanide-copper plated GlidCop inner conductors are measured against the reference Q of the annealed OFE co-axial cavity. This simple configuration allows a statistically significant number of repetitions of measurements and should provide accurate comparative measurements. |
|
|||||
WEPMS063 | Preliminary Results from Prototype Niobium Cavities for the JLab Ampere-Class FEL | vacuum, damping, coupling, electron | 2487 | |||||
|
Funding: This manuscript has been authored by Jefferson Science Associates, LLC under U. S. DOE Contract No. DE-AC05-06OR23177, and by the office of Naval Research under contract to the Department of Energy. |
In a previous paper the cavity* design for an Ampere-class cryomodule was introduced. We have since fabricated a 1500 MHz version of a single cell cavity with waveguide couplers for HOM and fundamental power, attached to one end of the cavity, a 5-cell cavity made from large grain niobium without couplers and a complete 5-cell cavity from polycrystalline niobium featuring waveguide couplers on both ends. A 750 MHz single cell cavity without endgroups has also been manufactured to get some information about obtainable Q-values, gradients and multipacting behavior at lower frequency. This contribution reports on the various tests of these cavities.
* R. A.Rimmer et al.; EPAC 2006, paper MOPCH182 |
|
|||||
WEPMS072 | Status and Performance of the Spallation Neutron Source Superconducting Linac | linac, radiation, vacuum, higher-order-mode | 2502 | |||||
|
Funding: SNS is managed by UT-Battelle, LLC, under contract DE-AC05-00OR22725 for the U. S. Department of Energy |
The Superconducting Linac at SNS has been operating with beam for almost two years. As the first operational pulsed superconducting linac, many of the aspect of its performance were unknown and unpredictable. A lot of experience has been gathered during the commissioning of its components, during the beam turn on and during operation at increasingly higher beam power. Some cryomodules have been cold for well over two years and have been extensively tested. The operation has been consistently conducted at 4.4 K and 10 and 15 pulses per second, with some cryomodules tested at 30 and 60 pps and some tests performed at 2 K. Careful balance between safe operational limits and the study of conditions, parameters and components that create physical limits has been achieved. This paper presents the experience and the performance of the superconducting cavities and of the associated systems with and without beam. |
|
|||||
WEPMS076 | Status of the SNS Cryomodule Test | electron, vacuum, radiation, linac | 2511 | |||||
|
Funding: SNS is managed by UT-Battelle, LLC, under contract DE-AC05-00OR22725 for the U. S. Department of Energy |
The cryomodule tests are on going to have better understandings of physics as a whole and eventually to provide safe and reliable operation for neutron production. Some features are revealed to be interesting issues and need more attentions than expected, such as operating condition, collective effects between cavities, HOM coupler issues, end-group stability, cavity-coupler interactions, and vacuum/gas physics, waiting for more investigations. Up to now SNS cryomodules were mainly tested at 4.4 K, 10 pulse per second (pps) and 30 pps/60 pps tests are under progress. This paper presents the experiences and the observations during tests of cryomodules. |
|
|||||
THOAKI02 | The Cornell ERL Superconducting 2-Cell Injector Cavity String and Test Cryomodule | alignment, emittance, linac, damping | 2572 | |||||
|
Funding: Work supported by NSF. |
Cornell University is developing and fabricating a SRF injector cryomodule for the acceleration of the high current (100 mA) beam in the Cornell ERL prototype and ERL light source. Major challenges include emittance preservation of the low energy, ultra low emittance beam, cw cavity operation, and strong HOM damping with efficient HOM power extraction. Prototypes have been completed for the 2-cell niobium cavity with helium vessel, coaxial blade tuner with piezo fine tuners, twin high power input couplers, and beam line HOM absorbers loaded with ferrites and ceramics. Axial symmetry of HOM absorbers, together with two symmetrically placed input couplers per cavity, avoids transverse on-axis fields, which would cause emittance growth. A one-cavity cryostat has been designed following concepts of the TTF cryostat, and is presently under fabrication and assembly. The cryostat design has been optimized for precise cavity alignment, good magnetic shielding, and high dynamic cryogenic loads from the RF cavities, input couplers, and HOM loads. In this paper we report on the status of the assembly and first test of the one-cavity test cryostat. |
|
Slides
|
|
|
||
THOAKI04 | Status of the Cryomodules for the SPIRAL 2 Superconducting LINAC | linac, vacuum, heavy-ion, coupling | 2578 | |||||
|
The SPIRAL 2 superconducting linac is composed of 2 cryomodule families. The first family in the low energy section, called cryomodules A, is composed of 12 cryomodules housing a single cavity at β=0.07. The second family in the high energy section, called cryomodules B, is composed of 7 cryomodules housing 2 cavities at β=0.12. The frequency of these QWR resonators is 88.050 MHz, and the design goal for the accelerating field Eacc is 6.5 MV/m. This paper describes the present status of the cryomodules development.
|
|
|
Slides
|
|
|
||
THICKI03 | Large Helium Refrigeration Plant Operating Experience | extraction, linear-collider, collider | 2700 | |||||
|
Air Products and Linde have signed a Teaming Agreement to pursue refrigeration services for the proposed International Linear Collider. Air Products brings unique helium liquefaction and refrigeration capabilities to the table through its operation of one third of the world's cryogenic liquefiers and ownership of Gardner Cryogenics the world's leading developer, designer and manufacturer of liquid helium storage, distribution and transportation equipment. Air Products is an industry leader throughout the helium supply chain, from providing technology for crude helium extraction from natural gas, to delivering liquid helium to end users, as well as through MRI helium supply activities. Air Products has designed and installed most of the world's crude helium extraction plants. Linde designs and builds cryogenic plants and systems for the most varied fields, from fundamental research and industrial HTS applications to the cooling of superconducting accelerators and cold neutron sources, fusion and fission applications and the industrial liquefaction of helium and hydrogen.
|
|
|
Slides
|
|
|
||
THICKI04 | Development of STF Cryogenic System in KEK | controls, superconducting-RF, booster, vacuum | 2701 | |||||
|
Under the leadership of KEK, the collaborating design activity has been performed in KEK in order to develop the STF (Superconducting RF Test Facility) cryogenic system, together with some positive Japanese industrial members. As the first activity of the collaboration, the initial plant of STF cryogenic system with capacity of 30W at 2.0K has been constructed for the testing of STF cryomodule, and been ready for its operation in KEK. In this session, the present status and schedule of STF cryogenic system in KEK shall be briefly reported.
|
|
|
Slides
|
|
|
||
THICKI05 | European Industries Potential Capabilities on Cryogenics for the Future IlC | linac, damping, positron, collider | 2704 | |||||
|
Following the construction of LHC, the European industries have demonstrated there ability to construct complete helium and nitrogen refrigeration systems both for the needs of the huge accelerator and the associated detectors. Eight 18 kW at 4.5 K and 2.4 kW at 1.8 K helium refrigeration systems have been constructed. Each refrigeration system is connected to 3 km of the 27 km long accelerator thanks to interconnecting valve boxes and high performances helium transfer lines. This is the biggest refrigeration system ever constructed in the world. The demand for cryogenics for the future ILC project is comparable in terms of equipment sizes but even bigger in terms of number of units required. The present refrigeration system scenario of ILC includes ten 22 kW at 4.5 K refrigerators and twelve 4.1 kW at 2 K refrigerators. In the present paper, this scenario will be presented and compared to the realizations done by the European Cryogenic Industries. Contact : Pascale.dauguet@airliquide.com
|
|
|
Slides
|
|
|
||
FROAKI02 | LHC Magnet Tests: Operational Techniques and Empowerment for Successful Completion | dipole, quadrupole, feedback, superconducting-magnet | 3742 | |||||
|
The LHC magnet tests operation team* developed various innovative techniques, particularly since early 2004, to complete the superconductor magnet testing by end 2006. Overall and cryogenic priority handling, rapid on-bench thermal cycling, rule-based goodness evaluation on round-the-clock basis, multiple, mashed web systems are some of these techniques applied with rigour for successful tests completion in time. This paper highlights these operation empowerment tools which had a pivotal role for success. A priority handling method was put in place to enable maximum throughput from twelve test benches, having many different constraints. For the cryogenics infrastructure, it implied judicious allocation of limited resources to the benches. Rapid On-Bench Thermal Cycle was a key strategy to accelerate magnets tests throughput, saving time and simplifying logistics. First level magnet appraisal was developed for 24 hr decision making so as to prepare a magnet further for LHC or keep it on standby. Web based systems (Tests Management and E-Traveller) were other essential ideas to track & coordinate various stages of tests handled by different teams.
|
|
|
Slides
|
|
|
||
FRYKI01 | Radidly-Cyling Superconducting Accelerator Magnets for FAIR at GSI | dipole, synchrotron, storage-ring, antiproton | 3745 | |||||
|
The demand for high beam intensities leads to the requirement of rapidly cycling cycling magnets for synchrotrons. An example is FAIR (Facility for Antiproton and Ion Research) at GSI, which will consist of two synchrotrons (SIS 100 and SIS 300) in one tunnel and several storage rings. The high field ramp rate (up to 1 T/s) and the repetition frequency of up to 1 Hz require R&D for the superconducting magnets of these rings. Persistent currents in the superconductor and eddy currents in wire, cable, iron and vacuum chamber reduce the field quality and generate cryogenic losses. A magnet lifetime of 20 years is desired, resulting in up to 108 magnet cycles. Therefore, special attention has to be paid to magnet material fatigue problems. R&D work is being done, in collaboration with many institutions, to reach the requirements mentioned above. Model dipoles were built and tested. The results of the R&D are reported. Full length dipoles for SIS 100 are under construction.
|
|
|
Slides
|
|
|
||
FROAC03 | The Commissioning of the LHC Technical Systems | dipole, insertion, extraction, simulation | 3801 | |||||
|
The LHC is an accelerator with unprecedented complexity; in addition, the energy stored in magnets and the beams exceeds other accelerators by one to two orders of magnitude. To avoid a plague of technical problems and ensure a safe machine start-up, the hardware commissioning phase was emphasized: the thorough commissioning of technical systems (vacuum, cryogenics, quench protection, power converters, electrical circuits, AC distribution, ventilation, demineralised water, injection system, beam dumping system, beam instrumentation, etc) is carried-out without beam. Activity started in June 2005 with the commissioning of individual systems, followed by operating a full sector of the machine as a whole. LHC architecture allows the commissioning of each of the eight sectors independently from the others, before the installation of other sectors is complete. Important effort went into the definition of the programme and the organization of the coordination in the field, as well as in the tools to record and analyze test results. This paper presents the experience with this approach, results from the commissioning of the first LHC sectors and gives an outlook for future activities.
|
|
|
Slides
|
|
|