A   B   C   D   E   F   G   H   I   K   L   M   O   P   Q   R   S   T   U   V   W  

injection

Paper Title Other Keywords Page
MOXKI01 LHC: Construction and Commissioning Status dipole, quadrupole, cryogenics, insertion 1
 
  • L. R. Evans
  The LHC is now in its final phase of hardware commissioning. The whole ring is complete apart from a few elements in the matching regions yet to be installed. The first of the eight sectors has been cooled down and power tests to full energy are underway. Beam commissioning will start as soon as the last sector becomes available, hopefully before the end of 2007. The commissioning plan foresees a short "engineering" run with colliding beams at or near the injection energy of 450 GeV. This will be followed by a shutdown to finish installing the detectors and to commission the last sectors to full current. A review of the commissioning status to date will be given.  
slides icon Slides  
 
MOXKI03 Status of the SNS - Machine and Science linac, target, beam-losses, beam-transport 7
 
  • S. Henderson
  Funding: ORNL/SNS is managed by UT-Battelle, LLC, for the U. S. Department of Energy under contract DE-AC05-00OR22725.

The Spallation Neutron Source (SNS) will be the world's leading pulsed neutron source, with design beam power capability of 1.4 MW. The SNS Construction Project was completed in June 2006. The accelerator complex was successfully commissioned during the construction phase of the project in seven discrete commissioning runs. The facility is now in the first of a three year performance ramp-up phase, in which the beam power, reliability and operating time will be increased to the baseline design values of 1.4 MW, 90% and 5000 hours respectively. Meanwhile, neutron scattering instruments are being constructed and commissioned in preparation for full user operations in 2009. The progress toward bringing the SNS to its full capabilities will be presented.

 
slides icon Slides  
 
MOYKI02 Commissioning of New Synchrotron Radiation Facilities synchrotron, storage-ring, radiation, synchrotron-radiation 17
 
  • Z. Zhao
  Several new synchrotron radiation facilities have been commissioned over the past two years, and almost every commissioning is an impressive success with a high performance level and a swift process. In this paper, an overview of the new synchrotron radiation facilities which are coming into operation, such as Diamond, SOLEIL, Australian Synchrotron and Indus-II, is presented.  
slides icon Slides  
 
MOZAKI02 New Developments in Super B Factories luminosity, damping, collider, emittance 32
 
  • P. Raimondi
  The design of a super B factory with luminosity in the range of 1036 cm-2 sec-1, based on innovative ideas like the crabbed waist, is being studied by an international collaboration, in close contact with the ILC studies.  
slides icon Slides  
 
MOZBKI02 The BEPC II: Status and Early Commissioning luminosity, linac, electron, quadrupole 53
 
  • J. Q. Wang
  • L. Ma, C. Zhang
    IHEP Beijing, Beijing
  BEPCII is the upgrade project of Beijing Electron Positron Collider (BEPC). The installation of its storage ring components except the superconducting (SC) insertion magnets was completed in early November, 2006. While the improvement of the cryogenic system for SC magnets is in progress, the commissioning of the synchrotron radiation (SR) mode for the so called back-up scheme with conventional magnets adopted in the interaction region (IR), started on Nov. 13, 2006. The first electron beam was stored on Nov. 18 and later beam was provided to SR users for about 1 month starting from Dec. 25, 2006. The commissioning of the collision mode including the electron and positrion rings started in Feb. 2007. The first beam collision was realized on Mar. 25. Then optimization of the beam parameters was done. On May 14, a 100mA to 100mA beam collision was achieved with 20 bunches for each beam. The luminosity estimated from the measured beam-beam parameters has reached that of BEPC. From May 25 the machine turns to the second run of the SR mode. This paper provides an overview of the construction and introduce the commissioning results of the backup scheme of BEPCII.  
slides icon Slides  
 
MOOBKI02 DAΦ NE Phi-Factory Upgrade for Siddharta Run luminosity, sextupole, dynamic-aperture, resonance 66
 
  • M. E. Biagini
  • D. Alesini, D. Babusci, R. Boni, M. Boscolo, F. Bossi, B. Buonomo, A. Clozza, G. O. Delle Monache, T. Demma, G. Di Pirro, A. Drago, A. Gallo, S. Guiducci, C. Ligi, F. Marcellini, G. Mazzitelli, C. Milardi, F. Murtas, L. Pellegrino, M. A. Preger, L. Quintieri, P. Raimondi, R. Ricci, U. Rotundo, C. Sanelli, G. Sensolini, M. Serio, F. Sgamma, B. Spataro, A. Stecchi, A. Stella, S. Tomassini, C. Vaccarezza, M. Zobov
    INFN/LNF, Frascati (Roma)
  • S. Bettoni
    CERN, Geneva
  • I. Koop, E. Levichev, P. A. Piminov, D. N. Shatilov, V. V. Smaluk
    BINP SB RAS, Novosibirsk
  • K. Ohmi
    KEK, Ibaraki
  An upgrade of the DAΦNE Phi-Factory at LNF is foreseen in view of the installation of the Siddharta detector in 2007. A new Interaction Region suitable to test the large crossing angle and crabbed waist collision schemes* will be installed. Other machine improvements, such as wigglers modifications, new injection kickers and chambers coating will be realized with the goal of reaching luminosity of the order of 1033/cm2/s. The principle of operation of the new scheme, together with hardware designs and simulation studies, will be presented.

*DAPHNE Upgrade Team, "DAPHNE Upgrade for Siddharta run", DAPHNE Tech. Note G-68, LNF-INFN, Dec. 2006

 
slides icon Slides  
 
MOZAAB02 MAX-IV Design: Pushing the Envelope dipole, emittance, linac, lattice 74
 
  • M. Eriksson
  • M. Berglund, M. Brandin, D. Kumbaro, P. Lilja, L.-J. Lindgren, L. Malmgren, M. Sjostrom, S. Thorin, E. J. Wallen, S. Werin
    MAX-lab, Lund
  • H. Tarawneh
    SESAME, Amman
  The proposed MAX IV facility is meant as a successor to the existing MAX-lab. The acceleraor part will consist of three storage rings, two new ones operated at 3 and 1.5 GeV respectively and the existing MAX III ring. The two new rings have identical lattices and are placed on top of each other. Both these rings have a very small emittances, 0.86 and 0.4 nm rad respectively, and offer sychrotron radiation of very high mean brilliance. As an injector, a 3 GeV linear accelerator is planned. The design philosophy and the special technical solutions called for are presented in this paper.  
slides icon Slides  
 
MOPAN005 Injector Improvements at the Brazilian Synchrotron Light Source synchrotron, linac, storage-ring, booster 152
 
  • P. F. Tavares
  • F. Arroyo, R. H.A. Farias, L. C. Jahnel, C. Pardine, C. Rodrigues
    LNLS, Campinas
  We present the results of hardware, software and operational improvements implemented at the injector complex of the 1.37 GeV electron storage ring of the Brazilian Synchrotron Light Source (LNLS) with the aim of improving injector stability and reliability, thus reducing the injection time. The improvements include changes to the 120 MeV injector LINAC RF system and high power modulators, injection automation and the implementation of a new procedure for reusing the current at the end of each user's shifts before injection by ramping the energy back down to 500 MeV (the injection energy) without dumping the beam. All of these changes allowed us to significantly reduce the overall time from the end of a shift to the delivery of beam in the following shift with a positive impact on the reduction of injection thermal transients for the storage ring and beamlines. Further improvements are expected in the near future as a result of planned changes to the injection timing system and of the installation of a recently assembled upgrade of the 500 MeV booster synchrotron RF system  
 
MOPAN012 Development of the Injection- and Extraction Systems for the Upgrade of SIS18 septum, cathode, vacuum, electron 167
 
  • U. B. Blell
  • A. V. Batrakov, S. A. Onischenko, G. E. Ozur
    Institute of High Current Electronics, Tomsk
  • J. Florenkowski, U. Kopf, C. Muehle, M. Petryk, I. J. Petzenhauser, P. J. Spiller
    GSI, Darmstadt
  SIS18 will serve as booster synchrotron for the proposed International Accelerator Facility FAIR at GSI. The aim is to provide high intensity proton and heavy ion beams of e.g. U28+-ions with a repetition rate of 2.7 - 4 cycles per second for injection into SIS100. The operation with low charge state heavy ions requires modifications of the injection and extraction systems. The goal is to minimize beam losses and thereby ion induced gas desorption during the injection and extraction processes. In order to increase the acceptance and for an injection at the reference energy it is necessary to build and install a new electrostatic inflector septum and a new inflector magnet. The electrostatic injection septum is designed for an operation at high field strength and enables a bake-out temperature of 300°C. This may be achieved by means of new cathode surface treatment procedures, e.g. with pulsed high intensity electron beams. Another technique is also under investigation, the coating of alumina by a plasma spray technique.  
 
MOPAN017 Noise and drift characterization of direct laser to RF conversion scheme for the laser based synchronization system for FLASH at DESY laser, controls, free-electron-laser, electron 182
 
  • F. Ludwig
  • B. Lorbeer, H. Schlarb, A. Winter
    DESY, Hamburg
  Funding: This contribution is funded by the EUROFEL project.

The next generation of FEL's (Free Electron Lasers) require a long and short term stable synchronisation of RF reference signals with an accuracy of 10 fs. For that an optical synchronisation system is developed for FLASH at DESY, that is based on optical pulse train which carry the timing information encoded in its precise repetition rate. The optical pulse train has to be converted into an RF signal to provide a local reference for calibration and operation of RF based devices. The drift and jitter performance of the optical to RF converter influences directly the phase stability of the accelerator. Three different methods for optical to RF converters, namely the direct photodiode detection, injection locking and a sagnac loop interferometer are currently under investigation. In this paper we concentrate on the jitter and drift performance of the direct photodiode conversion and show its limitations from measurement results.

 
 
MOPAN022 Investigation of Machine Operation and Related Radiation Dose at the ANKA Storage Ring undulator, radiation, wiggler, storage-ring 197
 
  • I. Birkel
  • E. Huttel, A.-S. Muller, P. Wesolowski
    FZK, Karlsruhe
  A new online network for radiation dose measurements offers the opportunity to register the dose rate at the ANKA storage ring every minute. The network consists of six mobile and two stationary monitors with a gamma and a neutron detector and a central computer. The analysis of the dose rate shows strong correlations between beam energy, current, machine parameters and dose rate.  
 
MOPAN028 Current Status of Virtual Accelerator at J-PARC 3 GeV Rapid Cycling Synchrotron controls, acceleration, beam-losses, simulation 215
 
  • H. Harada
  • K. Furukawa
    KEK, Ibaraki
  • H. Hotchi, Y. Irie, F. Noda, H. Sako, H. Suzuki
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
  • S. Machida
    STFC/RAL/ASTeC, Chilton, Didcot, Oxon
  • K. Shigaki
    Hiroshima University, Higashi-Hiroshima
  We have developed the logical accelerator called "Virtual Accelerator" based on EPICS for 3 GeV Rapid Cycling Synchrotron (RCS) in J-PARC. The Virtual Accelerator has a mathematical model of the beam dynamics in order to simulate the behavior of the beam and enables the revolutionary commissioning and operation of an accelerator. Additionally, we have constructed the commissioning tool based on the Virtual Accelerator. We will present a current status of the Virtual Accelerator system and some commissioning tool.  
 
MOPAN030 Analysis of Transverse Beam Oscillation at Photon Factory feedback, betatron, damping, factory 221
 
  • W. X. Cheng
  • T. Obina
    KEK, Ibaraki
  FPGA based bunch by bunch feedback system to cure the transverse instabilities has been in operation stably since Oct. 2005. Specification and performance of the system will be introduced, transient measurement has been done to analyze the instability modes, which helps to understand the instability sources. Bunch by bunch beam oscillation, together with the digital turn-by-turn beam position measurement, injection oscillation damping is recorded and analyzed, transverse beam oscillation with and without the bunch by bunch feedback system will be shown in this paper. Precise tune measurement during this period will be presented. Turn by turn phase space monitor is also available with the data, from which the nonlinear beam dynamics can be revealed.  
 
MOPAN031 Design Study of a Very Large Aperture Eddy Current Septum for J-PARC septum, linac, beam-transport, extraction 224
 
  • K. Fan
  • H. Kobayashi, H. Matsumoto, Y. Sakamoto
    KEK, Ibaraki
  An eddy current septum is selected as a backup of injection septum. Due to the high beam intensity and low beam energy, the injection beam size is very large. To accommodate the large size beam, large aperture septum is required. Large end field and large eddy current loss result in degradation of gap field. The paper discusses the eddy current loss effects on field distribution and introduces some correction methods.  
 
MOPAN032 Eddy Current Effects in an Opposite-field Septum septum, power-supply, optics, simulation 227
 
  • K. Fan
  • Y. Arakaki, I. Sakai
    KEK, Ibaraki
  A large aperture, thin septum, high field opposite-field septum magnet has been developed for the injection of 50GeV main ring of J-PARC. Due to the eddy current generated in septum conductor, magnet yoke and magnet end plate, the field distribution was degraded. In the paper, eddy current effects on both transverse field and longitudinal field distribution are calculated. Correction methods and experiment results are introduced.  
 
MOPAN034 Development of a Pulsed Sextupole Magnet System for Beam Injection at the Photon Factory Storage Ring emittance, sextupole, betatron, synchrotron 230
 
  • Y. Kobayashi
  • K. Harada, T. Honda, T. Miyajima, S. Nagahashi
    KEK, Ibaraki
  • N. Nakamura, H. Takaki
    ISSP/SRL, Chiba
  We proposed a single pulsed sextupole system for beam injection in electron storage rings. Now we are going to design a pulsed sextupole magnet and a ceramic chamber and install them at the Photon Factory storage ring next summer. The required specifications of the magnet and the vacuum chamber are estimated using a multi-particle tracking simulation. In this conference, we describe the design of the hardware for the system and the field measurement of the pulsed magnet.  
 
MOPAN039 Development of Hybrid Type Carbon Stripper Foils with High Durability at >1800K for RCS of J-PARC proton, ion, linac, laser 242
 
  • I. Sugai
  • T. Hattori, K. K. Kawasaki
    Research Laboratory for Nuclear Reactors, Tokyo Institute of Technology, Tokyo
  • Y. Irie
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
  • H. Kawakami, M. Oyaizu, A. Takagi, Y. Takeda
    KEK, Ibaraki
  The Japan Proton Accelerator Research Complex (J-PARC) requires thick carbon stripper foils (250-500 ug/cm2) to strip electrons from the H- beam supplied by the linac before injection into the RCS of J-PARC. For this high-intensity H- beam and circulating bunch beam, which gives much damage to conventional carbon stripper foils. Thus carbon stripper foils with high durability at 1800K produced by energy deposition in the foil are indispensable for this accelerator. Recently, we have successfully developed hybrid type thick boron mixed carbon stripper foils (HBC-foil). Namely, the lifetime measurement of the foils was tested by using a 3.2 MeV, Ne+ DC beams of 2.5 uA, in which a significant amount of energy was deposited in the foils. The maximum lifetime was found to be extremely long, 30-and 250-times longer than those of Diamond and commercially available best carbon foils, respectively. The foils were also found to be free from any shrinkage, and to show an extremely low thickness reduction rate even at a high temperature of 1800K during long beam irradiation. In this conference the foil preparation procedures and lifetime measurements with a 3.2 MeV, Ne+ is presented.  
 
MOPAN048 Design of Injection Pulsed Magnets for SESAME Ring kicker, septum, storage-ring, booster 266
 
  • S. Varnasseri
  • M. M. Shehab, G. Vignola
    SESAME, Amman
  In this paper the SESAME storage ring injection pulsed magnet system is described. The injection process in the SESAME storage ring requires septum and kicker magnets. In this paper we discuss the geometrical and magnetic field requirements for septum and kicker magnets and present the results obtained from magnetic field analysis and also the optimization of titanium coating for the injection kicker chambers. The final specification for thin septum and injection kickers are also presented.  
 
MOPAN054 Beam Instabilities Measurement and Cures at HLS feedback, electron, synchrotron, storage-ring 272
 
  • Y. L. Yang
  • Y. B. Chen, L. J. Huang, W. Li, L. Liu, B. Sun, J. H. Wang, K. Zheng, Z. R. Zhou
    USTC/NSRL, Hefei, Anhui
  In Hefei Light Source (HLS), coupled-bunch instabilities are major limiting factors in achieving higher beam intensity while maintaining good beam quality. To Measure and suppress beam instabilities, turn-by-turn (TBT) measurement and bunch-by-bunch(BxB) measurement & feedback system are under commission [1][2]. The design of the two systems and primary experiment results is presented. Measurement and detail analysing results in injection status will also be shown.  
 
MOPAN055 Bunch-by-Bunch Measurement and Feedback System of HLS feedback, controls, damping, emittance 275
 
  • K. Zheng
  • Y. B. Chen, L. J. Huang, W. Li, L. Liu, B. Sun, J. H. Wang, L. Wang, Y. L. Yang, Z. R. Zhou
    USTC/NSRL, Hefei, Anhui
  Funding: Supported by National Natural Science Project (10175063); National Natural Science Key Project (10535040)

In this paper, HLS (Hefei light Source) bunch-by-bunch measurement and feedback system will be introduced. This system is integrated with longitudinal oscillation measurement system, fast vector control, fiber notch filter and bunch current detection system. The detail of the two fronts will be shown. Some experimental results by this system are also present in this paper, as phase-space tracing, mode dumping rate, and feedback experiments.

 
 
MOPAN081 The LHC Collimator Controls Architecture - Design and Beam Tests controls, collimation, beam-losses, survey 344
 
  • S. Redaelli
  • R. W. Assmann, P. Gander, M. Jonker, M. Lamont, R. Losito, A. Masi, M. Sobczak
    CERN, Geneva
  The LHC collimation system will require simultaneous management by the LHC control system of more than 500 jaw positioning mechanisms in order to ensure the required beam cleaning and machine protection performance in all machine phases, from injection at 450~GeV to collision at 7~TeV. Each jaw position is a critical parameter for the machine safety which could cause a beam dump. In this paper, the architecture of the LHC collimator controls is presented. The basic design to face the accurate and real-time control of the LHC collimators and the interfaces to the other components of LHC Software Application and control infrastructures are described. The full controls architecture has been tested off-line in dedicated test benches, and in the real accelerator environment in the CERN SPS during beam tests with a full scale collimator prototype. The results and the lessons learned are presented.  
 
MOPAN090 Logging of Operation Data at TLS booster, feedback, kicker, linac 371
 
  • C.-K. Chang
  • H. C. Chen, M. J. Horng, J. A. Li, T. F. Lin, Y. K. Lin, Y.-C. Liu
    NSRRC, Hsinchu
  The Taiwan Light Source had been Top-Up operation in October 2005 and the beam current had increased to 300mA in early 2006. For normal operation, there are some important parameters of Top-up operation, such as beam stability, filling pattern and injection efficiency etc. These data have to be recorded and to be reference for the accelerator operating. Therefore, a LabVIEW-based data logging system had been developed. The system handles communication with other instruments via Ethernet and IEEE-488 interconnections. In this report, the design concept and the current status are described. The planned improvements are carried out in the future.  
 
MOPAN094 Operation Experiences of the Bunch-by-Bunch Feedback System for TLS feedback, kicker, controls, damping 383
 
  • K. T. Hsu
  • J. Chen, P. C. Chiu, S. Y. Hsu, K. H. Hu, C. H. Kuo, D. Lee
    NSRRC, Hsinchu
  Severe multi-bunch instabilities are bothered the operation of Taiwan Light Source (TLS) during the operation during 2004 just after SRF system upgrade. FPGA-based bunch-by-bunch feedback system was commissioning during late 2005 and early 2006. Multi-bunch instability in both transverse plans and longitudinal are well control. Delivery up to 400 mA stored beam was demonstrated. Transverse feedback system make low chromaticity operation is possible; this is very helpful to improve injection efficiency which are essential for routine top-up operation. Operation experiences of the bunch-by-bunch feedback system will be summary in this report.  
 
MOPAN107 Quadrupole Magnets for the 20 MeV FFAG, 'EMMA' quadrupole, vacuum, lattice, extraction 413
 
  • N. Marks
  • B. J.A. Shepherd
    STFC/DL/ASTeC, Daresbury, Warrington, Cheshire
  EMMA is a 20 MeV non-scaling Fixed Field Alternating Gradient accelerator (nsFFAG) proof-of-principle prototype, to be built at the Daresbury Laboratory as an accelerator physics experiment to explore the behaviour of such machines. Non-scaling FFAGs have potential applications in charged particle cancer therapy and also for particle physics; however, to date, no such accelerator has been constructed. The magnet designs present major challenges - the lattice is made up of 84 quadrupoles, with different horizontal offsets from the magnet centres in the focusing and defocusing quads. These offsets alone provide the necessary bending fields in the ring. The magnets are also very thin (55mm and 65mm yoke lengths) and end field effects therefore dominate. Careful design, followed by prototype construction and measurement, is essential. The magnets have been designed in 3D from the outset, using the CST EM Studio software. The paper will present the results of the design, showing how the magnets have been optimised to improve the integrated good gradient region, and will report on the progress of the prototyping work.  
 
MOPAN114 A Linear MOSFET Regulator for Improving Performance of the Booster Ramping Power Supplies at the APS power-supply, controls, booster, simulation 434
 
  • G. Feng
  • B. Deriy, J. Wang
    ANL, Argonne, Illinois
  Funding: Work supported by U. S. Department of Energy, Office of Science, Office of Basic Energy Sciences under Contract No. DE-AC02-06CH11357.

Due to the circuit topology of ramping power supplies used in the APS Booster ring, they are unable to follow the linear current ramp to the desired accuracy of 0.1%. In addition, those supplies are also sensitive to AC line perturbation. To improve the performance, a linear regulator using paralleled MOSFET devices in series with the power supply is proposed. The control algorithm uses a real-time current feedback loop to force the MOSFETs to work in the linear operation mode. By using this linear MOSFET regulator, the MOSFETs' drain to source voltage, and hence the voltage imposed on magnets can be regulated very quickly. As a result, the regulation of the magnet current can be improved significantly. So far the simulation results show that with the linear regulator the current regulation can be improved to better than 0.1%. Because of the high bandwidth of the linear regulator, it can reduce the harmonic content in the output current as well as the noises due to the AC line disturbance. A sextupole power supply has been set up to verify the proposed topology. This paper discusses the circuit topology, the regulation algorithm, and the experiment results.

 
 
MOPAS008 A Wide Aperture Quadrupole for the Fermilab Main Injector Synchrotron quadrupole, extraction, synchrotron, proton 455
 
  • D. J. Harding
  • C. L. Bartelson, B. C. Brown, J. A. Carson, W. Chou, J. DiMarco, H. D. Glass, D. E. Johnson, V. S. Kashikhin, I. Kourbanis, W. F. Robotham, M. Tartaglia
    Fermilab, Batavia, Illinois
  Funding: Work supported by the U. S. Department of Energy under Contract No. DE-AC02-76CH03000.

During the design of the Fermilab Main Injector synchrotron it was recognized that the aperture was limited at the beam transfer and extraction points by the combination of the Lambertson magnets and the reused Main Ring quadrupoles located between the Lambertsons. Increased intensity demands on the Main Injector from antiproton production for the collider program, slow spill to the meson fixed target program, and high intensity beam to the high energy neutrino program have led us to replace the aperture-limiting quadrupoles with newly built magnets that have the same physical length but a larger aperture. The magnets run on the main quadrupole bus, and must therefore have the same excitation profile as the magnets they replaced. We present here the design of the magnets, their magnetic performance, and the accelerator performance.

 
 
MOPAS011 Uniform Longitudinal Beam Profiles in the Fermilab Recycler Using Adaptive RF Correction antiproton, extraction, controls, luminosity 458
 
  • M. Hu
  • D. R. Broemmelsiek, B. Chase, J. L. Crisp, N. E. Eddy, P. W. Joireman, K. Y. Ng
    Fermilab, Batavia, Illinois
  Non-uniformity in longitudinal beam profiles due to potential well distortion have been observed in the Fermilab Recycler Ring. The main source of distortion, the analysis, and the experimental verification of a solution are presented. An adaptive algorithm has been developed to remove the distortion. This algorithm has been implemented in a custom FPGA-based module, which has been integrated into the current Low Level RF system.  
 
MOPAS035 Rapid-Cycling Dipole using Block-Coil Geometry and Bronze-Process Nb3Sn Superconductor dipole, synchrotron, coupling, multipole 512
 
  • P. M. McIntyre
  • A. D. McInturff, A. Sattarov
    Texas A&M University, College Station, Texas
  Funding: Doe gratn #DE-FG02-06ER41405

The block coil geometry utilized in recent high-field dipole development has significant benefit for applications requiring rapid cycling, since it intrinsically suppresses coupling currents between strands. A conceptual design for a 6 Tesla dipole has been studied for such applications, in which the intra-strand losses are minimized by using bronze-process Nb3Sn superconducting wire developed for ITER. That conductor provides isolated fine filaments and optimum matrix resistance between filaments. The block-coil geometry further accommodates placement of He cooling channels inside the coil, so that heat from radiation and from AC losses can be removed with minimum temperature rise in the coil. The design could be operated with supercritical helium cooling, and should make it possible to operate with a continuous ramp rate of 5-10 T/s.

 
 
MOPAS036 A Physics Based Approach for Ramping Magnet Control in a Compact Booster booster, controls, power-supply, storage-ring 515
 
  • S. M. Hartman
  • S. F. Mikhailov, V. Popov, Y. K. Wu
    FEL/Duke University, Durham, North Carolina
  Funding: Supported by US DoE grant #DE-FG02-01ER41175.

At Duke University, a booster synchrotron was recently commissioned as part of the HIGS upgrade. For the ramping magnet power supply controls, a scheme was developed to present the high level operator interface in terms of the physics quantities of the accelerator, i.e. the effective focusing strength of the magnets. This scheme allows for the nonlinearities of the magnets – a result of the extremely compact footprint of this booster – to be incorporated into the low level software. This facilitates machine studies and simplifies use of physics modeling. In addition, it simplifies operation, allowing the booster to ramp to any energy from the 0.27 GeV of the injector linac to the 1.2 GeV maximum of the Duke Storage Ring. The high level of flexibility of this system if further advanced by incorporating the level of tunability typically found in a storage ring control system. Tuning changes made during steady-state operation are automatically propagated to the waveforms which make up the booster ramp. This approach provides a good match to the wide operation modes of the Duke Storage Ring and its associated free electron laser, and may useful for other compact booster synchrotrons.

 
 
MOPAS046 LANSCE Radiation Resistant Water Manifold Retrofit for DC Magnets radiation, proton, storage-ring, scattering 536
 
  • M. J. Borden
  • J. F. O'Hara, E. M. Perez, B. J. Roller, V. P. Vigil, L. S. Walker
    LANL, Los Alamos, New Mexico
  Funding: Work supported by the United States Department of Energy, National Nuclear Security Agency, under contract DE-AC52-06NA25396

Large maintenance dose burdens have necessitated the development of radiation resistant water manifolds for use on DC magnets in the Proton Storage Ring, at the Los Alamos Neutron Science Center (LANSCE) accelerator. This paper will describe dose measurements and the mechanical design of radiation resistant water manifolds used in PSR.

 
 
MOPAS067 Control and Measurements of Longitudinal Coupled-bunch Instabilities in the ATF Damping Ring feedback, damping, single-bunch, extraction 584
 
  • D. Teytelman
  • W. X. Cheng, J. W. Flanagan, T. Naito, M. Tobiyama
    KEK, Ibaraki
  • A. Drago
    INFN/LNF, Frascati (Roma)
  • J. D. Fox
    SLAC, Menlo Park, California
  Funding: Work supported by U. S. Department of Energy contract DE-AC02-76SF00515 and by the US-Japan collaboration in High Energy Physics

Damping ring at the Accelerator Test Facility (ATF) is a storage ring with 714 MHz RF frequency and harmonic number of 330. The ring is used in both single and multibunch regimes. In both cases significant longitudinal dipole motion has been observed in the ring. A prototype longitudinal feedback channel using a Gproto baseband processing channel and a set of horizontal striplines has been constructed for the machine. The prototype allowed both suppression of the longitudinal motion and studies of the motion sources. In this paper we present the results of these studies including measurements of steady-state oscillation amplitudes, eigenmodal patterns, and growth and damping rates. Using measured growth rates we estimate the driving impedances. We also present the effect of the longitudinal stabilization on the energy spread of the extracted beam as documented by a screen monitor.

 
 
MOPAS081 Spallation Neutron Source (SNS) Diamond Stripper Foil Development proton, beam-losses, plasma, electron 620
 
  • R. W. Shaw
  • M. J. Borden, T. Spickermann
    LANL, Los Alamos, New Mexico
  • C. S. Feigerle
    University of Tennessee, Knoxville, Tennessee
  • Y. Irie
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
  • M. A. Plum, L. L. Wilson
    ORNL, Oak Ridge, Tennessee
  • I. Sugai, A. Takagi
    KEK, Ibaraki
  Funding: SNS is managed by UT-Battelle, LLC, for the U. S. DOE under contract DE-AC05-00OR22725. DOE contract W-7405-ENG-36 (LANL) and Japan SPS contract 18540303 (KEK) supported work at those institutions.

Diamond stripping foils are under development for the SNS. Free-standing, flat 350 microgram/cm2 foils as large as 17 x 25 mm have been prepared. These nano-textured polycrystalline foils are grown by microwave plasma-assisted chemical vapor deposition in a corrugated format to maintain their flatness. They are mechanically supported on a single edge by a residual portion of their silicon growth substrate; typical fine foil supporting wires are not required for diamond foils. Six foils were mounted on the SNS foil changer in early 2006 and have performed well in commissioning experiments at reduced operating power. A diamond foil was used during a recent experiment where 12 microCoulombs of protons, approximately 40% of the design value, were stored in the ring. A few diamond foils have been tested at LANSCE/PSR, where one foil was in service for a period of five months (820 Coulombs of integrated injected charge) before it was replaced. Diamond foils have also been tested in Japan at KEK (650 keV H-) where their lifetimes slightly surpassed those of evaporated carbon foils, but fell short of those for Sugai's new hybrid boron carbon (HBC) foils.

 
 
MOPAS102 Design of Beam Transfer Lines for the NSLS II booster, storage-ring, extraction, quadrupole 664
 
  • N. Tsoupas
  • R. Heese, R. Meir, I. Pinayev, J. Rose, T. V. Shaftan, C. Stelmach
    BNL, Upton, Long Island, New York
  Funding: Work supported by the US Department of Energy

The proposed NSLS II light source* to be built at Brookhaven National Laboratory utilizes a LINAC and a Booster with a Storage-ring which share the same tunnel, but at different horizontal planes. The Booster which accepts beam from the LINAC, accelerates the electron beam to an energy of 3.0 GeV and the beam is extracted to the BoostertoStorageRing(BtS) transport line. The BtS line transports the beam and injects it into the Storage ring . In order to facilitate the design of the BtS transfer line, the line has been partitioned in three sections which can be considered as independent. The function of each the three sections will be discussed in details and the procedure for the design of the BtS line and other details about the optics and the magnetic elements of the line will be presented in the paper. The LINAC to Booster beam transfer line will also be discussed.

*NSLS II CDR BNL

 
 
TUOCKI02 Summary of the RHIC Performance during the FY07 Heavy Ion Run luminosity, ion, proton, beam-losses 722
 
  • K. A. Drees
  • L. Ahrens, J. G. Alessi, M. Bai, D. S. Barton, J. Beebe-Wang, M. Blaskiewicz, J. M. Brennan, K. A. Brown, D. Bruno, J. J. Butler, R. Calaga, P. Cameron, R. Connolly, T. D'Ottavio, W. Fischer, W. Fu, G. Ganetis, J. Glenn, M. Harvey, T. Hayes, H.-C. Hseuh, H. Huang, J. Kewisch, R. C. Lee, V. Litvinenko, Y. Luo, W. W. MacKay, G. J. Marr, A. Marusic, R. J. Michnoff, C. Montag, J. Morris, B. Oerter, F. C. Pilat, V. Ptitsyn, T. Roser, J. Sandberg, T. Satogata, C. Schultheiss, F. Severino, K. Smith, S. Tepikian, D. Trbojevic, N. Tsoupas, J. E. Tuozzolo, A. Zaltsman, S. Y. Zhang
    BNL, Upton, Long Island, New York
  Funding: Work performed under Contract Number DE-AC02-98CH10886 under the auspices of the US Department of Energy.

After the last successful RHIC Au-Au run in 2004 (Run-4), RHIC experiments now require significantly enhanced luminosity to study very rare events in heavy ion collisions. RHIC has demonstrated its capability to operate routinely above its design average luminosity per store of 2x1026 cm-2 s-1. In Run-4 we already achieved 2.5 times the design luminosity in RHIC. This luminosity was achieved with only 40% of bunches filled, and with β* = 1 m. However, the goal is to reach 4 times the design luminosity, 8x1026 cm-2 s-1, by reducing the beta* value and increasing the number of bunches to the accelerator maximum of 111. In addition, the average time in store should be increased by a factor of 1.1 to about 60% of calendar time. We present an overview of the changes that increased the instantaneous luminosity and luminosity lifetime, raised the reliability, and improved the operational efficiency of RHIC Au-Au operations during Run-7.

 
slides icon Slides  
 
TUZBKI01 Present and Future High-Energy Accelerators for Neutrino Experiments proton, booster, target, extraction 731
 
  • I. Kourbanis
  Application of high-energy proton accelerators for high-intensity neutrino beam production is a challenging task from standpoints of accelerator physics and operation. An overview of the machines presently used for neutrino experiments will be given as well as of the future projects, in particular of the Fermilab accelerator complex conversion after the Tevatron Run II completion.  
slides icon Slides  
 
TUODKI01 Status of J-PARC Main Ring Synchrotron extraction, septum, synchrotron, acceleration 736
 
  • T. Koseki
  The J-PARC (Japan Proton Accelerator Research Complex) accelerator facility consists of a 400-MeV linac, a 3.0-GeV rapid cycling synchrotron (RCS), a 50-GeV slow cycling main ring synchrotron (MR). Beam commissioning of the linac has been started from this November and construction of the synchrotrons is now underway. The MR accelerates the 3-GeV beam from the RCS up to 30 - 50 GeV and provides the beam to the hadron beam facility via slow extraction and to the neutrino beam facility via fast extraction. In this paper, we present recent status of the accelerator construction and test operation results for some components of the MR. Beam commissioning scenario and related beam dynamics studies are also discussed.  
slides icon Slides  
 
TUODKI02 Optics Considerations for the PS2 lattice, extraction, proton, quadrupole 739
 
  • M. Benedikt
  • W. Bartmann, C. Carli, B. Goddard, S. Hancock, J. M. Jowett, Y. Papaphilippou
    CERN, Geneva
  CERN envisages replacing the existing Proton Synchrotron (PS) with a larger synchrotron (PS2) capable of injecting at higher energy into the SPS. Since it should increase the performance not only of the LHC but also CNGS and other users of beams from CERN's hadron injector complex, the new accelerator must retain much of the flexibility of the present complex. A number of candidate optics, with and without transition crossing, have been evaluated systematically and compared.  
slides icon Slides  
 
TUODKI03 Multi-batch Slip Stacking in the Main Injector at Fermilab kicker, simulation, beam-losses, booster 742
 
  • K. Seiya
  • T. Berenc, B. Chase, J. E. Dey, P. W. Joireman, I. Kourbanis, J. Reid
    Fermilab, Batavia, Illinois
  The Main Injector (MI) is going to use slip stacking scheme for the NuMI neutrino experiment for effectively increasing proton intensity to the NuMI target by about a factor two in a MI cycle. The MI is going to accept 11 pluses at injection energy from the Booster and accelerate them to 120 GeV. By using Slip stacking, two of them are merged into one and sent to Anti-proton production and 9 of them, one single and four doubled density pulses, are going to be sent to the Numi beam line. We have been doing low intensity beam studies with 11 pulses injection and accelerated them with the total intensity of 3·1012 ppp to 120GeV. We discuss beam loss and technical issues on multi-batch slip stacking.  
slides icon Slides  
 
TUODKI05 Overcoming Depolarizing Resonances in the AGS with Two Helical Partial Snakes resonance, polarization, extraction, betatron 748
 
  • H. Huang
  • L. Ahrens, M. Bai, K. A. Brown, C. J. Gardner, J. Glenn, F. Lin, A. U. Luccio, W. W. MacKay, T. Roser, S. Tepikian, N. Tsoupas, K. Yip, K. Zeno
    BNL, Upton, Long Island, New York
  Funding: Work performed under contract No. DE-AC02-98CH1-886 with the auspices of the DoE of United States, and support of RIKEN(Japan).

Dual partial snake scheme has provided polarized proton beams with 1.5*1011 intensity and 65% polarization for RHIC spin program. To overcome the residual polarization loss due to horizontal resonances in the AGS, a new string of quadrupoles have been added. The horizontal tune can now be set in the spin tune gap generated by the two partial snakes, such that horizontal resonances are avoided. This paper presents the accelerator setup and preliminary results.

 
slides icon Slides  
 
TUXAB02 E-cloud experiments and cures at RHIC electron, proton, ion, emittance 759
 
  • W. Fischer
  • M. Blaskiewicz, J. M. Brennan, H.-C. Hseuh, H. Huang, V. Ptitsyn, T. Roser, P. Thieberger, D. Trbojevic, J. Wei, S. Y. Zhang
    BNL, Upton, Long Island, New York
  • U. Iriso
    ALBA, Bellaterra (Cerdanyola del Valles)
  Funding: Work supported by U. S. DOE under contract No DE-AC02-98CH1-886.

Since 2001 RHIC has experienced electron cloud effects, which have limited the beam intensity. These include dynamic pressure rises – including pressure instabilities, a reduction of the stability threshold for bunches crossing the transition energy, and possibly slow emittance growth. We report on the main observations in operation and dedicated experiments, as well as the effect of various countermeasures including baking, NEG coated warm pipes, pre-pumped cold pipes, bunch patterns, scrubbing, and anti-grazing rings.

 
slides icon Slides  
 
TUZAAB03 Emittance Measurement and Modeling for the Fermilab Booster emittance, space-charge, dipole, quadrupole 799
 
  • X. Huang
  • S.-Y. Lee
    IUCF, Bloomington, Indiana
  • K. Y. Ng
    Fermilab, Batavia, Illinois
  Funding: DOE/NSF

We systematically measured the emittance evolution of a fast cycling proton accelerator on a turn-by-turn basis under various beam intensities via an ionization profile monitor (IPM). The vertical emittance growth rate was derived and phenomenologically analyzed. The transverse and longitudinal components in the horizontal beam size were separated by making use of their different evolution behaviors. The quadrupole mode beam size oscillation after transition crossing is also studied and explained. We found a considerable space-charge-induced emittance growth rate component in the vertical plane but not as much for the horizontal plane. We carried out multiparticle simulations to understand the mechanism of space-charge-induced emittance growth. The major sources of emittance growth were found to be the random skew-quadrupole and dipole field errors in the presence of large space-charge tune spread.

PRSTAB 9, 014202 (2006)

 
slides icon Slides  
 
TUZBAB03 The University of Maryland Electron Ring (UMER) Enters a New Regime of High-Tune-Shift Rings space-charge, emittance, electron, controls 820
 
  • R. A. Kishek
  • G. Bai, B. L. Beaudoin, S. Bernal, D. W. Feldman, R. Feldman, R. B. Fiorito, T. F. Godlove, I. Haber, T. Langford, P. G. O'Shea, C. Papadopoulos, B. Quinn, M. Reiser, D. Stratakis, D. F. Sutter, J. C.T. Thangaraj, K. Tian, M. Walter, C. Wu
    UMD, College Park, Maryland
  Funding: This work is funded by US Dept. of Energy and by the US Dept. of Defense Office of Naval Research.

Circular accelerators and storage rings have traditionally been designed with limited intensity in order to avoid resonances and instabilities. The possibility of operating a ring beyond the Laslett tune shift limit has been suggested but little tested, apart from a pioneering experiment by Maschke at the BNL AGS in the early 1980s. We have recently circulated the highest-space-charge beam in a ring to date in the University of Maryland Electron Ring (UMER), achieving a breakthrough both in the number of turns and in the amount of current propagated. At undepressed tunes of up to 7.6, the space charge in UMER is sufficient to depress the tune by nearly a factor of 2, resulting in tune shifts up to 3.6. This makes the UMER beam the most intense beam that has been propagated to date in a circular lattice. This is an exciting and promising result for future circular accelerators, and the UMER beam can now be used as a platform to study intense space charge dynamics in rings.

 
slides icon Slides  
 
TUZAC02 Modern Accelerator Control Systems controls, linac, positron, electron 873
 
  • K. Furukawa
  Discussion of modern approaches to accelerator control systems including software and hardware implications, in view of maintaining reliability under changing requirements.  
slides icon Slides  
 
TUZAC03 LHC Machine Protection extraction, beam-losses, kicker, dumping 878
 
  • R. Schmidt
  • R. W. Assmann, E. Carlier, B. Dehning, R. Denz, B. Goddard, E. B. Holzer, V. Kain, B. Puccio, B. Todd, J. A. Uythoven, J. Wenninger, M. Zerlauth
    CERN, Geneva
  This paper addresses the imposing challenges of the LHC Machine Protection System.  
slides icon Slides  
 
TUOCC02 Progress in Tune, Coupling, and Chromaticity Measurement and Feedback during RHIC Run 7 feedback, coupling, controls, betatron 886
 
  • P. Cameron
  • J. Cupolo, W. C. Dawson, C. Degen, A. Della Penna, L. T. Hoff, Y. Luo, A. Marusic, R. Schroeder, C. Schultheiss, S. Tepikian
    BNL, Upton, Long Island, New York
  • M. Gasior
    CERN, Geneva
  Funding: US DOE

Tune feedback was first implemented in RHIC in 2002 as a specialist activity. The transition to full operational status was impeded by dynamic range problems, as well as by overall loop instabilities driven by large coupling. The dynamic range problem was solved by the CERN development of the Direct Diode Detection Analog Front End. Continuous measurement of all projections of the betatron Eigenmodes made possible the world's first implementation of coupling feedback during beam acceleration, resolving the problem of overall loop instabilites. Simultaneous tune and coupling feedbacks were utilized as specialist activities for ramp development during the 2006 RHIC run. At the beginning of the 2007 RHIC run there remained two obstacles to making these feedbacks fully operational in RHIC - chromaticity measurement and control, and the presence of strong harmonics of the power line frequency in the betatron spectrum. We report here on progress in tune, coupling, and chromaticity measurement and feedback, and discuss the relevance of our results to the LHC commissioning effort. The results of investigations of power line harmonics in RHIC are presented elsewhere in these proceedings.

 
slides icon Slides  
 
TUPMN001 The Australian Synchrotron Project synchrotron, storage-ring, vacuum, undulator 911
 
  • A. Jackson
  Funding for the Australian Synchrotron, a 3 GeV synchrotron light source, was announced by the Victorian State Government in January 2003, and six months later bulldosers moved onto the green-field site in the South-East suberbs of Melbourne. After a remarkably fast construction and installation period the accelerators that form the heart of the faclity were commissioned in 2006. Installation of the first five beamlines will commence in January 2007 and it is expected that the first experiments will be carried out in April. In this presentation we give an update on the status of the facility and present highlights of the commissioning activities.  
 
TUPMN007 Final Commissioning Results from the Injection System for the Australian Synchrotron Project booster, synchrotron, quadrupole, sextupole 926
 
  • S. V. Weber
  • F. Bødker, H. Bach, N. Hauge, J. Kristensen, L. K. Kruse, S. P. Møller, S. M. Madsen
    Danfysik A/S, Jyllinge
  • M. J. Boland, R. T. Dowd, G. LeBlanc, M. J. Spencer, Y. E. Tan
    ASP, Clayton, Victoria
  • N. H. Hertel, J. S. Nielsen
    ISA, Aarhus
  Danfysik has delivered a full-energy turn-key injection system for the Australian Synchrotron. The system consists of a 100 MeV linac, a low-energy transfer beamline, a 130 m circumference 3-GeV booster, and a high energy transfer beamline. The booster lattice was designed to have many cells with combined-function magnets (dipole, quadrupole and sextupole fields) in order to reach a very small emittance. The injection system has been commissioned and found to deliver a beam with an emittance of less than 30 nm, and currents in single- and multi-bunch mode in excess of 0.5 and 5 mA, respectively, fulfilling the contractual performance specifications. The repetition frequency is 1 Hz. Results from the commissioning of the system will be presented.  
 
TUPMN009 Commissioning of the SOLEIL Synchroton Radiation Source feedback, insertion, insertion-device, coupling 932
 
  • A. Nadji
  • J. C. Besson, F. Bouvet, P. Brunelle, A. Buteau, L. Cassinari, M.-E. Couprie, J.-C. Denard, J.-M. Filhol, C. Herbeaux, J.-F. Lamarre, V. Le Roux, P. Lebasque, M.-P. Level, A. Loulergue, P. Marchand, L. S. Nadolski, R. Nagaoka, B. Pottin, M.-A. Tordeux
    SOLEIL, Gif-sur-Yvette
  The French 3rd generation synchrotron light source, SOLEIL, was successfully commissioned in 2006. The Linac and the Booster are operational at their design performances. During the early phase of the storage ring commissioning, the essential design parameters were reached very quickly while the project incorporates some innovative techniques such as the use of a superconducting RF cavity, solid state RF amplifiers, NEG coating for all straight parts of the storage ring and new BPM electronics. Prior to the start of the commissioning, some insertion devices and most of the insertion devices low gap vacuum vessels, including 10 mm inner vertical aperture vessels for the Apple-II type, were installed on the ring. The main results of the commissioning will be reviewed here, including discussion on diagnostics performances, orbit stability and control, optics correction, Top-up and the challenges in achieving operational status. The 10 beamlines of phase 1 are now under commissioning and regular user operation will start by spring 2007.  
 
TUPMN015 First Commissioning Results of the Metrology Light Source electron, storage-ring, kicker, radiation 947
 
  • J. Feikes
  • M. Abo-Bakr, T. Birke, J. Borninkhof, P. Budz, K. B. Buerkmann-Gehrlein, R. Daum, O. Dressler, V. Duerr, F. Falkenstern, H. G. Glass, H. G. Hoberg, J. Kolbe, J. Kuszynski, R. Lange, I. Mueller, R. Muller, J. Rahn, G. Schindhelm, T. Schneegans, Th. Schroeter, D. Schueler, E. Weihreter, G. Wuestefeld
    BESSY GmbH, Berlin
  • G. Brandt, R. Fliegauf, A. Hoehl, R. Klein, R. Muller, R. Thornagel, G. Ulm
    PTB, Berlin
  Funding: Physikalisch-Technische Bundesanstalt, Abbestr. 2 - 12, 10587 Berlin, Germany

The Physikalisch-Technische Bundesanstalt (PTB), the German national metrology institute, has built an electron storage ring in close cooperation with BESSY for energies between 200 MeV and 600 MeV. This storage ring, named Metrology Light Source (MLS), will mainly be used for radiometry and can be operated as a primary source standard. The spectral range of the MLS is optimized for UV, EUV and also for Terahertz radiation. Commissioning is planed for May 2007. First MLS commissioning results will be reported.

 
 
TUPMN045 PF-Ring and PF-AR Operational Status undulator, insertion, insertion-device, photon 1019
 
  • Y. Kobayashi
  • S. Asaoka, W. X. Cheng, K. Haga, K. Harada, T. Honda, T. Ieiri, S. Isagawa, M. Izawa, T. Kageyama, T. Kasuga, M. Kikuchi, K. Kudo, H. Maezawa, A. Mishina, T. Mitsuhashi, T. Miyajima, H. Miyauchi, S. Nagahashi, T. T. Nakamura, H. Nakanishi, T. Nogami, T. Obina, K. Oide, M. Ono, T. Ozaki, C. O. Pak, H. Sakai, Y. Sakamoto, S. Sakanaka, H. Sasaki, Y. Sato, T. Shioya, M. Tadano, T. Takahashi, S. Takasaki, Y. Tanimoto, M. Tejima, K. Tsuchiya, T. Uchiyama, A. Ueda, K. Umemori, S. Yamamoto, Ma. Yoshida, S. I. Yoshimoto
    KEK, Ibaraki
  In KEK, we have two synchrotron light sources which were constructed in the early 1980s. One is the Photon Factory storage ring (PF-ring) and the other is the Photon Factory advanced ring (PF-AR). The PF-ring is usually operated at 2.5 GeV and sometimes ramped up to 3.0 GeV to provide photons with the energy from VUV to hard X-ray region. The PF-AR is mostly operated in a single-bunch mode of 6.5 GeV to provide pulsed hard X-rays. Operational performances of them have been upgraded through several reinforcements. After the reconstruction of the PF-ring straight sections from March to September 2005, two short-gap undulators were newly installed. They allow us to produce higher brilliant hard X-rays even at the energy of 2.5 GeV. At present we are going to prepare a top-up operation for the PF-ring. In the PF-AR, new tandem undulators have been operated in one straight section since September 2006 to generate much stronger pulsed hard X-rays for the sub-ns resolved X-ray diffraction experiments. In this conference, we report operational status of the PF-ring and the PF-AR including other machine developments.  
 
TUPMN061 An Upgrade Proposal of Injection Bump System for HLS kicker, simulation, emittance, storage-ring 1067
 
  • L. Wang
  • G. Feng, W. Li, L. Liu, H. Xu
    USTC/NSRL, Hefei, Anhui
  • S. C. Zhang
    USTC, Hefei, Anhui
  The current injection bump system of Hefei Light Source was designed eight years ago, and operated five years ago. In this paper, the advantages and shortcomings of current bump system were analyzed, and reasonalbe design objective was summed up. According to new design goal, a new physical design of bump system for HLS ring was completed. The acceptance of injected beam and perturbation on stored beam were analyzed. At same time, the ELEGANT software was used to simulate the injection process under new designed bump system. The results showed that, with new designed bump system, the injection rate would be higher than 90%, and the perturbation on orbit of stored beam would be small enough.  
 
TUPMN064 Experimental Approaches for the Beam Dynamics Study in the PC RF Gun at the PAL laser, gun, emittance, simulation 1070
 
  • J. H. Park
  • J. Y. Huang, C. Kim, I. S. Ko, Y. W. Parc, S. J. Park
    PAL, Pohang, Kyungbuk
  • D. Xiang
    TUB, Beijing
  Funding: This work is supported in parts by the Center for High Energy Physics at the KNU and the Grant No. R01-2006-000-11309-0 from the Basic Research Program of the Korea Science and Engineering Foundation.

A high-brightness electron beam is emitted from a photo-cathode (PC) RF gun for use in the FIR (Far Infrared) facility being built at the Pohang Accelerator Laboratory (PAL). The beam dynamics study for the PAL XFEL injector is essencial to generate low emittance electron beam from the PC RF gun. The XFEL injector requires 1 nC beam with short bunch length and low emittance. This conditions are simulated with PARMELA code and then are realized on experimental conditions. The experimental conditions for the XFEL injector are measured with beam diagnostic devices such as ICT and Faraday cup for charge measurement, a spectrometer for beam energy measurement. In this article, we present the experimental approaches of the beam dynamics study for the XFEL injector.

wpjho@postech.ac.kr (Jangho Park)

 
 
TUPMN066 Status of the ALBA Project vacuum, storage-ring, septum, booster 1073
 
  • D. Einfeld
  The construction of ALBA, the 3 GeV third generation Synchrotron Light Source near Barcelona (Spain) is proceeding according to schedule. The works for the building started in June 2006 and access to the building for installation of the 100 MeV Linac is expected at the end of 2007. Most of the machine components are already under construction and some have already been delivered. This report will concentrate on recent design developments, component choices and current status. Also the results on the first prototypes will be discussed. Other papers at this conference deal with accelerator physics issues and low level RF.  
 
TUPMN074 Improvements to the Injection Efficiency at the Taiwan Light Source booster, storage-ring, septum, quadrupole 1091
 
  • Y.-C. Liu
  • H.-P. Chang, J. Chen, P. J. Chou, K. T. Hsu, K. H. Hu, C. H. Kuo, C.-C. Kuo, K.-K. Lin, G.-H. Luo, M.-H. Wang
    NSRRC, Hsinchu
  Taiwan light source started the 200 mA top-up operation in October 2005, and the stored beam current was subsequently ramped up to 300 mA top-up operation. In the early phase of top-up operation, the injection efficiency had large variation at different machine condition. We have developed the procedures to maintain the injection efficiency. These optimization procedures will be activated whenever the injection efficiency degrades during the top-up operation of TLS.  
 
TUPMN085 The Commissioning of the Diamond Storage Ring optics, storage-ring, feedback, single-bunch 1109
 
  • R. Bartolini
  The Diamond Light Source opened for user operation at the end January 2007. The storage ring was successfully commissioned at 3 GeV in three months by the end of December 2006. An intensive Accelerator Physics program allowed the design emittance of 2.7 nm with 150 mA stored beam to be reached as well as the commissioning of the first seven insertion devices. We describe here the results of the measurements performed to characterise accelerator optics, to bring the insertion device in operation and a first analysis of orbit stability and collective instabilities, as well as the status and plans for fast orbit feedback, multi-bunch feedback and top-up operation.  
 
TUPMN086 Operation of the Diamond Light Source Injector booster, linac, storage-ring, single-bunch 1112
 
  • C. Christou
  • V. C. Kempson
    Diamond, Oxfordshire
  The Diamond Light source injector consists of a 100 MeV pre-injector linac and a 3 GeV full energy booster. The injection system has been reliably providing beam to the storage ring since September 2006 in both multibunch and single bunch mode, at 5 Hz repetition rate. All user operation at present is carried out in multibunch mode, with an injection efficiency up to 95%. Single bunch and hybrid modes are being developed now for users later this year. Differences in operation between multibunch and single bunch mode are largely restricted to the linac, although a small correction in booster sextupole ramp is needed for single bunch operation. Single bunch purity has been measured in the storage ring to be greater than 99.9%. The timing system can be controlled to allow a wide range of filling patterns, including complete ring fill in both single and multibunch mode, and hybrid fills with individual single bunches placed in gaps between continuous bunch trains. Top-up operation is envisaged for user operation in the future, and trials are underway to ensure safe and efficient running in this mode.  
 
TUPMN088 Commissioning and Investigation of Beam Dynamics of Phase I Insertion Devices at Diamond optics, quadrupole, wiggler, undulator 1118
 
  • B. Singh
  • R. Bartolini, R. T. Fielder, E. C. Longhi, I. P.S. Martin
    Diamond, Oxfordshire
  Diamond is a 3 GeV low emittance third generation light source recently commissioned in Oxfordshire, UK. During Phase I of the project, seven insertion devices (IDs) have been installed and commissioned: these include 5 in-vacuum permanent magnet undulators, a variable polarization APPLE-II helical device and a superconducting wiggler. We present our experiences commissioning these devices and the results of the investigations of their effects on beam dynamics, including orbit distortion, linear tune shifts, beta-beating and beam lifetime. Alpha-matching with local and global tune compensations, as well as the LOCO algorithm, have been used to compensate the linear optic perturbations. The results are discussed and compared with theoretical predictions. Injection with IDs in operation has also been investigated in view of future top-up operation.  
 
TUPMN096 New Lattice Design for APS Storage Ring with Potential Tri-fold Increase of the Number of Insertion Devices lattice, emittance, dynamic-aperture, dipole 1139
 
  • V. Sajaev
  • M. Borland, A. Xiao
    ANL, Argonne, Illinois
  Funding: Work supported by the U. S. Department of Energy, Office of Science, Basic Energy Sciences, under Contract No. DE-AC02-06CH11357

APS has recently held a round of discussions on upgrade options for the APS storage ring. Several options were discussed that included both storage ring and energy-recovery linac options. Here we present a storage ring lattice that fits into the APS tunnel and has a number of significant improvements over the existing storage ring. The present APS lattice has 40-fold symmetry with each sector having one 5-m-long straight section for insertion device (ID) placement. Each sector also provides one beamline for radiation from the bending magnet. The upgrade lattice preserves locations of the existing insertion devices but provides for increased ID straight section length to accommodate 8-m-long insertion devices. This lattice also decreases emittance by a factor of two down to 1.6 nm rad. And last but not least, it provides two additional 2.1-m-long ID straight sections per sector with one of these straight sections being parallel to the existing bending magnet beamline. We also present dynamic aperture optimization, lifetime calculations, and other nonlinear-dynamics-related simulations.

 
 
TUPMN099 An Energy Recovery Linac Upgrade for the Advanced Photon Source Located in the Storage Ring Infield linac, storage-ring, emittance, dipole 1145
 
  • N. Sereno
  • M. Borland, H. W. Friedsam
    ANL, Argonne, Illinois
  Funding: Work supported by the U. S. Department of Energy, Office of Science, Office of Basic Energy Sciences, under Contract No. DE-AC02-06CH11357.

In the recent past, the Advanced Photon Source (APS) was asked by the U. S. Department of Energy to explore a revolutionary upgrade based on emerging energy recovery linac (ERL) technology. In an ERL, the energy of the 7-GeV, 100-mA beam is recovered after the beam passes through user beamlines by decelerating the beam back through the same superconducting linac cavities that accelerated it. The main constraint on this upgrade is that the existing APS beamlines not be disturbed. This requires that the APS storage ring be used as a single-pass transport line in the overall ERL beamline layout. A natural place to locate the ERL is inside the existing APS storage ring ‘‘infield'' area, which has unoccupied space south of the existing APS injector complex. Other important constraints include minimal disturbance of existing building structures and injector beamlines. The existing injector complex would be preserved so that existing operation can be continued through and even possibly beyond ERL commissioning. In this paper, we describe a layout that satisfies these constraints. We also estimate the amount of emittance increase the beam will experience before ring injection.

 
 
TUPMN107 A Proposed Multipole Wiggler for CAMD wiggler, storage-ring, lattice, radiation 1161
 
  • V. P. Suller
  • M. G. Fedurin
    BNL, Upton, Long Island, New York
  • P. Jines, D. J. Launey, T. A. Miller, Y. Wang
    LSU/CAMD, Baton Rouge, Louisiana
  It is proposed to replace the 7 Tesla wavelength shifter, which has been operating in CAMD since 1998, with a superconducting Multi Pole Wiggler (MPW). This will have 11 main poles with peak fields of 7.5 Tesla and will be accommodated in a cryo-cooled cryostat whose overall length will be 2.5 m. It will be necessary to modify the storage ring lattice parameters in order to inject into the reduced 20 mm vertical aperture of this MPW. The results are presented of tests which have been made of several different lattice configurations which have low vertical beta at the proposed location of the MPW.  
 
TUPMN112 ALS Top-off Simulation Studies for Radiation Safety simulation, photon, radiation, vacuum 1173
 
  • H. Nishimura
  • R. J. Donahue, R. M. Duarte, D. Robin, F. Sannibale, C. Steier, W. Wan
    LBNL, Berkeley, California
  Funding: Work supported by the U. S. Department of Energy under Contract No. DE-AC03-76SF00098

We plan to commission top-off injection at the Advanced Light Source in the near future. In order to guarantee radiation safety, we have been simulating the injection process to exclude the possibility of injected electrons traveling down the user's photon beam lines. As the final stage of our simulation study, we use photon beam line CAD drawings to define the beam line's aperture in the phase space which electrons must not enter. Then we virtually inject electrons from within these phase spaces backwards into the storage ring to prove that such electrons can never get back to the real injection point under any possible scenario. This paper summarizes such inverse tracking studies.

 
 
TUPMS003 Status of the Top-off Upgrade of the ALS radiation, brightness, booster, storage-ring 1197
 
  • C. Steier
  • B. J. Bailey, K. M. Baptiste, W. Barry, A. Biocca, W. E. Byrne, M. J. Chin, R. J. Donahue, R. M. Duarte, M. P. Fahmie, J. Gath, S. R. Jacobson, J. Julian, J.-Y. Jung, S. Kwiatkowski, S. Marks, R. S. Mueller, H. Nishimura, J. W. ONeill, S. Prestemon, D. Robin, S. L. Rossi, F. Sannibale, T. Scarvie, D. Schlueter, D. Shuman, G. D. Stover, CA. Timossi, T. Warwick, J. M. Weber, E. C. Williams
    LBNL, Berkeley, California
  Funding: This work was supported by the Director, Office of Science, Office of Basic Energy Sciences, U. S. Department of Energy under Contract No. DE-AC02-05CH11231.

The Advanced Light Source is currently being upgraded for top-off operation. This major facility upgrade will provide an improvement in brightness from soft x-ray undulators of about one order of magnitude and keep the ALS competitive with the newest intermediate energy light sources. Major components of the upgrade include making the booster synchrotron capable of full energy operation, radiation safety studies, improvements to interlocks and collimation systems, diagnostics upgrades as well as emittance improvements in the main storage ring. The project status will be discussed as well as results of major parts of the commissioning.

 
 
TUPMS007 NSLS VUV Ring Lifetime Study scattering, septum, simulation, closed-orbit 1203
 
  • L. Yang
  • S. L. Kramer, B. Podobedov
    BNL, Upton, Long Island, New York
  • S.-Y. Lee
    IUCF, Bloomington, Indiana
  Beam lifetime at VUV ring of National Synchrotron Light Source(NSLS) at BNL is limited by Touschek effect. This effect is affected by momentum acceptance and beam density. The geometry near injection septum, dynamic aperture and the RF acceptance all can limit the over all momentum acceptance. Extensive experiments including coupling, gas scattering, RF acceptance, have been done for understanding the lifetime, and the result is confirmed with theoretical predictions.  
 
TUPMS014 Commissioning of the Booster Injector Synchrotron for the HIGS Facility at Duke University booster, extraction, synchrotron, electron 1209
 
  • S. F. Mikhailov
  • O. Anchugov, N. Gavrilov, G. Y. Kurkin, Yu. Matveev, D. Shvedov, N. Vinokurov
    BINP SB RAS, Novosibirsk
  • M. D. Busch, M. Emamian, S. M. Hartman, Y. Kim, J. Li, V. Popov, G. Swift, P. W. Wallace, P. Wang, Y. K. Wu
    FEL/Duke University, Durham, North Carolina
  • C. R. Howell
    TUNL, Durham, North Carolina
  Funding: This work is supported by the US DoE grant #DE-FG02-01ER41175

A booster synchrotron has been built and recently commissioned at Duke University Free Electron Laser Laboratory (DFELL) as part of the High Intensity Gamma-ray Source (HIGS) facility upgrade. HIGS is developed collaboratively by the DFELL and Triangular Universities Nuclear Laboratory (TUNL). The booster will provide top-off injection into the Duke FEL storage ring in the energy range of 0.27 - 1.2 GeV. When operating the Duke storage ring to produce high energy Compton gamma ray beams above 20 MeV, continuous electron beam loss occurs. The lost electrons will be replenished by the booster injector operating in the top-off mode. The compactness of the booster posed a challenge for its development and commissioning. The booster has been successfully commissioned in 2006. This paper reports experience of commissioning and initial operation of the booster.

 
 
TUPMS015 Challenges for the Energy Ramping in a Compact Booster Synchrotron booster, extraction, sextupole, coupling 1212
 
  • S. F. Mikhailov
  • S. M. Hartman, J. Li, V. Popov, Y. K. Wu
    FEL/Duke University, Durham, North Carolina
  Funding: This work is supported by the US DoE grant #DE-FG02-01ER41175

A booster synchrotron has been recently commissioned at Duke University FEL Laboratory as a part of the High Intensity Gamma-ray Source (HIGS) facility. The booster will provide top-off injection into the storage ring in the energy range of 0.27 - 1.2 GeV. In order to minimize the cost of the project, the booster is designed with a very compact footprint. As a result, unconventionally high field bending magnets at 1.76 T are required. A main ramping power supply drives all dipoles and quadrupoles. Quadrupole trims are used to compensate for tune changes caused by the change of relative focusing strength during ramping. Sextupoles compensate for chromatic effects caused by dipole magnet pole saturation. All these compensations have to be performed as a function of beam energy. Above 1.1 GeV, where the magnets are heavily saturated, the reduction of dynamic aperture is compensated by redistribution of strength among the sextupole families. With these compensations, effects of the magnet saturation do not cause any considerable beam loss during energy ramping.

 
 
TUPMS040 Development of a THz Seed Source for FEL Microbunching Experiment at the Neptune Laboratory laser, radiation, plasma, electron 1275
 
  • S. Tochitsky
  • C. Joshi, C. Sung
    UCLA, Los Angeles, California
  Funding: This work is supported by US Department of Energy Grant No. DE-FG03-92ER40727

Seeded FEL/IFEL techniques can be used for modulation of a relativistic electron beam longitudinally on the radiation wavelength. However, in the 1-10 THz range, which is of particular importance for matched injection of prebunched electrons into a laser-driven plasma accelerating structure, a suitable radiation source is not available. At the UCLA Neptune Laboratory we have built and fully characterized a radiation source tunable in the range of 1-3 THz. The THz pulse is produced by mixing two CO2 laser lines in a noncollinear phase-matched GaAs crystal at room temperature. The crystal is pumped by 200 ns pulses of a dual beam TEA CO2 laser running at 1 Hz. A grating placed in each lasing section allowed to cover the spectral range for the difference frequency from 0.5-4.5 THz with a step of 30-40 GHz. The achieved narrow bandwidth of ~10-5 and the output power of 2kW are sufficient for seeding a single-pass, waveguide FEL amplifier-prebuncher*. These pulses were used to measure the coupling efficiency and the attenuation for different types of THz waveguides and the results will be reported.

* C. Sung et al. "Seeded FEL/IFEL techniques for radiation amplification and electron microbunching in the terahertz range" Phys. Rev. STAB, 2006 (to be published)

 
 
TUPMS051 Low Alpha Mode for SPEAR3 lattice, sextupole, electron, synchrotron 1308
 
  • X. Huang
  • W. J. Corbett, Y. Nosochkov, J. A. Safranek, J. J. Sebek, A. Terebilo
    SLAC, Menlo Park, California
  In the interest of obtaining shorter bunch length for shorter X-ray pulses, we have developed a low-alpha operational mode for SPEAR3. In this mode the momentum compaction factor is reduced by a factor of 21 or more from the usual achromat mode by introducing negative dispersion at the straight sections. We successfully stored 100~mA with the normal fill pattern at a lifetime of 30hrs. The bunch length was measured to be 6.9ps, compared to 17ps in the normal mode. In this paper we report our studies on the lattice design and calibration, orbit stability, higher order alpha measurement, lifetime measurement and its dependence on the sextupoles, injection efficiency and bunch lengths.  
 
TUPMS055 SPEAR3 Accelerator Physics Update photon, optics, feedback, electron 1311
 
  • J. A. Safranek
  • W. J. Corbett, S. M. Gierman, R. O. Hettel, X. Huang, J. J. Sebek, A. Terebilo
    SLAC, Menlo Park, California
  The SPEAR3 storage ring at Stanford Synchrotron Radiation Laboratory has been delivering photon beams for three years. We will give an overview of recent and ongoing accelerator physics activities, including 500 mA fills, work toward top-off injection, long-term orbit stability characterization & improvement, fast orbit feedback, new chicane optics, low alpha optics & short bunches, low emittance optics, and new insertion devices. The accelerator physics group has a strong program to characterize and improve SPEAR3 performance.  
 
TUPMS065 JLAMP: An Amplifier Based FEL in the JLab SRF ERL Driver wiggler, emittance, electron, undulator 1329
 
  • K. Jordan
  • S. V. Benson, D. Douglas, P. Evtushenko, C. Hernandez-Garcia, G. Neil
    Jefferson Lab, Newport News, Virginia
  Funding: This work supported by the Off. of Naval Research, the Joint Technology Off., the Commonwealth of Virginia, the Air Force Research Lab, Army Night Vision Lab, and by DOE Contract DE-AC05-060R23177.

Notional designs for ERL-driven high average power free electron lasers often invoke amplifier-based architectures. To date, however, amplifier FELs have been limited in average power output to values several orders of magnitude lower than those demonstrated in optical-resonator based systems; this is due at least in part to the limited electron beam powers available from their driver accelerators. In order to directly contrast the performance available from amplifiers to that provided by high-power cavity-based resonators, we have developed a scheme to test an amplifier FEL in the JLab SRF ERL driver. We describe an accelerator system design that can seamlessly and non-invasively integrate a 10 m wiggler into the existing system and which provides, at least in principle, performance that would support high-efficiency lasing in an amplifier configuration. Details of the design and an accelerator performance analysis will be presented.

 
 
TUPMS077 Injection Simulations for NSLS-II Storage Ring simulation, storage-ring, emittance, lattice 1350
 
  • I. Pinayev
  • J. Rose, T. V. Shaftan, L.-H. Yu
    BNL, Upton, Long Island, New York
  Operation of the NSLS-II storage ring in the top-up mode requires highly reliable injection with low losses. In this paper we provide results of the injection simulations for the storage ring. The alignment tolerances as well as requirements for the injected beam parameters are also discussed.  
 
TUPMS081 Design considerations of the NSLS-II Injection Linac linac, booster, emittance, single-bunch 1359
 
  • J. Rose
  • I. Pinayev, T. V. Shaftan
    BNL, Upton, Long Island, New York
  The NSLS-II injector consists of a 3 GeV booster injected by a 200MeV linac. Specifications of the linac are derived from Booster and Storage ring beam requirements. Linac design considerations are presented to meet these specifications.  
 
TUPMS083 Conceptual Design of the NSLS-II Injection System booster, lattice, storage-ring, emittance 1362
 
  • T. V. Shaftan
  • J. Beebe-Wang, J. Bengtsson, G. Ganetis, W. Guo, R. Heese, H.-C. Hseuh, E. D. Johnson, V. Litvinenko, A. U. Luccio, W. Meng, S. Ozaki, I. Pinayev, S. Pjerov, D. Raparia, J. Rose, S. Sharma, J. Skaritka, C. Stelmach, N. Tsoupas, D. Wang, L.-H. Yu
    BNL, Upton, Long Island, New York
  Funding: This work was supported by Department of Energy contract DE-AC02-98CH10886.

We present conceptual design of the NSLS-II injection system. The injection system consists of low-energy linac, booster and transport lines. We review the requirements on the injection system imposed by the storage ring design and means of meeting these requirements. We discuss main parameters and layout of the injection system components.

 
 
TUPAN008 Spiral FFAG for Protontherapy extraction, lattice, magnet-design, cyclotron 1404
 
  • J. Pasternak
  • B. Autin
    CERN, Geneva
  • J. Fourrier, E. Froidefond
    LPSC, Grenoble
  • F. Meot
    CEA, Gif-sur-Yvette
  • D. Neuveglise, T. Planche
    Sigmaphi, Vannes
  High rep rate of the FFAG accelerator and compactness of the spiral type of the design makes it a good candidate as medical machine for protontherapy and for biological research. The variable energy extraction with various methods is discussed. The principle of the lattice design together with the injection scheme and the beam dynamics simulations are presented. The spiral magnet design undertaken in the frame of the RACCAM project is briefly described.  
 
TUPAN016 Rare Isotope Accumulation and Deceleration in the NESR Storage Ring of the FAIR Project electron, ion, antiproton, secondary-beams 1425
 
  • M. Steck
  • C. Dimopoulou, A. Dolinskii, F. Nolden
    GSI, Darmstadt
  The storage ring NESR of the FAIR project can be operated with rare isotope beams which are produced by projectile fragmentation of a fast heavy ion beam. After stochastic pre-cooling at 740 MeV/u in a dedicated collector ring (CR) the rare isotopes will be accumulated in the NESR by a longitudinal accumulation technique in combination with electron cooling. Various schemes for the accumulation have been considered and evaluated. For experiments with stored beams and for transfer to an ion trap the ion beams can be decelerated to a minimum energy of 4 MeV/u. The deceleration mode of the NESR will also be available for deceleration of antiprotons to a minimum energy of 30 MeV. Fast extraction to a trap and slow extraction to fixed target are foreseen.  
 
TUPAN025 Selective Containment Measurements on Xe with the RF Charge Breeder Device BRIC ion, vacuum, electron, simulation 1445
 
  • V. Variale
  • P. A. Bak, G. I. Kuznetsov, B. A. Skarbo, M. A. Tiunov
    BINP SB RAS, Novosibirsk
  • A. Boggia
    Universita e Politecnico di Bari, Bari
  • T. Clauser, V. Valentino
    INFN-Bari, Bari
  • A. C. Raino
    Bari University, Science Faculty, Bari
  Funding: INFN and UE contract no. 515768 EURISOL_DS (RIDS)

The Radioactive Ion Beam (RIB) production with ISOL technique should require a charge breeder device to increase the ion acceleration efficiency and reduce greatly the production cost. The "charge breeder" is a device designed to accept RIB with charge state +1 and in order to increase their charge state up to +n. Recently, at the INFN section of Bari first and at LNL (Italy) then, a new charge breeder device, based on an EBIS ion source called BRIC, has been developed. The new feature of BRIC, with respect to the classical EBIS, is given by the insertion, in the ion drift chamber, of a Radio Frequency (RF) - Quadrupole aiming to filtering the unwanted masses and then making a selective more efficient containment of the wanted ions. The RF test measurements for Ar gas confirm, as foreseen by simulation results* that the selective containment can be obtained. More measurements on the selective containment of heavier element ions (more close to the radioactive ion produced with ISOL technique) like Xe are needed to study with more details that effect. In this contribution new measurements on the rf selective containement in BRIC for Xe gas will be presented and discussed.

* V. Variale and M. Claudione, "BRICTEST: a code for charge breeding simulations in RF quadrupolar field", NIM in Phys. res. A 543 (2005) 403-414.

 
 
TUPAN033 DAΦ NE Setup and Performances During the Second FINUDA Run luminosity, collider, coupling, wiggler 1457
 
  • C. Milardi
  • D. Alesini, M. E. Biagini, C. Biscari, R. Boni, M. Boscolo, B. Buonomo, A. Clozza, G. O. Delle Monache, T. Demma, E. Di Pasquale, G. Di Pirro, A. Drago, A. Gallo, A. Ghigo, S. Guiducci, M. Incurvati, P. Iorio, C. Ligi, F. Marcellini, C. Marchetti, G. Mazzitelli, L. Pellegrino, M. A. Preger, L. Quintieri, P. Raimondi, R. Ricci, U. Rotundo, C. Sanelli, M. Serio, F. Sgamma, B. Spataro, A. Stecchi, A. Stella, S. Tomassini, C. Vaccarezza, M. Zobov
    INFN/LNF, Frascati (Roma)
  • J. D. Fox, D. Teytelman
    SLAC, Menlo Park, California
  • E. Levichev, S. A. Nikitin, P. A. Piminov, D. N. Shatilov
    BINP SB RAS, Novosibirsk
  Beam operations on DAΦNE restarted on October 2006 after a four months shut-down to remove the KLOE experimental detector and to install the FINUDA one. This period has been also used for maintenance and implementation of several upgrades. In the first two months of operation the peak and integrated luminosity already exceeds the values obtained during the first FINUDA run by 20%. The DAΦNE goal is to deliver 1 fb-1 integrated luminosity by the end of May 2007. The collider performances during the run are presented together with the improvements obtained in terms of ring nonlinearities and beam dynamics coming from several collider modifications.  
 
TUPAN034 Super-B Factory using Low Emittance Storage Rings and Large Crossing Angle collider, interaction-region, factory, luminosity 1460
 
  • J. Seeman
  • M. E. Biagini, P. Raimondi
    INFN/LNF, Frascati (Roma)
  • Y. Cai, M. K. Sullivan, U. Wienands
    SLAC, Menlo Park, California
  Funding: Work supported by US DOE contract DE-AC02-76SF00515.

Submitted for the High Luminosity Study Group for an Asymmetric Super-B-Factory: Parameters are being studied for a high luminosity e+e- collider operating at the Upsilon 4S that would deliver a luminosity of over 1036/cm2/s. This collider would use a novel combination of linear collider and storage ring techniques. In this scheme an electron beam and a positron beam at 4 GeV x 7 GeV are stored in low-emittance damping rings similar to those designed for a Linear Collider (LC). A LC style interaction region is included in the ring to produce sub-millimeter vertical beta functions at the collision point. A large crossing angle (±30 mrad) is used at the collision point to allow beam separation and reduce the hourglass effect. Beam currents of about 3 A x 2 A in 1700 bunches can produce a luminosity of 1036/cm2/s. Design parameters and beam dynamics effects are discussed.

 
 
TUPAN043 RF Amplitude and Phase Tuning of J-PARC DTL linac, beam-transport, monitoring, controls 1481
 
  • M. Ikegami
  • H. Asano, T. Kobayashi
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
  • K. Hasegawa, T. Ito, T. Morishita, S. Sato, A. Ueno
    JAEA/LINAC, Ibaraki-ken
  • Z. Igarashi, H. Tanaka
    KEK, Ibaraki
  • H. Sako
    JAEA, Ibaraki-ken
  The beam commissioning of J-PARC linac has been started in November 2006. In the beam commissioning, the tuning of the RF phase and amplitude for its DTL (Drift Tube Linac) has been performed with a phase-scan method. Detailed results of the RF tuning are presented with a brief discription of the tuning procedure.  
 
TUPAN044 Acceleration Scheme in the AIA and its Control System acceleration, induction, ion, simulation 1484
 
  • T. Iwashita
  • Y. Arakida, T. Kono, Y. Shimosaki, K. Takayama
    KEK, Ibaraki
  • T. S. Dixit
    GUAS/AS, Ibaraki
  • K. Okazaki
    Nippon Advanced Technology Co. Ltd., Ibaraki-prefecture
  An All Ion Accelerator (AIA), an injector-free induction synchrotron (IS) is proposed as a modification of the KEK booster*. The Booster is a rapid cycle synchrotron operating at a repetition rate of 20Hz. The AIA based on the booster requires more flexible trigger generation for the acceleration or confinement system than the one used for the IS POP experiment**. Assuming Ar+18 injection from a 200 kV ion source, the revolution period changes from 9.08usec to 333nsec at the end, and the required acceleration voltage changes from few tens of volts to 6.4kV at the middle of acceleration. Since a number of available acceleration cells is finite and their maximum pulse width and output voltage are limited to 500 nsec and 2 kV/cell, respectively, the dynamic allocation of acceleration cells in real time is indispensable, where a trade-off between the voltage amplitude and integrated pulse-length is realized. The acceleration scheme employing fast DSPs and a trigger control system is designed so as to meet the above requirement. Its whole story will be presented, including beam simulation results in the proposed AIA.

* E. Nakamura et al., in PAC07** K. Takayama et al., "Experimental Demonstration of the Induction Synchrotron" appeared in Phys. Rev. Lett. soon and in PAC07

 
 
TUPAN046 A Modification Plan of the KEK 500MeV Booster to an All-ion Accelerators (An Injector-free Synchrotron) ion, acceleration, kicker, extraction 1490
 
  • E. Nakamura
  • T. Adachi, Y. Arakida, T. Iwashita, M. Kawai, T. Kono, H. Sato, Y. Shimosaki, K. Takayama, M. Wake
    KEK, Ibaraki
  • T. S. Dixit
    GUAS/AS, Ibaraki
  • S. I. Inagaki
    Kyushu University
  • T. Kikuchi
    Utsunomiya University, Utsunomiya
  • K. Okazaki
    Nippon Advanced Technology Co. Ltd., Ibaraki-prefecture
  • K. T. Torikai
    NIRS, Chiba-shi
  A medium-energy synchrotron capable of accelerating all ion species based on a novel technology of the induction synchrotron* has been proposed as an all-ion accelerator (AIA)**. The AIA without any specific injector employs a strong focusing lattice and induction acceleration, driven by novel switching power supplies. All ions, including cluster ions with any charge state, are accelerated in a single accelerator. A plan to modify the existing KEK 500 MeV Booster to the AIA is under consideration. Its key aspects, such as an ion-source, a low-field injection scheme and induction acceleration***, are described. Deep implant of moderate-energy heavy ions provided from the AIA into various materials may create a new alloy in bulk size. Energy deposition caused by the electro-excitation associated with passing of swift ions through the material is known to largely modify its structure. The similar irradiation on metal in a small physical space of less than a mm in diameter and in a short time period less than 100 nsec is known to create a particularly interesting warm dense-matter state. The AIA capable is a quite interesting device as a driver to explore these new paradigms.

* K. Takayama, et al., "Experimental Demonstration of the Induction Synchrotron", PAC07.** K. Takayama, et al., PCT/JP2006/308502 (2006).*** T. Dixit, et al., PAC07.

 
 
TUPAN051 Design of Dynamic Collimator for J-PARC Main Ring target, collimation, extraction, beam-losses 1505
 
  • M. Tomizawa
  • A. Y. Molodozhentsev, M. J. Shirakata
    KEK, Ibaraki
  The J-PARC main ring has a beam collimator section downstream of the injection area. The allowed beam loss is about 500 W. The beam halo during injection can be scraped by a standard collimator scheme. The beam halo can grow during the acceleration. Such a halo may cause a serious beam loss for extracted beam. A collimation during acceleration (dynamic collimator) is usefull to reduce the uncontrolable beam loss at the extraction. We will report the design and simulation of the dynamic collimation.  
 
TUPAN052 New Beam Optics Design of Injection/Fast Extraction/Abort Lines of J-PARC Main Ring extraction, kicker, quadrupole, beam-losses 1508
 
  • M. Tomizawa
  • A. Y. Molodozhentsev, E. Nakamura, I. Sakai, M. Uota
    KEK, Ibaraki
  J-PARC Main Ring has three straight sections for injection, slow extraction and fast extraction. Injection line has been redesigned so as to give a higher reliability for the thin septa. The magnetic field can be reduced by adding an extra kicker. New optics for the fast extraction with a larger acceptance has been proposed. In this design, the thin septa are replaced by kickers with a large aperture. Beam with an arbitrary energy can be aborted from opposite side from the fast extraction. An external abort line has been designed to deliver the beam aborted with an arbitrary energy to a dump just by using a static quadrupole doublet for the focus.  
 
TUPAN061 Updated Simulation for the Nuclear Scattering Loss Estimation at the RCS Injection Area scattering, beam-losses, simulation, space-charge 1526
 
  • P. K. Saha
  • H. Hotchi, Y. Irie, F. Noda
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
  • S. Machida
    STFC/RAL/ASTeC, Chilton, Didcot, Oxon
  We have updated the simulation for the realistic beam loss estimation at the RCS (Rapid Cycling Synchrotron) injection area of J-PARC(Japan Proton Accelerator Research Complex). At the injection area, beam loss caused by the nuclear scattering together with the multiple coulomb scattering at the charge-exchange foil is the dominant one and is an important issue for designing mainly the foil thickness and other beam elements like, the falling time of bump magnets after the injection is finished and so on. The simulation tool GEANT for the scattering effect and the real injection process have been employed together in order to estimate the beam loss turn by turn including identification of loss points too.  
 
TUPAN080 Screening of Cyclotron Magnetic Field in C400 Axial Injection Beam-line cyclotron, shielding, insertion, simulation 1559
 
  • N. Yu. Kazarinov
  • V. Aleksandrov, V. Shevtsov, A. Tuzikov
    JINR, Dubna, Moscow Region
  • Y. Jongen
    IBA, Louvain-la-Neuve
  The screening of the optical elements placed at the horizontal part of the axial injection beam-line of the C400 cyclotron for hadron therapy is performed. An influence of the injection channel shielding elements on magnetic field distribution in the median plane of the C400 cyclotron was studied. The 3D ANSYS model is used for this purpose.  
 
TUPAN081 Axial Injection Beam-Line of C400 Cyclotron for Hadron Therapy ion, cyclotron, quadrupole, emittance 1562
 
  • N. Yu. Kazarinov
  • V. Aleksandrov, V. Shevtsov
    JINR, Dubna, Moscow Region
  • Y. Jongen
    IBA, Louvain-la-Neuve
  The axial injection beam-line of the C400 cyclotron for hadron therapy is presented. The influence of the strong magnetic field from the cyclotron on particles dynamics is taking into account during simulation. The effect of the beam space charge neutralization due to residual gas in the beam-line on parameters of the injected beam is evaluated.  
 
TUPAN086 An Improved Beam Screen for the LHC Injection Kickers impedance, kicker, coupling, vacuum 1574
 
  • M. J. Barnes
  • F. Caspers, L. Ducimetiere, N. Garrel, T. Kroyer
    CERN, Geneva
  The two LHC injection kicker magnet systems must produce a kick of 1.3 T.m with a flattop duration variable up to 7860 ns, and rise and fall times of less than 900 ns and 3000 ns, respectively. Each system is composed of two resonant charging power supplies and four 5 Ω transmission line kicker magnets with matched terminating resistors and pulse forming networks. A beam screen is placed in the aperture of the magnets: the screen consists of a ceramic tube with conductors on the inner wall. The conductors provide a path for the image current of the, high intensity, LHC beam and screen the ferrite against Wake fields. The conductors initially used gave adequately low beam impedance however inter-conductor discharges occurred during pulsing of the magnet: an alternative design was discharge free at the nominal operating voltage but the beam impedance was too high for the ultimate LHC beam. This paper presents the results of a new development undertaken to meet the often conflicting requirements for low beam impedance, shielding of the ferrite, fast field rise time and good electrical behaviour. High voltage test results and thermal measurements are also presented.  
 
TUPAN087 Scenarios for Beam Commissioning of the LHC Collimation System collimation, optics, proton, simulation 1577
 
  • C. B. Bracco, C. B. Bracco
    EPFL, Lausanne
  • R. W. Assmann, S. Redaelli, G. Robert-Demolaize
    CERN, Geneva
  A complex system of collimators has been designed to protect the superconducting LHC magnets against quench and damage from the high intensity proton beams. The considerable number of collimators and the resulting number of degrees of freedom for their set-up requires a well prepared commissioning strategy. Efficiency studies for various implementations of the LHC collimation system have been performed, taking into account the evolution in optics and beam intensity according to the LHC commissioning schedule. This paper explains the present plans for the set-up sequence of collimators and discusses the relevant tolerances induced from the collimation system for the first years of the LHC operation.  
 
TUPAN088 Beam Scraping for LHC Injection emittance, proton, beam-losses, extraction 1580
 
  • H. Burkhardt
  • G. Arduini, S. Bart Pedersen, C. Fischer, JJ. G. Gras, A. Koschik, D. K. Kramer, S. Redaelli
    CERN, Geneva
  Operation of the LHC will require injection of very high intensity beams from the SPS to the LHC. Fast scrapers have been installed and will be used in the SPS to detect and remove any existing halo before beams are extracted, to minimize the probability for quenching of super-conducting magnets at injection in the LHC. We briefly review the functionality of the scraper system and report about measurements that have recently been performed in the SPS on halo scraping and re-population of tails.  
 
TUPAN090 Parametric Field Modelling for the LHC Main Magnets in Operating Conditions quadrupole, dipole, multipole, extraction 1586
 
  • M. DiCastro
  • L. Bottura, L. Deniau, N. J. Sammut, S. Sanfilippo, D. Sernelius, W. Venturini Delsolaro
    CERN, Geneva
  The first injections and ramps in the LHC will require a prediction of the settings of the main ring powering circuits as well as the main correctors. For this reason we are developing a parametric model of the magnetic field generated by the LHC magnets that will provide the field dependence on current, ramp-rate, time, and history. The model of the field is fitted on magnetic field measurements performed during the acceptance tests in operating conditions before their installation in the machine. In this paper we summarise the different steps necessary to select the relevant data and identify the parameters: the data extraction, the cleaning and the validation of the measurements, and the fitting procedure that is used to obtain the parameters from the experimental results. The main result reported is a summary of the value of the parameters obtained with the above procedure, and describing the behaviour of the magnetic field in the LHC main superconducting magnets (i.e. arc, dispersion suppressors and matching sections).  
 
TUPAN093 Simulation of the CERN PS Booster Performance with 160 MeV H- Injection from Linac4 simulation, linac, emittance, space-charge 1595
 
  • F. Gerigk
  • M. Aiba, C. Carli, M. Martini
    CERN, Geneva
  • S. M. Cousineau
    ORNL, Oak Ridge, Tennessee
  The ultimate luminosity (2.3 x 1034 cm-2 s-1) in the LHC can only be reached or even exceeded if a major upgrade of the CERN proton injector complex takes place. The first identified bottleneck towards higher brightness beams is the 50 MeV proton injection of Linac2 into the PS booster (PSB). Doubling the intensity in the PSB can be achieved with a new linac (Linac4) which increases the injection energy to 160 MeV. Linac4 will provide H- ions and charge-exchange injection will be used in the PSB instead of using the present multi-turn proton injection scheme. The code ACCSIM is used to study the H- injection process and to determine if the requested intensities can be reached within the specified emittance budgets. The results are then compared with ORBIT simulations. In the longitudinal plane we use ESME to study various capture schemes.  
 
TUPAN094 PS2 Injection, Extraction and Beam Transfer Concepts extraction, septum, kicker, ion 1598
 
  • B. Goddard
  • W. Bartmann, M. Benedikt, A. Koschik, T. Kramer
    CERN, Geneva
  The replacement of CERN's existing 26 GeV Proton Synchrotron (PS) machine with a separated-function synchrotron PS2 has been identified as an important part of the possible future upgrade programme of the CERN accelerator complex. The PS2 will require a number of new beam transfer systems associated with injection, extraction, beam dumping and transfer. The different requirements are briefly presented, together with an overview of the conceptual design of these systems, based on the initial PS2 parameter set. The required equipment sub-system performance is derived and discussed. Possible limitations are analysed and the impact on the overall design and parameter set is discussed.  
 
TUPAN100 Performance Reach of the collimation, proton, insertion, simulation 1613
 
  • G. Robert-Demolaize
  • R. W. Assmann, C. B. Bracco, S. Redaelli, Th. Weiler
    CERN, Geneva
  State-of-the-art tracking tools have been developed for detailed LHC collimation and beam loss studies. This includes full chromatic treatment of both beam lines and error models. This paper reviews the main results on the performance reach of the multi-stage LHC collimation system that is being installed in the LHC. Limitations on the allowed proton loss rates and the stored intensity can be derived from the comparison of local losses with estimated quench limits for the superconducting magnets. The origins of the cleaning-related performance limitations are presented and possible improvements are discussed.  
 
TUPAN101 Tracking Studies with Variable Magnetic Field to Characterize Quadrupole Failures in LHC quadrupole, beam-losses, resonance, simulation 1616
 
  • A. Gomez Alonso
  • R. Schmidt
    CERN, Geneva
  During LHC operation, energies up to 360 MJ will be stored in each proton beam and more than 10 GJ in the superconducting magnets. With these energies, a magnet failure can lead to important equipment damage if the beam is not extracted in time. The machine protection systems should detect such failures and trigger the beam extraction system. In order to characterize the beam response after magnet failures, tracking simulations have been performed with MAD-X. The magnetic field was set to change with time according to realistic current changes in the electrical circuits with the magnets after a powering failure. The effect on the beam of powering failures in the normal conducting quadrupoles has been studied. For fast failures (beam lost in less than 100 ms) the nonlinear effects are negligible. For slower failures, higher order resonances may lead to beam losses of up to ~8% of the beam.  
 
TUPAN109 160 MeV H- Injection into the CERN PSB linac, dipole, septum, emittance 1628
 
  • W. J.M. Weterings
  • G. Bellodi, J. Borburgh, T. Fowler, F. Gerigk, B. Goddard, K. Hanke, M. Martini, L. Sermeus
    CERN, Geneva
  The H- beam from the proposed LINAC4 will be injected into the four existing rings of the PS Booster at 160 MeV. A substantial upgrade of the injection region is required, including the modification of beam distribution system and the construction of a new H- injection system. This paper discusses beam dynamics and hardware requirements and presents the results of optimisation studies of the injection process for different beam characteristics and scenarios. The resulting conceptual design of the injection region is presented, together with the main hardware modifications and performance specifications.  
 
TUPAN113 Injection Studies on the ISIS Synchrotron space-charge, emittance, lattice, simulation 1640
 
  • B. Jones
  • D. J. Adams, C. M. Warsop
    STFC/RAL/ISIS, Chilton, Didcot, Oxon
  The ISIS Facility at the Rutherford Appleton Laboratory in the UK produces intense neutron and muon beams for condensed matter research. It is based on a 50 Hz proton synchrotron which, once the commissioning of a new dual harmonic RF system is complete, will accelerate about 3.5·1013 protons per pulse from 70 to 800 MeV, corresponding to mean beam powers of 0.2 MW. The multi-turn charge-exchange injection process strongly affects transverse beam distributions, space charge forces, beam loss and therefore operational intensity. The evolution of longitudinal distributions and subsequent trapping efficiency is also intimately linked with injection. Optimising injection is therefore a key consideration for present and future upgrades. Work is now under way looking at this process in more detail, and relates closely to other transverse space charge studies on the ring. This paper presents work including: space charge simulations of the present machine and comparison with observations; assessment of related loss mechanisms; and study of optimal painting schemes. Plans and preparations for more detailed experimental work are also summarised.  
 
TUPAS007 The Investigation of Injection Timing for the IPNS RCS proton, space-charge, acceleration, simulation 1667
 
  • S. Wang
  • F. R. Brumwell, J. C. Dooling, R. Kustom, G. E. McMichael, M. E. Middendorf
    ANL, Argonne, Illinois
  Funding: This work is supported by the U. S. Department of Energy under contract no. W-31-109-ENG-38.

The Intense Pulsed Neutron Source (IPNS) Rapid Cycling Synchrotron (RCS) accelerates 3.2x 1012 protons from 50 MeV to 450 MeV at 30 Hz. During the 14.2 ms acceleration period, the RF frequency varies from 2.21 MHz to 5.14 MHz. In order to improve capture efficiency, we varied the injection timing and the early RF voltage profiles. The experimental results are compared with similar studies at ISIS and calculation done with the 1-D tracking code, Capture-SPC. This allowed us to optimize injection time and the RF voltage profile for better capture efficiency. An optimized injection time and RF voltage profile was found that resulted in raising the capture efficiency from 85.1% to 88.6%. These studies have now also been expanded to included 2nd harmonic RF during the capture and initial acceleration cycle in the RCS.

 
 
TUPAS013 Some Physics Issues of Carbon Stripping Foils proton, electron, ion, booster 1679
 
  • W. Chou
  • M. A. Kostin
    NSCL, East Lansing, Michigan
  • J. R. Lackey, Z. Tang
    Fermilab, Batavia, Illinois
  • R. J. Macek
    LANL, Los Alamos, New Mexico
  • P. S. Yoon
    Rochester University, Rochester, New York
  Funding: Work supported by Universities Research Association, Inc. under contract No. DE-AC02-76CH03000 with the U. S. Dept. of Energy.

Carbon foils are widely used in charge-exchange injection in high intensity hadron accelerators. There are a variety of physics issues associated with the use of carbon foils, including stripping efficiency, energy deposition, foil lifetime (temperature rise, mechanical stress and buckling), multiple Coulomb scattering, large angle single Coulomb scattering, energy straggling and radiation activation. This paper will give a brief discussion of these issues based on the study of the Proton Driver and experience of the Fermilab Booster. Details can be found in Ref*.

* W. Chou et al., "Transport and Injection of 8 GeV H- Ions," Fermilab-TM-2285 (2007).

 
 
TUPAS014 Fast Beam Stacking using RF Barriers booster, simulation, proton, acceleration 1682
 
  • W. Chou
  • D. Capista, E. Griffin, K. Y. Ng, D. Wildman
    Fermilab, Batavia, Illinois
  Funding: Work supported by Universities Research Association, Inc. under contract No. DE-AC02-76CH03000 with the U. S. Dept. of Energy.

Two barrier rf systems were fabricated, tested and installed in the Fermilab Main Injector.* Each can provide 8-10 kV rectangular pulses (the rf barriers) at 90 kHz. When a stationary barrier is combined with a moving barrier, injected beams from the Booster can be continuously deflected, folded and stacked in the Main Injector (MI), which leads to doubling of the beam intensity. This paper gives a report on the beam experiment using this novel technology.

* W. Chou, D. Wildman and A. Takagi, "Induction Barrier RF and Applications in Main Injector," Fermilab-Conf-06-227 (2006).

 
 
TUPAS015 Operational Aspects of the Main Injector Large Aperture Quadrupole quadrupole, lattice, beam-losses, extraction 1685
 
  • W. Chou
  • C. L. Bartelson, B. C. Brown, D. Capista, J. L. Crisp, J. DiMarco, J. Fitzgerald, H. D. Glass, D. J. Harding, B. Hendricks, D. E. Johnson, V. S. Kashikhin, I. Kourbanis, W. F. Robotham, T. Sager, M. Tartaglia, L. Valerio, R. C. Webber, M. Wendt, D. Wolff, M.-J. Yang
    Fermilab, Batavia, Illinois
  Funding: Work supported by Universities Research Association, Inc. under contract No. DE-AC02-76CH03000 with the U. S. Dept. of Energy.

A two-year Large Aperture Quadrupole (WQB) Project was completed in the summer of 2006 at Fermilab.* Nine WQBs were designed, fabricated and bench-tested by the Technical Division. Seven of them were installed in the Main Injector and the other two for spares. They perform well. The aperture increase meets the design goal and the perturbation to the lattice is minimal. The machine acceptance in the injection and extraction regions is increased from 40π to 60π mm-mrad. This paper gives a brief report of the operation and performance of these magnets. Details can be found in Ref**.

* D. Harding et al, "A Wide Aperture Quadrupole for the Fermilab Main Injector," this conference.
** W. Chou, Fermilab Beams-doc-#2479, http://beamdocs.fnal.gov/AD-public/DocDB/DocumentDatabase

 
 
TUPAS016 Collimation System Design for Beam Loss Localization with Slipstacking Injection in the Fermilab Main Injector collimation, beam-losses, simulation, proton 1688
 
  • A. I. Drozhdin
  • B. C. Brown, D. E. Johnson, I. Kourbanis, N. V. Mokhov, I. Rakhno, V. Sidorov
    Fermilab, Batavia, Illinois
  • K. Koba
    KEK, Ibaraki
  Results of modeling with the STRUCT and MARS15 codes of beam loss localization and related radiation effects are presented for the slipstacking injection to the Fermilab Main Injector. Simulations of proton beam loss are done using multi-turn tracking with realistic accelerator apertures, nonlinear fields in the accelerator magnets and time function of the RF manipulations to explain the results of beam loss measurements. The collimation system consists of one primary and four secondary collimators. It intercepts a beam power of 1.6 kW at a total scraping rate of 5%, with a beam loss rate in the ring outside the collimation region of 1 W/m or less. Based on thorough energy deposition and radiation modeling, a corresponding collimator design was developed that satisfies all the radiation and engineering constraints.  
 
TUPAS018 A Conceptual Design of an Internal Injection Absorber of 8 GeV H- Injection into the Fermilab Main Injector proton, linac, dipole, simulation 1694
 
  • D. E. Johnson
  • A. Z. Chen, I. Rakhno
    Fermilab, Batavia, Illinois
  Funding: Work supported by Universities Research Association, Inc. under contract No. DE-AC02-76CH03000 with the U. S. Dept. of Energy.

A 8 GeV H- superconducting linac has been proposed as an alternative injector for the Main Injector to support a 2 MW Neutrino program. An injection absorber is required to accept protons generated after the secondary stripping foil which will intercept the un-stripped H- and H0 particles after the MI primary foil injection point. The motivations underlying the choice of a compact internal absorber over an external absorber will be discussed. We show that using a high-Z material (tungsten) for the inner shielding allows the construction a compact absorber that can take a very intense beam and fits within the existing enclosure. The absorber requirements and a shielding design and the results of energy deposition calculations are presented.

 
 
TUPAS020 An 8 GeV H- Multi-turn Injection System for the Fermilab Main Injector simulation, proton, linac, dipole 1700
 
  • D. E. Johnson
  • J. Beebe-Wang, C. J. Liaw, D. Raparia
    BNL, Upton, Long Island, New York
  Funding: Work supported by Universities Research Association, Inc. under contract No. DE-AC02-76CH03000 with the U. S. Dept. of Energy.

The technique for H- charge exchange for multi-turn injection utilizing stripping foils in the energy range of a few hundred MeV has been used at many labs for decades and most recently up to 1 GeV at the SNS. Utilization the beam from the proposed Proton Driver* would permit the extension of this technique up to 8 GeV. The injection layout and required accelerator modifications are discussed. Results from transverse and longitudinal simulations are presented.

* W. G. Foster and J. A. MacLachlan, "A Multi-mission 8 GeV Injector Linac as a Fermilab Booster Replacement", Proc. Of LINAC-2002, Gyeongju, Korea, p.86.

 
 
TUPAS026 Operation and Performance of the New Fermilab Booster H- Injection System booster, closed-orbit, lattice, optics 1709
 
  • J. R. Lackey
  • F. G. Garcia, M. Popovic, E. Prebys
    Fermilab, Batavia, Illinois
  Funding: Work supported by the U. S. Department of Energy under Contract No. DE-AC02-76CH03000.

The operation and performance of the new, 15 Hz, H- charge exchange injection system for the FNAL Booster is described. The new system installed in 2006 was necessary to allow injection into the Booster at up to 15 Hz. It was built using radiation hardened materials which will allow the Booster to reliably meet the high intensity and repetition rate requirements of the Fermilab's HEP program. The new design uses three orbit bump magnets (Orbmps) rather than the usual four and permits injection into the Booster without a septum magnet. Injection beam line modification and compensation for the quadrupole gradients of the Orbmp magnets is discussed.

 
 
TUPAS030 Electron Cooling Rates Characterization at Fermilab's Recycler antiproton, electron, emittance, diagnostics 1715
 
  • L. R. Prost
  • A. V. Shemyakin
    Fermilab, Batavia, Illinois
  Funding: Operated by Universities Research Association Inc. under Contract No. DE-AC02-76CH03000 with the United States Department of Energy.

A 0.1 A, 4.3 MeV DC electron beam is routinely used to cool 8 GeV antiprotons in Fermilab's Recycler storage ring. While the primary function of the electron cooler is to increase the longitudinal phase-space density of the antiprotons, significant transverse cooling rates have been observed as well. Numerical characterization of electron cooling is done by two types of measurements: friction force measurements by the voltage jump method and diffusion/cooling rates measurements. The paper will present the recent measurement results and will compare them to a non-magnetized model.

 
 
TUPAS038 The Concept Design of a New Transfer Line from Booster to Recycler for the Fermilab Proton Plan Phase 2 Campaign booster, emittance, kicker, lattice 1727
 
  • D. E. Johnson
  • M. Xiao
    Fermilab, Batavia, Illinois
  Funding: Work supported by URA under contract No. DEAC02-76CH03000 with the U. S.Dept. of Energy.

Upon the termination of the Fermilab Collider program, the current Recycler anti-proton storage ring will be converted to a proton pre-injector for the Main Injector synchrotron. This is scheduled to increase the beam power for the 120 GeV Neutrino program to upwards of 700KW. A transport line that can provide direct injection from the Booster to the Recycler while preserving direct injection from the Booster into the Main Injector and the 8 GeV Booster Neutrino program will be discussed,and its concept design will be presented.

 
 
TUPAS040 Momentum Spread Reduction at Beam Extraction from the Fermilab Booster at Slipstacking Injection to the Main Injector booster, extraction, synchrotron, emittance 1733
 
  • A. I. Drozhdin
  • W. Pellico, X. Yang
    Fermilab, Batavia, Illinois
  In order to reduce the momentum spread of the beam at extraction from the Booster to the Main Injector with slip stacking injection, the bunch rotation at the end of the cycle is applied. However, the fast RF voltage reduction often causes beam loading issues to Booster RF cavities, and the reliability of extracted beam becomes a problem. An alternative solution is investigated - modulating the RF voltage with twice of the synchrotron frequency introduces bunch length oscillation, and the beam is extracted at the time when the bunch length reaches maximum and the momentum spread becomes minimal.  
 
TUPAS041 Injection Parameters Optimization for the Fermilab Booster space-charge, booster, beam-losses, linac 1736
 
  • A. I. Drozhdin
  • W. Pellico, X. Yang
    Fermilab, Batavia, Illinois
  The maximal capacitance for the Booster to deliver the 8-GeV beam to downstream accelerators is limited by the beam loss. Most of losses happen at injection due to space charge effect being the strongest at the injection energy. Optimizing the RF voltage ramp in the presence of the space charge effect to capture more beam and simultaneously keep small beam emittance has been numerically investigated using 3-D STRUCT code. The results of simulations agree well with the measurements in the machine. Possibilities, such as beam painting and using the second rf harmonic at injection, for further reductions of beam loss in order to reach the maximum beam intensity delivered from the Booster have been investigated.  
 
TUPAS044 Design of a High Temperature Oven for an ECR Source for the Production of Uranium Ion Beams ion, ion-source, plasma, cyclotron 1742
 
  • T. J. Loew
  • S. R. Abbott, M. L. Galloway, D. Leitner, C. M. Lyneis
    LBNL, Berkeley, California
  VENUS is the superconducting electron cyclotron resonance (ECR) ion source at the Lawrence Berkeley National Lab's 88-Inch Cyclotron. To generate neutral atoms for ionization, the source utilizes a resistively-heated high temperature oven that is located in a magnetic field of up to 4 Tesla and operates at temperatures up to about 2000°C. However, temperatures between 2100-2300°C are required to produce the desired 280eμA of high charge state uranium ion beams, and increased thermal and structural effects, combined with elevated chemical reactivity significantly reduce the oven's ability to operate in this envelope. The oven has been redesigned with higher thermal efficiency, improved structural strength and chemically compatible species in order to produce the desired high intensity, high charge state uranium beams. Aspects of the engineering development are presented.  
 
TUPAS047 Multi-turn Operation of the University of Maryland Electron Ring (UMER) quadrupole, dipole, electron, space-charge 1751
 
  • M. Walter
  • G. Bai, B. L. Beaudoin, S. Bernal, D. W. Feldman, T. F. Godlove, I. Haber, R. A. Kishek, P. G. O'Shea, C. Papadopoulos, M. Reiser, D. Stratakis, D. F. Sutter, J. C.T. Thangaraj, C. Wu
    UMD, College Park, Maryland
  Funding: This work is funded by US Dept. of Energy grant numbers DE-FG02-94ER40855 and DE-FG02-92ER54178.

The University of Maryland Electron Ring (UMER) is a low energy, high current recirculator for beam physics research. The electron beam current is adjustable from 0.7 mA, an emittance dominated beam, to 100 mA, a strongly space charge dominated beam. UMER is addressing issues in beam physics relevant to many applications that require intense beams of high quality such as advanced concept accelerators, free electron lasers, spallation neutron sources, and future heavy-ion drivers for inertial fusion. The primary focus of this presentation is experimental results and improvements in multi-turn operation of the electron ring. Transport of a low current beam over 100 turns (3600 full lattice periods) has been achieved. Results of high current, space charge dominated multi-turn transport will also be presented.

 
 
TUPAS048 Beam Extraction Concepts and Design for the University of Maryland Electron Ring (UMER) extraction, dipole, quadrupole, electron 1754
 
  • M. Walter
  • G. Bai, B. L. Beaudoin, S. Bernal, D. W. Feldman, T. F. Godlove, I. Haber, R. A. Kishek, P. G. O'Shea, C. Papadopoulos, M. Reiser, D. Stratakis, D. F. Sutter, J. C.T. Thangaraj, C. Wu
    UMD, College Park, Maryland
  Funding: This work is funded by US Dept. of Energy grant numbers DE-FG02-94ER40855 and DE-FG02-92ER54178.

The University of Maryland Electron Ring (UMER) is a low energy, high current recirculator for beam physics research. The electron storage ring has been closed and recent operations have been focused on achieving multi-turn transport. An entire suite of terminal diagnostics is available for time-resolved phase space measurements of the beam. These diagnostics have been mounted and tested at several points on the ring before it was closed. UMER utilizes a unique injection scheme which uses the fringe fields of an offset quadrupole to assist a pulsed dipole in bending the beam into the ring. Similar concepts, along with more traditional electrostatic methods, are being considered for beam extraction. This presentation will focus on the recent efforts to design and deploy these major subsystems required for beam extraction.

 
 
TUPAS060 Particle Simulations of a Linear Proton Dielectric Wall Accelerator simulation, proton, acceleration, focusing 1790
 
  • B. R. Poole
  • D. T. Blackfield, S. D. Nelson
    LLNL, Livermore, California
  Funding: This work was performed under the auspices of the U. S. Department of Energy, the University of California, Lawrence Livermore National Laboratory under Contract No. W-7405-Eng-48.

The dielectric wall accelerator (DWA) is a compact induction accelerator structure that incorporates the accelerating mechanism, pulse forming structure, and switch structure into an integrated module. The DWA consists of stacked stripline Blumlein assemblies, which can provide accelerating gradients in excess of 100 MeV/meter. Blumleins are switched sequentially according to a prescribed acceleration schedule to maintain synchronism with the proton bunch as it accelerates. A finite difference time domain code (FDTD) is used to determine the applied acceleration field to the proton bunch. Particle simulations are used to model the injector as well as the accelerator stack to determine the proton bunch energy distribution, both longitudinal and transverse dynamic focusing, and emittance associated with various DWA configurations.

 
 
TUPAS083 Design and Performance of the Matching Beamline between the BNL EBIS and an RFQ ion, rfq, emittance, quadrupole 1844
 
  • J. G. Alessi
  • E. N. Beebe, J. Brodowski, A. Kponou, M. Okamura, A. I. Pikin, D. Raparia, J. Ritter, L. Snydstrup, V. Zajic
    BNL, Upton, Long Island, New York
  Funding: Work performed under the auspices of the U. S. Department of Energy and the U. S. National Aeronautics and Space Administration.

A part of a new EBIS-based heavy ion preinjector, the low energy beam transport (LEBT) section between the high current EBIS and the RFQ is a challenging design, because it must serve many functions. In addition to the requirement to provide an efficient matching between the EBIS and the RFQ, this line must serve as a fast switchyard, allowing singly charged ions from external sources to be transported into the EBIS trap region, and extracted, highly charged ions to be deflected to off-axis diagnostics (time-of-flight, or emittance). The space charge of the 5-10 mA extracted heavy ion beam is a major consideration in the design, and the space charge force varies for different ion beams having Q/m from 1-0.16. The line includes electrostatic lenses, spherical and parallel-plate deflectors, magnetic solenoid, and diagnostics for measuring current, charge state distributions, emittance, and profile. A prototype of this beamline has been built, and results of tests will be presented.

 
 
TUPAS096 Setup and Performance of the RHIC Injector Accelerators for the 2007 Run with Gold Ions booster, ion, emittance, extraction 1862
 
  • C. J. Gardner
  • L. Ahrens, J. G. Alessi, J. Benjamin, M. Blaskiewicz, J. M. Brennan, K. A. Brown, C. Carlson, W. Fischer, J. Glenn, M. Harvey, T. Hayes, H. Huang, G. J. Marr, J. Morris, F. C. Pilat, T. Roser, F. Severino, K. Smith, D. Steski, P. Thieberger, N. Tsoupas, A. Zaltsman, K. Zeno
    BNL, Upton, Long Island, New York
  Funding: Work performed under the auspices of the US Department of Energy.

Gold ions for the 2007 run of the Relativistic Heavy Ion Collider (RHIC) at Brookhaven National Laboratory (BNL) are accelerated in the Tandem, Booster and AGS prior to injection into RHIC. The setup and performance of this chain of accelerators will be reviewed with a focus on improvements in the quality of beam delivered to RHIC. In particular, more uniform stripping foils between Booster and AGS, and a new bunch merging scheme in AGS promise to provide beam bunches with reduced longitudinal emittance for RHIC.

 
 
TUPAS098 RHIC Beam-Based Sextupole Polarity Verification sextupole, dipole, optics, quadrupole 1868
 
  • Y. Luo
  • P. Cameron, A. Della Penna, T. Satogata, D. Trbojevic
    BNL, Upton, Long Island, New York
  Funding: Work supported by U. S. DOE under contract No DE-AC02-98CH10886.

A beam-based method was proposed and applied to check the polarities of the arc sextupoles in the Relativistic Heavy Ion Collider (RHIC) with repetitive local horizontal bumps. Wrong sextupole polarities can be easily identified from mismatched signs and amplitudes of the horizontal and vertical tune shifts from bump to bump and/or from arc to arc. This check takes less than 2 hours for both RHIC Blue and Yellow rings. Tune shifts in both planes during this study were tracked with a high-resolution baseband tunemeter (BBQ) system. This method was successfully used to the sextupole polarity check in the RHIC run06.

 
 
TUPAS103 RHIC Challenges for Low Energy Operations luminosity, proton, power-supply, electron 1877
 
  • T. Satogata
  • L. Ahrens, M. Bai, J. M. Brennan, D. Bruno, J. J. Butler, K. A. Drees, A. V. Fedotov, W. Fischer, M. Harvey, T. Hayes, W. Jappe, R. C. Lee, W. W. MacKay, G. J. Marr, R. J. Michnoff, B. Oerter, E. Pozdeyev, T. Roser, F. Severino, K. Smith, S. Tepikian, N. Tsoupas
    BNL, Upton, Long Island, New York
  Funding: Work supported by U. S. DOE under contract No DE-AC02-98CH1-886

There is significant interest in RHIC heavy ion collisions at c.m. energies of 5-50 GeV/u, motivated by a search for the QCD phase transition critical point. The low end of this energy range is well below the nominal RHIC injection c.m. energy of 19.6 GeV/u. There are several challenges that face RHIC operations in this regime, including longitudinal acceptance, magnet field quality, lattice control, and luminosity monitoring. We report on the status of work to address these challenges and include results from beam tests of low-energy RHIC operations with protons and gold.

 
 
TUPAS104 Heavy Ion Driver with the Non-Scaling FFAG acceleration, ion, lattice, emittance 1880
 
  • A. G. Ruggiero
  • J. G. Alessi, E. N. Beebe, A. I. Pikin, T. Roser, D. Trbojevic
    BNL, Upton, Long Island, New York
  Funding: Supported by the U. S. Department of Energy under Contract No. DE-AC02-98CH10886. ** Work supported by the U. S. Department of Energy under Contract No. DE-AC02-05CH11231

We explore the possibility of using two non-scaling FFAG with a smaller number of distributed RF cavities for a high power heavy ion driver. The pulsed heavy ion source would consist of an Electron Beam Ion Source (EBIS), fed continuously from a high charge state Electron Cyclotron Resonance (ECR) source. The Radio Frequency Quadrupole (RFQ) and a short 10 MeV/u linac would follow the ion source. Microseconds long heavy ion beam bunches from the EBIS would be injected in a single turn into a multi-pass small aperture non-scaling Fixed Field Alternating Gradient (FFAG) accelerator. The heavy ion maximum kinetic energy is assumed to be 400 MeV/u with a total of 400 kW power for uranium ion beams. Partially stripped heavy ions would be accelerated from 10 MeV/u to 67 MeV/u with a first non-scaling FFAG, while, after further stripping, a second non-scaling FFAG would accelerate from 67 to 400 MeV/u.

 
 
TUPAS107 Proton Beam Emittance Growth at RHIC emittance, electron, proton, luminosity 1886
 
  • S. Y. Zhang
  • V. Ptitsyn
    BNL, Upton, Long Island, New York
  Funding: Work supported by U. S. DOE under contract No DE-AC02-98CH1-886

The beam emittance growth in RHIC polarized proton runs has a dependence on the dynamic pressure rise, which is caused by the electron cloud and peaked at the end of the beam injection and the early energy acceleration. This emittance growth is usually presented without beam instability, and it is slower than the ones above the instability threshold. The effect on the machine luminosity, nevertheless, is significant, and it is currently a limiting factor in machine performance. The electron cloud is substantially reduced at the store, the emittance growth there has no dependence on the bunch spacing and instead it has a clear dependence on the beam-beam parameter. The results of the machine operation and beam studies will be reported.

 
 
WEYKI02 Experimental Demonstration of 1 GeV Energy Gain in a Laser Wakefield Accelerator laser, electron, plasma, simulation 1911
 
  • A. J. Gonsalves
  • D. L. Bruhwiler, J. R. Cary
    Tech-X, Boulder, Colorado
  • E. Cormier-Michel
    University of Nevada, Reno, Reno, Nevada
  • E. Esarey, C. G.R. Geddes, W. Leemans, K. Nakamura, C. B. Schroeder, C. Toth
    LBNL, Berkeley, California
  • S. M. Hooker
    OXFORDphysics, Oxford, Oxon
  GeV-class electron accelerators have a broad range of uses, including synchrotron facilities, free electron lasers, and high-energy particle physics. The accelerating gradient achievable with conventional radio frequency (RF) accelerators is limited by electrical breakdown within the accelerating cavity to a few tens of MeV, so the production of energetic beams requires large, expensive accelerators. One promising technology to reduce the cost and size of these accelerators (and to push the energy frontier for high-energy physics) is the laser-wakefield accelerator (LWFA), since these devices can sustain electric fields of hundreds of GV/m. In this talk, results will be presented on the first demonstration of GeV-class beams using an intense laser beam. Laser pulses with peak power ranging from 10-40TW were guided in a 3.3 cm long gas-filled capillary discharge waveguide, allowing the production of high-quality electron beams with energy up to 1 GeV. The electron beam characteristics and laser guiding, and their dependence on laser and plasma parameters will be discussed and compared to simulations.  
slides icon Slides  
 
WEOBKI01 Stable Electron Beams with Low Absolute Energy Spread from a Laser Wakefield Accelerator with Plasma Density Ramp Controlled Injection laser, plasma, electron, simulation 1916
 
  • C. G.R. Geddes
  • J. R. Cary
    Tech-X, Boulder, Colorado
  • E. Cormier-Michel
    University of Nevada, Reno, Reno, Nevada
  • E. Esarey, W. Leemans, K. Nakamura, D. Panasenko, G. R.D. Plateau, C. B. Schroeder, C. Toth
    LBNL, Berkeley, California
  Funding: Supported by DOE, including grant DE-AC02-05CH11231, DARPA, and by an INCITE computational award.

Laser wakefield accelerators produce accelerating gradients up to hundreds of GeV/m and narrow energy spread, and have recently demonstrated energies up to GeV and improved stability [*,**] using electrons self trapped from the plasma. Controlled injection and staging can further improve beam quality by circumventing tradeoffs between energy, stability, and energy spread/emittance. We present experiments demonstrating production of a stable electron beam near 1 MeV with 100 keV level energy spread and central energy stability by using the plasma density profile to control self injection, and supporting simulations. A 10 TW laser pulse was focused near the downstream edge of a mm-long hydrogen gas jet. The plasma density near focus is decreasing in the laser propagation direction, which changes the wake phase velocity and reduces the trapping threshold. This allows stable self trapping and low absolute energy spread. Simulations indicate that such beams can be post accelerated to form high energy, high quality, stable beams, and experiments are under investigation.

* Geddes et al, Nature v431 no7008, 538 (2004).** Leemans et al, Nature Physics v2 no10, p696 (2006)

 
slides icon Slides  
 
WEOCKI04 Longitudinal Momentum Mining of Antiprotons at the Fermilab Recycler: Past, Present, and Future antiproton, emittance, luminosity, collider 1941
 
  • C. M. Bhat
  • B. Chase, C. Gattuso, P. W. Joireman
    Fermilab, Batavia, Illinois
  Funding: Operated by Universities Research Association, Inc. for the U. S. Department of Energy under contract DE-AC02-76CH03000.

The Recycler is the primary antiproton repository for the Tevatron collider at Fermilab. Stored antiproton beam intensity has been steadily increased to about 450·1010 over the last three years. We have used the technique of longitudinal momentum mining* in the Recycler to extract constant intensity and constant longitudinal emittance antiproton bunches for collider operation since early 2005. Since then, the Recycler has played a critical role in the luminosity performance of the Tevatron; the peak proton-antiproton luminosity has been raised by a factor of about three and a world record luminosity of 2.31·1032cm-2s-1 has been achieved. Recently, many improvements have been implemented in the antiproton mining and stacking schemes used in the Recycler to handle higher intensity beam. In this paper we discuss morphing during antiproton stacking, reducing longitudinal emittance dilution, and use of soft mining buckets to maintain low peak density and control the beam instability during mining. In addition we present past and current performance of mining and beam stacking RF manipulations.

* C. M. Bhat, Phys. Letts. A Vol. 330 (2004), p 481

 
slides icon Slides  
 
WEZAB02 Results on CLIC Proof of Principle from CTF3 linac, collider, extraction, beam-loading 1979
 
  • R. Corsini
  The CLIC Test Facility CTF3, built at CERN by an international collaboration, aims at demonstrating the feasibility of the CLIC scheme of Multi-TeV electron-positron collider by 2010. In its final configuration CTF3 will consist of a 150 MeV drive beam linac followed by a 42 m long delay loop and an 84 m combiner ring. The installation includes a two-beam test stand and a test decelerator. The linac and delay loop have been already commissioned, while the combiner ring will be completed by the first half of 2007. High gradient testing of accelerating structures is also under way. The status of the facility, the experimental results obtained and the future plans will be presented.  
slides icon Slides  
 
WEOAC03 Transverse Impedance of LHC Collimators impedance, octupole, collimation, insertion 2003
 
  • E. Metral
  • G. Arduini, R. W. Assmann, A. Boccardi, T. Bohl, C. B. Bracco, F. Caspers, M. Gasior, O. R. Jones, K. K. Kasinski, T. Kroyer, S. Redaelli, G. Robert-Demolaize, G. Rumolo, R. J. Steinhagen, Th. Weiler, F. Zimmermann
    CERN, Geneva
  • F. Roncarolo
    UMAN, Manchester
  • B. Salvant
    EPFL, Lausanne
  The transverse impedance in the LHC is expected to be dominated by the numerous collimators, most of which are made of Fibre-Reinforced-Carbon to withstand the impacts of high intensity proton beams in case of failures, and which will be moved very close to the beam, with full gaps of few millimetres, in order to protect surrounding super-conducting equipments. We present an estimate of the transverse resistive-wall impedance of the LHC collimators, the total impedance in the LHC at injection and top energy, the induced coupled-bunch growth rates and tune shifts, and finally the result of the comparison of the theoretical predictions with measurements performed in 2004 and 2006 on a prototype collimator installed in the SPS.  
slides icon Slides  
 
WEPMN004 Operation of the SOLEIL RF Systems feedback, controls, cryogenics, booster 2050
 
  • P. Marchand
  • P. Bosland, P. Bredy
    CEA, Gif-sur-Yvette
  • H. D. Dias, M. D. Diop, M. E. El Ajjouri, J. L. Labelle, R. L. Lopes, M. Louvet, C. M. Monnot, F. Ribeiro, T. Ruan, R. Sreedharan, K. Tavakoli, C. G. Thomas-Madec
    SOLEIL, Gif-sur-Yvette
  The 352 MHz RF accelerating systems for the SOLEIL Booster (BO) and Storage Ring (SR) have been commissioned. In the BO, a 5-cell copper cavity of the CERN-LEP type is powered with a 35 kW solid state amplifier. In the SR, the required RF accelerating voltage (up to 4.4 MV) and power (650 kW at full beam current of 500 mA) will be provided by two cryomodules, each containing a pair of superconducting cavities, specifically designed for SOLEIL. The parasitic impedances of the high order modes are strongly attenuated by means of four coaxial couplers, located on the tube connecting the two cavities. The first cryomodule is operational, while the second one, which is being constructed by ACCEL (Germany), will be implemented beginning of 2008. Both cryomodules will be cooled down with liquid helium from a single 350 W liquefier and each cavity is powered with a 190 kW solid state amplifier. With the first cryomodule and two amplifiers in operation, the first year objective of storing 300 mA was successfully achieved. The RF system commissioning and operation results are reported.  
 
WEPMN038 Development of the Beam Chopper Timing System for Multi-Turn Injection to the J-PARC RCS linac, controls, extraction, synchrotron 2125
 
  • F. Tamura
  • S. Anami, E. Ezura, K. Hara, C. Ohmori, A. Takagi, M. Toda, M. Yoshii
    KEK, Ibaraki
  • K. Hasegawa, M. Nomura, A. Schnase, M. Yamamoto
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
  Multi-turn injection using charge exchange is employed for the J-PARC Rapid Cycling Synchrotron (RCS). To improve the bunching factor of the beam in the ring, the momentum offset injection scheme is used. In each turn, the bunch trains from the linac are injected into the RF buckets with a momentum offset. The bunch train is called the "intermediate pulse". The intermediate pulses are generated in the low energy section of the linac by the RF chopper and pre-chopper. Since the pulse must be synchronized to the RF voltage in the ring, the timing signals for the choppers are generated by the low-level RF (LLRF) system of the RCS and the signals are sent to the chopper control. The RF chopper and the pre-choppers require different pulse widths. Thanks to the direct digital synthesis (DDS) in the LLRF system, precise zero-cross signals for the reference of the chopper pulses are generated without difficulties. The cable route from the RCS LLRF system to the linac chopper control system is more than one kilometer. Thus, the chopper pulses are sent via optical cables. We developed the chopper timing module. We describe the details of the hardware and the preliminary test results.  
 
WEPMN044 The Pulsed Power Supply using IGBT Topology for CSNS Injection System Bump Magnet power-supply, controls, simulation, pulsed-power 2140
 
  • L. Shen
  • Y. L. Chi, C. Huang
    IHEP Beijing, Beijing
  The China Spallation Neutron Source (CSNS) Rapid Cycling Synchrotron(RCS) injection system needs three pulsed power supplies to drive twelve bump magnets. The current of the three pulsed power supplies are 11813A,9706A,8205A. Two of the pulsed power supplies work in controlled method at falling edge. This paper introduces the design of the three pulsed power supplies, the circuit simulation results and the demonstration of power supplies stability.  
 
WEPMN069 Low Power Measurements on an AGS Injection Kicker Magnet kicker, impedance, proton, simulation 2188
 
  • M. J. Barnes
  • G. D. Wait
    TRIUMF, Vancouver
  Funding: Work supported by a contribution from the Canada Foundation for Innovation.

The present AGS injection kickers at A5 location were designed for 1.5 GeV proton injection. Recent high intensity runs have pushed the transfer kinetic energy to 1.94 GeV, but with an imperfect matching in transverse phase space. Space charge forces result in both fast and slow beam size growth and beam loss as the size exceeds the AGS aperture. An increase in the AGS injection energy to 2 GeV with adequate kick strength would greatly reduce the beam losses making it possible to increase the intensity from 70 TP (70 * 1012 protons/s) to 100 TP. R&D studies* have been undertaken by TRIUMF, in collaboration with BNL, to design two new kicker magnets for the AGS A10 location to provide an additional kick of 1.5 mrad to 2 GeV protons. TRIUMF has designed and built a prototype 12.5 Ω transmission line kicker magnet with rise and fall times of 100 ns, 3% to 97% and field uniformity of (±)1% over 85% of the aperture, powered by matched 12.5 Ω pulse-forming lines. This paper describes the results of detailed capacitance and inductance measurements, on the prototype magnet, and compares these with predictions from 2D and 3D electromagnetic simulations.

*L. Ahrens, R. B. Armenta, M. J. Barnes, E. W Blackmore, C. J. Gardner, O. Hadary, G. D. Wait, W. Zhang, "Design Concept for AGS Injection Kicker Upgrade to 2 GeV", PAC 2005, Knoxville Tennessee.

 
 
WEPMN088 The IPNS Second Harmonic RF Upgrade acceleration, controls, extraction, proton 2233
 
  • M. E. Middendorf
  • F. R. Brumwell, J. C. Dooling, D. Horan, R. Kustom, M. K. Lien, G. E. McMichael, M. R. Moser, A. Nassiri, S. Wang
    ANL, Argonne, Illinois
  Funding: This work is supported by the U. S. Department of Energy under contract no. W-31-109-ENG-38.

The Intense Pulsed Neutron Source (IPNS) rapid cycling synchrotron (RCS) is used to accelerate protons from 50 MeV to 450 MeV, at a repetition rate of 30 Hz. The original ring design included two identical RF systems, each consisting of an accelerating cavity, cavity bias supply, power amplifiers and low level analog electronics. The original cavities are located 180 degrees apart in the ring, and provide a total peak accelerating voltage of ~21 kV over the 2.21 MHz to 5.14 MHz revolution frequency sweep. A third RF system has been constructed and installed in the RCS. The third RF system is capable of operating at the fundamental revolution frequency for the entire acceleration cycle, providing an additional peak accelerating voltage of up to ~11kV, or at the second harmonic of the revolution frequency for the first ~4 ms of the acceleration cycle, providing an additional peak voltage of up to ~11kV for bunch shape control, resulting in a modest increase in bunch length. We describe here to date, the hardware implementation and operation of the third RF cavity in the second harmonic mode.

 
 
WEPMN101 Coupling Interaction Between the Power Coupler and the Third Harmonic Superconducting Cavity coupling, klystron, beam-loading, cryogenics 2268
 
  • J. Li
  • N. Solyak
    Fermilab, Batavia, Illinois
  • T. Wong
    Illinois Institute of Technology, Chicago, Illinois
  Funding: U. S. Department of Energy

Fermilab has developed a third harmonic superconducting cavity operating at the frequency of 3.9 GHz to improve the beam performance for the FLASH user facility at DESY. It is interesting to investigate the coupling interaction between the SRF cavity and the power coupler with or without beam loading. The coupling of the power coupler to the cavity needs to be determined to minimize the power consumption and guarantee the best performance for a given beam current. In this paper, we build and analyze an equivalent circuit model containing a series of lumped elements to represent the resonant system. An analytic solution of the required power from the generator as a function of the system parameters has also been given based on a vector diagram.

 
 
WEPMS023 Progress on New High Power RF System for LANSCE DTL power-supply, linac, impedance, controls 2382
 
  • J. T.M. Lyles
  • S. Archuletta, D. Baca, J. Davis, D. Rees, P. A. Torrez
    LANL, Los Alamos, New Mexico
  Funding: Work supported by the United States Department of Energy, National Nuclear Security Agency, under contract DE-AC52-06NA25396

A new 200 MHz RF system is being developed for the LANSCE proton drift tube linac (DTL). A planned upgrade will replace parts of the DTL RF system with new generation components. When installed for the LANSCE-R project, the new system will reduce the total number of electron power tubes from twenty-four to seven in the DTL plant. The 3.4 MW final power amplifier will use a Thales TH628 Diacrode. This state-of-the-art device eliminates the large anode modulator of the present triode system, and will be driven by a new tetrode intermediate power amplifier. In this mode of operation, this intermediate stage will provide 150 kW of peak power. The first DTL tank requires up to 400 kW of RF power, which will be provided by the same tetrode driver amplifier. A prototype system is being constructed to test components, using some of the infrastructure from previous RF projects. High voltage DC power became available through innovative re-engineering of an installed system. A summary of the design and construction of the intermediate power amplifier will be presented and test results will be summarized.

 
 
WEPMS091 Conceptual Design of the NSLS-II RF Systems damping, lattice, wiggler, booster 2550
 
  • J. Rose
  • A. Blednykh, W. Guo, P. Mortazavi, N. A. Towne
    BNL, Upton, Long Island, New York
  RF system requirements are derived from machine parameters and beam stability specifications. The conceptual design of the RF system for NSLS-II to meet these requirements is presented, consisting of 500 MHz superconducting main cavities, 1500 MHz SCRF harmonic cavities for bunch lengthening, and the RF power and cryogenic systems.  
 
THXAB03 Commissioning of the Spallation Neutron Source Accelerator Systems linac, target, coupling, beam-losses 2603
 
  • M. A. Plum
  Funding: ORNL/SNS is managed by UT-Battelle, LLC, for the U. S. Department of Energy under contract DE-AC05-00OR22725.

The Spallation Neutron Source accelerator complex consists of a 2.5 MeV H- front-end injector system, a 186 MeV normal-conducting linear accelerator, a 1 GeV superconducting linear accelerator, an accumulator ring, and associated beam transport lines. The linac was commissioned in five discrete runs, starting in 2002 and completed in 2005. The accumulator ring and associated beam transport lines were commissioned in two runs in February and April 2006. With the completed commissioning of the SNS accelerator, the facility has begun initial low-power operations. In the course of beam commissioning, most beam performance parameters and beam intensity goals have been achieved at low duty factor. A number of beam dynamics measurements have been performed, including emittance evolution, transverse coupling in the ring, beam instability thresholds, and beam distributions on the target. The commissioning results, achieved beam performance and initial operating experience of the SNS will be presented.

 
slides icon Slides  
 
THOBAB01 EMMA - the World's First Non-scaling FFAG acceleration, extraction, diagnostics, factory 2624
 
  • T. R. Edgecock
  EMMA - the Electron Model of Muon Acceleration - is to be built at the CCLRC Daresbury Laboratory in the UK. It will demonstrate the principle of non-scaling FFAGs and be used to study the features of this type of accelerator in detail. Although a model of the muon accelerators in a Neutrino Factory, EMMA will have sufficient flexibility to study a variety of applications. It has been designed by an international collaboration of accelerator physicists and will be built as part of the CONFORM project using funds recently approved in the UK.  
slides icon Slides  
 
THPMN004 A Synchrotron Based Particle Therapy Accelerator synchrotron, vacuum, extraction, quadrupole 2713
 
  • S. P. Møller
  • T. Andersen, F. Bødker, A. Baurichter, P. A. Elkiaer, C. E. Hansen, N. Hauge, T. Holst, I. Jensen, L. K. Kruse, S. M. Madsen, M. Sager, S. V. Weber
    Danfysik A/S, Jyllinge
  • K. Blasche
    BTE Heidelberg, Ingeniurburo, Schriesheim
  • B. Franczak
    GSI, Darmstadt
  Danfysik and Siemens have entered a cooperation to market and build Particle Therapy* systems for cancer therapy. The accelerators will consist of an injector (7 MeV/u proton and light ions), a compact and simple synchrotron and a choice of fixed-angle horizontal and semi-vertical beamlines together with gantry systems. The optimized lattice configuration, including the design of injection and extraction systems, provides large transverse phase space acceptance with minimum magnet apertures. The resulting synchrotron will have light magnets, low values of peak power for pulsed operation and minimum dc power consumption. The beam can be accelerated to the maximum magnetic rigidity of 6.6 Tm in less than 1 s. A beam of 48-250 MeV protons and 88-430 MeV/u carbon ions can be slowly extracted during up to 10s. The intensity for protons and carbon ions will be well beyond the needs of scanning beam applications. The design and performance specs of the synchrotron will be described in detail including simulations. Design and manufacture of the subsystems are in progress. *Particle Therapy is a work in progress and requires country-specific regulatory approval prior to clinical use.  
 
THPMN008 Evaluation of Luminosity Reduction in the ILC Head-on Scheme from Parasitic Collisions luminosity, simulation, beam-beam-effects, extraction 2722
 
  • J. Brossard
  • M. Alabau
    IFIC, Valencia
  • D. A.-K. Angal-Kalinin
    STFC/DL/ASTeC, Daresbury, Warrington, Cheshire
  • P. Bambade, T. Derrien
    LAL, Orsay
  • O. Napoly, J. Payet
    CEA, Gif-sur-Yvette
  An interaction region with head-on collisions is being developed for the ILC as an alternative to the base line 14 mrad crossing angle design, motivated by simpler beam manipulations upstream of the interaction point and a more favourable configuration for the detector and physics analysis. The design of the post-collision beam line in this scheme involves however a number of technological challenges, one of which is the strength requirement for the electrostatic separators placed immediately after the final doublet to extract the spent beam. In this paper, we examine in detail the main mechanism behind this requirement, the multi-beam kink instability, which results from the long-range beam-beam forces at the parasitic crossings after the bunches have been extracted. Our analysis uses realistic bunch distributions, the Guinea-Pig program to treat beam-beam effects at the interaction point and the DIMAD program to track the disrupted beam distributions in the post-collision beam line. A version of the beam-beam deflection based interaction point feedback system with an improved filtering algorithm is also studied to mitigate the luminosity deterioration from the instability.  
 
THPMN039 Femtosecond Electron Beam Dynamics in Photocathode Accelerator electron, gun, laser, emittance 2805
 
  • J. Yang
  • K. Kan, T. Kondoh, Y. Yoshida
    ISIR, Osaka
  Ultrashort electron beams, of the order of 100 fs, are essential to reveal the hidden dynamics of intricate molecular and atomic processes in nanofabrication through experimentation such as time-resolved electron diffraction and femto-chemistry. The transverse and longitudinal dynamics of ultrashort electron beam in a photocathode linear accelerator were studied for femtosecond electron beam generation. The emittance growth and bunch length increase due to the rf and the space charge effects in the rf gun were investigated with the laser injection phase. The dependences of the emittance, bunch length and energy spread on the bunch charge were measured experimentally and compared with the theoretical simulation. The increase of the bunch length due to the space charge effect was also investigated during the bunch compression in magnetic field.  
 
THPMN046 Conceptual Design of the PEFP Rapid Cycling Synchrotron extraction, lattice, proton, synchrotron 2817
 
  • B. Chung
  • Y.-S. Cho
    KAERI, Daejon
  • Y. Y. Lee
    BNL, Upton, Long Island, New York
  Funding: *This work was supported by the 21C Frontier R&D program sponsored by Ministry of Science and Technology, Korean Government

The Proton Engineering Frontier Project (PEFP) is a research project to develop a 100 MeV, 20 mA pulsed proton linear accelerator to be used in basic/applied scientific R&D programs and industrial applications. The PEFP proposes the 1.0 GeV synchrotron accelerator as an extension of the PEFP linac, which is a 30 Hz rapid-cycling synchrotron (RCS) with the injection energy of 100 MeV. The target beam power is 87 kW at 1.0GeV in the first stage. The high intensity RCS is one of the important challenges for the spallation neutron source. The conceptual lattice design of the RCS as well as the simulations of an injection system is described in this paper.

 
 
THPMN063 CTF3 Combiner Ring Commissioning optics, quadrupole, linac, collider 2850
 
  • F. Tecker
  • C. Biscari, A. Ghigo
    INFN/LNF, Frascati (Roma)
  • E. Bressi
    CNAO Foundation, Milan
  • R. Corsini, S. Doebert, P. K. Skowronski, P. Urschutz
    CERN, Geneva
  • A. Ferrari
    UU/ISV, Uppsala
  CLIC Test Facility 3 (CTF3) has the objective to demonstrate the remaining feasibility issues of the CLIC two-beam technology for a future multi-TeV linear collider. One key issue is the efficient generation of a very high current 'drive beam' that serves as the power source for the acceleration of the main beam to high energy. This large current beam is produced by interleaving bunches in a combiner ring using transverse deflecting RF cavities. The 84 m long CTF3 combiner ring and the connecting transfer line have been recently installed and put into operation. The latest commissioning results will be presented.  
 
THPMN082 Beam Injection Into EMMA Non-scaling FFAG kicker, septum, extraction, acceleration 2898
 
  • T. Yokoi
  • S. Machida
    STFC/RAL/ASTeC, Chilton, Didcot, Oxon
  FFAG accelerators have been getting attention as promising candidates for the muon accelerators of a neutrino factory due to their large transverse acceptance and the capability of fast particle acceleration. Non-scaling FFAGs, which are a variation of FFAGs, are nowadays being intensively studied for their simple structure and operational flexibility. To demonstrate the technical feasibility of non-scaling FFAGs and to investigate their beam dynamics, a project to construct a small electron non-scaling FFAG (EMMA) has been proposed in the UK. In EMMA the injection and extraction energies must be arbitrarily changed for a beam with emittance of 3 mm to study the beam dynamics in detail for the entire range of operating energy. In addition, in the planned machine the betatron tunes vary more than a factor of two during acceleration. The requirement of variable injection or extraction energy requires careful optimisation of the of injection elements and operational conditions. The details and design status of the scheme will be described in this paper.  
 
THPMN104 Recent Studies of Dispersion Matched Steering for the ILC Bunch Compressor and Main Linac emittance, linac, quadrupole, alignment 2954
 
  • P. Lebrun
  • L. Michelotti, J.-F. Ostiguy
    Fermilab, Batavia, Illinois
  Beam Based Alignment techniques are expected to play a critical role to the emittance preservation for the ILC. The Dispersion Free Steering (DFS) method is studied in detail in the 2nd statge of the bunch Compressor and in the beginning of the curved Main Linac. It is shown than in absence of cavity tilts (rotations on the YZ plane), DMS provides a unique and stable solution with negligible emittance growth. If cavity tilts are about 200 to 300 micro-radiant, the DMS solution is no longer unique and significant emittance occurs as well. While within the ILC budget, other dynamical effects, such a large beam jitter or sudden ground motion will cause severe performance degradation. A Variant of the DFS algorithm can be used to re-aling cavity supports, leading to better LET performance. In presence of perturbations (klystron jitter, ground motion,.. ) such DFS solutions are easier to maintain and improved if they are stable and unique. Therefore, it is suggested to consider using movers on quadrupole/BPM and, a bit more controversial, for the support system of the r.f. cavities, especially at low energy, where spurious dispersion due to cavity tilts are large.  
 
THPMN112 Colliding Pulse Injection Experiments in Non-Collinear Geometry for Controlled Laser Plasma Wakefield Acceleration of Electrons plasma, electron, laser, collider 2975
 
  • C. Toth
  • D. L. Bruhwiler, J. R. Cary
    Tech-X, Boulder, Colorado
  • E. Esarey, C. G.R. Geddes, W. Leemans, K. Nakamura, D. Panasenko, C. B. Schroeder
    LBNL, Berkeley, California
  Funding: Supported by DOE grant DE-AC02-05CH11231, DARPA, and and INCITE computational grant.

Colliding laser pulses* have been proposed as a method for controlling injection of electrons into a laser wakefield accelerator (LWFA) and hence producing high quality relativistic electron beams with energy spread below 1% and normalized emittances below 1 micron. The original proposal relied on three coaxial pulsesI. One pulse excites a plasma wake, and a collinear pulse following behind it collides with a counterpropagating pulse forming a beat pattern that boosts background electrons into accelerating phase. A variation of this method uses only two laser pulses** which may be non-collinear. The first pulse drives the wake, and beating of the trailing edge of this pulse with the colliding pulse injects electrons. Non-collinear injection avoids optical elements on the electron beam path (avoiding emittance growth). We report on progress of non-collinear experiments at LBNL, using the Ti:Sapphire laser at the LOASIS facility of LBNL. Preliminary results indicate that electron beam properties are affected by the second beam. Details of the experiment will be presented.

* E. Esarey, et al, Phys. Rev. Lett 79, 2682 (1997).** G. Fubiani, Phys. Rev. E 70, 016402 (2004).

 
 
THPMN114 Recent Progress at LBNL on Characterization of Laser Wakefield Accelerated Electron Bunches Using Coherent Transition Radiation electron, plasma, radiation, laser 2981
 
  • W. Leemans
  • E. Esarey, C. G.R. Geddes, N. H. Matlis, G. R.D. Plateau, C. B. Schroeder, C. Toth, J. Van Tilborg
    LBNL, Berkeley, California
  Funding: Work supported by US DoE Office of High Energy Physics under contract DE-AC03-76SF0098 and DARPA.

At LBNL, laser wakefield accelerators (LWFA) now produce ultra-short electron bunches with energies up to 1 GeV[1]. As femtosecond electron bunches exit the plasma they radiate a strong burst in the terahertz range[2,3], via coherent transition radiation (CTR). Measuring the CTR properties allows non-invasive bunch-length diagnostics[4], a key to continuing rapid advance in LWFA technology. In addition, this method of CTR generation provides very high peak power that can lead novel THz-based applications. Experimental bunch length characterizations through electro-optic sampling as well as bolometric analysis are presented. Measurements demonstrate both the shot-by-shot stability of bunch parameters, and femtosecond synchronization between bunch, THz pulse, and laser beam.

[1] W. P. Leemans et al., Nature Physics 2, 696(2006)[2] W. P. Leemans et al., PRL 91, 074802(2003)[3] C. B. Schroeder et al., PRE 69, 016501(2004)[4] J. van Tilborg et al., PRL 96, 014801(2006)

 
 
THPMN115 Injection and Extraction Lines for the ILC Damping Rings quadrupole, damping, extraction, kicker 2984
 
  • I. Reichel
  Funding: This work was supported by the U. S. Department of Energy under Contract No. DE-AC02-05CH11231.

The current design for the injection and extraction lines into and out of the ILC Damping Rings is presented as well as the design for the abort line. Due to changes of the geometric boundary conditions by other subsystems of the ILC a modular approach has been used to be able to respond to recurring layout changes while reusing previously designed parts. Available beam dynamics studies for those lines are discussed.

 
 
THPMS018 High Average Current Betatrons for Industrial and Security Applications betatron, acceleration, focusing, electron 3035
 
  • S. Boucher
  • R. B. Agustsson, P. Frigola, A. Y. Murokh, M. Ruelas
    RadiaBeam, Los Angeles, California
  • F. H. O'Shea, J. B. Rosenzweig, G. Travish
    UCLA, Los Angeles, California
  Funding: DOE Grant DE-FG02-04ER84051

The fixed-field alternating-gradient (FFAG) betatron has emerged as a viable alternative to RF linacs as a source of high-energy radiation for industrial and security applications. For industrial applications, high average currents at modest relativistic electron beam energies, typically in the 5 to 10 MeV range, are desired for medical product sterilization, food irradiation and materials processing. For security applications, high power x-rays in the 3 to 20 MeV range are needed for rapid screening of cargo containers and vehicles. In a FFAG betatron, high-power output is possible due to high duty factor and fast acceleration cycle: electrons are injected and accelerated in a quasi-CW mode while being confined and focused in the fixed-field alternating-gradient lattice. The beam is accelerated via magnetic induction from a betatron core made with modern low-loss magnetic materials. Here we present the design and status of a prototype FFAG betatron, called the Radiatron, as well as future prospects for these machines.

 
 
THPMS023 Designing LWFA in the Blowout Regime laser, plasma, electron, acceleration 3050
 
  • W. Lu
  • S. Fonseca, L. O. Silva, J. H. Vieira
    Instituto Superior Tecnico, Lisbon
  • C. Joshi, W. B. Mori, F. S. Tsung, M. Tzoufras
    UCLA, Los Angeles, California
  Funding: This work was supported by DOE and NSF under grant Nos. DE-FG03-92ER40727, DE-FC02-01ER41179, DE-FG02-03ER54721, and NSF-Phy-0321345.

The extraordinary ability of space-charge waves in plasmas to accelerate charged particles at gradients that are orders of magnitude greater than that in current accelerators has been well documented. We develop a phenomenological framework for Laser Wakefield Acceleration (LWFA) in the 3D nonlinear regime, in which the plasma electrons are expelled by the radiation pressure of a short pulse laser, leading to nearly complete blowout. This theory provides a recipe for designing a LWFA for given laser and plasma parameters and estimates the number and the energy of the accelerated electrons whether self-injected or externally injected. These formulas apply for self-guided as well as externally guided pulses (e.g. by plasma channels). Based on this theory, we will present scenarios on how to build a single stage accelerator with output energies from GeV to TeV. Particle-In-Cell (PIC) simulations are used to verify our theory. This work was supported by DOE and NSF under grant Nos. DE-FG03-92ER40727, DE-FC02-01ER41179, DE-FG02-03ER54721, and NSF-Phy-0321345.

 
 
THPMS039 Wakefield Effects in the Beam Delivery System of the ILC emittance, vacuum, focusing, simulation 3088
 
  • K. L.F. Bane
  • A. Seryi
    SLAC, Menlo Park, California
  Funding: Work supported by US Department of Energy contract DE-AC02-76SF00515

The main linac of the International Linear Collider (ILC) accelerates short, high peak current bunches into the Beam Deliver System (BDS) on the way to the interaction point. In the BDS wakefields are excited by the resistance of the beam pipe walls and by beam pipe transitions that will tend to degrade the emittance of the beam bunches. In this report we calculate the effect on emittance of incoming jitter or drift, and of misalignments of the beam pipes with respect to the beam axis, both analytically and through multi-particle tracking. Finally, we discuss ways of ameliorating the wake effects in the BDS.

 
 
THPMS093 Muon Acceleration with the Racetrack FFAG acceleration, extraction, lattice, betatron 3202
 
  • D. Trbojevic
  Funding: Supported by the U. S. Department of Energy under Contract No. DE-AC02-98CH10886.

Muon acceleration for muon collider or neutrino factory is still in the stage where further improvements are likely as a result of further study. This report presents a design of the racetrack non-scaling Fixed Field Alternating Gradient (NS-FFAG) accelerator to allow fast muon acceleration in small number of turns. The racetrack design is made of four arcs: two arcs at opposite sides have a smaller radius and are made of closely packed combined function magnets, while two additional arcs with a very large radius are used for muon extraction, injection, and RF accelerating cavities. The ends of the large radii arcs are geometrically matched at the connections to the arcs with smaller radii. The dispersion and both horizontal and vertical amplitude functions are matched at the central energy.

 
 
THPMS097 Laser Plasma Acceleration Experiment at the Naval Research Laboratory electron, laser, plasma, acceleration 3214
 
  • D. Kaganovich
  • D. F. Gordon, A. Ting
    NRL, Washington, DC
  The traditional long term strategy for producing high quality electron beams in a single stage LWFA involves three elements: operation in the resonant or standard regime, the use of optical guiding to extend the acceleration region, and external injection of a precisely-phased, high quality injection electron bunch. The standard regime and optical guiding has been studied by many research groups and promise good results for the acceleration. The creation of the electron beam for external injection is still a very problematic issue. Recently, quasi-monoenergetic acceleration of particles from the background plasma has been observed in simulations and experiments operating in a shorter pulse regime. Such quasi-monoenergetic electrons could be a candidate for injection into a following stage of standard LWFA. We are in the initial stage of experiments to generate injection electrons using the HD-LIPA schemes with a 10 TW 50 fs laser system. The second stage accelerator is a capillary discharge plasma channel for extended acceleration distance. Preliminary results, including statistics on the stability of quasi-monoenergetic acceleration, will be presented.  
 
THPAN002 A Self-Consistent Model for Emittance Growth of Mismatched Charged Particle Beams in Linear Accelerators emittance, simulation, focusing, plasma 3220
 
  • R. P. Nunes
  • R. Pakter, F. B. Rizzato
    IF-UFRGS, Porto Alegre
  Funding: CNPq, Brazil

The goal of this work is to analyze the envelope dynamics of magnetically focused and high-intensity charged particle beams. As known, beams with mismatched envelopes decay into its equilibrium state with a simultaneous increasing of emittance. This emittance growth implies that, in the stationary regime, the transverse phase-space of the beam is characterized by a tenuous population of hot particles around a dense population of cold particles. To describe this emittance growth, it was used the test-particle approach for the development of a simplified self-consistent macroscopic model, whose self-consistency is a result of the inclusion of the emittance growth into the envelope equation. The model is then compared with full N-particle beam simulations and the agreement is shown to be quite reasonable. The model revealed to be useful to understand the physical aspects of the problem and is computationally faster when compared with full simulations.

 
 
THPAN038 Generation and Acceleration of High Brightness Electron Bunch Train in ATF of KEK electron, beam-loading, gun, laser 3312
 
  • S. Liu
  • S. Araki, M. K. Fukuda, M. Takano, N. Terunuma, J. Urakawa
    KEK, Ibaraki
  • K. Hirano
    NIRS, Chiba-shi
  Laser Undulator Compact X-ray source (LUCX) is a test bench for compact high brightness X-ray generator at KEK in order to demonstrate the possibility on K-edge digital subtraction angiography, based on the Compton Scattering. For this project, one of the challenging problems is to generate and accelerate high brightness multi-bunch electron beams, compensating the energy difference due to beam loading effect. In this paper, we calculate the transient beam loading voltage and energy gain from RF field in standing wave gun cavity and traveling wave accelerating tube for multi-bunch train, considering the process of propagation, buildup of RF field in them and the special RF pulse shape. We generated and accelerated 100 bunch electron beam train with 50nC, which beam loading effect was compensated effectively by adjusting the laser injection timing. By BPM and OTR system, we measured the electron beam energy bunch by bunch. The average energy of 100 bunch train is 40.5MeV and maximum energy difference bunch to bunch is 0.26MeV, the relative energy spread of single bunch is about 0.13%. The transverse emittance can be optimized roughly to 3.6 pimm.mrad.  
 
THPAN039 Space Charge Effects for JPARC Main Ring resonance, sextupole, space-charge, acceleration 3315
 
  • A. Y. Molodozhentsev
  • T. Koseki, M. Tomizawa
    KEK, Ibaraki
  The JPARC Main Ring should provide the beam power up to 0.8MW at the maximum energy of 50GeV. According to the basic operation scenario during the injection period 8 bunches with the maximum bunch power up to 100kW should be created around the ring. In frame of this report we present the space charge effects in combination with the nonlinear resonances, caused by the machine imperfection, for different beam intensities and different machine operation scenario, including the Main Ring RF system, the collimator system of the RCS-MR beam line and the MR collimation system. The measured field data for main magnets of the ring has been taken into account for this study.  
 
THPAN063 Analytic Description of the Phase Slip Effect in Race-Track Microtrons electron, longitudinal-dynamics, microtron, synchrotron 3369
 
  • Yu. A. Kubyshin
  • A. V. Poseryaev, V. I. Shvedunov
    MSU, Moscow
  • J. P. Rigla
    UPC, Barcelona
  Design of modern race-track microtrons (RTMs) requires better understanding of the longitudinal beam dynamics in these machines, in particular of the phase slip effect which is important for low energy beams. We generalize an analytical approach for the description of the synchronous particle motion and synchrotron oscillations, developed in our previous papers, by including the fringe fields of the RTM end magnets. Explicit, though approximate, formulas are derived and an algorithm for improving their accuracy is formulated. The efficiency of the analytic description is checked numerically, in particular by tracking simulations using the RTMTRace code. Explicit examples of low energy injection schemes and applications of this formalism for the injection phase fixing are given.  
 
THPAN093 Booster Requirements for Advanced Photon Source 1-nm Emittance Upgrade Lattices lattice, booster, emittance, simulation 3438
 
  • N. Sereno
  • M. Borland
    ANL, Argonne, Illinois
  Funding: Work supported by the U. S. Department of Energy, Office of Science, Office of Basic Energy Sciences, under Contract No. DE-AC02-06CH11357

In recent years, we have explored various upgrade options for the Advanced Photon Source (APS) storage ring that would provide the user community higher brightness. Increased brightness would be accomplished by reducing the emittance of the storage ring as well as increasing the stored beam current from 100 mA to 200 mA. Two upgrade lattices were developed that reduce the effective beam emittance to 1 nm from the present 2.7 nm. These lattices have reduced dynamic aperture compared to the present ring lattice, which may require a reduced emittance booster to minimize injection losses. This paper describes injection tracking simulations that explore how high the booster emittance can be and still have no losses at injection for the 1-nm ring upgrade lattices. An alternative booster lattice is presented with reduced emittance compared to the present booster lattice (65 nm). The proposed low-emittance booster lattice would add pole-face windings to the existing booster dipoles and hence would not require replacement of the existing booster magnets.

 
 
THPAN097 International Linear Collider Damping Ring Lattice Design lattice, damping, dynamic-aperture, emittance 3450
 
  • A. Xiao
  • L. Emery
    ANL, Argonne, Illinois
  Funding: Work supported by the U. S. Department of Energy, Office of Science, Office of Basic Energy Sciences, under Contract No. DE-AC02-06CH11357.

We present a lattice design based on the theoretical-minimum-emittance (TME) cell for the International Linear Collider (ILC0 6.6-km 5-GeV damping ring. Several areas are discussed: momentum compaction, lattice layout, injection and extraction, circumference adjusters, phase adjuster, and dynamic aperture calculation with multipole errors.

 
 
THPAN104 Coupled Optics Reconstruction from TBT Data using MAD-X optics, lattice, quadrupole, betatron 3471
 
  • Y. Alexahin
  • E. Gianfelice-Wendt
    Fermilab, Batavia, Illinois
  • V. V. Kapin
    MEPhI, Moscow
  • F. Schmidt
    CERN, Geneva
  Funding: Work supported by the Universities Research Assoc., Inc., under contract DE-AC02-76CH03000 with the U. S. Dept. of Energy

Turn-by-turn BPM data provide immediate information on the coupledoptics functions at BPM locations. In the case of small deviations from the known (design) uncoupled optics some cognizance of the sources of perturbation, BPM calibration errors and tilts can also be inferred without detailed lattice modelling. In practical situations, however, fitting the lattice model with the help of some optics code would lead to more reliable results. We present an algorithm for coupled optics reconstruction from TBT data on the basis of MAD-X and give examples of its application for the Fermilab Tevatron and Booster accelerators.

 
 
THPAN108 TBT Optics and Impedance Measurements at the Fermilab Main Injector impedance, closed-orbit, optics, vacuum 3480
 
  • E. Gianfelice-Wendt
  • Y. Alexahin
    Fermilab, Batavia, Illinois
  Funding: Work supported by the U. S. Department of Energy under Contract No. DE-AC02-76CH03000.

The Main Injector (MI) is a rapid cycling multipurpose accelerator. After completion of the Tevatron Run II, its primary application will be the acceleration of high intensity proton beams for neutrino experiments. To achieve the intensity goal a detailed knowledge of the optics and transverse impedances is necessary which can be obtained from Turn-By-Turn (TBT) beam position measurements. The recent MI Beam Position Monitor system upgrade made it possible to apply the TBT data analysis methods which were successfully used by the authors for the Tevatron. We present the results of MI optics measurements and the impedance estimates obtained from the betatron phase advance dependence on beam current.

 
 
THPAN114 Simulations of Beam-wire Experiments at RHIC dynamic-aperture, simulation, resonance, beam-losses 3492
 
  • T. Sen
  • H. J. Kim
    Fermilab, Batavia, Illinois
  We report on simulations of beam-beam experiments performed at RHIC in 2006. These experiments were designed to observe the influence of a single parasitic interaction on beam quality. Several observables such as tunes, emittances and losses were simulated with the weak-strong code BBSIM. These simulation results are compared to observed values. Simulations of the wire compensation experiment to be carried out in RHIC are also shown.  
 
THPAN116 Lattice Measurement for Fermilab Main Injector lattice, quadrupole, extraction, focusing 3498
 
  • M.-J. Yang
  The installation of seven large aperture quadrupoles during the shut-down of 2006 necessitates new measurements to ascertain the state of machine lattice, both at injection and at extraction. These new quadrupoles replaced existing quadrupoles at each of the seven injection/extraction locations around the Fermilab Main Injector. Though extensive magnet measurement had been made the effect of trim coils used to compensate differences in magnet characteristics has to be verified. The result of lattice analysis and others will be discussed.  
 
THPAN117 Electron Cloud Studies at Tevatron and Main Injector electron, vacuum, proton, emittance 3501
 
  • X. Zhang
  • A. Z. Chen, W. Chou, B. M. Hanna, K. Y. Ng, J.-F. Ostiguy, L. Valerio, R. M. Zwaska
    Fermilab, Batavia, Illinois
  Funding: Work supported by the U. S. Department of Energy under Contract No. DE-AC02-76CH03000

Estimates indicate that the electron cloud effect could be a limiting factor for Main Injector intensity upgrades, with or without a the presence of a new 8 GeV superconducting 8GeV Linac injector. The effect may turn out to be an issue of operational relevance for other parts of the Fermilab accelerator complex as well. To improve our understanding of the situation, two sections of specially made vacuum test pipe outfitted for electron cloud detection with ANL provided Retarding Field Analyzers (RFAs), were installed in the Tevatron and the Main Injector. In this report we present some measurements, compare them with simulations and discuss future plans for studies.

 
 
THPAS030 Low-current, Space-Charge Dominated Beam Transport at the University of Maryland Electron Ring (UMER) lattice, space-charge, quadrupole, dipole 3561
 
  • S. Bernal
  • B. L. Beaudoin, R. A. Kishek, P. G. O'Shea, M. Reiser, D. F. Sutter
    UMD, College Park, Maryland
  Funding: This work is funded by the US Dept. of Energy and by the Office of Naval Research.

The University of Maryland Electron Ring (UMER) is designed for the transport of low energy (10 keV), high current (100 mA) electrons in a 72-magnetic-quadrupole lattice over an 11.5 m circumference. With these parameters, and a typical single-particle phase advance per period of 76 deg., space charge is extreme. However, high current is not necessary for establishing space charge dominated transport in UMER. In fact, low current (0.6 mA) beam transport in combination with longer full-lattice periods can yield strong space charge conditions. All 72 quadrupoles are needed, though, to yield beams with relatively small cross sections, as required for emittance-dominated transport. We present results of calculations and experiments that demonstrate the low-current, high space charge regime in UMER. We also discuss the use of Collins-type insertions for matching into the ring lattice.

 
 
THPAS038 Compensation of the Beam Dynamics Effects Caused by the Extraction Lambertson Septum of the HIGS Booster extraction, septum, booster, coupling 3582
 
  • J. Li
  • S. Huang, S. F. Mikhailov, V. Popov, Y. K. Wu
    FEL/Duke University, Durham, North Carolina
  Funding: Supported by US DoE grant #DE-FG02-01ER41175

As part of the High Intensity Gamma-Ray Source (HIGS) upgrade, the booster synchrotron has been recently commissioned. The booster ramps the electron beam between 0.27 and 1.2 GeV for top-off injection into the Duke storage ring. It has symmetrical injection/extraction schemes with a bumped orbit. The injection/extraction kickers and corresponding septa are located in the opposite straight sections of the booster ring separated by about 1/4 of the vertical betatron wave. Due to the nonideal properties of the magnetic material, the magnetic field leaks out into the stored beam chamber, which directly results in orbit distortion, tune and chromaticity shifts and change of coupling. These effects caused by the extraction septum have been measured as a function of extraction energy. Based upon the measurements, we have developed a scheme to compensate the dynamics effects mentioned above.

 
 
THPAS052 Charge and Wavelength Scaling of the UCLA/URLS/INFN Hybrid Photoinjector emittance, gun, cathode, simulation 3609
 
  • A. Fukasawa
  • D. Alesini, M. Ferrario, B. Spataro
    INFN/LNF, Frascati (Roma)
  • A. Boni, B. D. O'Shea, J. B. Rosenzweig
    UCLA, Los Angeles, California
  • L. Ficcadenti, A. Mostacci, L. Palumbo
    Rome University La Sapienza, Roma
  Short-bunched beam is required for the improving the emission of the free electron laser and wakefield accelerations, as well as low emittance beam. To achieve both of short length and low emittance, we are developing SW/TW Hybrid gun. Two standing wave cells make a photocathode RF gun and the gun is connected directory to the input coupler of the traveling wave structure, and the total length is about 3 m. The low emittance beam produced in the RF gun is bunching in the traveling wave structure in the scheme of, so called, "velocity bunching". PARMELA simulation shows that 1 nC bunch can be achieve 3.0 mm.mrad for the normalized rms emittance and 0.14 mm for the rms bunch length, simultaneously. We also calculates the cases of 1 pC bunch in S-band and 250 pC bunch in X-band to get shorter bunch length and lower emittance. 1 pC bunch is scaled to 1/1000 in its volume (one-tenth for each dimension). It can result in 0.0047 mm short while the emittance is 0.091 mm.mrad. In X-band case, where the structures are scaled down one-fourth in the length and four times in the field strength, the bunch length and the emittance are 0.027 mm and 1.1 mm.mrad, respectively.  
 
THPAS072 Multipass Steering Protocols at Jefferson Lab linac, quadrupole, controls, focusing 3648
 
  • R. M. Bodenstein
  • M. G. Tiefenback
    Jefferson Lab, Newport News, Virginia
  Funding: Authored by Jefferson Science Associates, LLC under U. S. DOE Contract No. DE-AC05-06OR23177

The CEBAF recirculating accelerator consists of two CW superconducting RF linacs, through which an electron beam is accelerated for up to 5 passes. Focusing and steering elements affect each pass differently, requiring a multipass steering protocol to correct the orbits. Perturbations include lens misalignments (including long-term ground motion), BPM offsets, and focusing and steering from RF fields inside the cavities. A previous treatment of this problem assumed all perturbations were localized at the quadrupoles and the absence of x-y coupling. Having analyzed the problem and characterized the solutions, we developed an empirical iterative protocol to compare against previous results in the presence of skew fields and cross-plane coupling. We plan to characterize static and acceleration-dependent components of the beam line perturbations to allow systematic and rapid configuration of the accelerator at different linac energy gains.

 
 
THPAS076 ORBIT Injection Dump Simulations of the H0 and H- Beams septum, dipole, scattering, beam-losses 3657
 
  • J. A. Holmes
  • M. R. Perkett
    Denison University, Granville, Ohio
  • M. A. Plum, J.-G. Wang, Y. Zhang
    ORNL, Oak Ridge, Tennessee
  Funding: ORNL/SNS is managed by UT-Battelle, LLC, for the U. S. Department of Energy under contract DE-AC05-00OR22725.

Simulations of the transport of H0 and H- beams to the SNS ring injection dump are carried out using the ORBIT code. During commissioning and early operations, beam losses in this region have been the highest in the accelerator and presented the most obvious hurdle to cross in achieving high intensity operation. Two tracking models are employed:

  1. a piecewise continuous symplectic representation of the lattice elements in the injection chicane and dump line, and
  2. particle tracking in full 3D magnetic fields, as obtained from OPERA code evaluations.
The physics models also include estimations of scattering from both the primary and secondary stripper foils, and beam losses due to apertures throughout the beam line.
 
 
THPAS078 3D Modeling of SNS Ring Injection Dump Beam Line dipole, simulation, beam-losses, emittance 3660
 
  • J.-G. Wang
  Funding: ORNL/SNS is managed by UT-Battelle, LLC, for the U. S. Department of Energy under contract DE-AC05-00OR22725.

The SNS ring injection dump beam line has been suffering high beam losses since its commissioning. In order to understand the mechanisms of the beam losses, we have built a 3D simulation model consisting of three injection chicane dipoles and one injection dump septum. The magnetic field distributions and the 3D particle trajectories in the model are obtained. The study has clearly shown two design problems causing beam losses in the injection dump beam line. This paper reports our simulation model, particle trajectory calculations, beam losses due to small vertical aperture of the injection dump septum and inadequate focusing down stream. The remedy of the beam losses is also discussed.

 
 
THPAS098 A Low γt Injection Lattice for Polarized Protons in RHIC quadrupole, lattice, optics, proton 3714
 
  • C. Montag
  Funding: Work performed under the auspices of the US Department of Energy.

Polarized protons are injected into the Relativistic Heavy Ion Collider (RHIC) just above transition energy. When installation of a cold partial Siberian snake in the AGS required lowering the injection energy by Delta gamma=0.56, the transition energy in RHIC had to be lowered accordingly to ensure proper longitudinal matching. This paper presents lattice modifications implemented to lower the transition energy by ∆ γt=0.8.

 
 
FRYAB02 High-Performance EBIS for RHIC ion, electron, heavy-ion, rfq 3782
 
  • J. G. Alessi
  • E. N. Beebe, O. Gould, A. Kponou, R. Lockey, A. I. Pikin, D. Raparia, J. Ritter, L. Snydstrup
    BNL, Upton, Long Island, New York
  Funding: Work performed under the auspices of the U. S. Department of Energy and the U. S. National Aeronautics and Space Administration.

An Electron Beam Ion Source (EBIS), capable of producing high charge states and high beam currents of any heavy ion species in short pulses, is ideally suited for injection into a synchrotron. An EBIS-based, high current, heavy ion preinjector is now being built at Brookhaven to provide increased capabilities for the Relativistic Heavy Ion Collider (RHIC), and the NASA Space Radiation Laboratory (NSRL). Benefits of the new preinjector include the ability to produce ions of any species, fast switching between species to serve the simultaneous needs of multiple programs, and lower operating and maintenance costs. A state-of-the-art EBIS, operating with an electron beam current of up to 10 A, and producing multi-milliamperes of high charge state heavy ions, has been developed at Brookhaven, and has been operating very successfully on a test bench for several years. The present performance of this high-current EBIS will be presented, along with details of the design of the scaled-up EBIS for RHIC, and the status of its construction. Other aspects of the project, including design and construction of the heavy ion RFQ, Linac, and matching beamlines, will also be mentioned.

 
slides icon Slides  
 
FROAC01 The Spallation Neutron Source Accumulator Ring RF System controls, proton, extraction, beam-loading 3795
 
  • T. W. Hardek
  • M. S. Champion, M. T. Crofford, H. Ma, M. F. Piller
    ORNL, Oak Ridge, Tennessee
  • K. Smith, A. Zaltsman
    BNL, Upton, Long Island, New York
  Funding: SNS is managed by UT-Batelle, LLC, under contract DE-AC05-00OR22725 for the U. S. Department of Energy.

The Spallation Neutron Source (SNS) accumulator ring is a fixed-frequency proton storage ring located at the output of the SNS Linear Accelerator (Linac). Its purpose is to convert 1 millisecond H- beam pulses from the SNS Linac into high-intensity 695 nanosecond pulses of protons for delivery to the neutron target. The RF bunching system controls longitudinal beam distribution during the accumulation process and maintains a 250+ nanosecond gap required for beam extraction. The RF system consists of three stations which operate at a beam revolution frequency of 1.05 MHz while a fourth station provides a second harmonic component at 2.1 MHz. The beam pulse at extraction consists of 1.6·1014 protons representing a peak beam current of 52 amperes. The system utilizes four 600kW tetrodes to provide the RF current necessary to produce the 40kV peak-bunching voltage and to control phase and amplitude at this high beam current. In this paper we review the design concepts incorporated into this heavily beam-loaded RF system and discuss its commissioning status.

 
slides icon Slides  
 
FRZKI04 Plasma Accelerators - Progress and the Future plasma, electron, laser, acceleration 3845
 
  • C. Joshi
  In recent months plasma accelerators have set new records: The first laser wakefield accelerator to demonstarte near GeV beam with large charge and good beam quality in a table-top device at LBNL, and the energy-doubling of the SLAC beam in a short plasma channel by the plasma wakefield acceleration technique. These two events, happening at two different laboratories signifies a coming of age of advanced accelerator R&D.  
slides icon Slides  
 
FRPMN002 Preliminary Studies for Top-up Operations at the Australian Synchrotron synchrotron, diagnostics, electron, storage-ring 3856
 
  • M. J. Boland
  • D. J. Peake
    ASP, Clayton, Victoria
  • R. P. Rassool
    Melbourne
  The Australian Synchrotron is now a fully commissioned synchrotron light source providing beam for users. With the facility now fully operational, the next major advancement in machine operations will be top-up mode. The advantages of running top-up are well documented by other third generation light sources; in broad terms it leads to a better quality beam for users and better experimental results. An overview will be given of the top-up runs that have been conducted and the instrumentation that was used. It has been demonstrated that top-up operation is possible, however improvements in injection efficiency and beam stability during injection are required before this can become a routine mode of operation.  
 
FRPMN004 Storage Ring Turn-By-Turn BPMs At The Australian Synchrotron storage-ring, coupling, synchrotron, simulation 3865
 
  • Y. E. Tan
  • M. J. Boland, R. T. Dowd, G. LeBlanc, M. J. Spencer
    ASP, Clayton, Victoria
  The Australian Synchrotron's Storage Ring is equipped with a full compliment of 98 Libera Electron Beam Position Processors from I-Tech (EBPPs) [1]. The EBPPs are capable of measuring beam position data at turn-by-turn (TBT) rates and have long history buffers. TBT data from the EBPPs has been used to determine the linear optics of the storage ring lattice using techniques developed at other facilities. This is a useful complement to other methods of determining the linear optics such as LOCO. Characteristics of the EBPPs such as beam current dependence have been studied during commissioning and will also be presented.  
 
FRPMN021 Investigation of the Injection into the ANKA Storage Ring by a Turn by Turn BPM System kicker, booster, septum, storage-ring 3958
 
  • E. Huttel
  • I. Birkel, A.-S. Muller, P. Wesolowski
    FZK, Karlsruhe
  Modern BPM Electronics allow turn by turn acquisition of the position for both the injected and stored beam. This offers additional opportunities for diagnostics. In addition to the slow acquisition system installed at ANKA, two LIBERA ELECTRON units (www.i-tech.si) have been installed. I. E. the system was used to investigate and optimize the Injection. The stray field of the Septum causes a bump of the stored beam. The settings of the Kicker could be optimized for minimized the orbit distortion. By measuring the phase space of the injected beam the injection efficiency will be improved.  
 
FRPMN031 Commissioning and Status of New BPM Electronics for COD Measurement at the SPring-8 Storage Ring pick-up, storage-ring, controls, target 3997
 
  • T. Fujita
  • S. Sasaki, M. Shoji, T. Takashima
    JASRI/SPring-8, Hyogo-ken
  At SPring-8 storage ring, a signal processing circuit for closed orbit measurement and a part of its control system were replaced during summer shutdown period of 2006. In the new circuit, one of four beam signals at the frequency of 508.58 MHz, which is the acceleration frequency of the SPring-8, is selected by a multiplexer and down-converted to IF frequency. The IF signal is sampled by 2 MSPS 16-bit ADC and detected with DSP. On the DSP, spurious frequencies are eliminated by digital filter and effective band-width can be changed by averaging. During the commissioning of the new circuit after the summer shutdown, DSP parameters such as number of averaging were decided to measure beam positions at all BPMs in 3 seconds, although the new circuit was designed with a target repetition of a few 10 Hz or around 100 Hz with resolution of sub-microns. With the DSP parameters, position resolution of less than 0.5 micron is achieved. In this paper, we also describe long term stability, current dependence and beam filling pattern dependence of the new circuit compared with the old one in addition to the position resolution and measurement repetition.  
 
FRPMN036 Resonance Correction systems for JPARC Main Ring resonance, sextupole, quadrupole, coupling 4024
 
  • A. Y. Molodozhentsev
  • T. Koseki, M. Tomizawa
    KEK, Ibaraki
  • S. Machida
    STFC/RAL/ASTeC, Chilton, Didcot, Oxon
  The injection time for the JPARC Main Ring for the basic scenario is about 120ms, which corresponds to about 20,000 turns. The particle losses at the Main Ring collimator should be less than 1% from the expected maximum beam power at the injection energy. To keep the particle losses for the Main Ring operation below the limit, the correction systems have been suggested to eliminate possible resonance excitation. The proposed correction schemes allow us to suppress linear and nonlinear resonances. The calculated and/or measured field data for main magnets of the ring has been taken into account for this study.  
 
FRPMN065 Fast Vertical Single-Bunch Instability at Injection in the CERN SPS - An Update impedance, simulation, space-charge, emittance 4162
 
  • G. Arduini
  • T. Bohl, H. Burkhardt, E. Metral, G. Rumolo
    CERN, Geneva
  • B. Salvant
    EPFL, Lausanne
  Following the first observation of a fast vertical instability for a single high-brightness bunch at injection in the SPS in 2003, a series of detailed measurements and simulations has been performed in order to assess the resulting potential intensity limitations for the SPS, as well as possible cures. During the 2006 run, the characteristics of this instability were studied further, extending the intensity range of the measurements, and comparing the experimental data with simulations that take into account the latest measurements of the transverse machine impedance. In this paper, we summarize the outcome of these studies and our understanding of the mechanisms leading to this instability. The corresponding intensity limitations were also determined.  
 
FRPMN070 Controlled Longitudinal Emittance Blow-up in the CERN PS emittance, simulation, quadrupole, acceleration 4186
 
  • H. Damerau
  • M. Morvillo, E. N. Shaposhnikova, J. Tuckmantel, J.-L. Vallet
    CERN, Geneva
  The longitudinal emittance of the bunches in the CERN PS must be increased before transition crossing to avoid beam loss due to a fast vertical instability. This controlled blow-up is essential for all high-intensity beams in the PS, including those for transfer to the LHC. The higher harmonic 200 MHz RF system (six cavities) used for this blow-up has to generate a total RF voltage which, for the most demanding blow-up, is comparable to the voltage of the main RF cavities. The system is presently subject to a major upgrade and a possible reduction in the number of higher harmonic RF cavities installed is under consideration. To determine the minimum required, detailed simulations and machine development studies to optimize the longitudinal blow-up have been performed. Further options to produce the required longitudinal emittance using other RF systems are also analyzed. The results obtained for the different scenarios for the longitudinal blow-up are presented and compared in this paper.  
 
FRPMN078 Improved Algorithms to Determine Non-Linear Optics Model of the SPS from Non-Linear Chromaticity multipole, octupole, simulation, optics 4231
 
  • R. Tomas
  • G. Arduini, G. Rumolo, F. Zimmermann
    CERN, Geneva
  • R. Calaga
    BNL, Upton, Long Island, New York
  • A. Faus-Golfe
    IFIC, Valencia
  Funding: This work is partially supported by the U. S. DOE

In recent years several measurements of the SPS non-linear chromaticity have been performed in order to determine the non-linear optics model of the SPS machine at injection energy for different cycles. In 2006 additional measurements have been performed at injection and during the ramp for the cycle used to accelerate the LHC beam. New and more robust matching algorithms have been developed in 2006 to fit the model to the measurements up to arbitrary chromatic order. In this paper we describe the algorithms used in the analysis of the data and we summarize and compare the results from all experiments.

 
 
FRPMN082 Diagnostic and Timing Supports for Top-Up Injection Operation for the TLS diagnostics, controls, storage-ring, synchrotron 4252
 
  • J. Chen
  • P. C. Chiu, K. T. Hsu, S. Y. Hsu, K. H. Hu, C. H. Kuo, D. Lee, C.-J. Wang, C. Y. Wu
    NSRRC, Hsinchu
  Routine top-up operation of Taiwan Light Source (TLS) was started from October 2005 after high efficiency multi-bunch instabilities suppression system put into service. To support the top-up operation, various diagnostics and timing supports are needed. These include diagnostics for injection efficiency, filling pattern of the storage ring, tune, instability, loss pattern measurement. Timing control of the injection process are also needed. Design consideration and details of these efforts will be summary in this report. Further possible improvement will be also discussed.  
 
FRPMN107 Observations of Rising Tune During the Injection Instability of the IPNS RCS Proton Bunch electron, proton, background, space-charge 4345
 
  • J. C. Dooling
  • F. R. Brumwell, L. Donley, K. C. Harkay, R. Kustom, M. K. Lien, G. E. McMichael, M. E. Middendorf, A. Nassiri, S. Wang
    ANL, Argonne, Illinois
  Funding: This work is supported by the U. S. DOE under contract no. W-31-109-ENG-38.

In the IPNS RCS, a single proton bunch (h=1) is accelerated from 50 MeV to 450 MeV in 14.2 ms. The bunch experiences an instability shortly after injection (<1 ms). During the first 1 ms, the beam is bunched but little acceleration takes place; thus, this period of operation is similar to that of a storage ring. Natural vertical oscillations (assumed to be tune lines) show the vertical tune to be rising toward the bare tune value, suggesting neutralization of space charge and a reduction of its detuning effects. Neutralization time near injection ranges from 0.25 ms - 0.5 ms, depending on the background gas pressure. Oscillations move from the LSB to the USB before disappearing. Measurements made with a recently installed pinger system show the horizontal chromaticity to be positive early but approaching zero later in the cycle. The vertical chromaticity is negative throughout the cycle. During pinger studies, two lines are observed, suggesting the formation of islands. Neutralization of the beam space charge implies the generation of plasma in the beam volume early in the cycle which may then dissipate as the time-varying electric fields of the beam become stronger.

 
 
FRPMN109 200-mA Studies in the APS Storage Ring impedance, storage-ring, kicker, vacuum 4354
 
  • K. C. Harkay
  • Y.-C. Chae, L. Emery, L. H. Morrison, A. Nassiri, G. J. Waldschmidt
    ANL, Argonne, Illinois
  Funding: Work supported by U. S. Department of Energy, Office of Science, Office of Basic Energy Sciences, under Contract No. DE-AC02-06CH11357.

The Advanced Photon Source storage ring is normally operated with 100 mA of beam current. A number of high-current studies were carried out to determine the multibunch instability limits. The longitudinal multibunch instability is dominated by the rf cavity higher-order modes (HOMs), and the coupled-bunch instability (CBI) threshold is bunch-pattern dependent. We can stably store 200 mA with 324 bunches, and the CBI threshold is 245 mA. With 24 bunches, several components are approaching temperature limits above 160 mA, including the HOM dampers. We do not see any CBI at this current. The transverse multibunch instabilities are most likely driven by the resistive wall impedance; there is little evidence that the dipole HOMs contribute. Presently, we rely on the chromaticity to stabilize the transverse multibunch instabilities. When we stored beam up to 245 mA, we used high chromaticity, and the beam was transversely stable. The stabilizing chromaticity was studied as a function of current. We can use these experimental results to predict multibunch instability thresholds for various upgrade options, such as smaller-gap or longer ID chambers and the associated increased impedance.

 
 
FRPMN115 A Novel FPGA-Based Bunch Purity Monitor System at the APS Storage Ring storage-ring, electron, photon, controls 4384
 
  • W. E. Norum
  • B. X. Yang
    ANL, Argonne, Illinois
  Funding: Work supported by U. S. Department of Energy, Office of Science, Office of Basic Energy Sciences, under Contract No. DE-AC02-06CH11357

Bunch purity is an important source quality factor for the magnetic resonance experiments at the Advanced Photon Source. Conventional bunch-purity monitors utilizing time-to-amplitude converters are subject to dead time. We present a novel design based on a single field-programmable gate array (FPGA) that continuously processes pulses at the full speed of the detector and front-end electronics. The FPGA provides 7778 single-channel analyzers (six per RF bucket). The starting time and width of each single-channel analyzer window can be set to a resolution of 178 ps. A detector pulse arriving inside the window of a single-channel analyzer is recorded in an associated 32-bit counter. The analyzer makes no contribution to the system dead time. Two channels for each RF bucket count pulses originating from the electrons in the bucket. The other four channels on the early and late side of the bucket provide estimates of the background. A single-chip microcontroller attached to the FPGA acts as an EPICS IOC to make the information in the FPGA available to the EPICS clients.

 
 
FRPMS006 Optimization of the Helical Orbits in the Tevatron proton, resonance, antiproton, optics 3874
 
  • Y. Alexahin
  Funding: Work supported by the Universities Research Assoc., Inc., under contract DE-AC02-76CH03000 with the U. S. Dept. of Energy

To avoid multiple head-on collisions the proton and antiproton beams in the Tevatron move along separate helical orbits created by 7 horizontal and 8 vertical electrostatic separators. Still the residual long-range beam-beam interactions can adversely affect particle motion at all stages from injection to collision. With increased intensity of the beams it became necessary to modify the orbits in order to mitigate the beam-beam effect on both antiprotons and protons. This report summarizes the work done on optimization of the Tevatron helical orbits, outlines the applied criteria and presents the achieved results.

 
 
FRPMS008 IPM Measurements in the Tevatron proton, quadrupole, emittance, single-bunch 3883
 
  • A. Jansson
  • K. Bowie, T. Fitzpatrick, R. Kwarciany, C. Lundberg, D. Slimmer, L. Valerio, J. R. Zagel
    Fermilab, Batavia, Illinois
  Funding: Work supported by the US Department of Energy

Two Ionization Profile Monitors (IPMs) were installed in the Tevatron in 2006. The detectors are capable of resolving single bunches turn-by-turn, using a combination of gas injection to boost the ionization signal and very fast and sensitive electronics to detect it. This paper presents recent improvements to the system hardware and its use for beam monitoring. In particular, the correction of beam size oscillations observed at injection is discussed.

 
 
FRPMS015 Correction of Second Order Chromaticity at Tevatron sextupole, betatron, quadrupole, resonance 3922
 
  • A. Valishev
  • G. Annala, V. A. Lebedev, R. S. Moore
    Fermilab, Batavia, Illinois
  Correction of the second order betatron tune chromaticity is essential for operation at the working point near half integer resonance which is proposed as one of the ways to improve performance of the Tevatron. In this report the new chromaticity correction scheme with split sextupole families is described. Details of implementation and commissioning at the present working point are discussed.  
 
FRPMS016 A BPM Calibration Procedure using TBT Data lattice, closed-orbit, emittance, kicker 3928
 
  • M.-J. Yang
  • J. L. Crisp, P. S. Prieto
    Fermilab, Batavia, Illinois
  Accurate BPM calibration is important in most lattice analysis. This paper describes a procedure developed as a logical extension of TBT data lattice analysis to extract relative calibration between BPMs in the machine. The method has been applied previously to the Recycler Ring and recently to Main Injector at Fermilab with amazing success. The results will be presented. The BPM position resolution is crucial to the procedure and will also be addressed.  
 
FRPMS017 Magnetic Error Analysis of Recycler Pbar Injection Transfer Line quadrupole, proton, extraction, coupling 3934
 
  • M.-J. Yang
  Detailed study of Fermilab Recycler Ring pbar injection transfer line became feasible with recent completion of BPM system upgrades, which includes its up-stream machine, the Main Injector. Data was taken both with proton during dedicated study and with pbar during regular beam transfer, in the opposite direction. The two Lambertson magnets on either end of transfer line have been identified as having substantial amount of error field. Using harmonic orbit decomposition the error fields were mapped and results are presented.  
 
FRPMS028 Simulations of Electron Cloud Effects on the Beam Dynamics for the FNAL Main Injector Upgrade electron, emittance, synchrotron, simulation 3985
 
  • K. G. Sonnad
  • C. M. Celata, M. A. Furman, D. P. Grote, J.-L. Vay, M. Venturini
    LBNL, Berkeley, California
  Funding: Work supported by the U. S. DOE under Contract no. DE-AC02-05CH11231.

The Fermilab main injector (MI) is being considered for an upgrade as part of the high intensity neutrino source (HINS) effort. This upgrade will involve a significant increasing of the bunch intensity relative to its present value. Such an increase will place the MI in a regime in which electron-cloud effects are expected to become important. We have used the electrostatic particle-in-cell code WARP, recently augmented with new modeling capabilities and simulation techniques, to study the dynamics of beam-electron cloud interaction. This study involves a systematic assesment of beam instabilities due to the presence of electron clouds.

 
 
FRPMS094 Beam Breakup Instabilities in Dielectric Structures simulation, single-bunch, diagnostics, controls 4300
 
  • A. Kanareykin
  • W. Gai, J. G. Power
    ANL, Argonne, Illinois
  • C.-J. Jing, A. L. Kustov, P. Schoessow
    Euclid TechLabs, LLC, Solon, Ohio
  Funding: This research is supported by the US Department of Energy

We report on the experimental and numerical investigation of beam breakup (BBU) effects in dielectric structures resulting from parasitic wakefields. The experimental program focuses on measurements of BBU in a number of wakefield devices: (a) a 26 GHz power extraction structure; (b) a high gradient dielectric wakefield accelerator; (c) a wakefield structure driven by a high current ramped bunch train for multibunch BBU studies. New beam diagnostics will provide methods for studying parasitic wakefields that are currently unavailable at the AWA facility. The numerical part of this research is based on a particle-Green's function based beam breakup code we are developing that allows rapid, efficient simulation of beam breakup effects in advanced linear accelerators. The goal of this work is to be able to compare the accurate numerical results obtained from the new BBU code with the results of the detailed experimental measurements. An external focusing system for the control of the beam in the presence of strong transverse wakefields is considered.

 
 
FRPMS116 Diagnostics of BNL ERL diagnostics, beam-losses, gun, emittance 4387
 
  • E. Pozdeyev
  • I. Ben-Zvi, P. Cameron, K. A. Drees, D. M. Gassner, D. Kayran, V. Litvinenko, G. J. Mahler, T. Rao
    BNL, Upton, Long Island, New York
  Funding: Work supported by U. S. DOE under contract No DE-AC02-98CH1-886

The ERL Prototype project is currently under development at the Brookhaven National Laboratory. The ERL is expected to demonstrate energy recovery of high-intensity beams with a current of up to a few hundred milliamps, while preserving the emittance of bunches with a charge of a few nanocoulombs produced by a high-current SRF gun. To successfully accomplish this task the machine will include beam diagnostics that will be used for accurate characterization of the three dimensional beam phase space at the injection and recirculation energies, transverse and longitudinal beam matching, orbit alignment, beam current measurement, and machine protection. This paper outlines requirements on the ERL diagnostics and describes its setup and modes of operation.