A   B   C   D   E   F   G   H   I   K   L   M   N   O   P   Q   R   S   T   U   V   W  

beam-losses

Paper Title Other Keywords Page
MOZMH01 Experience and Lessons with the SNS Superconducting Linac cavity, linac, lattice, emittance 26
 
  • Y. Zhang
    ORNL, Oak Ridge, Tennessee
 
 

Experience and lessons with the SNS superconducting linac over the first 5 years of commissioning and operation are reviewed. As the beam power was ramped up to 1 MW, the linac beam loss has been maintained below 1 W/m and residual activation has been held to a safe level. This can be attributed mainly to a robust accelerator design as well as to dedicated beam dynamics studies during this period. In addition to a review of both transverse and longitudinal beam phase-space measurements, we will review several hardware lessons learned with this high-power proton linac − such as nonlinear multipole components of the linac quadrupoles, beam collimators, high-order-mode couplers of the superconducting cavities, and cavity piezo tuners.

 

slides icon

Slides

 
MOPEA039 Beam Study for FFAG Accelerator at KURRI betatron, synchrotron, acceleration, injection 157
 
  • Y. Kuriyama, Y. Ishi, J.-B. Lagrange, Y. Mori, T. Planche, M. Takashima, T. Uesugi, E. Yamakawa
    KURRI, Osaka
  • H. Imazu, K. Okabe, I. Sakai, Y. Takahoko
    University of Fukui, Faculty of Engineering, Fukui
 
 

In Kyoto University Research Reactor Institute (KURRI), The FFAG accelerator complex for accelerator driven sub-critical reactor (ADSR) project has been already constructed and world first ADSR experiment has been done at May, 2009. In the main ring, proton beams of 11.5 MeV are injected and accelerated up to 100 MeV. During the acceleration, two different types of beam loss have been observed. To investigate these beam loss, betatron and synchrotron motion have been measured experimentally. The details of measurements will be described in this presentation.

 
MOPEA060 Reconstructions of the Control System for the Charge Exchange System at the 3GeV RCS in J-PARC controls, status, vacuum, EPICS 214
 
  • M. Kawase, M. Kinsho, O. Takeda, Y. Yamazaki, M. Yoshimoto
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
 
 

The charge exchange device for 3GeV RCS in J-PARC, which require that a broken foil is exchanged for a new foil by remote control and automatically in vacuum. The control system's important task will be to control under the unified management of the vacuum system and foil driving system and to support EPICS. This device consists of the vacuum system using PLC (Programmable Logic Controller) and the foil driving system using MCU (Multi Control Unit). A workstation (WS) was required, and we developed control system which control under the unified management of 2 different type of system. The uniform management control system became complex system. In fact, therefore control system was unfinished system, it did not protect trouble such as the vacuum gate valve closed while transfer rod insert in the ring. Each algorithm of PLC, MCU and WS was reviewed, and the control system that was able to do the unified management was restructured. Each algorithm of PLC, MCU and WS was debugged so that this control system is made remote control using EPICS. We introduce the reconstruction of the control system for the charge exchange system at the RCS in J-PARC.

 
MOPEA077 Material Studies for the ISIS Muon Target target, proton, neutron, background 253
 
  • A. Bungau, R. Cywinski
    University of Huddersfield, Huddersfield
  • C. Bungau
    Manchester University, Manchester
  • P.J.C. King, J.S. Lord
    STFC/RAL, Chilton, Didcot, Oxon
 
 

The ISIS neutron spallation source uses a separate muon target 20 m upstream of the neutron target for MuSR research. Because ISIS is primarily a neutron source, it imposes restrictions upon the muon target, which normally are not present at other muon facilities like PSI or TRIUMF. In particular it is not possible to use thicker targets and higher energy proton drivers because of the loss of neutrons and the increased background at neutron instruments. In this paper we investigate possible material choices for the ISIS muon target for increased muon yield.

 
MOPEA080 Electron Beam Polarization Measurement using Touschek Lifetime Technique electron, polarization, storage-ring, injection 262
 
  • C. Sun, J.Y. Li, S.F. Mikhailov, V. Popov, W. Wu, Y.K. Wu
    FEL/Duke University, Durham, North Carolina
  • A. Chao
    SLAC, Menlo Park, California
  • H. Xu, J. Zhang
    USTC/NSRL, Hefei, Anhui
 
 

Touschek lifetime of an electron beam in a storage ring depends on the beam polarization through the intrabeam scattering effect. Consequently, the electron beam polarization can be determined by comparing the measured Touschek lifetime of a polarized beam and an unpolarized beam. In this paper, we report a systematic experimental procedure to study the radiative polarization of a stored electron beam. Based upon this technique, we have successfully observed the polarization build-up of a 1.15 GeV electron beam in the Duke storage ring. Using the Touchek lifetime data, we are able to determine the equilibrium degree of the electron beam polarization and the time constant for the polarization build-up process.

 
MOPEB009 Low Leakage Field Septa for J-PARC Main Ring Injection System Upgrade septum, injection, vacuum, simulation 295
 
  • K. Fan, K. Ishii, H. Matsumoto, N. Matsumoto
    KEK, Ibaraki
 
 

Injection into the J-PARC main ring is implemented by 4 kickers and 2 pulsed septa at 3 GeV in a long straight section. To accommodate the injection beam of 54 pmm.mrad, both septa have large physical acceptance of 81 pmm.mrad. However, large aperture leads to large end fringe field interfereing the circulating beam and causing beam loss, which has been observed even at low beam intensity during the beam commissioning. To provide users a proton beam with high beam power, the injection beam intensity will increase greatly in future, which creates difficulties for the present injection system. To accommodate these high intensity beams with low beam loss, the injection system needs to be upgraded. Taking account the strong space charge effects, even larger physical is needed to reduce the localized beam loss, which creates severer end fringe leakage field. This paper will discuss the problems encountered in operating the present septa, and give an optimized design for the new septa.

 
MOPEB010 Development of a High Radiation Resistant Septum for JPARC Main Ring Injection System septum, radiation, injection, proton 298
 
  • K. Fan, K. Ishii, H. Matsumoto, N. Matsumoto
    KEK, Ibaraki
 
 

The J-PARC is a high intensity proton accelerator complex, which consists of a LINAC, a Rapid Cycling Synchrotron (RCS) and a Main Ring (MR). The MR injection system employs a high-field septum to deflect the incoming beam from the RCS, which has been used for the beam commissioning study with low beam intensity successfully. Relative large beam losses in the injection area have been observed, which is proportional to the injection beam intensity. In future, the beam intensity will increase about 100 times to realize high beam power (~MW) operation required from neutrino experiments. The beam loss at the injection region is expected increase greatly due to the space charge effects, which creates severe radiation problems. Since the present injection septum coil is organic insulated, which will be destroyed under such a severe irradiation quickly. To cope with this problem, a new high radiation resistant injection septum magnet is developed, which uses inorganic insulation material (Mineral Insulated Cable - MIC) to prevent the septum from radiation damage. This paper investigates different effects caused by the MIC and gives an optimization design.

 
MOPEB025 SIS100 Fast Ramped Magnets and their Cryopump Functionality for the Operation with High Intensity Intermediate Charge State Heavy Ions vacuum, dipole, ion, heavy-ion 331
 
  • E.S. Fischer, J. Macavei, A. Mierau, P. Schnizer, P.J. Spiller, St. Wilfert
    GSI, Darmstadt
 
 

The FAIR SIS100 accelerator at GSI Darmstadt will be equipped with fast ramped superconducting magnets. The high current Uranium beam modes with intermediate charge states, require ultra low vacuum pressures that can be achieved in long term operation only by cold beam pipes acting as a cryopump with stable temperatures well below 12 K for all operating cycles. The straightforward layout for reliable cooling usually conflicts with an efficient design for fast ramped superconducting accelerator magnets, strongly affected by AC loss generation, field distortion and mechanical stability problems. A full functional vacuum chamber design for SIS 100 has to take into account all these conflicting boundary conditions and trade off between mechanical stability, acceptable field distortions, AC loss minimisation and achievable temperatures. We discuss the cooling conditions for the dipoles and for the beam pipe including first test results. The analysis of the principal design aspects for the vacuum chamber with respect to the magnets operation parameters and an integral design approach are given. We present a technological feasible solution for model testing and full scale manufacturing.

 
MOPEB066 Beam Commissioning of Spallation Neutron and Muon Source in J-PARC target, proton, emittance, neutron 424
 
  • S.I. Meigo, M. Futakawa, M. Ohi, S. Shinichi
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
  • H. Fujimori
    KEK/JAEA, Ibaraki-Ken
 
 

In J-PARC, Materials and Life Science experimental Facility (MLF) is aimed at promoting experiments using the world highest intensity pulsed neutron and muon beams which are produced at a thick mercury target and a thin carbon graphite target by 3-GeV proton beams, respectively. The first beam was achieved at the target without significant beam loss in May 2008. It is succeeded stable operation with beam power of larger than 300 kW. After beam irradiation, the residual dose of radiation on the beam transport line is remarkably small where the highest dose is 20 microSv/h. In order to confirm stable operation of the facility, especially for the wellness of the target, it is important to obtain the beam profile at the target. We developed new technique by using imaging plate which is attached on the target vessel by remote handling technique via master slave manipulators. It is found that the beam profile shows good agreement with the calculation. It is also found that the beam scattering effect on the muon production target shows good agreement with the simulation calculation.

 
MOPEC010 LHC Aperture Measurements optics, betatron, closed-orbit, emittance 477
 
  • S. Redaelli, M.C. Alabau Pons, M. Giovannozzi, G.J. Müller, F. Schmidt, R. Tomás, J. Wenninger
    CERN, Geneva
 
 

The mechanical aperture of the Large Hadron Collider (LHC) is a critical parameter for the operation of the machine due to the high stored beam intensities in the superconducting environment. Betatron and momentum apertures must be therefore precisely measured and optimized. In this paper, we present the results of beam-based measurements of the LHC aperture. The experimental results are compared with the expectations from the as-built model of the LHC aperture, taking into account the optics imperfections of the superconducting magnets. The impact of these measurements on various aspects of the LHC operation are also discussed.

 
MOPEC016 Interaction of Macro-Particles with the LHC Proton Beam proton, acceleration, electron, vacuum 492
 
  • F. Zimmermann, M. Giovannozzi
    CERN, Geneva
  • A. Xagkoni
    National Technical University of Athens, Athens
 
 

We study the interaction of macro-particles residing inside the LHC vacuum chamber, e.g. soot or thermal-insulation fragments, with the circulating LHC proton beam. The coupled equations governing the motion and charging rate of metallic or dielectric micron-size macro-particles are solved numerically to determine the time spent by such "dust" particles close to the path of the beam as well as the resulting proton-beam losses, which could lead to a quench of superconducting magnets and, thereby, to a premature beam abort.

 
MOPEC024 RHIC BBLR Measurements in 2009 lattice, proton, emittance, interaction-region 510
 
  • R. Calaga, W. Fischer, G. Robert-Demolaize
    BNL, Upton, Long Island, New York
 
 

Long range beam-beam experiments were conducted during the Run 2009 in the yellow and the blue beams of the RHIC accelerator with DC wires. The effects of a long-range interaction with a DC wire on colliding and non-colliding bunches with the aid of orbits, tunes, and losses were studied. Results from distance and currents scans and an attempt to compensate a long-range interaction with a DC wire is presented.

 
MOPEC047 High Current Proton FFAG Accelerators space-charge, emittance, lattice, proton 564
 
  • R.J. Barlow, A.M. Toader, S.C. Tygier
    UMAN, Manchester
 
 

Accelerator Driven Subcritical Reactors require a high currents of energetic protons. We compute the limits imposed by space charge, and explore what can be achieved using various proposed FFAG lattices. Limitations due to beam losses and reliability are also discussed

 
MOPEC058 StrahlSim, a Computer Code for the Simulation of Charge Exchange Beam Loss and Dynamic Vacuum in Heavy Ion Synchrotrons ion, vacuum, simulation, injection 594
 
  • P. Puppel, U. Ratzinger
    IAP, Frankfurt am Main
  • L.H.J. Bozyk
    TU Darmstadt, Darmstadt
  • P.J. Spiller
    GSI, Darmstadt
 
 

StrahlSim is a unique code for the simulation of charge exchange driven beam loss and dynamic vacuum effects in heavy ion synchrotrons. Dynamic vacuum effects are one of the most challenging problems for accelerators using intermediate charge state, high intensity heavy ion beams (e.g. AGS Booster, LEIR, SIS18). StrahlSim can be used as a design tool for synchrotrons, e.g. for the estimation of pumping power needed to stabilize the dynamic vacuum. Recently, StrahlSim has been extended to simulate time dependent longitudinal pressure profiles. The new code calculates a self-consistent static pressure distribution along the accelerator and simulates local pressure rises caused by dynamic and systematic beam losses. StrahlSim determines the loss distribution of charge exchanged beam ions and respects the beam energy dependence of the charge exchange cross sections. The beam loss calculated by means of the new time dependent longitudinal pressure profiles has been benchmarked with measured data from the latest SIS18 machine experiments.

 
MOPEC068 High Intensity Beam Operations in the J-PARC 3-GeV RCS injection, space-charge, linac, emittance 624
 
  • H. Hotchi, H. Harada, P.K. Saha, Y. Shobuda, F. Tamura, K. Yamamoto, M. Yamamoto
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
  • Y. Irie
    KEK, Ibaraki
 
 

We have recently demonstrated 300-kW output in the J-PARC 3-GeV RCS. In this paper we will discuss beam dynamics issues in such a high intensity beam operation together with the corresponding beam simulation results.

 
MOPEC069 Status and Progress of the J-PARC 3-GeV RCS cavity, injection, neutron, extraction 627
 
  • M. Kinsho
    JAEA/J-PARC, Tokai-mura
 
 

The J-PARC 3-GeV rapid cycling synchrotron (RCS) has been operated for the neutron and MLF users program from December 23rd, 2008. The RCS operations not only in support of the MLF but also were providing beam to support commissioning of the MR. In parallel we are challenging to realize higher beam power operations with better stability. Before scheduled maintenance last summer beam power was limited by the front end of about 20 kW, after that maintenance the RCS has been operated the beam power of more than 100 kW for MLF users. After beam deliver operation to the MR and MLF, while the priority has been given to their beam tuning, the RCS also continues further beam studies toward higher beam intensity. On December 7th, 2009, the RCS achieved the beam power of more than 300kW to the neutron production target with 25Hz. This presentation will concentrate itself on the outcome of the J-PARC RCS commissioning program, including the discussion on the issues of the high-power operation.

 
MOPEC074 Injection Upgrade on the ISIS Synchrotron injection, scattering, dipole, simulation 639
 
  • B. Jones, D.J. Adams, S.J.S. Jago, H. V. Smith, C.M. Warsop
    STFC/RAL/ISIS, Chilton, Didcot, Oxon
 
 

The ISIS Facility at the Rutherford Appleton Laboratory in the UK produces intense neutron and muon beams for condensed matter research. The accelerator facility consists of a 70 MeV H- linac and a 50 Hz proton synchrotron accelerating up to 3.75x1013 protons per pulse from 70 to 800 MeV, delivering a mean beam power of 0.24 MW. Present upgrade studies are investigating how replacement of the existing linac and increased injection energy could increase beam power in the existing ISIS ring. Such an upgrade would replace one of the oldest sections of the ISIS machine, and with reduced space charge and optimised injection, may allow substantially increased intensity in the ring, perhaps towards the 0.5 MW regime. A critical aspect of such an upgrade would be the new higher energy injection straight. This paper summarises beam dynamics and hardware requirements for 180MeV H- charge exchange injection into ISIS including; optimisation of the injection magnets; requirements for beam dumps and results of stripping foil simulations with estimates of stripping efficiency and foil heating.

 
MOPEC085 Status of the SNS Power Ramp Up linac, ion, ion-source, resonance 660
 
  • M.A. Plum
    ORNL, Oak Ridge, Tennessee
 
 

The Spallation Neutron Source accelerator complex consists of a 2.5 MeV H- front-end injector system, a 186 MeV normal-conducting linear accelerator, a 1 GeV superconducting linear accelerator, an accumulator ring, and associated beam transport lines. Since initial operation began in 2006, the beam power has been steadily increasing toward the design goal of 1.4 MW. In September 2009 the power surpassed 1 MW for the first time, and operation at the 1 MW level is now routine. The status of the beam power ramp-up program and present operational limitations will be described.

 
MOPD002 Acceleration of Intermediate Charge State Heavy Ions in SIS18 ion, injection, acceleration, heavy-ion 669
 
  • P.J. Spiller, H. Eickhoff, H. Kollmus, P. Puppel, H. Reich-Sprenger
    GSI, Darmstadt
  • L.H.J. Bozyk
    FIAS, Frankfurt am Main
 
 

After partially completing the upgrade program of SIS18, the number of intermediate charge state heavy ions accelerated to the FAIR booster energy of 200 MeV/u, could be increased by a factor of 50. Meanwhile, more than 1010 Uranium ions with charge state 27+ have been accelerated with moderate beam loss by ionization and reasonably stable residual gas pressure conditions. The specific challenge for the SIS18 booster operation is the high cross section for ionization due to the low charge state in combination with gas desorption processes and the dynamic vacuum pressure. Especially for this operation mode which is requied to match the intensity requirements for FAIR, an extended upgrade program of SIS18 is presently ongoing and partially completed. The achieved progress in minimizing the ionization beam loss underlines that the chosen technical strategies described in this report are appropriate.

 
MOPD016 Injection Upgrades for the ISIS Synchrotron injection, space-charge, controls, linac 705
 
  • J.W.G. Thomason, D.J. Adams, D.J.S. Findlay, I.S.K. Gardner, S.J.S. Jago, B. Jones, A.P. Letchford, R.J. Mathieson, S.J. Payne, B.G. Pine, A. Seville, H. V. Smith, C.M. Warsop, R.E. Williamson
    STFC/RAL/ISIS, Chilton, Didcot, Oxon
  • J. Pasternak
    STFC/RAL, Chilton, Didcot, Oxon
  • C.R. Prior, G.H. Rees
    STFC/RAL/ASTeC, Chilton, Didcot, Oxon
 
 

The ISIS Facility based at the Rutherford Appleton Laboratory in the UK is the world's most productive spallation neutron source. Presently it runs at beam powers of 0.2 MW, with RF upgrades in place to supply increased powers for the new Second Target Station. Increasing injection energy into the synchrotron beyond the existing 70 MeV level has significant potential to increase intensity as a result of reduced space charge. This paper outlines studies for this upgrade option, which include magnet and power supply upgrades to achieve a practical injection system, management of increased injection region activation levels due to higher energy un-stripped particles and ensuring the modified longitudinal and transverse beam dynamics during injection and acceleration are possible with low loss at higher intensity levels.

 
MOPD033 Simulation for a Beam Matching Section with RFQSIM simulation, rfq, emittance, ion 756
 
  • N. Mueller, M. Baschke, J.M. Maus, A. Schempp
    IAP, Frankfurt am Main
 
 

The goal of the Frankfurt Funneling Experiment is to multiply beam currents by merging two low energy ion beams. In an ideal case this would be done without any emittance growth. Our setup consists of two ion sources, a Two-Beam-RFQ accelerator and a multi cell deflector which bends the beams to one common beam axis. The end section of the RFQ electrodes are designed to achieve a 3d focus at the crossing point of the two beam axis. New simulations with the RFQSIM-Code for a matching system with extended electrodes will be presented.

 
MOPD041 Recent Progress in the Beam Commissioning of J-PARC Linac linac, DTL, emittance, proton 774
 
  • M. Ikegami
    KEK, Ibaraki
  • A. Miura, G.H. Wei
    JAEA/J-PARC, Tokai-mura
  • H. Sako
    JAEA, Ibaraki-ken
 
 

The user operation of J-PARC linac was started in December 2008, and it has been operated with the limited beam power of less than 1.2 kW making efforts at improving hardware availability. Since November 2007, the beam power from the linac has been increased to 7.2 kW that corresponds to 120 kW from the downstream 3-GeV synchrotron. We also performed a high-power demonstration run with 18 kW (or 300 kW from the synchrotron) that corresponds to the design beam power for the present configuration. In the course of the beam power ramp-up, we have suffered from significant beam losses in the beam transport line after the linac. Accordingly, the emphasis of the beam tuning has been shifted to the mitigation of the uncontrolled beam losses. Some of the loss mechanisms are identified in the beam studies, and we have succeeded in mitigating them. In this paper, we present recent progress in the beam commissioning of J-PARC linac with emphasis on the effort to mitigate the beam losses.

 
MOPD063 Experimental Study of the SNS MEBT Chopper Performance power-supply, extraction, high-voltage, target 831
 
  • A.V. Aleksandrov, C. Deibele
    ORNL, Oak Ridge, Tennessee
 
 

The chopper system for the Spallation Neutron Source (SNS) provides a gap in the beam for clean extraction from the accumulator ring. It consists of a pre-chopper in the low energy beam transport and a faster chopper in the medium energy beam transport (MEBT). It took several iterations to develop a working design with the required parameters. In this paper we describe the latest design of the MEBT chopper deflector and give results of the experimental verification of the chopper effectiveness, the gap cleanness and the rise time measured with high resolution using the SNS laser wire. The effect on the losses will be discussed as well.

 
MOPE010 Observation of Dust Trapping Using Video Cameras electron, vacuum, radiation, insertion 975
 
  • Y. Tanimoto, T. Honda, S. Sakanaka
    KEK, Ibaraki
 
 

Sudden decrease in the beam lifetime is sometimes observed in many electron storage rings. Such an event has been commonly attributed to dust trapping, but its mechanism has not been entirely elucidated yet. Our recent research at PF-AR has shown that trapped dust with certain conditions can be visually observed by video cameras, and the recorded movies revealed that the trapped dust moved longitudinally. In addition, the light emission from the dust indicated that its temperature reached 1000 K or more. Thus, direct observation of trapped dust has been proved to be an effective way to investigate the dust trapping mechanism. We have carried on this research with advanced cameras, such as high-sensitivity or high-speed cameras, and the results will be presented.

 
MOPE015 Application of a Single-Wire Proportional Counter to the Beam Loss Monitoring at J-PARC MR space-charge, ion, septum, monitoring 990
 
  • K. Satou, T. Toyama
    J-PARC, KEK & JAEA, Ibaraki-ken
  • H. Harada, K. Yamamoto
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
 
 

A single-wire proportional counter which has the maximum gain of 6·104 is used as a beam loss monitor (p-BLM), thus low-level beam loss can be monitored. However, it involves gain reduction problem by the space charge effect. It is essential to estimate the space charge effect to utilize a proportional counter for beam loss monitoring. The calibration procedure is discussed for the p-BLMs for 3-50BT and MR. Measurements of residual dose were made and some nuclei were identified. Radiation from the short-life nucleus, Fe53 (T1/2=8.51m), may be a good index to predict a residual dose after a long term beam operation.

 
MOPE063 New On-line Gain Drift Compensation for Resonant Current Monitor under Heavy Heat Load resonance, proton, pick-up, target 1122
 
  • P.-A. Duperrex, V. Gandel, D.C. Kiselev, Y. Lee, U. Müller
    PSI, Villigen
 
 

For high intensity beam operation (3mA, 1.8MW) in the PSI cyclotron, a new current monitor for proton beams has been installed during the 2009 maintenance period. This current monitor is an actively cooled re-entrant cavity with its resonance tuned at the 2nd RF harmonic (101 MHz). Operating this system presents several challenges due to the heavy shower of energetic particles, the resonator being placed 8 m behind a graphite target. The resonator is actively cooled with water, its external surface was blackened to improve the radiation cooling and its mechanical structure was optimized for good heat conduction. The resonance characteristics are extremely sensitive to structural changes of the resonator. Because of non-uniform temperature distribution and dynamical changes the observed gain drift during operation is of the order of 10%. To correct these drifts 2 tests signals 50 kHz off the RF frequency are measured on-line during beam operation. They provide an innovative mean to estimate and to correct on-line the resonator gain. This paper will present the measurement method and the achieved performances.

 
TUOAMH01 First Cleaning with LHC Collimators collimation, betatron, insertion, proton 1237
 
  • D. Wollmann, O. Aberle, G. Arnau-Izquierdo, R.W. Assmann, J.-P. Bacher, V. Baglin, G. Bellodi, A. Bertarelli, A.P. Bouzoud, C. Bracco, R. Bruce, M. Brugger, S. Calatroni, F. Caspers, F. Cerutti, R. Chamizo, A. Cherif, E. Chiaveri, P. Chiggiato, A. Dallocchio, R. De Morais Amaral, B. Dehning, M. Donze, A. Ferrari, R. Folch, P. Francon, P. Gander, J.-M. Geisser, A. Grudiev, E.B. Holzer, D. Jacquet, J.B. Jeanneret, J.M. Jimenez, M. Jonker, J.M. Jowett, Y. Kadi, K. Kershaw, L. Lari, J. Lendaro, F. Loprete, R. Losito, M. Magistris, M. Malabaila, A. Marsili, A. Masi, S.J. Mathot, M. Mayer, C.C. Mitifiot, N. Mounet, E. Métral, A. Nordt, R. Perret, S. Perrollaz, C. Rathjen, S. Redaelli, G. Robert-Demolaize, S. Roesler, A. Rossi, B. Salvant, M. Santana-Leitner, I. Sexton, P. Sievers, T. Tardy, M.A. Timmins, E. Tsoulou, E. Veyrunes, H. Vincke, V. Vlachoudis, V. Vuillemin, Th. Weiler, F. Zimmermann
    CERN, Geneva
  • I. Baishev, I.A. Kurochkin
    IHEP Protvino, Protvino, Moscow Region
  • D. Kaltchev
    TRIUMF, Vancouver
 
 

The LHC has two dedicated cleaning insertions: IR3 for momentum cleaning and IR7 for betatron cleaning. The collimation system has been specified and built with tight mechanical tolerances (e.g. jaw flatness ~ 40 μm) and is designed to achieve a high accuracy and reproducibility of the jaw positions. The practically achievable cleaning efficiency of the present Phase-I system depends on the precision of the jaw centering around the beam, the accuracy of the gap size and the jaw parallelism against the beam. The reproducibility and stability of the system is important to avoid the frequent repetition of beam based alignment which is currently a lengthy procedure. Within this paper we describe the method used for the beam based alignment of the LHC collimation system, its achieved accuracy and stability and its performance at 450GeV.

 

slides icon

Slides

 
TUOAMH03 Channeling and Volume Reflection Based Crystal Collimation of the Tevatron Circulating Beam Halo (T980) collimation, collider, scattering, simulation 1243
 
  • V.D. Shiltsev, G. Annala, R.A. Carrigan, A.I. Drozhdin, T.R. Johnson, A.M. Legan, N.V. Mokhov, R.E. Reilly, D.A. Still, R. Tesarek, J.R. Zagel
    Fermilab, Batavia
  • R.W. Assmann, V.P. Previtali, W. Scandale
    CERN, Geneva
  • Y.A. Chesnokov, I.A. Yazynin
    IHEP Protvino, Protvino, Moscow Region
  • V. Guidi
    INFN-Ferrara, Ferrara
  • Yu.M. Ivanov
    PNPI, Gatchina, Leningrad District
  • S. Peggs
    BNL, Upton, Long Island, New York
 
 

The T980 crystal collimation experiment is underway at the Tevatron to study various crystal types and parameters and evaluate if this technique would increase TeV beam-halo collimation efficiency at high-energy hadron colliders such as the Tevatron and the LHC. The setup has been substantially enhanced during the Summer 2009 shutdown by installing a new O-shaped crystal in the horizontal goniometer, adding a vertical goniometer with two alternating crystals (O-shaped and multi-strip) and additional beam diagnostics. First measurements with the new system are quite encouraging, with channeled and volume-reflected beams observed on the secondary collimators as predicted. Investigation of crystal collimation efficiencies with crystals in volume reflection and channeling modes are described in comparison with an amorphous primary collimator. Results on the system performance are presented for the end-of-store studies and for entire collider stores. Planning is underway for dedicated studies during a Tevatron post-collider physics running period.

 

slides icon

Slides

 
TUOCMH03 Initial Experience with the Machine Protection System for LHC interlocks, injection, dumping, kicker 1277
 
  • R. Schmidt, R.W. Assmann, B. Dehning, M. FERRO-LUZZI, B. Goddard, M. Lamont, A.P. Siemko, J.A. Uythoven, J. Wenninger, M. Zerlauth
    CERN, Geneva
 
 

Nominal beam parameters at 7TeV/c will only be reached after some years of operation, with each proton beam having a stored energy of 360MJ. However, a small fraction of this energy is sufficient to damage accelerator equipment or experiments in case of uncontrolled beam loss. The correct functioning of the machine protection systems is vital during the different operational phases already for initial operation. When operating the complex magnet system, with and without beam, safe operation relies on the protection and interlock systems for the superconducting circuits. For safe injection and transfer of beam from SPS to LHC, transfer line parameters are monitored, beam absorbers must be in the correct position and the LHC must be ready to accept beam. At the end of a fill and in case of failures beams must be properly extracted onto the dump blocks, for some failures within less than few hundred microseconds. Safe operation requires many systems: beam dumping system, beam interlocks, beam instrumentation, equipment monitoring, collimators and absorbers, etc. We describe the commissioning of the LHC machine protection system and the experience during the initial operation.

 

slides icon

Slides

 
TUYRA02 Challenges and Solutions for J-PARC Commissioning and Early Operation extraction, rfq, cavity, resonance 1304
 
  • T. Koseki
    J-PARC, KEK & JAEA, Ibaraki-ken
 
 

The J-PARC accelerator facility consists of a 400 MeV H- linac, a 3-GeV RCS, a 50-GeV MR (Main Ring) and related experimental facilities. Beam commissioning of the facility is started from the upstream accelerators while construction of the downstream accelerators and experimental facilities is in progress. The beam commissioning of MR, MLF(Materials and Life science experimental Facility) and Hadron experimental facility started in JFY 2008. In this presentation, we present an overview of the J-PARC commissioning status. Recent progress of MR commissioning will be described in more detail. The talk will focus on the issues, challenges, solutions, and lessons learned during the commissioning and early operations of J-PARC.

 

slides icon

Slides

 
TUPEA022 Simulations of the Full Impact of the LHC Beam on Solid Copper and Graphite Targets target, proton, simulation, synchrotron 1375
 
  • N.A. Tahir
    GSI, Darmstadt
  • V.E. Fortov, I. Lomonosov, A. Shutov
    IPCP, Chernogolovka, Moscow region
  • R. Piriz
    Universidad de Castilla-La Mancha, Ciudad Real
  • R. Schmidt
    CERN, Geneva
 
 

Safety of the personnel and the equipment is an issue of great concern when operating with mighty particle beams like the ones generated by the LHC. Any uncontrolled release of even a very small fraction of the beam energy could cause considerable damage to the equipment. A worst case scenario is in which the entire beam is lost at a single point. Over the past years, we have carried out extensive numerical simulations to assess the consequences of an accident of this magnitude. We have simulated the thermodynamic and the hydrodynamic response of cylindrical targets made of solid copper and solid graphite, respectively, that are facially irradiated with one LHC beam. Our simulations show that the 7 TeV/c LHC protons will penetrate up to about 35 m in solid copper and about 10 m in solid graphite during the 89 μs beam duration time. In both cases, the target is severely damaged and a substantial part of the target is converted into High Energy Density Matter state.

 
TUPEA034 Laser Recycler Using An Asymmetrical Con-focal Cavity laser, cavity, ion, optics 1402
 
  • I. Yamane
    KEK, Ibaraki
  • M. Nakamura, H. Okuno
    RIKEN Nishina Center, Wako
 
 

An asymmetrical con-focal cavity is composed of tow concave mirrors with different focal length, placed face to face, and their axes and focal points coincide. When a laser beam is injected in parallel with the mirror axis, from backward of and just outside of the mirror with the smaller focal length, the laser beam is trapped in the cavity and repeats reflection by mirrors. Then, the beam reflected by the mirror with the larger focal length passes every time the focal point and the period by which pulses return to the focal point is constant. Therefore, if the repetition period of the injected laser pulse is equal to the repetition period in the cavity, all laser pulses comes to the focal point at the same time and the beam intensity is stacked up. Calculation on the performance of an asymmetrical con-focal cavity shows that a laser pulse can be recycled more than a few tens turns and the beam intensity can be stacked to more than a few tens times of the original beam intensity when the laser beam is a Gaussian beam and the reflectance of the mirrors is 100%. Results of calculation is examined using a He-Ne laser and a pair of high reflection mirrors.

 
TUPEB036 Tune Resonance Phenomena in the SPS and Machine Protection via Fast Position Interlocking resonance, closed-orbit, simulation, extraction 1602
 
  • T. Baer, B. Araujo Meleiro, T.B. Bogey, J. Wenninger
    CERN, Geneva
  • T. Baer
    DESY, Hamburg
 
 

The Super Proton Synchrotron (SPS) at CERN with a peak energy of 450GeV is at the top of the LHC preaccelerator-complex. Apart from the LHC, SPS is with Tevatron the accelerator with the largest stored beam energy of up to 2.5MJ. The SPS has a known vulnerability to fast equipment failures that led to an uncontrolled loss of a high intensity beam in 2008, which resulted in major damage of a main dipole. The beam loss was caused by a fast tune decrease towards an integer resonance. Simulations and distinct experimental studies provide clear understanding of the beam dynamics at different SPS tune resonances. Diverging closed orbit oscillations, dispersion explosion and increased beta-beating are the driving effects that lead to a complete beam loss in as little as 3 turns (70μs). Dedicated experiments of fast failures of the main power converters reveal that the current interlock systems are much too slow for an adequate machine protection. To counteract the vulnerability of the SPS, current research focuses on a new fast position interlock system which is planned to become operational in 2010.

 
TUPEB062 Beam Commissioning and Performance Characterisation of the LHC Beam Dump Kicker Systems kicker, extraction, dumping, injection 1659
 
  • J.A. Uythoven, E. Carlier, L. Ducimetière, B. Goddard, V. Kain, N. Magnin
    CERN, Geneva
 
 

The LHC beam dump system was commissioned with beam in 2009. This paper describes the operational experience with the kicker systems and the tests and measurements to qualify them for operation. The kicker performance was characterized with beam by measurements of the kicker waveforms using bunches extracted at different times along the kicker sweep. The kicker performance was also continuously monitored for each pulse with measurement and analysis of each kick pulse, allowing diagnostic of errors and of long-term drifts. The results are described and compared to the expectations.

 
TUPEB066 Injection Beam Loss and Beam Quality Checks for the LHC injection, kicker, target, controls 1671
 
  • B. Goddard, V. Baggiolini, W. Bartmann, C. Bracco, L.N. Drosdal, E.B. Holzer, V. Kain, D. Khasbulatov, N. Magnin, M. Meddahi, A. Nordt, M. Sapinski
    CERN, Geneva
  • M. Vogt
    DESY, Hamburg
 
 

The quality of the injection into the LHC is monitored by a dedicated software system which acquires and analyses the pulse waveforms from the injection kickers, and measures key beam parameters and compares them with the nominal ones. The beam losses at injection are monitored on many critical devices in the injection regions, together with the longitudinal filling pattern and maximum trajectory offset on the first 100 turns. The paper describes the injection quality check system and the results from LHC beam commissioning, in particular the beam losses measured during injection at the various aperture limits. The results are extrapolated to full intensity and the consequences are discussed.

 
TUPEB067 Beam Commissioning of the Injection Protection Systems of the LHC injection, proton, kicker, extraction 1674
 
  • W. Bartmann, R.W. Assmann, C. Bracco, B. Dehning, B. Goddard, E.B. Holzer, V. Kain, M. Meddahi, A. Nordt, S. Redaelli, A. Rossi, M. Sapinski, D. Wollmann
    CERN, Geneva
 
 

The movable LHC injection protection devices in the SPS to LHC transfer lines and downstream of the injection kicker in the LHC were commissioned with low-intensity beam. The different beam-based alignment measurements used to determine the beam centre and size are described, together with the results of measurements of the transverse beam distribution at large amplitude. The system was set up with beam to its nominal settings and the protection level against various failures was determined by measuring the transmission and transverse distribution into the LHC as a function of oscillation amplitude. Beam losses levels for regular operation were also extrapolated. The results are compared with the expected device settings and protection level, and the implications for LHC operation discussed.

 
TUPEB071 Mechanical Engineering and Design of the LHC Phase II Collimators collimation, status, alignment, diagnostics 1683
 
  • A. Bertarelli, A. Dallocchio, L. Gentini, N. Mariani, R. Perret, M.A. Timmins
    CERN, Geneva
 
 

Phase II collimators will complement the existing system to improve the expected high RF impedance and limited efficiency of Phase I jaws. An international collaborative effort has been launched to identify novel advanced materials responding to the very challenging requirements of the new collimators. Complex numerical calculations simulating extreme conditions and experimental tests are in progress. In parallel, an innovative modular design concept of the jaw assembly is being developed to allow fitting in alternative materials, minimizing the thermally induced deformations, withstanding accidents and tolerate high radiation doses. Phase II jaw assembly is made up of a molybdenum back-stiffener ensuring high geometrical stability and a modular jaw split in threes sectors. Each sector is equipped with a high-efficiency independent cooling circuit. Beam position monitors (BPM) are embedded in the jaws to accelerate setup time and improve beam monitoring. An adjustment system will permit to fine-tune the jaw flatness just before commissioning the system. A full scale collimator prototype is being manufactured by CERN workshops to validate each feature of the new design.

 
TUPEB075 Preliminary results of the crystal collimation test in UA9 collimation, radiation, simulation, lattice 1695
 
  • D. Mirarchi, G. Cavoto
    INFN-Roma, Roma
  • R. Losito, W. Scandale
    CERN, Geneva
  • A.M. Taratin
    JINR, Dubna, Moscow Region
 
 

We present a detailed analysis of the beam loss data collected at the SPS during the 2009 machine developments devoted to test crystal collimation. Scintillator counters and Gas electron multiplier detectors were installed in special points to detect the effect of inelastic interaction of protons with the crystals in various orientation with respect to the beam. Clear correlations of the counting rates with the crystal positions and orientation were detected during the data-taking and were crucial to put the crystal in optimal channeling position. For one of the crystal the pattern of losses showed evidence of several planar and axial channeling conditions.

 
TUPEC075 Studies of Beam Dynamics for eRHIC electron, emittance, ion, linac 1889
 
  • G. Wang, M. Blaskiewicz, A.V. Fedotov, Y. Hao, J. Kewisch, V. Litvinenko, E. Pozdeyev, V. Ptitsyn
    BNL, Upton, Long Island, New York
 
 

We present our studies on various aspects of the beam dynamics in 'racetrack' design of the first stage electron-ion collider at RHIC (eRHIC), including transverse beam break up instabilities, electron beam emittance growth and energy loss due to synchrotron radiation, electron beam losses due to Touschek effects and residue gas scattering, beam-beam effects at the interaction region and emittance growth of ion beam due to electron bunch to bunch noises. For all effects considered above, no showstopper has been found.

 
TUPD028 Fast Beam-ion Instability Studies at SOLEIL ion, vacuum, feedback, wakefield 1985
 
  • R. Nagaoka, L. Cassinari, M.D. Diop, M.-P. Level, C. Mariette, R. Sreedharan
    SOLEIL, Gif-sur-Yvette
 
 

Ever since the commissioning times, transverse instabilities, which now have been identified as the so called Fast Beam-Ion Instability (FBII), have existed in the SOLEIL storage ring. Though along with the improvement of the vacuum level with increasing beam dose its relative importance has decreased to a large extent as compared to the classical instabilities due to the coupling impedance, the FBII still exists persistently at high current, making it difficult to attain a stable beam at the final goal of 500 mA. In particular, sudden beam losses are frequently encountered after keeping the beam stable over a certain time with transverse feedback at the final current, which raised a question as to whether the observed phenomena are compatible with the saturating effect of the FBII. Experimental analysis using the bunch by bunch feedback diagnostics as well as theoretical and numerical analysis using multibunch tracking have been carried out to understand the instability quantitatively and to elucidate the mechanism of the beam losses.

 
TUPD065 Long-Range Beam-Beam Compensation in RHIC dynamic-aperture, proton, simulation, emittance 2072
 
  • H.J. Kim, T. Sen
    Fermilab, Batavia
  • W. Fischer
    BNL, Upton, Long Island, New York
 
 

In order to avoid the effects of long-range beam-beam interactions which produce beam blow-up and deteriorate beam life time, a compensation scheme with current carrying wires has been proposed. Two long-range beam-beam compensators were installed in RHIC rings in 2006. The effects of the compensators have been experimentally investigated. An indication was observed that the compensators are beneficial to beam life time in measurements performed in RHIC during 2009. In this paper, we report the effects of wire compensator on beam loss and emittance for proton-proton beams at collision energy.

 
TUPD066 Electron Lens in RHIC electron, proton, betatron, simulation 2075
 
  • H.J. Kim, T. Sen
    Fermilab, Batavia
 
 

Increasing the luminosity requires higher beam intensity and often focusing the beam to smaller sizes at the interaction points. The effects of head-on interactions become even more significant. The head-on interaction introduces a tune spread due to a difference of tune shifts between small and large amplitude particles. A low energy electron beam so called electron lens is expected to improve intensity lifetime and luminosity of the colliding beams by reducing the betatron tune shift and spread. In this paper we discuss the results of beam simulations with the electron lens in RHIC.

 
WEYRA01 The FAIR Accelerators: Highlights and Challenges ion, space-charge, heavy-ion, injection 2430
 
  • O. Boine-Frankenheim
    GSI, Darmstadt
 
 

The FAIR accelerator project at GSI should increase the intensity of primary proton and heavy ion beams by up to two orders of magnitude, relative to the existing GSI facility. In addition to the design of the new synchrotron SIS-100 and the storage rings, the intensity upgrade of the SIS-18 synchrotron plays a key role for the FAIR project. Recently a new record beam intensity for intermediate charge state uranium ions has been achieved in the SIS-18. Still several challenges related to beam intensity effects and phase space conservation have to be mastered in order to reach the beam parameters required for the injection into SIS-100. In SIS-100 beam loss control and machine protection are of major concern. Lost energetic heavy ions can cause a more severe damage of accelerator components than the corresponding amount of protons. Gradual beam loss of energetic ions is expected to occur in SIS-100 mainly during slow extraction of intense beams. Coherent transverse instabilities induced by the beam pipe impedance are a potential cause of fast beam loss and emittance increase. Cures and protection measures together with the result of simulation studies will be summarized.

 

slides icon

Slides

 
WEPEA016 Frequency Maps at PETRA III kicker, dynamic-aperture, injection, wiggler 2511
 
  • A. Kling, K. Balewski
    DESY, Hamburg
 
 

PETRA III is a 3rd generation synchrotron radiation light source which started commissioning in April 2009. Recently, first frequency map measurements have been made using the turn-by-turn capabilities of the beam position monitors and horizontal as well as vertical kicker magnets. The results are in good agreement with expectations from tracking studies performed with SixTrack.

 
WEPEB006 Present Status of MPS and TS for IFMIF/EVEDA Accelerator controls, EPICS, status, target 2695
 
  • H. Takahashi, T. Kojima, S. Maebara, T. Narita, H. Sakaki, K. Tsutsumi
    JAEA, Rokkasho, Kamikita, Aomori
 
 

Control System for IFMIF/EVEDA accelerator prototype consists of the six subsystems; Central Control System (CCS), Local Area Network (LAN), Personnel Protection System (PPS), Machine Protection System (MPS), Timing System (TS) and Local Control System (LCS). The subsystems have been designed and their test benches been fabricated at JAEA. The IFMIF/EVEDA accelerator prototype provides a deuteron beam with the power more than 1 MW, which is as same as that in cases of J-PARC and SNS. In the control system, MPS and TS with high performance and precision are strongly required to avoid the radio-activation of the accelerator components. The prototypes of the MPS and TS are testing in conjunction with the injector test starting at CEA/Saclay from autumn in 2010. These results will feedback the design and the fabrication of the control components. This paper presents the development status of the TS modules and EPICS drivers for TS and MPS, and the prospects to apply them to the Injector test.

 
WEPEB042 Optimization of the Position of the Radial Loop Pickups in the CERN PS pick-up, controls, quadrupole, optics 2782
 
  • S. Aumon
    EPFL, Lausanne
  • S. Aumon, H. Damerau, S.S. Gilardoni
    CERN, Geneva
 
 

A part of the beam losses at transition crossing of high intensity beams in the CERN PS have been attributed to an excursion of the closed orbit. The orbit jump occurs simultaneously with the jump of the transition energy triggered by pulsed quadrupoles. Investigations showed that the position of the pickups used for the radial loop system was not optimized with respect to the dispersion change caused by the fast change of the transition energy. Thanks to new electronics of the orbit measurement system, turn-by-turn orbit data could be recorded around transition crossing. Their analysis, together with calculations of the transverse optics, allowed determining a new choice of pickup positions for the radial loop. In comparison to the previous pickup configuration, the new configuration improves the mean radial position not only during transition crossing, but all along the acceleration cycle.

 
WEPEB061 A Fiber Beam Loss Monitor for the SPring-8 X-FEL: Test Operation at the SPring-8 250 MeV Compact SASE Source FEL, undulator, electron, vacuum 2830
 
  • X.-M. Maréchal
    JASRI/SPring-8, Hyogo-ken
  • Y. Asano, T. Itoga
    RIKEN/SPring-8, Hyogo
 
 

Fiber-based beam loss monitors (BLM) have attracted much attention in recent years. Among them, systems using the detection of the Cerenkov light generated by the secondary charged particles hitting an optical fiber set along the vacuum chamber, offer the possibility to detect beam losses with a very fast response time (less than a few ms) over long distances, good position accuracy and sensitivity at a reasonable cost. For the undulator section of the SPring-8 X-FEL, radiation safety considerations set the desirable detection limit at 1 pC (corresponding to a 0.1% beam loss of the initial 1 nC/pulse) over more than a hundred meter. We report on a the test operation of a fiber-based BLM carried out at the 250 MeV SPring-8 Compact SASE Source (SCSS), a 1/16th model of the future X-FEL. The expected detection limit of the BLM based on a large (400 μm) core multimode fiber is below 2 pC over 120 m (for a corresponding 10 mV signal) while the position accuracy is expected to be better than one meter.

 
WEPEB062 Fiber Beam Loss Monitor for the SPring-8 X-FEL: A Numerical Study of its Design and Performance electron, FEL, vacuum, simulation 2833
 
  • T. Itoga, Y. Asano
    RIKEN/SPring-8, Hyogo
  • X.-M. Maréchal
    JASRI/SPring-8, Hyogo-ken
 
 

A fiber-based beam loss monitors (BLM) is under development for the undulator section of the SPring-8 X-FEL: the system is based on the detection of the Cerenkov light generated by the secondary charged particles hitting an optical fiber set along the vacuum chamber. Various parameters come into account in the final performance of the system, such as the impact angle and energy of the lost electrons, the fiber position (angular and radial) with respect to the point of impact, fiber characteristics (numerical aperture, index, diameter), etc. Thorough numerical studies have been carried out to investigate the performances of the system. Comparison with the experimental results obtained at the SPring-8 Compact SASE Source (SCSS), a 1/16th model of the future X-FEL are also given.

 
WEPEB064 Electricity Generation from Scattered Secondary Particles Induced by Synchrotron Radiation radiation, vacuum, synchrotron, synchrotron-radiation 2839
 
  • Y. Shimosaki, K. Kobayashi
    JASRI/SPring-8, Hyogo-ken
 
 

Electricity generation from scattered secondary particles has been examined for a kind of energy-recovery by using a beam loss monitor at the SPring-8 storage ring, in which PIN photodiodes are utilized without a reversed bias voltage in similar to a solar cell. The system and results will be reported.

 
WEPEB065 Beam Loss of J-PARC Rapid Cycling Synchrotron at Several Hundred kW Operation injection, neutron, target, proton 2842
 
  • K. Yamamoto, H. Harada, S. Hatakeyama, N. Hayashi, H. Hotchi, P.K. Saha, M. Yoshimoto
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
  • R. Saeki
    KEK/JAEA, Ibaraki-Ken
 
 

A 3GeV Rapid-Cycling Synchrotron (RCS) in Japan Proton Accelerator Research Complex (J-PARC) has continuously provided more than 100kW proton beam to the Neutron target since October 2009. And we also successfully accelerated 300kW beam for one hour on December 10th by way of trial. We found some problems through these experiences. We report those problems and the residual dose in such high intensity operation.

 
WEPEB067 Beam Containment System for NSLS-II injection, shielding, radiation, dipole 2848
 
  • S.L. Kramer, W.R. Casey, P.K. Job
    BNL, Upton, Long Island, New York
 
 

The shielding design for the NSLS-II will provide adequate protection for the full injected beam loss in two periods of the ring around the injection point, but the remainder of the ring is shielded for lower losses of <10% full beam loss. This will require a system to insure that beam losses don't exceed these levels for a period of time that could cause levels outside the shield walls. This beam containment system will measure, provide a level of control and alarm indication of the beam power losses along the beam path from the source (e-gun, linac) thru the injection system and the storage ring. This system will consist of collimators that will provide limits to (an potentially measure) the beam miss-steering and control the loss points of the charge and monitors that will measure the average beam current losses along the beam path and alarm when this beam power loss exceeds the level set by the shielding specifications. This will require some new ideas in beam loss detection capability and collimation. The initial planning and R&D program will be presented.

 
WEPEB069 LHC Beam Loss Measurements and Quench Level Abort Threshold Accuracy proton, simulation, injection, neutron 2854
 
  • M. Sapinski, B. Dehning
    CERN, Geneva
  • A. Priebe
    Poznań University of Technology, Poznań
 
 

The LHC beam loss measurement system is mainly used to trigger the beam abort in case a magnet coil quench level is approached. The predicted heat deposition in the superconducting coils of the magnets have been determined by particle shower simulation codes, while the liquid helium cooling capacity of the system has been both simulated and measured. The results have been combined to determine the abort thresholds. Measurements of the energy depositions of lost protons from the initial beams in the LHC are used to determine the accuracy of the beam abort threshold settings. The simulation predictions are reviewed and compared with the measurement results.

 
WEPEB070 Particle Shower Simulations and Loss Measurements in the LHC Magnet Interconnection Regions simulation, proton, injection, dipole 2857
 
  • C. Kurfuerst, B. Dehning, E.B. Holzer, A. Nordt, M. Sapinski
    CERN, Geneva
 
 

Particle losses in the LHC arcs are mainly expected in the interconnection region between a dipole and quadrupole magnet. The maximal beam size, the maximal orbit excursion and aperture changes cause the enhancement of losses at this location. Extensive Geant4 simulations have been performed to characterise this particular region to establish beam abort settings for the beam loss monitors in these areas. Data from first LHC beam loss measurements have been used to check and determine the most likely proton impact locations. This input has been used to optimise the simulations used for the definition of thresholds settings. The accuracy of these settings is investigated by comparing the simulations with actual loss measurements.

 
WEPEB074 Requirements of CLIC Beam Loss Monitoring System linac, monitoring, diagnostics, injection 2869
 
  • M. Sapinski, B. Dehning, E.B. Holzer, M. Jonker, S. Mallows, Th. Otto
    CERN, Geneva
  • C.P. Welsch
    Cockcroft Institute, Warrington, Cheshire
 
 

The Compact Linear Collider (CLIC) is a proposed multi-TeV linear electron-positron collider being designed by a world-wide collaboration. It is based on a novel two-beam acceleration scheme in which two beams (drive and main beam) are placed in parallel to each other and energy is transferred from the drive beam to the main one. Beam losses on either of them can have catastrophic consequences for the machine because of high intensity (drive beam) or high energy and small emittance (main beam). In the framework of machine protection, a Beam Loss Monitoring system has to be put in place. This paper discusses the requirements for the beam loss system in terms of detector sensitivity, resolution, dynamic range and ability to distinguish losses originating from various sources. A particular attention is given to the two-beam module where the protection from beam losses is particularly challenging and important.

 
WEPEB075 Beam Halo Studies for CTF3 resonance, lattice, diagnostics, controls 2872
 
  • S.T. Artikova
    MPI-K, Heidelberg
  • R.B. Fiorito, A.G. Shkvarunets, H.D. Zhang
    UMD, College Park, Maryland
  • C.P. Welsch
    Cockcroft Institute, Warrington, Cheshire
 
 

Beam halo can have severe effects on the performance of high energy accelerators. It reduces the experimental throughput, may lead to noise in the experiments, or even damaging of accelerator components. In order to understand and ideally control the formation and evolution of beam halo, detailed simulation studies are required. In this contribution halo generation mechanisms and the underlying physical principles are first presented, before the particular case of the CLIC Test Facility (CTF3) is discussed in detail. Analytical, numerical and simulation studies are combined to estimate the relevant sources of halo formation and to study halo propagation in the different CTF3 sections.

 
WEPEC022 Beam Behavior due to Crab Cavities Break down cavity, feedback, controls, vacuum 2938
 
  • K. Nakanishi, Y. Funakoshi, M. Tobiyama
    KEK, Ibaraki
 
 

Crab cavities were installed in KEKB in 2007. The function of the cavity is to tilt the bunch of the beam in the longitudinal direction. But if the RF phase gets out of control, the cavity kicks the beam like a steering magnet. To avoid this unwanted kick, the RF phase must be controlled well. In beam operation, some disturbances may occur such as a discharge, a quench, etc. When such disturbances occur, it is very difficult to control the RF phase precisely. We can't trust measured RF phase at that time. In KEKB, beam is aborted quickly when a disturbance is detected. Beam behavior before detect the disturbances has been investigated. We discuss following items. (1)How fast should the beam be aborted after detecting disturbances? (2)How fast should RF be turned off after detecting disturbances? (3)What a kind of disturbance is harmful? (4)Is the beam abort necessary at all? (Is just to turn RF off OK?)

 
WEPE054 The MICE Muon Beam: Status and Progress target, acceleration, proton, synchrotron 3467
 
  • A.J. Dobbs, M. Apollonio, K.R. Long, J. Pasternak
    Imperial College of Science and Technology, Department of Physics, London
  • D.J. Adams
    STFC/RAL/ISIS, Chilton, Didcot, Oxon
 
 

The international Muon Ionisation Cooling Experiment (MICE) is designed to provide a proof of principal of the ionisation cooling technique proposed to reduce the muon beam phase space at a future Neutrino Factory or Muon Collider. The pion production target is a titanium cylinder that is dipped into the proton beam of the Rutherford Appleton Laboratory's ISIS 800 MeV synchrotron. Studies of the particle rate in the MICE muon beam are presented as a function of the beam loss induced in ISIS by the MICE target. The implications of the observed beam loss and particle rate on ISIS operation and MICE data taking is discussed.

 
WEPE062 MICE Target Operation and Monitoring target, acceleration, monitoring, emittance 3485
 
  • P. Hodgson, C.N. Booth, P.J. Smith
    Sheffield University, Sheffield
 
 

The MICE experiment requires a beam of low energy muons to demonstrate muon cooling. A target mechanism has been developed that inserts a small titanium target into the circulating ISIS beam during the last 2ms before extraction. The target mechanism has been in operation in the ISIS beam during 2009 and a large set of useful data has been obtained describing the target's operational parameters. This has allowed the commissioning of the initial section of the MICE beam line and instrumentation, and the close monitoring of target performance. This work describes these target parameters and presents some of the results from operational shifts.

 
THPPMH02 The Joy of Accelerator Physics emittance, dipole, collider, neutron 3658
 
  • J. Wei
    TUB, Beijing
 
 

Since being introduced to accelerator physics, I have had the privilege to study and work with some of the best physicists on some of the most exciting projects. My first assignment was to simulate transition-crossing in RHIC in which a shocking 86% beam loss led to a redesign of its RF system which later earned me a Ph.D. Participation in the design, R&D, construction, and the commissioning of RHIC, not only was I introduced to the fascinating world of accelerator physics but was also trained as a physicist for accelerator projects. Since then, I have had the opportunity to work and lead teams of physicists and engineers on accelerator projects: US-LHC/AP at BNL, SNS/AP at ORNL, SNS ring, CSNS in China, and now CPHS at Tsinghua. The accelerator profession is uniquely rewarding in that ideas and dreams can be turned into reality through engineering projects, through which one experiences endless learning in physics, technology, teamwork and friendship. An example of enjoying the fun and friendship is the work on crystalline beams as a hobby for the past 18 years.


*Wei, Li, Sessler, Okamoto PRL73(94)3089; 80(98)2606
*Wei, Harrison XVI RCNP Osaka(97)
*Wei et al PAC99 2921
*Wei et al PAC01(01)319
*Wei RMP75(03)1383
*Wei et al NIMA600(09)10
*Wei et al PAC09

 

slides icon

Slides

 
THPEB003 Determination of the Acceptance of SIS-18 using an RF Voltage ion, emittance, synchrotron, heavy-ion 3879
 
  • S. Sorge, G. Franchetti, A.S. Parfenova
    GSI, Darmstadt
 
 

The present heavy ion synchrotron SIS-18 will be upgraded to be used as a booster for further synchrotrons being part of the FAIR project underway at GSI. We present a technique to measure the acceptance of an accelerator based on the extension of a previous method by the measurement of particle loss which we have applied to SIS-18. Here, we used an RF voltage to transversally excite a coasting heavy ion beam. The resulting transverse growth of the beam leads to particle loss when the beam width exceeds the limiting aperture. The acceptance has been determined from the time evolution of the beam current measured after particle have started to hit the aperture.

 
THPEB010 Electrostatic Septum for 50GeV Proton Synchrotron in J-PARC septum, alignment, cathode, extraction 3900
 
  • Y. Arakaki, S. Murasugi, R. Muto, K. Okamura, Y. Shirakabe, M. Tomizawa
    KEK, Ibaraki
  • D. Horikawa, I. Sakai
    University of Fukui, Faculty of Engineering, Fukui
  • M. Nishikawa
    Nippon Advanced Technology Co. Ltd., Ibaraki-prefecture
 
 

The two electrostatic septa are one of the most important device for the slow extraction in 50GeV proton synchrotron. We have developed the thin ribbon type septum in order to reduce the beam loss. If alignment of ribbons is poor, the effective thickness seen from the beam become large, and it would increase the beam-hitting rate. The alignment of ribbon over 1.5m long septa was measured by a laser-focus displacement meter. The achieved effective thickness of septa is estimated to be 0.075mm and 0.080mm respectively. We will report a high voltage conditioning and a performance under beam commissioning.

 
THPEB012 Beam Test of Sawtooth-wave Pre-Buncher Coupled to a Multilayer Chopper background, bunching, target, ion 3906
 
  • M. Okada, H. Ishiyama, I. Katayama, H. Miyatake, K. Niki, Y. Watanabe
    KEK, Ibaraki
  • S. Arai
    RIKEN Nishina Center, Wako
  • H. Makii
    JAEA, Ibaraki-ken
 
 

In TRIAC (Tokai Radioactive Ion Accelerator Complex), intense bunched beams are planned for measurements of 12C(alpha, gamma) reactions. For 2-4MHz bunching to the 26MHz linac beams, sawtooth-wave pre-buncher has been developed. Since the wave applied to the pre-buncher is pseudo sawtooth shape synthesized from three sine waves, particles in out-of-bunch phase become backgrounds to the bunched beams. In order to remove them, a multilayer chopper has been newly installed upstream the pre-buncher. The multilayer chopper has 20 electrodes (40mm wide, 10mm long, and 0.1mm thick) piled up with gaps of 1.9mm in vertically to the beam direction. And a square-shape electric potential (100V maximum, 2-4 MHz) is applied to each electrodes alternately. The short gap makes it possible to realize sharp beam-chopping with relatively low electric potential and weak leakage electric field, although beam particles could be lost by 5% or more, since this chopper is set on the way of beams. As a result, the ratio of bunched particles to backgrounds has been improved from 3:1 to 99:1 by the chopper. High intensity beam test by 16O4+ beam will be also reported.

 
THPEB015 Beam Injection Tuning of the J-PARC Main Ring injection, closed-orbit, septum, kicker 3915
 
  • G.H. Wei
    KEK/JAEA, Ibaraki-Ken
  • A. Ando, Y. Hashimoto, T. Koseki, J. Takano
    J-PARC, KEK & JAEA, Ibaraki-ken
  • S. Igarashi, K. Ishii, M. Tomizawa, M. Uota
    KEK, Ibaraki
  • P.K. Saha, K. Satou, M.J. Shirakata
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
 
 

The beam commissioning of J-PARC (Japan Proton Accelerator Research Complex) MR (Main Ring) was started from May 2008 and is in progress. As usual, injection tuning is in the first stage and strongly related to other tuning items. Starting with design schemes, making adjustment due to leakage field influence from injection septum, doing envelope matching considering dilution of beam profile in Main Ring are reported in this paper. The 'Without bump' scheme was got on June 15th 2008, while 'With bump' scheme on February 15th 2009. Beam orbit betatron oscillation to the MR close orbit which cause by injection error is less than 1 mm both in horizontal and vertical direction. Meanwhile, Beam Optics matching for 3 GeV beam from 350BT to MR has been well done too, which is also very important.


* T. Koseki, Challenges and Solutions for J-PARC Commissioning and Early Operation, in these proceedings

 
THPEB018 Systematic Beam Loss Study due to the Foil Scattering at the 3-GeV RCS of J-PARC injection, simulation, scattering, target 3921
 
  • P.K. Saha, H. Harada, H. Hotchi, K. Yamamoto, Y. Yamazaki, M. Yoshimoto
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
  • I. Sugai
    KEK, Ibaraki
 
 

The beam loss caused by the nuclear scattering together with the multiple Coulomb scattering at the stripping foil is one of the key issue in RCS (Rapid Cycling Synchrotron) of the J-PARC (Japan Proton Accelerator Research Accelerator). In order to have a very realistic understanding, a systematic study with both experiment and simulation has been carried out recently. A total of seven targets with different thickness were used and the measured beam losses were found to be good in agreement with that in the simulation. A detail and realistic understanding from such a study will be very useful not only to optimize the foil system including the thickness and size at present with the injection beam energy of 181 MeV but also for the near future upgrade with 400 MeV and in addition can be a good example for similar existing and proposing projects.

 
THPEB019 First Step Analysis of Hybrid Type Boron-doped Carbon Stripper Foils For RCS of J-PARC ion, proton, electron, target 3924
 
  • Y. Yamazaki, M. Kinsho, O. Takeda, M. Yoshimoto
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
  • I. Sugai
    KEK, Ibaraki
 
 

J-PARC requires thick carbon stripper foils to strip electrons from the H- beam supplied by the linac before injection into the Rapid Cycling Synchrotron (RCS). Foil thickness is about 200 μg/cm2 corresponding to conversion efficiency of 99.7% from the primary H- beams of 181MeV energy to H+. For this purpose, we have successfully developed hybrid type thick boron-doped carbon (HBC) stripper foils, which showed a drastic improvement not only with respect to the lifetime, but also with respect to thickness reduction and shrinkage at high temperature during long beam irradiation. We started to study carbon stripper foils microscopically why carbon foils have considerable endurance for the beam impact by boron-doped. At first, we made a comparison between nominal carbon and HBC by the electric microscope and ion-induced analysis. In this paper, we will introduce some results for characteristics of HBC foils.

 
THPEB020 Beam Study Results with HBC Stripping Foils at the 3-GeV RCS in J-PARC scattering, injection, vacuum, extraction 3927
 
  • M. Yoshimoto, H. Harada, N. Hayashi, H. Hotchi, Y. Irie, M. Kawase, M. Kinsho, R. Saeki, P.K. Saha, K. Yamamoto, Y. Yamazaki
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
  • T. Ishiyama
    KEK/JAEA, Ibaraki-Ken
  • I. Sugai
    KEK, Ibaraki
 
 

The hybrid type thick boron-doped carbon (HBC) stripping foils are installed and used for the beam injection at the 3GeV RCS (Rapid Cycling Synchrotron) in J-PARC (Japan Proton Accelerator Research Complex). The HBC foils are developed by Sugai group in KEK, which improved the lifetime drastically. Up to now, the performance deterioration of the stripping foils can not be seen after the long beam irradiation for the 120kW user operation and 300kW high power beam demonstration at the RCS. In order to examine the characteristic of the HBC foils, various beam studies were carried out. The beam-irradiated spot at the foil was measured by scanning the foil setting position, the charge exchange efficiency was evaluated with various thickness foils, and the effect of the SiC fibers supporting the foil mounting was checked with different mounting foils. Beam study results obtained with using the HBC foils will be presented. In addition, the trends of outgas from the stripping foils and the deformations of the foils during the beam irradiation will be reported.

 
THPEB030 Stripping Foil Issues for H- Injection into the CERN PSB at 160 MeV emittance, scattering, proton, electron 3951
 
  • B. Goddard, M. Aiba, C. Bracco, C. Carli, M. Meddahi, W.J.M. Weterings
    CERN, Geneva
 
 

Beam physics considerations for the stripping foil of the 160 MeV PSB H- injection system are described, including the arguments for the foil type, thickness, geometry and positioning. The foil performance considerations are described, including expected stripping efficiency, emittance growth, energy straggling, temperature and lifetime. The different beam loss mechanisms are quantified in the context of the aperture limits, operational considerations and collimation requirements.

 
THPEC084 Crystal Collimation Efficiency Measured with the Medipix Detector in SPS UA9 Experiment proton, collimation, extraction, impedance 4252
 
  • E. Laface, W. Scandale, L. Tlustos
    CERN, Geneva
  • V. Ippolito
    INFN-Roma, Roma
 
 

The UA9 experiment was performed in 6 MDs from May to November 2009 with the goal of studying the collimation properties of a crystal in the framework of a future exploitation in the LHC collimation system. An important parameter evaluated for the characterization of the crystal collimation is the efficiency of halo extraction when the crystal is in channeling mode. In this paper it is explained how this efficiency can be measured using a pixel detector, the Medipix, installed in the Roman Pot of UA9. The number of extracted particles counted by the Medipix is compared with the total number of circulating particles measured by the Beam Current Transformers (BCTs): from this comparison the efficiency of the system composed by the crystal, used in channeling mode, and a tungsten absorber is proved to be greater than 85%.

 
THPE012 U400 Cyclotron Spiral Inflector with Beam Vertical Focusing Effect cyclotron, ion, emittance, focusing 4536
 
  • I.A. Ivanenko, B. Gikal, G. Gulbekyan
    JINR, Dubna, Moscow Region
 
 

The main losses of the injected beam are localized at the centre region of the cyclotron. One of the problems is the defocusing action of the spiral inflector. At the present work the method of decreasing of the vertical defocusing effect of the spiral inflector is presented. The decreasing of the vertical defocusing is achieved by means of special form of the inflector electric field. At FLNR, JINR, the new type of the inflector was investigated and manufactured. At the present time the inflector is installed and works at the U400 cyclotron. The experiments with the new inflector have shown the increasing of the beam intensity and more tuneble work of the cyclotron.

 
THPE050 Real Beam Line Optics from a Synthetic Beam optics, quadrupole, emittance, diagnostics 4629
 
  • R.M. Bodenstein, Y. Roblin, M.G. Tiefenback
    JLAB, Newport News, Virginia
 
 

The Continuous Electron Beam Accelerator Facility (CEBAF) at Jefferson Lab can be described as a series of concatenated beamlines. Methods used to measure the Twiss parameters in closed orbit machines are not applicable in such open ended systems. We are using properly selected sets of real orbits in the accelerator, as one would for numerical analysis. The evolution of these trajectories along the beamline models the behavior of a synthetic beam which deterministically supplements beam profile-based Twiss parameter measurements and optimizes the efficiency of beamline tuning. Examples will be presented alongside a description of the process.

 
THPE055 Linear Optics Measurements and Corrections Using AC Dipole In RHIC dipole, quadrupole, optics, injection 4644
 
  • G. Wang, M. Bai, L. Yang
    BNL, Upton, Long Island, New York
 
 

We report recent experimental results on linear optics measurements and corrections using ac dipole. In RHIC 2009 run, the concept of the SVD correction algorithm is tested at injection energy for both identifying the artificial gradient errors and correcting it using the trim quadrupoles. The measured phase beatings were reduced by 30% and 40% respectively for two dedicated experiments. In RHIC 2010 run, ac dipole is used to measure beta* and chromatic beta function. For the 0.65m beta* lattice, we observed a factor of 3 discrepancy between model and measured chromatic function in the yellow ring.

 
THPE069 Simulation of Space Charge Effects in JPARC simulation, injection, space-charge, emittance 4677
 
  • K. Ohmi, K. Fan, S. Igarashi, Y. Sato
    KEK, Ibaraki
  • H. Hotchi, Y. Shobuda
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
 
 

Nonlinear space charge interaction in high intensity proton rings causes beam loss, which limits the performance. Simulations based on particle in cell method has been performed for JPARC-Rapid Cycle Synchrotron and Main Ring. Beam loss estimation during acceleration and resonances analysis are discussed with various simulations using dynamic and frozen models.

 
THPE079 Proposal of a Relationship between Dynamic Aperture and Intensity Evolution in a Storage Ring dynamic-aperture, injection, simulation, hadron 4704
 
  • M. Giovannozzi
    CERN, Geneva
 
 

A scaling law for the time-dependence of the dynamic aperture, i.e., the region of phase space where stable motion occurs, was proposed in previous papers, about ten years ago. The use of fundamental theorems of the theory of dynamical systems allowed showing that the dynamic aperture has a logarithmic dependence on time. In this paper this result, proven by mean of numerical simulations, is used as a basis for deriving a scaling law for the intensity evolution in a storage ring. The proposed scaling law is also tested against experimental data showing a remarkable agreement.

 
THPE093 CRAB Cavity in CERN SPS cavity, emittance, closed-orbit, collider 4740
 
  • H.J. Kim, T. Sen
    Fermilab, Batavia
 
 

Beam collisions with a crossing angle at the interaction point are often necessary in colliders to reduce the effects of parasitic collisions which induce emittance growth and decrease beam lifetime. The crossing angle reduces the geometrical overlap of the beams and hence the luminosity. Crab cavity offer a promising way to compensate the crossing angle and to realize effective head-on collisions. Moreover, the crab crossing mitigates the synchro-betatron resonances due to the crossing angle. A crab cavity experiment in SPS is proposed as a proof of principle before deciding on a full crab-cavity implementation in the LHC. In this paper, we investigate the effects of a single crab cavity on beam dynamics in the SPS and life time.

 
THPE099 RHIC Proton Beam Lifetime Increase with 10- and 12-pole Correctors proton, luminosity, multipole, sextupole 4752
 
  • W. Fischer, J. Beebe-Wang, Y. Luo, S. Nemesure
    BNL, Upton, Long Island, New York
  • L.K. Rajulapati
    SBU, Stony Brook, New York
 
 

The RHIC beam lifetime in polarized proton operation is dominated by the beam-beam effect, parameter modulations, and nonlinear magnet errors in the interaction region magnets. Sextupole and skew sextupole errors have been corrected deterministically for a number of years based on tune shift measurements with orbit bumps in the triplets. During the most recent polarized proton run 10- and 12-pole correctors were set through an iterative procedure, and used for the first time operationally in one of the beams. We report on the procedure to set these high-order multipole correctors and estimate their effect on the integrated luminosity.