A   B   C   D   E   F   G   H   I   K   L   M   N   O   P   Q   R   S   T   U   V   W  

emittance

Paper Title Other Keywords Page
MOP001 CTF3 Probe Beam LINAC Commissioning and Operations laser, linac, gun, cavity 46
 
  • W. Farabolini, D. Bogard, A. Curtoni, P. Girardot, F. Peauger, C.S. Simon
    CEA, Gif-sur-Yvette
  • E. Chevallay, M. Divall Csatari, N. Lebas, M. Petrarca
    CERN, Geneva
  • A. Palaia, R.J.M.Y. Ruber, V.G. Ziemann
    Uppsala University, Uppsala
 
 

The probe beam LINAC, CALIFES, of the CLIC Test Facility (CTF3) has been developed by CEA Saclay, LAL Orsay and CERN to deliver trains of short bunches (0.75 ps) spaced by 0.666 ps at an energy around 170 MeV with a charge of 0.6 nC to the TBTS (Two-beam Test Stand) intended to test the high gradient CLIC accelerating structures. Based on 3 former LIL accelerating structures and on a newly developed RF photo-injector, the whole accelerator is powered with a single 3 GHz klystron delivering pulses of 45 MW through a RF pulse compression cavity and a network of waveguides, splitters, phase-shifters and an attenuator. We relate here results collected during the various commissioning and operation periods which led to nominal performances and stable beam characteristics delivered to the TBTS. Progress has been made in the laser system for beam charge and stability, in space charge compensation for emittance, in RF compression law for energy and energy spread. The installation of a specially developed RF power phase shifter for the first accelerating structure used in velocity bunching allows the control of the bunch length.

 
MOP003 Injector Operation with Low Charge Bunches solenoid, booster, simulation, laser 52
 
  • Y.A. Kot
    DESY, Hamburg
 
 

The three stage bunch compression system proposed for the European XFEL will be able to achieve overall compression of about 100. This would lead to the reduction of the bunch length up to 2.5 10-5 m for the designed bunch charge of 1nC. It is anticipated that the final compression would be limited here mainly by rf tolerances (jitter) which are determined by technical specifications of the manufacturer. For a large variety of experiments it could be however desirable to go to shorter bunches even on cost of less radiation power. A good possibility to achieve this might be to operate the injector at lower than 1nC bunch charge. In this paper the possibility of the operation of the injector with low charge bunches was investigated. On this issue simulations with ASTRA code have been done in order to find suitable working points for the low charge regimes and to figure out the dependence of the bunch parameters on the initial bunch charge at the cathode. The results of these simulations for the injectors at FLASH and XFEL as well as the discussion about possible problems are presented.

 
MOP011 Injector Linac Upgrade for SuperKEKB positron, linac, electron, injection 70
 
  • T. Kamitani, M. Akemoto, D.A. Arakawa, A. Enomoto, S. Fukuda, K. Furukawa, T. Higo, H. Honma, K. Hosoyama, N. Iida, M. Ikeda, E. Kadokura, K. Kakihara, H. Katagiri, M. Kikuchi, Y. Kojima, M. Kurashina, S. Matsumoto, T. Matsumoto, H. Matsushita, S. Michizono, K. Mikawa, T. Mimashi, T. Miura, H. Nakajima, K. Nakanishi, K. Nakao, Y. Ogawa, S. Ohsawa, T. Sanami, M. Satoh, T. Shidara, A. Shirakawa, T. Sugimura, T. Suwada, T. Takenaka, M. Tawada, Y. Yano, K. Yokoyama, M. Yoshida
    KEK, Ibaraki
 
 

The KEKB-factory will be upgraded for 40 times higher lumnosity (SuperKEKB). The injector linac is required to increase the beam intensities (e-:1nC -> 5nC, e-:1nC -> 4nC) and reduce the emittances (e-:300 -> 20 um, e+: 2100 -> 10 um ) for the SuperKEKB. A photo-cathode RF gun will be introduced to generate the high-intensity and low-emittance electron beams. A positron damping ring will be constructed to reduce the emittance. A new matching device (a flux concentrator or a superconducing magnet) and an L-band capture section will be introduced to increase the positron intensity. Beam line layout down to the damping ring will be rearranged to have sufficient beam acceptance considering the positron emitttance. This paper describes details of the upgrade scheme of the injector linac.

 
MOP017 A Rescue Mode for the Diamond Light Source Pre-Injector Linac klystron, linac, booster, injection 82
 
  • C. Christou
    Diamond, Oxfordshire
 
 

The Diamond Light Source injection system consists of a 100MeV linac and a 3GeV full-energy booster. The injector is used to fill the storage ring from empty and to provide beam for a 10 minute top-up cycle. The high power RF for the linac is generated by two S‑band klystrons, the first powering a buncher and accelerating structure, and the second feeding a second accelerating structure. With the klystrons feeding the two accelerating structures independently, a failure in the klystron or modulator feeding the lower energy structure and bunchers renders the linac, and hence the injection system as a whole, inoperable. In order to address this problem, the RF feed to the linac has been reconfigured to enable either klystron to power the first structure and bunchers; this has involved a rebuild of the waveguide network in the linac vault to include two four-way S-band switches, and the development of a lower energy operating mode for the linac, booster and linac-to-booster transfer line. Details are presented in this paper of the installation and test of the switching network, and the first results are reported of the new operating mode.

 
MOP019 CLIC Ring to Main Linac linac, booster, electron, wakefield 88
 
  • F. Stulle, D. Schulte, J. Snuverink
    CERN, Geneva
  • A. Latina
    Fermilab, Batavia
  • S. Molloy
    Royal Holloway, University of London, Surrey
 
 

The low emittance transport had been identified as one of the feasibility issues for CLIC. We discuss beam dynamics challenges occurring in the beam lines of the RTML connecting the damping rings and the main linac. And we outline how these motivate design choices for the general RTML layout as well as its integration into the overall CLIC layout. Constraints originating from longitudinal dynamics and stabilization requirements of beam energy and phase at the main linac entrance are emphasized.

 
MOP039 First Beams Produced by the Spiral-2 Injectors ion, ECR, heavy-ion, proton 139
 
  • J.-L. Biarrotte
    IPN, Orsay
  • P. Bertrand
    GANIL, Caen
  • C. Peaucelle
    IN2P3 IPNL, Villeurbanne
  • T. Thuillier
    LPSC, Grenoble
  • O. Tuske, D. Uriot
    CEA, Gif-sur-Yvette
 
 

The SPIRAL-2 superconducting linac driver, which aims at delivering 5 mA, 40 MeV deuterons and up to 1 mA, 14.5 A.MeV q/A=1/3 heavy ions, has now entered its construction phase in GANIL (Caen, France). The linac is composed of two injectors feeding one single RFQ, followed by a superconducting section based on 88 MHz independently-phased quarter-wave cavities with room-temperature focusing elements. The first stages of the injectors have been fully built and are now operational. They have been partly commissioned with beam in Grenoble and Saclay in 2010. This paper describes the results obtained so far in this context.

 
MOP040 Advanced Unilac Upgrade for Fair rfq, simulation, quadrupole, ion 142
 
  • H. Vormann, W.A. Barth, L.A. Dahl, W. Vinzenz, S.G. Yaramyshev
    GSI, Darmstadt
  • A. Kolomiets, S. Minaev
    ITEP, Moscow
  • U. Ratzinger, R. Tiede
    IAP, Frankfurt am Main
 
 

To provide for the high beam currents as required of the FAIR project, the GSI Unilac High Current Injector (HSI) must deliver 18 mA of U4+ ions at the end of the prestripper section. With the design existing up to 2008, the RFQ could not reach the necessary beam currents at the RFQ output, as simulations had shown. Furthermore, parts of the existing LEBT must be modified, and a new straight source branch must be added to provide for the full required beam current. As a first step of an HSI frontend upgrade, the RFQ has been modernized in summer 2009 with a completely new electrode design. Commissioning of the HSI has shown that the transmission of the RFQ increased significantly (from 55% to 85% in high current Uranium operation, 95% in medium current operation). As expected, further bottlenecks for the transmission of the complete HSI (matching LEBT-to-RFQ, matching to the Superlens) have been detected. An upgrade of LEBT magnets is foreseen for 2010, the additional linear source branch will follow.

 
MOP044 High Current U40+-operation in the GSI-UNILAC ion, target, heavy-ion, DTL 154
 
  • W.A. Barth, G. Clemente, L.A. Dahl, P. Gerhard, L. Groening, M. Kaiser, B. Lommel, M.T. Maier, S. Mickat, W. Vinzenz, H. Vormann
    GSI, Darmstadt
 
 

A low current high duty factor U10+-beam from the Penning Ion Source as well as a high current low duty factor U4+-beam from a MeVVa source were used for machine investigations in the GSI-UNILAC and synchrotron (SIS18). Carbon stripper foils (20, 40 and 50 ug/cm2) were mounted in the gas stripper section at 1.4 MeV/u to provide for highly charged uranium ions (40+) to be delivered to the SIS18 for life time beam measurements. High current tests were performed to check the durability of the carbon foils. No measurable variation of the stripped low and high current beam in the poststripper DTL could be detected during the life time of the foils. An U40+-beam current of up to 1.0·10+11 particles per 100mues could be reached in the transfer line to the SIS18. This paper will report on the investigations of stripper foils with different thickness. Additionally long time observation of all relevant beam parameters (transverse emittance, energy spread and energy loss, bunch shape, beam transmission up to the SIS-injection) are presented.

 
MOP047 The Overview of the Accelerator System for the Facility for Rare Isotope Beams at Michigan State University* linac, ion, target, acceleration 163
 
  • X. Wu, M. Doleans, W. Hartung, M.J. Johnson, F. Marti, R.C. York, Q. Zhao
    NSCL, East Lansing, Michigan
  • E. Pozdeyev, E. Tanke
    FRIB, East Lansing, Michigan
 
 

The Facility for Rare Isotope Beams (FRIB) will accelerate stable beams of heavy ions to > 200 MeV/u with beam powers of up to 400 kW onto an in-flight fragmentation target to produce rare isotopes. The accelerator system will include a room-temperature front end, a double-folded superconducting driver linac, and a beam delivery system. The front end will include superconducting ECR ion sources, a beam bunching system and a radio frequency quadrupole. The driver linac will include three acceleration segments using superconducting quarter-wave and half-wave cavities with frequencies of 80.5 and 322 MHz, and two 180 degree folding systems to minimize the cost of conventional construction. Charge-stripping and multi-charge-state beam acceleration will be used for the heavier ions to increase acceleration efficiency. The beam delivery system will transport accelerated stable beams to the in-flight fragmentation target. End-to-end beam simulations with errors have been performed to evaluate the performance of the driver linac. We will discuss recent progress in the accelerator design and the beam dynamics studies for the baseline accelerator system.

 
MOP093 Design of Low Level RF Control System for Accelerator controls, cavity, LLRF, superconducting-cavity 274
 
  • Y.S. Lee, J.-S. Chai
    SKKU, Suwon
  • K.R. Kim, K.-H. Park
    PAL, Pohang, Kyungbuk
 
 

The low level RF (LLRF) control system for PLS is being upgraded to improve the performance of the system. The LLRF control system under development consists of FPGA, and high speed ADC and DAC as well as analog front-end devices which process the signal from cavity and to RF high power system. In addition, it utilizes digital signal processing technology based on FPGA. In order to optimize the accelerating electric field in the cavity, it is required to maintain field stability less than ±1% in amplitude and 1° in phase. And the resonance condition of the cavity should be monitored and controlled. The various digital signal processing theories such as digital filters, Cordic, PI control enable to meet these requirements and to control the feedback signal less than a microsecond. The LLRF control system is also equipped with the Ethernet by the cPCI. The preliminary design study on the LLRF control system for PLS superconducting cavity will be described in this paper.

 
MOP102 Space Charge Lens for Focusing Heavy Ion Beams electron, space-charge, ion, plasma 298
 
  • K. Schulte, M. Droba, O. Meusel, U. Ratzinger
    IAP, Frankfurt am Main
 
 

Space charge lenses use a confined electron cloud for the focusing of ion beams. Due to the electric space charge field, focusing is independent of the particle mass. For this reason the application of the space charge lens especially in the field of heavy ion beams is advantageous. Moreover, the trapped non neutral plasma cloud compensates the space charge forces of the ion beam. The focusing strength is given by the confined electron density whereas the density distribution influences the mapping quality of the space charge lens. An important parameter for the focusing capability of the space charge lens is besides the homogeneous electron distribution a high electron density. In ongoing theoretical and experimental work methods have been developed to determine the most important parameters like electron temperature and electron density distribution for an optimized lens design. Based on the experimental results a new space charge lens has been designed to focus low energy heavy ion beams like 2,4 AkeV U4+ at the low energy transport section into the GSI High Current Injector. Experimental results will be presented and compared with numerical simulations.


*W. Barth, "THE INJECTOR SYSTEMS OF THE FAIR PROJECT", LINAC08, Victoria, BC, Canada

 
TU101 Overview of FELs under Construction Including FELs at Fermi Elettra, SPRing8 and Frascati SPARC FEL, electron, undulator, linac 337
 
  • G. Penco
    ELETTRA, Basovizza
 
 

This talk will report the present status of the worlwide FEL projects under construction including FELs at Fermi Elettra, SPRing8 and Frascati SPARC

 

slides icon

Slides

 
TU203 Plans for the ESS Linac cavity, linac, cryomodule, controls 367
 
  • S. Peggs, M. Eshraqi, H. Hahn, A. Jansson, M. Lindroos, A. Ponton, K. Rathsman, C.G. Trahern
    ESS, Lund
  • S. Bousson
    IPN, Orsay
  • R. Calaga
    BNL, Upton, Long Island, New York
  • H. Danared
    MSL, Stockholm
  • G. Devanz, R.D. Duperrier
    CEA, Gif-sur-Yvette
  • J. Eguia
    Fundación TEKNIKER, Eibar (Gipuzkoa)
  • S. Gammino
    INFN/LNS, Catania
  • S.P. Møller
    ISA, Aarhus
  • C. Oyon
    SPRI, Bilbao
  • R.J.M.Y. Ruber
    Uppsala University, Uppsala
  • T. Satogata
    JLAB, Newport News, Virginia
 
 

Following selection of Lund as the site for the long-pulse ESS (European Spallation Source), a team of accelerator and target experts has been working on an update of the 2003 ESS linac design. Improvements to the 2003 design will be summarised, and the latest designs for the linac will be presented.

 

slides icon

Slides

 
TUP007 BERLinPro - A Compact Demonstrator ERL for High Current and Low Emittance Beams cavity, linac, SRF, gun 407
 
  • J. Knobloch, M. Abo-Bakr, W. Anders, A. Jankowiak, T. Kamps, O. Kugeler, B.C. Kuske, P. Kuske, A.N. Matveenko, A. Meseck, A. Neumann, T. Quast, J. Rudolph
    HZB, Berlin
 
 

Energy recovery linacs (ERLs) are proving to be a powerful option to provide very high current beams with exceptional beam parameters and the flexibility to tailor these for many applications, from next-generation light sources to electron coolers. Helmholtz Zentrum Berlin (HZB) is focusing on ERLs for future x-ray light sources. Although ERL facilities exist for the IR and THz range, their moderate parameters (current, emittance, energy) are insufficient for future x-ray sources. HZB is therefore proposing to develop the 100-MeV ERL facility BERLinPro for accelerator studies and technology development to demonstrate the feasibility of an x-ray user facility. This paper presents an overview of the project and the key components of the facility.

 
TUP009 First Commissioning Experience at the SwissFEL Injector Test Facility laser, gun, electron, solenoid 410
 
  • T. Schietinger, M. Aiba, B. Beutner, M. Dach, A. Falone, R. Ganter, R. Ischebeck, F. Le Pimpec, N. Milas, P. Narang, G.L. Orlandi, M. Pedrozzi, S. Reiche, C. Vicario
    PSI, Villigen
 
 

The Paul Scherrer Institute is commissioning a 250 MeV injector test facility in preparation for the SwissFEL project. Its primary purpose is the demonstration of a high-brightness electron beam meeting the specifications of the SwissFEL main linac. At the same time it is advancing the development and validation of the accelerator components needed for the realization of the SwissFEL facility. We report the results of the first commissioning phase, which includes the gun section of the injector up to 7 MeV electron energy. Electrons are generated by a 2.6-cell laser-driven photocathode RF gun operating at 3 GHz followed by an emittance compensating focusing solenoid. The diagnostic system for this phase consists of a spectrometer dipole, a series of screens and beam position monitors and several charge measuring devices. Slit and pinhole masks can be inserted for phasespace scans and emittance measurements. The completion of the entire injector facility proceeds in three stages, culminating with the integration of the magnetic compression chicane expected for early 2011.

 

poster icon

Poster

 
TUP011 Layout of the PITZ Transverse Deflecting System for Longitudinal Phase Space and Slice Emittance Measurements klystron, electron, diagnostics, high-voltage 416
 
  • L.V. Kravchuk, V.V. Paramonov
    RAS/INR, Moscow
  • A. Anisimov, M.V. Lalayan, A.Yu. Smirnov, N.P. Sobenin
    MEPhI, Moscow
  • D. Churanov, E.V. Ivanov, S.V. Kutsaev, M. Urbant, A.A. Zavadtsev, D.A. Zavadtsev
    Nano, Moscow
  • A. Donat, W. Köhler, M. Krasilnikov, J. Meissner, M. Pohl, J. Schultze, F. Stephan, G. Trowitzsch, R.W. Wenndorff
    DESY Zeuthen, Zeuthen
  • C. Gerth, M. Hoffmann, M. Hüning
    DESY, Hamburg
 
 

Transverse Deflecting Systems are designated for longitudinal beam diagnostics of ultra-short electron bunches in modern FEL projects. At the European XFEL, Transverse Deflecting Systems are foreseen at three locations. A prototype of the TDS in the injector of the European XFEL will be installed at PITZ which is identical in terms of deflecting structure, low-level RF system and powerful RF hardware. This PITZ TDS has the aim to prove the required performance for all TDS subsystems as well as serve as a diagnostics tool for PITZ. Results of the test cells measurements of a S-band travelling wave structure are presented, showing very good agreement with calculated parameters. RF power supply system, including 3 MW klystron and other RF hardware, is described. Solid state 130 kV Marx modulator has been developed for the klystron feeding. 10 kV module of the modulator has been built and tested. The modulator allows for high voltage shutdown within pulse.

 
TUP014 Construction of Injector System for SPring-8 X-FEL cavity, gun, klystron, controls 425
 
  • H. Hanaki, T. Asaka, H. Ego, H. Kimura, T. Kobayashi, S. Suzuki, M. Yamaga
    JASRI/SPring-8, Hyogo-ken
  • T. Fukui, T. Inagaki, N. Kumagai, Y. Otake, T. Shintake, K. Togawa
    RIKEN/SPring-8, Hyogo
 
 

The injector of the 8 GeV linac generates an electron beam of 1 nC, accelerates it up to 30 MeV, and compresses its bunch length down to 20 ps. Even slight RF instability in its multi-stage bunching section fluctuates the bunch width and the peak current of an electron beam and it accordingly results in unstable laser oscillation in the undulator section. The acceptable instabilities of the RF fields in the cavities, which permit 10% rms variation of the peak beam current, are only about 0.01% rms in amplitude and 120 fs rms in phase according to beam simulation. The long-term RF variations can be compensated by feedback control of the RF amplitude and phase, the short-term or pulse-to-pulse variations, however, have to be reduced as much as possible by improving RF equipment such as amplifiers. Thus we have carefully designed and manufactured the RF cavities, amplifiers and control systems, giving the highest priority to the stabilization of the short-term variations. Components of the injector will be completed by the end of the May 2010, and the injector will be perfected in the summer 2010. We will present the performance of the completed devices in the conference.

 
TUP015 A Compact X-band Linac for an X-ray FEL linac, FEL, wakefield, klystron 428
 
  • C.D. Nantista, C. Adolphsen, K.L.F. Bane, Z. Huang, Z. Li, F. Wang, F. Zhou
    SLAC, Menlo Park, California
 
 

With the growing demand for FEL light sources, cost issues are being revaluated. To make the machines more compact, higher-frequency room-temperature linacs are being considered, in particular, ones using C-band (5.7 GHz) rf technology where 40 MV/m gradients are possible. In this paper, we show that an X-band (11.4 GHz) linac using the technology developed for NLC/GLC can provide an even lower cost solution. In particular, stable operation is possible at gradients of 100 MV/m for single bunch operation, and 70 MV/m for multibunch operation. The concern of course is whether the stronger wakefields will lead to unacceptable emittance dilution. However, we show that the small emittances produced in a 250 MeV, low bunch charge, LCLS-like S-band injector and bunch compressor can be preserved in a multi-GeV X-band linac with reasonable alignment tolerances.

 
TUP016 A Proposal for Increasing the Energy of the Fermi@elettra Linac linac, FEL, klystron, wakefield 431
 
  • G. D'Auria
    ELETTRA, Basovizza
 
 

FERMI@Elettra is a soft X-ray, fourth generation light source facility in the last phase of its construction stage at the Elettra Laboratory in Trieste, Italy. It will be based on a seeded FEL, driven by the existing normal conducting linac that is presently expected to operate at 1.5 GeV. Two differet FEL lines will produce very short coherent photon pulses (25-200 fs) in the UV snd soft X-ray region (100-4 nm). FEL1 will cover 100-20 nm, FEL2 20-4 nm. Here a possibility to extend the FERMI spectral range capability down to the water window (1.0-2.0 nm) is presented. The suggested upgrading foresees the increase of the linac energy up to 2.4-2.5 GeV, leaving untouched the existing undulator chains and the overall length of the accelerator.

 
TUP028 Status of the FETS Commissioning and Comparison with Particle Tracking Results rfq, simulation, ion, ion-source 461
 
  • J.K. Pozimski, R.D. Howard, S. Jolly
    Imperial College of Science and Technology, Department of Physics, London
  • J.J. Back
    University of Warwick, Coventry
  • M.A. Clarke-Gayther, D.C. Faircloth, S.R. Lawrie, A.P. Letchford
    STFC/RAL/ISIS, Chilton, Didcot, Oxon
  • D.C. Plostinar
    STFC/RAL/ASTeC, Chilton, Didcot, Oxon
 
 

In order to contribute to the development of high power proton accelerators in the MW range, to prepare the way for an ISIS upgrade and to contribute to the UK design effort on neutrino factories, a front end test stand (FETS) is being constructed at the Rutherford Appleton Laboratory (RAL) in the UK. The aim of the FETS is to demonstrate the production of a 60 mA, 2 ms, 50 pps chopped beam at 3 MeV with sufficient beam quality. The status of the FETS will be given and experimental results from the commissioning of LEBT and ion source will be presented. Previous measurements showed that the emittance of the beam delivered by the ion source exceeded our expectations by more than a factor of 3. Since then various changes in the beam extraction/post accelerator region reduced the beam emittance more than a factor of 2. The results from measurements will be compared with numerical simulations of the particle dynamics from the ion source to the end of the MEBT and the results discussed in respect to further work.

 
TUP034 Beam Commissioning Results for the RFQ and MEBT of the EBIS Based Preinjector for RHIC rfq, linac, ion, injection 473
 
  • M. Okamura, J.G. Alessi, E.N. Beebe, K. Kondo, R.F. Lambiase, V. LoDestro, R. Lockey, M. Mapes, A. McNerney, D. Phillips, A.I. Pikin, D. Raparia, J. Ritter, L. Smart, L. Snydstrup, A. Zaltsman
    BNL, Upton, Long Island, New York
  • T. Kanesue
    Kyushu University, Hakozaki
  • A. Schempp, J.S. Schmidt, M. Vossberg, C. Zhang
    IAP, Frankfurt am Main
  • J. Tamura
    Department of Energy Sciences, Tokyo Institute of Technology, Yokohama
 
 

The EBIS based preinjector for the RHIC is now being commissioned. During the step-wise commissioning of the preinjector from January 2009 to June 2010, the RFQ was commissioned first using Test EBIS in January 2009 and then moved to its final location and commissioned again with RHIC EBIS in March 2010. The RFQ accelerates ions from 17 keV/u to 300 keV/u and operates at 100.625 MHz. The RFQ is followed by a short (81 cm) Medium Energy Beam Transport (MEBT), which consists of four quadrupoles and one buncher cavity. Temporary diagnostics for this commissioning included an emittance probe, TOF system, fast Faraday cup, and beam current measurement units. This contribution will report results of RFQ and MEBT commissioning with helium and gold beams.

 
TUP037 Conceptual Design of Linear Injector for SSC of HIRFL linac, DTL, rfq, ion 482
 
  • Y. He, W. Chang, X. Du, Y. Ma, L.P. Sun, Z.J. Wang, J.W. Xia, C. Xiao, Y.Q. Yang, S.H. Zhang, Z.L. Zhang, H.W. Zhao
    IMP, Lanzhou
  • J.E. Chen, M. Kang, Y.R. Lu, Q.F. Zhou, K. Zhu
    PKU/IHIP, Beijing
 
 

Heavy Ion Research Facility at Lanzhou (HIRFL) consists of two cyclotrons (SFC and SSC), one synchrotron (CSRm), and one storage ring (CSRe). The two cyclotrons are in series as the injector of the synchrotron. An additional LINAC injector for SSC is considered to increase the beam time at targets. The new injector consists of an RFQ and four IH-DTL tanks. A pre-buncher in the front of RFQ is 13 MHz to match the RF frequency of SSC. The LINAC can operate in two modes. In the first mode, the middle-mass ions output with energy of 0.54 MeV/u, and then SSC accelerates them up to the energy of 5.62 MeV/u. The beam is used to do the Super Heavy Elements (SHE) experiments. In the second mode, the very heavy ions output with energy of 0.97 MeV/u, and then SSC accelerates them up to energy of 10.06 MeV/u. The beam is injected into CSRm after stripped. Code LINREV and DAKOTA are used to design and optimize the acceleration structures of DTLs. The energy spread less than ±0.5% and bunch length less than 2.6 ns are achieved at the exit of the last tank. These can match the ideal acceptance of SSC. A simulation from LEBT to exit of DTL is done by Beampath to benchmark the design.


* All authors belong to PKU-IMP RF LINAC Research Center for Heavy Ions.

 
TUP041 The New GSI HLI-RFQ for CW-Operation rfq, ion, alignment, ECR 494
 
  • M. Vossberg, A. Schempp, C. Zhang
    IAP, Frankfurt am Main
  • W.A. Barth, L.A. Dahl
    GSI, Darmstadt
 
 

A new CW-RFQ has been built for the upgrade of the HLI (High Charge State Injector) of GSI for operating with a 28GHz-ECR-Ion source and simultaneous increase of the beam duty cycle from 25 % now to 100 %. The new HLI 4-rod RFQ will accelerate charged ions from 4 keV/u to 300 keV/u for the injection into the IH-structure. High beam transmission, a small energy spread and small transverse emittance growth and good input matching are design goals. Properties of this CW-RFQ, status of project and first measurements will be presented.

 
TUP044 A Two-meter Long RFQ for the Direct Plasma Injection Scheme at IMP rfq, ion, ion-source, injection 503
 
  • Z.L. Zhang, X.H. Guo, Y. He, Y. Liu, S. Sha, A. Shi, L.P. Sun, H.W. Zhao
    IMP, Lanzhou
  • R.A. Jameson, A. Schempp
    IAP, Frankfurt am Main
  • M. Okamura
    BNL, Upton, Long Island, New York
 
 

A RFQ has been designed and built for research of direct plasma injection scheme (DPIS), which can provide high current and highly charged beams. Because of the strong space charge forces of beam from laser ion source, the beam dynamics design of the RFQ was carried out with a new code LINACSrfq which can treat space charge effectively due to equipartitioning design strategy. Another feature of the RFQ is its high energy gain in two-meter long which will be described in detail. Construction of the RFQ cavity and the 100MHz/250kW amplifier has been completed and ready for test. A laser ion source is being tested. The assembling of the whole system including the ion source, the RFQ, the beam analyzing and diagnostic system is being done. Preliminary test results will be presented.

 
TUP064 The Optimization Design and Tolerance Analysis of DTL in SSC-INAC DTL, quadrupole, simulation, cavity 557
 
  • Z.J. Wang, Y. He, W. Wu, C. Xiao, Y.Q. Yang
    IMP, Lanzhou
 
 

The separated function DTL in SSC(Separated Sector Cyclotron)-linac is being designed. According to the design requirements, 238U34+ ions are accelerated from 0.143MeV/u to 0.976MeV/u throught the DTL. The method coupling DAKOTA(Design Analysis Kit for Optimization and Terascale Application) and beam simulation code BEAMPATH is used to analyze tolerance of the structure. The tolerance of beam parameters to various type of random errors and misalignment are studied with Monte Carlo simulation,so as to de ne the engineering tolerance and alignment. In this paper, the beam dynamics simulation and the tolerance analysis of the SSC-linac are presented.

 
TUP065 Concept Design of CW SC Proton Linac Based on Spoke Cavity for China ADS cavity, linac, proton, simulation 1
 
  • Z. Li
    Southwest University of Science and Technology, Mianyang, Sichuan
 
 

A system ADS study program has been proposed and organized by Chinese Academy of Sciences. As part of the study program, concept design of a 10mA 1.5GeV Continue Wave (CW) superconducting proton linac has been started in the Institute of High Energy Physics (IHEP). In this paper the design of the 325MHz part of this linac, which is composed of a room temperature Radio Frequency Quadrupole (RFQ), eight 4-cell room temperature Cross bar H-type (CH) cavities and three kinds of spoke cavities with total number of 78, is presented. The main parameters and detailed beam dynamic simulation results of the CH and spoke section are introduced.

 
TUP067 Reduction of Transverse Emittance Growth in J-PARC DTL DTL, linac, beam-transport, quadrupole 563
 
  • H. Sako, M. Ikegami, A. Miura, G.H. Wei
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
 
 

Transverse emittance growth was observed in J-PARC Drift Tube Linac (DTL). In order to suppress the growth, we searched for optimum parameters at MEBT1, by measuring transverse emittance using four wire scanner monitors at the exit of DTL. At 15 mA peak beam current in Dec 2009, horizontal and vertical rms emittance was reduced by 12 % and 10 %, respectively, by setting the amplitudes of the first and second bunchers to 120 % and 90 % with respect to the designed settings. The resulting normalized horizontal and vertical emittance was 0.230 and 0.205 pi mm mrad. At 20 mA in Jan 2010, horizontal and vertical rms emittance was reduced by 17 % and 10 %, respectively, by setting the amplitudes of the first and second bunchers to 110 % and 80 % with respect to the designed settings. The resulting normalized horizontal and vertical emittance was 0.273 and 0.253 pi mm mrad. At 15 mA, we further reduced the horizontal and vertical emittance to 0.171 and 0.200 pi mm mrad by increasing the eighth quadruple magnet field at MEBT1 by 20 % to the designed value. The measured transverse emittance dependence on buncher electric field and quadruple magnetic field will be compared with simulation.

 
TUP074 LEBT Beam Tuning Using Neutralized Ions in the SARAF Front End ion, solenoid, simulation, dipole 584
 
  • L. Weissman, D. Berkovits, Y. Yanay
    Soreq NRC, Yavne
 
 

The SARAF front end is composed of a proton/deuteron ECR ion source and a LEBT to match the beam to a 4-rod RFQ. The LEBT is consisting of an analyzing magnet, an aperture, three magnetic solenoid lenses and a diagnostic system. The typical operation vacuum, downstream the analyzing magnet, is of the order of 10-6 mbar at 5 mA analyzed beam current. In the emittance measurement we identify a beam of secondary-species particles, differently affected by the solenoid and so arriving with a different phase-space profile at the emittance detector. The secondary beam is the result of a charge exchange interaction in which an ion interacts with residual gasses in the beam line, most likely hydrogen gas coming from the ion source, and become neutral. For 20 keV protons colliding with H2 the calculated ion neutralization rate is 1%/m/10-6 mbar. Since the neutral portion of the beam is not affected by the magnetic focusing / steering elements, a none concentric neural and ion beams in the phase-space is a measure of mistuned beam or misalign magnets. These effects were proved and followed by beam dynamics simulation and are used to match the beam to the RFQ.

 
TUP086 Emittance Measurements for Stable and Radioactive Ion Beams ion, ion-source, ECR, insertion 608
 
  • S.A. Kondrashev, A. Barcikowski, A. Levand, P.N. Ostroumov, R.C. Pardo, G. Savard, R.H. Scott, T. Sun, R.C. Vondrasek, G.P. Zinkann
    ANL, Argonne
 
 

An emittance meter based on a pepper-pot coupled to a CsI (Tl) scintillator has been developed over the last several years [1] at Argonne National Laboratory. A compact version of such a probe for on-line emittance measurements has been designed, built and installed into the low energy beam transport (LEBT) line of the Argonne Tandem Linac Accelerator System (ATLAS) and also downstream of the gas catcher of the recently commissioned Californium Rare Isotope Breeder Upgrade (CARIBU). The probe has demonstrated the capability to measure emittance of ion beams with a current density as low as 10 nA/cm2. Systematic emittance measurements in the ATLAS LEBT for different ion species have been done and results will be presented. The probe, based on a pepper-pot coupled to an MCP viewing system, has been designed and built to measure the emittance of low intensity (102-106 ions/s) radioactive CARIBU ion beams.


[1] S. Kondrashev et al. Development of a pepper-pot emittance probe and its application for ECR ion beam studies. Nuclear Instruments and Methods in Physics Research A 606, 2009, pp. 296-304.

 
TUP089 Transverse Emittance Measurements in MEBT at SNS coupling, electron, linac, ion 614
 
  • A.P. Zhukov, A.V. Aleksandrov, A.P. Shishlo
    ORNL, Oak Ridge, Tennessee
 
 

The latest modifications of the MEBT emittance scanner and the test results are presented. The scanner consists of a slit and harp placed in the MEBT section of SNS Linac with H- energy of 2.5 MeV. It was initially commissioned during the early days of SNS. The initial design allowed to get information about beam core but was incapable of getting precise data about halo. Several improvements in hardware and software were performed recently. They significantly increased signal to noise ratio, reduced harp wires electron coupling and increased scan speed. The latest measurements with the new system show a good agreement with the simulation results from simple models.

 
TUP091 Energy and Energy Spread Measurements Using the Rutherford Scattering Technique for Tuning the SARAF Superconducting Linac cavity, proton, rfq, diagnostics 620
 
  • J. Rodnizki, A. Perry, L. Weissman
    Soreq NRC, Yavne
 
 

The SARAF accelerator is designed to accelerate both deuteron and proton beams up to 40 MeV. Phase I of SARAF consists of a a 4-rod RFQ (1.5 MeV/u) and a superconducting module housing 6 half-wave resonators and 3 superconducting solenoids (4-5 MeV). The ions energy and energy spread were measured using the Rutherford scattering technique . This technique is used to tune the cavities to the desired amplitude and phase. The downstream HWR is used as a buncher and the beam energy spread as function of the bunching RF voltage is applied to estimate the longitudinal emittance. In this work, we present a longitudinal emittance measurement algorithm, which is based on the bunch energy spread as a function of the buncher's amplitude, similar to the standard algorithm that uses the bunches' temporal spread. The tuning and measured longitudinal parameters are in qualitative agreement with the predicted beam dynamics simulation.

 
TUP096 First Results of Slice Emittance Diagnostics with an Energy Chirped Beam at PITZ laser, dipole, cathode, booster 635
 
  • Ye. Ivanisenko, G. Asova, H.-J. Grabosch, M. Krasilnikov, M. Mahgoub, M. Otevrel, S. Rimjaem, F. Stephan
    DESY Zeuthen, Zeuthen
  • M.A. Khojoyan
    YerPhI, Yerevan
  • G. Vashchenko
    NSC/KIPT, Kharkov
 
 

Recent successes in existing linac based FEL facilities operation and improvements in future FEL designs became possible due to detailed research in high-brightness electron beam production. The Photo Injector Test facility in Zeuthen (PITZ) is the DESY center for electron source characterization and optimization. New slice emittance diagnostics was recently commissioned at PITZ. In the measurement approach a bunch is accelerated off-crest in the accelerating cavity downstream the gun, a part of the bunch is selected after a dipole with a slit perpendicular to the dispersive direction, and the transverse emittance of the bunch part is measured using a quadrupole or a slit scan. Test measurement results are presented for 1 nC charge, flat-top and Gaussian longitudinal laser shapes.

 
TUP097 Methodical Studies for Tomographic Reconstruction As a Novel Method For Emittance Measurements At the PITZ Facility laser, lattice, quadrupole, electron 638
 
  • G. Asova, M. Krasilnikov, J. Saisut, F. Stephan
    DESY Zeuthen, Zeuthen
  • G. Asova
    INRNE, Sofia
 
 

The Photo-Injector Test Facility at DESY in Zeuthen, PITZ, is dedicated to development of high brightness electron sources for linac-based FELs like FLASH and the European XFEL. A key parameter to judge on the beam quality for an FEL is the transverse phase space distribution, wherefrom the PITZ beamline is equipped with three Emittance Measurement Systems as the only dedicated to that apparatus. In 2010 the diagnostics has been upgraded with a module for tomographic reconstruction comprising three FODO cells, each surrounded by two observation screens. The anticipated advantages of tomographic measurements are improved resolution for low charge beams and ability to evaluate both transverse planes simultaneously. Major operational challenges are the low beam energies the module will be used with - 15 - 30 MeV, strong space charge effects for high bunch charges and, consequently, difficulties to match the beam into the optics of the lattice. This contribution presents studies on the performance of the module for different initial conditions as bunch charge and temporal laser pulse shape. Influence of residual noise on the quality of the reconstructed phase space is discussed.

 
TUP102 Phase Space Analysis at the SwissFEL Injector Test Facility background, gun, diagnostics, electron 653
 
  • B. Beutner, R. Ischebeck, T. Schietinger
    PSI, Villigen
 
 

Phase I of the SwissFEL Injector Test Facility consists of a 2.6-cell S-band RF gun, a spectrometer, and a series of transverse beam diagnostic systems such as YAG screens, slit and pepper-pot masks. Its primary purpose is the demonstration of a high-brightness electron beam meeting the specifications of the SwissFEL main linac. Phase space characterization at beam energies up to 7 MeV, where space charge still dominates, is performed with YAG screens in combination with slit- and pinhole (pepper-pot) masks. Advanced image analysis is used to mitigate artefacts due to background, pixel readout noise, or dark current. We present our data analysis procedure for the slit scan method, with particular emphasis on image processing and its effect on the reconstructed emittance. Pepper-pot measurements using an independent analysis framework are used to cross-check the slit scan results.

 
TUP103 Profile Monitors for the SwissFEL Injector Test Facility electron, radiation, target, cavity 656
 
  • R. Ischebeck, B. Beutner, G.L. Orlandi, M. Pedrozzi, T. Schietinger, V. Schlott, V.G. Thominet
    PSI, Villigen
 
 

The SwissFEL Injector Test Facility consists of an RF gun, an accelerating section for a final energy of 250 MeV, and two diagnostics sections. Transverse profiles of the electron beam can be recorded at 27 locations by imaging fluorescent crystals that can be inserted into the beam. At 21 of these, the fluorescent screens are complemented by optical transition radiation monitors and wire scanners. Here, we will evaluate the performance of transverse profile monitors experimentally and numerically and compare the measured profiles with a numerical model of the accelerator. Profile monitors are used in conjunction with a slit and a pepper pot to determine the transverse phase space distribution of the bunches. Experimental measurements at the SwissFEL Injector Test Facility will be presented.

 
TUP111 Status of MICE, the International Muon Ionization Cooling Experiment target, solenoid, cavity, collider 671
 
  • M. Popovic
    Fermilab, Batavia
  • L. Coney
    UCR, Riverside, California
  • P.M. Hanlet
    IIT, Chicago, Illinois
  • D.M. Kaplan
    Illinois Institute of Technology, Chicago, Illinois
 
 

Muon ionization cooling provides the only practical solution to prepare high brilliance beams necessary for a neutrino factory or muon colliders. The muon ionization cooling experiment (MICE) is thus a strategic R&D project for neutrino physics. It is under development at the Rutherford Appleton Laboratory (UK). It comprises a dedicated beam line to generate a range of input emittance and momentum, with time-of-flight and Cherenkov detectors to ensure a pure muon beam. A first measurement of emittance is performed in the upstream magnetic spectrometer with a scintillating fiber tracker. A cooling cell will then follow, alternating energy loss in liquid hydrogen and RF acceleration. A second spectrometer identical to the first one and a particle identification system provide a measurement of the outgoing emittance. In the 2010 run, completed in August, the beam and most detectors have been fully commissioned. The time of the first measurement of input beam emittance is closely approaching. The plan of steps of measurements of emittance and emittance reduction (cooling), that will follow in 2011 and later, will be reported.


I submit this as chair of the MICE speakers bureau. If accepted, I will find a member of the collaboration that will register to the conference and present the contribution.

 
WE102 The Status of the SARAF Linac Project rfq, cavity, proton, cryogenics 679
 
  • L. Weissman, D. Berkovits, I. Eliyahu, I. Gertz, A. Grin, S. Halfon, G. Lempert, I. Mardor, A. Nagler, A. Perry, J. Rodnizki
    Soreq NRC, Yavne
  • A. Bechtold
    NTG Neue Technologien GmbH & Co KG, Gelnhausen
  • K. Dunkel, M. Pekeler, C. Piel
    RI Research Instruments GmbH, Bergisch Gladbach
 
 

Phase I of the Soreq Applied Research Accelerator Facility, SARAF, has been installed and is currently being commissioned at Soreq NRC [1]. According to the Phase I design, SARAF should yield 2 mA proton and deuteron beams at energies up to 4 and 5 MeV, respectively. The status of the main Phase I components is reported. We further present beam commissioning results, which include acceleration of a 1 mA CW proton beam up to 3 MeV. Further improvements in the facility in order to achieve the desired performance are discussed.

 

slides icon

Slides

 
WE201 Operation and Upgrades of the LCLS FEL, linac, undulator, electron 694
 
  • J.C. Frisch, R. Akre, J. Arthur, C. Bostedt, J.D. Bozek, A. Brachmann, P.H. Bucksbaum, R.N. Coffee, F.-J. Decker, Y.T. Ding, D. Dowell, S.A. Edstrom, P. Emma, A.S. Fisher, J.N. Galayda, A. Gilevich, J.B. Hastings, G.R. Hays, P. Hering, Z. Huang, R.H. Iverson, H. Loos, M. Messerschmidt, A. Miahnahri, S.P. Moeller, H.-D. Nuhn, D.F. Ratner, J.A. Rzepiela, D.C. Schultz, T.J. Smith, H. Tompkins, J.L. Turner, J.J. Welch, J. Wu, G. Yocky
    SLAC, Menlo Park, California
  • R.M. Bionta
    LLNL, Livermore, California
  • G. Pile
    ANL, Argonne
 
 

The LCLS FEL began user operations in September 2009, with photon energies from 800eV to 2 KeV and pulse energies above 2 mJ. Both long pulse (50-200 femtosecond FWHM) and short pulse (<10 femtosecond FWHM at 150 uJ) pulses were delivered at user request. In addition the FEL was operated at fundamental photon energies up to 10 KeV in preparation for hard X-ray experiments. FEL operating parameters, performance and reliability results will be presented, in addition to plans for upgrades to the facility.

 

slides icon

Slides

 
TH302 Source and Injector Design for Intense Light Ion Beams Including Space Charge Neutralisation ion, space-charge, rfq, ion-source 740
 
  • N. Chauvin, O. Delferrière, R.D. Duperrier, R. Gobin, P.A.P. Nghiem, D. Uriot
    CEA, Gif-sur-Yvette
 
 

New PIC ray-tracing methods allows to design and simulate the transport of high intensity proton, H- and deuteron beam in the LEBT systems of future facilities like FAIR Proton Linac or IFMIF-EVADA and SPIRAL2 deuteron linacs. These techniques enable a precise prediction of the effect of residual gas ionisation and the consequent neutralisation of the large beam space charge on the beam emittances.

 
TH303 Experimental Observation of Space Charge Driven Resonances in a Linac DTL, resonance, space-charge, simulation 745
 
  • L. Groening, W.A. Barth, W.B. Bayer, G. Clemente, L.A. Dahl, P. Forck, P. Gerhard, I. Hofmann, M. Kaiser, M.T. Maier, S. Mickat, T. Milosic, H. Vormann, S.G. Yaramyshev
    GSI, Darmstadt
  • D. Jeon
    ORNL, Oak Ridge, Tennessee
  • D. Uriot
    CEA, Gif-sur-Yvette
 
 

Recent experiments at the Universal Linear Accelerator (UNILAC) at GSI provided evidence for space charge driven resonances along a periodic DTL. A transverse fourth order resonance has been detected by recording the four fold symmetry in phase space. As predicted in [D. Jeon et al., Phys. Rev. ST Accel. Beams 12, 054204 (2009)], the resonance dominates over the envelope instability. Additionally, evidence for resonant emittance transfer from the longitudinal to the transverse plane has been found for settings providing equal depressed tunes of the involved planes.

 

slides icon

Slides

 
THP001 FNAL HINS Beam Measurements and the Future of High Intensity Linac Instrumentation* rfq, diagnostics, laser, linac 755
 
  • V.E. Scarpine, S. Chaurize, B.M. Hanna, S. Hays, J. Steimel, R.C. Webber, M. Wendt, D. Wildman, D.H. Zhang
    Fermilab, Batavia
 
 

The intensity frontier, having been identified as one leg of the future of particle physics, can be meet by the development of a multi-GeV high-intensity linac. In order to address the low-energy needs of such an accelerator, Fermilab started the High Intensity Neutrino Source (HINS) project. HINS is a research project to address accelerator physics and technology questions for a new concept, low-energy, high-intensity, long pulse H- superconducting linac. The development of such an accelerator puts strict requirements on beam diagnostics. This paper will present beam measurement results of the HINS ion source and 2.5 MeV RFQ as well as discuss the role of HINS as a test facility for the development of future beam diagnostic instrumentation required for the intensity frontier.

 
THP003 Diagnostic Lines for the 160 MeV H- Linac4 at CERN linac, injection, diagnostics, quadrupole 758
 
  • B. Mikulec, G. Bellodi, K. Hanke, T. Hermanns
    CERN, Geneva
  • M. Eshraqi
    ESS, Lund
 
 

Linac4 will be the new linear accelerator of the CERN accelerator chain delivering H- ions at 160 MeV from 2016. The increased injection energy compared to the 50 MeV of its predecessor Linac2, combined with a H- charge-exchange injection, will pave the way to reach ultimate goals for the LHC luminosity. Extensive commissioning for Linac4 is planned for the coming years. For this purpose, the beam will be studied after the exit of Linac4 in a straight line ending at the Linac4 dump, equipped with various beam instruments. An almost 180 m long transfer line will guide the beam to the charge exchange injection point at the entry of the Proton Synchrotron Booster. About 50 m upstream of this point, two measurement lines will be upgraded to perform transverse emittance measurements as well as energy and energy spread measurements of the Linac4 beam. A detailed description of the beam measurement principles and setups at these three Linac4 diagnostics lines related to distinct Linac4 commissioning phases will be given.

 
THP005 Beam Dynamics Optimisation of Linac4 Structures for Increased Operational Flexibility linac, DTL, focusing, rfq 764
 
  • G. Bellodi, M. Eshraqi, M.G. Garcia Tudela, L.M. Hein, J.-B. Lallement, A.M. Lombardi, P.A. Posocco, E. Sargsyan
    CERN, Geneva
  • J. Stovall
    TechSource, Santa Fe, New Mexico
 
 

Linac4 is a new 160 MeV, 40 mA average beam current H- accelerator which will be the source of particles for all proton accelerators at CERN as from 2015. Construction started in October 2008, and beam commissioning of the 3MeV frontend is scheduled for early next year. A baseline design of the linac beam dynamics was completed 2 years ago and validated by a systematic campaign of transverse and longitudinal error studies to assess tolerance limits and machine activation levels. Recent studies have been mainly focused on optimising this design to achieve both a smoother performance for nominal beam conditions and to gain operational flexibility for non-nominal scenarios. These include a review of the chopper beam dynamics design, a re-definition of the DTL and CCDTL inter-tank regions and a study of operational schemes for reduced beam currents (either permanent or in pulse-to-pulse mode). These studies have been carried out in parallel to first specifications for a beam commissioning strategy of the linac and its low-energy front-end.

 
THP006 Accuracy Determination of the CERN LINAC4 Emittance Measurements at the Test Bench for 3 and 12 MeV space-charge, DTL, linac, proton 767
 
  • F. Roncarolo, E. Bravin, U. Raich
    CERN, Geneva
  • B. Cheymol
    Université Blaise Pascal, Clermont-Ferrand
 
 

The CERN LINAC4 commissioning will start in 2011, at first in a laboratory test stand where the 45 KeV H- source is already installed and presently tested, and later in the LINAC4 tunnel. A movable diagnostics bench will be equipped with the necessary sensors capable of characterizing the H- beam in different stages, from 3 MeV up to the first DTL tank at 12 MeV. In this paper we will discuss the accuracy of the transverse emittance measurement that will be performed with the slit-grid method. The system's mechanical and geometric parameters have been determined in order to achieve the required resolution and sensitivity. Space charge effects during the beam transfer from the slit to the grid and scattering effects at the slit have been considered to determine the overall emittance measurement accuracy.

 
THP007 Overview of the CERN LINAC4 Beam Instrumentation linac, diagnostics, instrumentation, electron 770
 
  • F. Roncarolo, G. Bellodi, E. Bravin, B. Dehning, M. Duraffourg, G.J. Focker, D. Gerard, E.B. Holzer, LF. Lenardon, U. Raich, L. Søby, M. Sordet, J. Tan, G. Tranquille, VC. Vuitton, C. Zamantzas
    CERN, Geneva
  • B. Cheymol
    Université Blaise Pascal, Clermont-Ferrand
 
 

The CERN LINAC4 will represent the first upgrade of the LHC injection chain, by accelerating H- ions from 45 KeV to 160 MeV for charge-exchange injection into the PS Booster. In order to provide its safe and efficient commissioning and operation, a wide variety of beam diagnostics devices has been designed for installation at convenient locations all over the accelerator length and in the transfer line to the PS Booster. This paper gives an overview of all instrumentation devices, including those to measure beam position, transverse and longitudinal profile, beam current and beam loss. The well advanced status of the system design and the main instrument features are discussed.

 
THP070 Simulation Study of the RF Chopper rfq, linac, cavity, simulation 911
 
  • Y. Kondo
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
  • M. Ikegami, F. Naito
    KEK, Ibaraki
  • J. Qiang
    LBNL, Berkeley, California
 
 

For the beam current upgrade of the J-PARC linac, a new RFQ (RFQ III)is developing. The peak beam current of RFQ III is 50mA. To increase the peak current from the existing RFQ (RFQ I), the longitudinal and/or transverse emittances are expected to be increased. However, the increase of the longitudinal emittance will affect the performance of the RF chopper system. In this paper, detailed simulations of the RF chopper system are described and the requirement for the longitudinal emittance of the RFQ is clarified.

 
THP077 Development of PteqHI multipole, rfq, space-charge, simulation 923
 
  • J.M. Maus, R.A. Jameson, A. Schempp
    IAP, Frankfurt am Main
 
 

For the development of high energy and high duty cycle RFQs accurate particle dynamic simulation tools are important for optimizing designs, especially in high current applications. To describe the external fields in RFQs as well as the internal space charge fields with image effect, the Poisson equation has to be solved taking the boundary conditions into account. In PteqHI a multigrid Poisson solver is used to solve the Poisson equation. This method will be described and compared to analytic solutions for the Two-term-potential to verify the answer of the Poisson solver.

 
THP078 Analytical Analysis of Particle-core Dynamics space-charge, resonance, focusing, simulation 926
 
  • Y.K. Batygin
    LANL, Los Alamos, New Mexico
 
 

Particle-core interaction is the well-developed model of halo formation in high-intensity beams. In present paper an analytical solution for averaged single particle dynamics around uniformly charged beam core is obtained. The problem is analyzed through sequence of canonical transformations of Hamiltonian describing nonlinear particle oscillations. An analytical expression for maximum particle deviation from the axis is obtained. Results of the study are in good agreement with numerical simulations and with previously achieved data.

 
THP080 Intrabeam Stripping in H- Linacs linac, radiation, focusing, cavity 929
 
  • V.A. Lebedev, J.-F. Ostiguy, N. Solyak
    Fermilab, Batavia
  • A.V. Aleksandrov, A.P. Shishlo
    ORNL, Oak Ridge, Tennessee
 
 

A beam loss in the superconducting part of the SNS linac has been observed during its commissioning and operation. Although this loss does not prevent the SNS high power operation it results in an almost uniform irradiation of linac components and increased radiation levels in the tunnel. A multi-particle tracking could not explain the beam loss and its dependence on the machine parameters. It was recently found that the loss is related to the intrabeam particle collisions resulting in a stripping of one of two H- ions. The paper describes experimental observations and corresponding calculations of the intrabeam stripping.

 
THP082 Beam Dynamics Simulations and Measurements for the PIAVE-ALPI Linac simulation, cavity, linac, ion 935
 
  • M. Comunian, E. Fagotti, F. Grespan, A. Palmieri, A. Pisent, C. Roncolato
    INFN/LNL, Legnaro (PD)
 
 

As far as beam dynamics is concerned, the layout of the PIAVE-ALPI SuperConducting linac, it is injected either by a XTU tandem, up to 14 MV, or by the s-c PIAVE injector, made with 2 SC-RFQ. The linac (at the present 64 cavities for a total voltage up to 48 MV) is build up in two branches connected by an achromatic and isochronous U-bend. The PIAVE-ALPI complex is able to accelerate beams up to A/q = 7. The linac is quite complex due the presence of several accelerating, (SC RFQs and cavities), focusing and transport elements. The linac operation, optimized for the needs of the users, is described. In particular the effects of a flexible use of the cavities on the beam dynamics is addressed. The automatic tuning procedure of the Toutatis-Tracewin programs is used for the simulation, and the comparison with the actual linac performances is reported.

 
THP086 Beam Transport in a Proton Dielectric Wall Accelerator* proton, focusing, beam-transport, quadrupole 941
 
  • Y.-J. Chen, D.T. Blackfield, G.J. Caporaso, S.A. Hawkins, S.D. Nelson, B. R. Poole
    LLNL, Livermore, California
 
 

Compact dielectric wall (DWA) accelerator technology is being developed at the Lawrence Livermore National Laboratory [1]. The DWA accelerator's beam tube is a stack of high gradient insulators, consisting of alternating layers of insulators and conductors. Characteristically, insulators' surface breakdown thresholds go up as the applied voltages' pulse width goes down. To attain the highest accelerating gradient in the DWA accelerator, the accelerating voltage pulses should have the shortest possible duration. This can be done by appropriately timing the switches in the transmission lines, which feed the continuous HGI tube. The accelerating voltage pulses arrive at the accelerator axis along the beam tube at different times so as to appear to the charged particle bunch as a traveling accelerating voltage wave. We have studied the beam transport in a baseline DWA configuration by performing PIC simulations using the 3-D, EM PIC code, LSP [2]. Sensitivity of the output beam parameters to the switch timing will be presented. In addition to the baseline configuration, various alternative focusing schemes will be discussed.


[1] G. J. Caporaso, Y-J Chen and S. E. Sampayan, "The Dielectric Wall Accelerator", Rev. of Accel. Sci. and Tech., vol. 2, p. 253 (2009).
[2] Alliant Techsystems Inc., http://www.lspsuite.com/.

 
THP089 Beam Dynamics Studies of the REX-ISOLDE Linac in Preparation for its Role as Injector for the HIE-ISOLDE SC Linac at CERN simulation, linac, rfq, cavity 950
 
  • M.A. Fraser, R.M. Jones
    UMAN, Manchester
  • M.A. Fraser, M. Pasini, D. Voulot
    CERN, Geneva
 
 

The superconducting High Intensity and Energy (HIE) ISOLDE linac will replace most of the existing accelerating infrastructure of the Radioactive ion beam EXperiment (REX) at CERN, however, the 101.28 MHz RFQ and 5 MV IH cavity will remain in the role of injector for the upgrade, boosting the beam up to an energy of 1.2 MeV/u. We present the results of a beam dynamics investigation of the injector focused most critically on matching the longitudinal beam parameters from the RFQ to the SC machine, which is complicated largely by the IH cavity employing a Combined Zero Degree* (KONUS) beam dynamics design. The longitudinal beam parameters at the RFQ are reconstructed from measurement using the three-gradient method and combined with beam dynamics measurements and simulations of the IH structure to design the matching section for the SC linac.


*Ratzinger, U., "The IH-structure and its capability to accelerate high current beams," Particle Accelerator Conference, 1991

 
THP096 Investigation of the Effects of Charge Scaling on Emittance Exchange at the Fermilab A0 Photoinjector quadrupole, cavity, space-charge, booster 962
 
  • A.S. Johnson, H.T. Edwards, E.R. Harms, A.H. Lumpkin, J. Ruan, J.K. Santucci, Y.-E. Sun, R. Thurman-Keup
    Fermilab, Batavia
  • P. Piot
    Northern Illinois University, DeKalb, Illinois
 
 

Next generation accelerators, such as high-energy physics colliders and light sources, will be interested in phase space manipulations techniques within two degrees of freedom for enhanced performance. At the Fermilab A0 Photoinjector, a proof-of-principle experiment to demonstrate the exchange of the transverse and longitudinal emittances is ongoing. The emittance exchange beamline consists of a 3.9 GHz normal conducting deflecting mode cavity inserted between two doglegs. Electron bunches of varying charge levels from 250 pC to 1 nC and energy of 14.3 MeV are consistently sent through the exchange beamline. In this paper we will present our latest results on the effects of charge on the emittance exchange process.

 
THP101 Femtosecond Electron Bunch Generation using Photocathode RF Gun laser, electron, gun, linac 968
 
  • K. Kan, T. Kondoh, T. Kozawa, K. Norizawa, A. Ogata, J. Yang, Y. Yoshida
    ISIR, Osaka
 
 

Femtosecond electron beam, which is essential for pump-probe measurement, was generated with a 1.6-cell S-band photocathode rf gun. The rf gun was driven by femtosecond UV laser pulse (266 nm), which was generated with third-harmonic-generation (THG) of Ti:Sapphire femtosecond laser (800 nm). The longitudinal and transverse dynamics of the electron bunch generated by the UV laser was investigated. The bunch length was measured with the dependence of energy spread on acceleration phase in a linac, which was set at the downstream of the rf gun. Transverse emittance at the linac exit was also measured with Q-scan method.

 
THP102 Photocathode Femtosecond Electron Linac and Its Applications electron, gun, laser, linac 971
 
  • J. Yang, K. Kan, T. Kondoh, N. Naruse, Y. Nurooka, K. Tanimura, Y. Yoshida
    ISIR, Osaka
  • J. Urakawa
    KEK, Ibaraki
 
 

Photocathode rf electron linac facilities have been developed in Osaka University to reveal the hidden dynamics of intricate molecular and atomic processes in materials. One of the linacs was developed using a booster linear accelerator and a magnetic bunch compressor. This linac was successfully produced a 100-fs high-brightness electron single bunch and initiated the first experimental study of radiation chemistry in the femtosecond time region. Another was constructed with a photocathode rf gun to generate a near-relativistic 100-fs electron beam with a beam energy of 1~4 MeV. A time-resolved MeV electron diffraction was successfully developed with this gun to study the ultrafast dynamics of structure change in materials.

 
THP105 Design of a 1 kHz Repetition Rate S-Band Photoinjector gun, solenoid, cathode, cavity 977
 
  • J.H. Han
    Diamond, Oxfordshire
 
 

At many laboratories S-band photoinjectors operate to provide high quality beams; however the repetition rates are limited to about 100 Hz. This limitation mainly occurs due to the guns where a high RF amplitude of about 100 MV/m is required to keep the beam quality from the space charge force. In this paper we design an injector consisting of an S-band gun with improved cooling and S-band acceleration modules for a repetition rate up to 1 kHz. The technical feasibility and beam dynamics optimization are discussed.

 
THP109 Potential for an Ultra-low Emittance Thermionic Triode Gun gun, cathode, electron, space-charge 989
 
  • X.W. Dong, M. Borland, G. Decker, K.-J. Kim, J.G. Power, N. Sereno
    ANL, Argonne
 
 

The proposed X-ray Free Electron Laser Oscillator* requires an ultra-low emittance gun that generates continuous electron bunches at 1 to 10 MHz. Recently, T. Shintake raised the possibility of using a pulsed triode gun with a thermionic cathode. In this paper, we investigate the feasibility for such a gun as part of an injector producing normalized emittances in the 0.1 μm range with 2 ps rms duration for 50 pC/bunch. We also explore some implementation concepts.


*K. J. Kim et al., Phys. Rev. Lett. 100, 244802 (2008)

 
THP114 H- Ion Source Development for High Performance ion, ion-source, plasma, controls 1004
 
  • K.F. Johnson, E. Chacon-Golcher, E.G. Geros, R. Keller, G. Rouleau, L. Rybarcyk, J. Stelzer
    LANL, Los Alamos, New Mexico
  • O.A. Tarvainen
    JYFL, Jyvaskyla
 
 

The Los Alamos Neutron Sciene Center (LANSCE) accelerator facility has the capability of accelerating both H+ and H- ion beams. LANSCE H- User Programs rely on the ion source's ability to deliver an appropriate beam current within a given emittance limit. An active H- ion source development program is ongoing with the goal of improving source performance (e.g. reliability, availability, increased out current, etc.) The formation of H- ions in the LANSCE negative ion source occurs on the surface of a negatively biased electrode (converter), exposed to a flux of positive ions incident from a cusp-confined, filament-driven discharge. The source typically delivers a 16 mA pulsed (60 Hz) H- beam with a source lifetime of 35 days. A program to reach 28-35 mA with the LANSCE source is outlined. It includes efforts to improve filament performance, elevating source body temperatures, optimizing converter geometry and location, optimizing converter cooling, and increasing the number of filaments from two to three.

 
THP116 Tests of the Versatile Ion Source (VIS) for High Power Proton Beam Production plasma, proton, extraction, permanent-magnet 1010
 
  • S. Gammino, G. Castro, L. Celona, G. Ciavola, D. Mascali, R. Miracoli
    INFN/LNS, Catania
  • G. Adroit, O. Delferrière, R. Gobin, F. Senée
    CEA, Gif-sur-Yvette
  • F. Maimone
    GSI, Darmstadt
 
 

The sources adapted to beam production for high power proton accelerators must obey to the request of high brightness, stability and reliability. The Versatile Ion Source (VIS) is based on permanent magnets (maximum value around 0.1 T on the chamber axis) producing an off-resonance microwave discharge. It operates up to 80 kV without a bulky high voltage platform, producing several tens of mA of proton beams and monocharged ions. The microwave injection system and the extraction electrodes geometry have been designed in order to optimize the beam brightness. Moreover, the VIS source ensures long time operations without maintenance and high reliability in order to fulfil the requirements of the future accelerators. A description of the main components and of the source performances will be given. A brief summary of the possible options for next developments of the project will be also presented, particularly for pulsed mode operations, that are relevant for future projects.