A   B   C   D   E   F   G   H   I   K   L   M   N   O   P   Q   R   S   T   U   V   W  

injection

Paper Title Other Keywords Page
MO1BCI03 Status of LHC Commissioning dipole, quadrupole, vacuum, optics 7
 
  • J. Wenninger
    CERN, Geneva
 
 

Beam commissioning of the LHC started with injection tests in August 2008, and a circulating beam was obtained in little over 3 days in September 2008. Unfortunately a powering incident in one the eight LHC sectors set an abrupt end to the beam commissioning in 2008. This talk will review the LHC beam commissioning achievements. It will describe the repair the LHC sector affected by the incident and present the measures that have been taken to avoid similar incidents in the future. The commissioning steps foreseen for the 2009 run and towards LHC design performance will be outlined.

 

slides icon

Slides

 
MO2BCI03 J-PARC Status linac, acceleration, neutron, proton 18
 
  • Y. Yamazaki
    J-PARC, KEK & JAEA, Ibaraki-ken
 
 

The Japan Proton Accelerator Research Complex (J-PARC) is a multi-purpose facility making full use of secondary particles like neutrons, muons, Kaons, and neutrinos produced by the MW-class proton accelerators. The J-PARC accelerator scheme inserts a 3-GeV Rapid-Cycling Synchrotron (RCS) in between a 400-MeV injector linac (at present 181 MeV) and a several-ten GeV Main Ring (MR). The RCS has already demonstrated extraction of one pulse of 2.6·1013 protons at 3 GeV, which corresponds to 315 kW if operated at 25 Hz, with a beam loss less than one percent, and a beam power of 210 kW for a period of 70 sec in September. The beam circulation and RF capture in MR have been done in May. Also, the neutron production target was beam-commissioned, providing high-resolution, high-efficiency neutrons. The RCS users’ run and the 30-GeV MR acceleration are planned in December. Rationale for the J-PARC accelerator scheme will be resumed on the basis of the results and difficulties encountered during the development, the construction and the commissioning. The upgrade plan, and, hopefully, some experimental results will be presented.

 

slides icon

Slides

 
MO3RAI03 Construction and Commissioning of BEPCII luminosity, linac, cavity, positron 33
 
  • C. Zhang, L. Ma, G. Pei, J.Q. Wang
    IHEP Beijing, Beijing
 
 

BEPCII is major upgrades of BEPC (Beijing Electron-Positron Collider). It is a double ring e±e collider as well as a synchrotron radiation (SR) source with its outer ring, or SR ring. As a collider, BEPCII operates in the beam energy region of 1-2.1 GeV with design luminosity of 1*1033cm-2s-1 at 1.89 GeV. As a light source, the SR ring operates at 2.5 GeV and 250 mA. Construction of the project started in the beginning of 2004. Installation of the storage ring components completed in October 2007. The BESIII detector was moved to the Interaction Region (IR) on May 6, 2008. In accordance to the progress of construction, the beam commissioning of BEPCII is carried out in 3 phases: Phase 1, with conventional magnets instead of the superconducting insertion magnets (SIM’s)n in the IR; Phase 2, with SIM’s in the IR; Phase 3, joint commissioning with the detector. The maximum luminosity reached to 2.3*1032cm-2s-1. This paper summarizes progress of the construction and commissioning in 3 phases, while focusing on the third phase.


* On behalf of the BEPCII Team

 

slides icon

Slides

 
MO3PBI02 Accelerator Physics Challenges for the NSLS-II Project sextupole, electron, quadrupole, emittance 49
 
  • S. Krinsky
    BNL, Upton, Long Island, New York
 
 

Funding: This work was supported by Department of Energy contract DE-AC02-98CH10886.


The NSLS-II is an ultra-bright synchrotron light source based upon a storage ring with a 30-cell double-bend-achromat lattice with damping wigglers used to lower the emittance below 1 nm. In this talk we discuss the accelerator physics challenges for the design including: optimization of dynamic aperture; estimation of Touschek lifetime; achievement of required orbit stability; and analysis of ring impedance and collective effects.

 

slides icon

Slides

 
MO4RAI01 Experience with DAΦNE Upgrade Including Crab Waist luminosity, sextupole, feedback, positron 80
 
  • C. Milardi, D. Alesini, M.E. Biagini, C. Biscari, A. Bocci, R. Boni, M. Boscolo, F. Bossi, B. Buonomo, A. Clozza, G.O. Delle Monache, T. Demma, E. Di Pasquale, G. Di Pirro, A. Drago, A. Gallo, A. Ghigo, S. Guiducci, C. Ligi, F. Marcellini, G. Mazzitelli, F. Murtas, L. Pellegrino, M.A. Preger, L. Quintieri, P. Raimondi, R. Ricci, U. Rotundo, C. Sanelli, M. Serio, F. Sgamma, B. Spataro, A. Stecchi, A. Stella, S. Tomassini, C. Vaccarezza, M. Zobov
    INFN/LNF, Frascati (Roma)
  • N. Arnaud, D. Breton, L. Burmistrov, A. Stocchi, A. Variola, B.F. Viaud
    LAL, Orsay
  • S. Bettoni
    CERN, Geneva
  • P. Branchini
    roma3, Rome
  • M. Esposito
    Rome University La Sapienza, Roma
  • E.B. Levichev, P.A. Piminov, D.N. Shatilov
    BINP SB RAS, Novosibirsk
  • K. Ohmi
    KEK, Ibaraki
  • V.V. Smaluk
    BINP, Novosibirsk
  • D. Teytelman
    SLAC, Menlo Park, California
  • P. Valente
    INFN-Roma, Roma
 
 

In 2007 DAΦNE was upgraded to operate in a regime of large Piwinski angle, with a novel IR optics, reduced vertical beta at the interaction point, and additional sextupoles providing for crab waist collisions. The specific luminosity was boosted by more than a factor of four, and the peak luminosity was more than doubled with respect to the maximum value obtained with the original collider configuration. The DAΦNE commissioning as well as the first experience with large Piwinski angle and crab waist collisions scheme will be reported.

 

slides icon

Slides

 
MO4RAC04 First Polarized Proton Collisions at a Beam Energy of 250 GeV in RHIC polarization, resonance, proton, betatron 91
 
  • M. Bai, L. A. Ahrens, J.G. Alessi, G. Atonian, A. Bazilevsky, J. Beebe-Wang, M. Blaskiewicz, J.M. Brennan, K.A. Brown, D. Bruno, J.J. Butler, R. Connolly, T. D'Ottavio, K.A. Drees, W. Fischer, G. Ganetis, C.J. Gardner, R.L. Gill, J.W. Glenn, Y. Hao, T. Hayes, H. Huang, R.L. Hulsart, A. Kayran, J.S. Laster, R.C. Lee, A.U. Luccio, Y. Luo, W.W. MacKay, Y. Makdisi, G.J. Marr, A. Marusic, G.T. McIntyre, K. Mernick, R.J. Michnoff, M.G. Minty, C. Montag, B. Morozov, J. Morris, P. Oddo, B. Oerter, F.C. Pilat, V. Ptitsyn, D. Raparia, G. Robert-Demolaize, T. Roser, T. Russo, T. Satogata, V. Schoefer, K. Smith, D. Svirida, S. Tepikian, D. Trbojevic, N. Tsoupas, J.E. Tuozzolo, G. Wang, M. Wilinski, A. Zaltsman, A. Zelenski, K. Zeno, S.Y. Zhang
    BNL, Upton, Long Island, New York
 
 

Funding: Work supported by Brookhaven Science Associates, LLC under Contract No. DE-AC02-98CH10886 with the U.S. Department of Energy.


After having provided collisions of polarized protons at a beam energy of 100 GeV since 2001, the Relativistic Heavy Ion Collider~(RHIC) at BNL reached its design energy of polarized proton collision at 250 GeV. With the help of the two full Siberian snakes in each ring as well as careful orbit correction and working point control, polarization was preserved during acceleration from injection to 250~GeV. During the course of the Physics data taking, the spin rotators on either side of the experiments of STAR and PHENIX were set up to provide collisions with longitudinal polarization at both experiments. Various techniques to increase luminosity like further beta star squeeze and RF system upgrades as well as gymnastics to shorten the bunch length at store were also explored during the run. This paper reports the performance of the run as well as the plan for future performance improvement in RHIC.

 

slides icon

Slides

 
MO6PFP012 Correction Coil System for Compact High Intensity Cyclotron vacuum, cyclotron, cavity, ion 157
 
  • T.J. Zhang, C.J. Chu, G.F. Song, S.M. Wei, J.Q. Zhong
    CIAE, Beijing
  • J.J. Yang
    TUB, Beijing
 
 

To limit the cost for the main magnet of a compact cyclotron CYCIAE-100, the cast steel is used for the top/bottom yoke and return yoke. The imperfection may not be ignored and the harmonic coils on the return yokes will make the fields reaching the requirements easier during the shimming. The centering coils will not only compensate the 1st harmonic fields at the center region, which is usually remain big, but also correct the off-center injection of the beam. The thermal deformation and the vacuum pressure may change the fields distribution during the machine operation and therefore It is necessary to use trim coils to adjust the fields. We arrange the trim coils inside the two opposite valleys of the main magnet. The second harmonics from the trim coils are not big eough to affect the beam dynamics significantly from the beam dynamics study. In this paper, the effects of correction coils of three types are presented. The detail configuration of the correction coils is introduced in the paper as well. One concern is the potential interference of some water cooled coils could have with vacuum. Some experience for the coils inside the high vacuum tank is tested and the results are given.

 
MO6PFP018 The Pulsed Magnet System for the Simultaneous Injection of KEK-PF and KEKB Ring linac, power-supply, factory, electron 172
 
  • T. Mimashi, K. Furukawa, N. Iida, K. Kakihara, M. Kikuchi, T. Miyajima, S. Nagahashi, M. Sato, M. Tawada, A. Ueda
    KEK, Ibaraki
  • N. Ishii
    Tigold, Chiba 289-1226
  • K. Iwamoto
    KFG, NEUSS
  • S. Kodama, A. Sasagawa
    KYOCERA Corporation, Higashiomi-city, Shiga
  • T. Kudo
    MELCO SC, Tsukuba
  • H. Mori
    Nichicon (Kusatsu) Corporation, Shiga
 
 

The KEK Linac delivers the beam to KEK-Photon factory storage ring, KEKB ring and the advanced ring for photon factory. In order to deliver the beam to the KEK-photon factory and KEKB ring simultaneously, the pulsed bending magnet was installed at the end of KEKB Linac. The pulsed bending magnet extract 2.5GeV electron beam to the PF beam transfer line. The deflection angle of the magnet is 0.114 radians and the field strength is almost 1.22T. The peak current stability is better than 0.1% at 24kA operation. The maximum repetition rate is 25Hz. The 1.2m long ceramic chamber is inserted into the 1m long magnet. This system makes possible the top up operation of PF ring.

 
MO6PFP019 Development of Pulsed Bending Magnet for Simultaneous Top-Up Injection to KEKB and PF Ring linac, electron, power-supply, pick-up 175
 
  • M. Tawada, M. Kikuchi, T. Mimashi, S. Nagahashi, A. Ueda
    KEK, Ibaraki
 
 

KEKB linac is a 600 m long electron linac and is used to deliver beam to four rings, KEKB HER ring (electron, 8 GeV), KEKB LER ring (positron, 3.5 GeV),PF ring (electron, 2.5 GeV) and PF-AR ring (electron, 6.5 GeV). KEKB rings are operated under top-up injection mode and have occupied the current linac operation mostly. Simultaneous injection to three rings (KEKB HER and KEKB LER and PF) is required due to the top-up injection to PF ring is required recently. We have developed the pulsed bending magnet for this. This magnet produces 114 mrad deflection angle for 2.5 GeV PF beam. The fast switching between KEKB and PF can be performed up to 25 Hz. We will describe this magnet system in detail.

 
MO6PFP026 Design Considerations for the TPS Pulsed Magnets System kicker, septum, booster, storage-ring 190
 
  • C.-H. Chang, C.K. Chan, H.-P. Chang, J.-R. Chen, P.J. Chou, C.-S. Fann, J.C. Huang, C.-S. Hwang, Y.-H. Liu, C.-S. Yang
    NSRRC, Hsinchu
 
 

The highly stable pulsed magnets are designed for injection and extraction the electron beams operation in Taiwan Photon Source. The injection to the booster at 0.15 GeV is performed with septum and kicker devices as well as the extraction from the booster at 3 GeV. There are 5 in-vacuum septum and kicker magnets used for booster injection and extraction processes. For the storage ring, an injection of the electron beam into the storage ring is performed with a septum magnet and four identical kicker magnets. All pulsed magnets are designed for injection into the 3-GeV storage ring. The kicker magnet is excited with a 4.8-μs half-sine current waveform. A prototype of kicker magnet with 0.6 m of length is made and tested for examining the field errors. The field performances of the kicker magnet are presented. All pulsed magnets are fed with special current waveform. Both pulsed magnets are considered with the goal to achieve reliable work.

 
MO6PFP046 First Field Test of FiDeL the Magnetic Field Description for the LHC dipole, controls, quadrupole, optics 241
 
  • L. Bottura, M.C.L. Buzio, N. Catalan-Lasheras, L. Deniau, M. DiCastro, S.D. Fartoukh, M. Giovannozzi, P. Hagen, J.-P. Koutchouk, M. Lamont, J. Miles, RV. Remondino, N.J. Sammut, S. Sanfilippo, F. Schmidt, D. Sernelius, R.J. Steinhagen, M. Strzelczyk, E. Todesco, R. Tomás, W. Venturini Delsolaro, L. Walckiers, J. Wenninger, R. Wolf, P. Xydi
    CERN, Geneva
 
 

The start-up of the LHC has provided the first field test for the concept, functionality and accuracy of FiDeL, the Field Description for the LHC. FiDeL is primarily a parametric model of the transfer function of the main field integrals generated by the series of magnets in the LHC powering circuits, from main optical elements to high-order harmonic correctors, both superconducting and normal-conducting magnets. In addition, the same framework is used to predict harmonic errors of both static and dynamic nature, and forecast appropriate corrections. In this paper we give a description of the level of detail achieved in the model and the rationale adopted for the LHC start-up. Beam-based measurements have been used for an assessment of the first-shot accuracy in the prediction of the current setting for the main arc magnets*.


*The work reported has been performed by the authors and the FiDeL Team

 
MO6PFP050 Hysteresis Effects of MCBX Magnets on the LHC Operation in Collision simulation, controls, collider, superconducting-magnet 250
 
  • N.J. Sammut, C. Giloux, M. Lamont, W. Venturini Delsolaro, S.M. White
    CERN, Geneva
 
 

The Large Hadron Collider beams are brought into collision by superconducting orbit corrector magnets which generate the parallel separation and crossing angles at the interaction points during the different cycle phases. Unfortunately, the magnetic field errors that result from hysteresis effects in the operation region of these magnets lead to unwanted orbit perturbations. In a previous paper, it has been shown that these effects are within the perturbations coming from beam-beam interactions for the MCBC and the MCBY magnets but are significant in the case of the MCBX magnets. This paper presents a refined model of their field in the frame of the Field Description for the LHC (FiDeL), the results obtained from new magnetic measurements in cold conditions to test the model, the powering mechanism employed to maximize their field reproducibility, and the impact the modeling error is predicted to have on the LHC orbit.

 
MO6PFP054 Pre-Cycle Selection for the Superconducting Main Magnets of the Large Hadron Collider coupling, dipole, collider, superconducting-magnet 259
 
  • A.P. Verweij, N.J. Sammut, W. Venturini Delsolaro, R. Wolf
    CERN, Geneva
 
 

Pre-cycles for setting up the main magnets of the Large Hadron Collider are necessary for ensuring field reproducibility and low field-decay rates at injection. In this paper we propose standard pre-cycles for the main magnets of the LHC. We study the influence of the pre-cycle parameters on the field decay at injection by two different models. One already proven model is semi-empirical based on magnetic measurements of the magnets. The other is a new network based model of a Rutherford cable which directly calculates the current redistribution and associated magnetization change in the cable strands. The pre-cycle to be used may depend on the history of the machine or may have to be changed because of unforeseen phenomena in the machine. The choice of a new pre-cycle on the basis of magnetic measurements alone is a lengthy process. We confirm the usefulness of the network based model as a tool for selecting new pre-cycles, including decay-blocking degaussing pre-cycles, and compare with magnetic measurements.

 
MO6PFP068 Magnetic Parameters of a Nb3Sn Superconducting Magnet for a 56 GHz ECR Ion Source solenoid, sextupole, ECR, ion 286
 
  • P. Ferracin, S. Caspi, H. Felice, D. Leitner, C.M. Lyneis, S. Prestemon, G.L. Sabbi, D.S. Todd
    LBNL, Berkeley, California
 
 

Third generation Electron Cyclotron Resonance (ECR) ion sources operate at rf frequencies between 20 and 30 GHz and employ NbTi superconducting magnets with a conductor peak field of 6-7 T. A significant gain in performance can be achieved by replacing NbTi with Nb3Sn, allowing solenoids and sextupole coils to reach a field of 15 T in the windings. In this paper we describe the design of a Nb3Sn superconducting magnet for a fourth generation ECR source operating at a rf frequency of 56 GHz. The magnet design features a configuration with an internal sextupole magnet surrounded by three solenoids. A finite element magnetic model has been used to investigate conductor peak fields and the operational margins. Results of the numerical analysis are presented and discussed.

 
MO6PFP073 PAMELA Magnets - Design and Performance dipole, multipole, octupole, proton 301
 
  • H. Witte, J.H. Cobb, T. Yokoi
    OXFORDphysics, Oxford, Oxon
  • K.J. Peach, S.L. Sheehy
    JAI, Oxford
 
 

Funding: This work was supported by EPSRC grant EP/E032869/1.


PAMELA is a design study of a non-scaling FFAG for hadron therapy aiming to deliver 250 MeV protons and 400 MeV/u carbon ions. This paper outlines the general magnet design required for the 250 MeV proton case. The magnet design is challenging because of the combination of required field strength (up to 4T), geometric constraints (the magnets need to be short) and large beam aperture (up to 160 mm). All magnets are combined function magnets with dipole, quadrupole, sextupole and octupole field components of good field quality.

 
MO6RFP003 The Vacuum System of HIRFL vacuum, ion, heavy-ion, storage-ring 351
 
  • X.T. Yang, D.Z. Guo, C.Y. Hao, S.J. Hou, Z.J. Hu, Y.S. Jia, M.L. Lou, S.M. Lv, X.L. Ma, J. Meng, Z.S. Nie, Z.W. Niu, W.S. Yang, Z.M. You, J.H. Zhang, Y.G. Zhao
    IMP, Lanzhou
 
 

The vacuum system of HIRFL is a large and complex system. HIRFL consists of two ECR ion sources, a sector focus cyclotron (SFC), a separate sector cyclotron (SSC) and a multipurpose cooling storage ring system which has a main ring (CSRm) and an experiment ring (CSRe). Several beam lines connect these accelerators together and transmit various heavy ion beams to more than 10 experiment terminals. According to the requirements of the ion acceleration and ion lifetime, the working pressure in each accelerator is different. SFC is nearly 50 years old. After upgrade, the working pressure in SFC is improved from 10E-6mbar to 10E-8mbar. The pressure in SSC which was built in 1980s reaches the same level. The cooling storage ring system with a length of 500m came into operation in 2007. The average pressure in CSRm and CSRe is 5E-12mbar and 8E-12mbar respectively. Different designs were adopt for vacuum system of dozens beam lines to meet various experiment terminals requirement. For instance, some shockproof measures have to be taken for the heavy ion microbeam facility. A clean and large throughput differential pumping system was built for the Gas-filled Recoil Separator and so on.

 
MO6RFP006 Neon Venting of Activated NEG Beam Pipes in the CERN LHC Long Straight Sections without Losing Vacuum Performance vacuum, ion, shielding, insertion 360
 
  • G. Bregliozzi
    CERN, Geneva
 
 

In the CERN Large Hadron Collider, about 6 km of the UHV beam pipe are at ambient temperature and serve as experimental or utility insertions. The vacuum of these sectors rely on TiZrV non-evaporable getter (NEG) coating to achieve very low pressure. In the case of venting to atmosphere, the use of NEG coatings implies the bake-out of the vacuum sector to recover the low pressure and reactivate the NEG coatings. A new method to vent a vacuum sector to atmosphere allows performing short interventions without losing completely the performance of the already activated NEG coating. The principle is to over-pressurize the vacuum sector with neon gas which is not pumped by the NEG coatings, remove the faulty component and then pump down the sector again. The injection of such a gas in the vacuum sector aims at preserving the saturation of the NEG coatings during the exchange of the component. A detailed description of this new venting system will be presented and discussed. Preliminary results obtained from a laboratory venting system and its evaluation in the LHC tunnel to replace existing components will be presented.

 
MO6RFP008 Experimental Studies of Carbon Coatings as Possible Means of Suppressing Beam Induced Electron Multipacting in the CERN SPS vacuum, electron, dipole, emittance 366
 
  • E.N. Shaposhnikova, G. Arduini, J. Axensalva, E. Benedetto, S. Calatroni, P. Chiggiato, K. Cornelis, P. Costa Pinto, B. Henrist, J.M. Jimenez, E. Mahner, G. Rumolo, M. Taborelli, C. Yin Vallgren
    CERN, Geneva
 
 

Electron cloud build-up is a major limitation for the operation of the SPS with LHC beam above nominal intensity. These beams are envisaged in the frame of the LHC luminosity upgrade and will be available from the new injectors LPSPL and PS2. A series of studies have been conducted in order to identify possible means to suppress electron multipacting by coating the existing SPS vacuum chambers with thin films of amorphous carbon. After a description of the experimental apparatus installed in the SPS, the results of the tests performed with beam in 2008 will be presented.

 
MO6RFP010 Installation and Commissioning of Vacuum Systems for the LHC Particle Detectors vacuum, controls, background, monitoring 372
 
  • R. Veness, S. Blanchard, P. Lepeule, D. Ramos, A. Rossi, G. Schneider
    CERN, Geneva
 
 

The LHC collider has recently completed commissioning at CERN. At four points around the 27 km ring, the beams are put into collision in the centre of the experiments ALICE, ATLAS, CMS and LHCb which are installed in large underground caverns. The ‘experimental vacuum systems’ which transport the beams through these caverns and collision points are a primary interface between machine and experiment and were developed and installed as one project at CERN. Each system has a different geometry and materials as required by the experiment. However, they all have common requirements from the machine, and use many common technologies developed for the project. In this paper we give an overview of the four systems stressing the similarities between them. We explain the technologies that were developed and applied for the installation, test, bakeout and subsequent closure of the experimental vacuum systems. We also discuss lessons learnt from the project.

 
MO6RFP016 Vacuum Status during the Beam Operation of RCS in J-PARC vacuum, proton, extraction, ion 384
 
  • J. Kamiya, Y. Hikichi, K. Kanazawa, M. Kinsho, N. Ogiwara, Y. Takiyama
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
 
 

Since the start of the beam commissioning on October 2007, we have succeeded to increase the beam power of the Rapid Cycling Synchrotron (RCS) in the Japan Proton Accelerator Research Complex (J-PARC). The effect of the high power beam on the vacuum had become visible above the beam power of 50 kW. When the high power beam was operated at 25 Hz, the vacuum pressure became higher. Especially the vacuum of the injection area became worse than other areas. The residual gas analyzer was installed in order to investigate which kinds of outgassing were desorbed by the high power beam. The carbon compound mainly increased with the high power beam in the area. The source of the ougtassing is thought to be carbon foils for charge exchange and/or a electron catcher which was installed in order to collect the stripped electron by the carbon foil. After this, the RCS forwards into the stage where the high power beam is continuously operated during a few weeks. We will report the results of the conditioning effect on the vacuum by the beam itself.

 
MO6RFP029 Injection Layout for PAMELA proton, ion, cyclotron, rfq 414
 
  • M.J. Easton, M. Aslaninejad, J. Pasternak, J.K. Pozimski
    Imperial College of Science and Technology, Department of Physics, London
  • K.J. Peach
    JAI, Oxford
  • T. Yokoi
    OXFORDphysics, Oxford, Oxon
 
 

For PAMELA project, the injection lay out for both protons as well as carbon 6+ ions is discussed. Injection system would consist of a 30 MeV cyclotron for protons and a chain of elements for carbon ions such as ECR ion source, bending magnets and focusing solenoids; RFQ, IH/CH structures and a striping foils. The charge particle simulation for different protons as well as carbon ions passing through the elements has been carried out with General Particle Tracer (GPT), software.

 
MO6RFP030 The MISHA Ion Source for Hadron Therapy Facilities plasma, ion, ECR, extraction 417
 
  • S. Gammino, L. Celona, G. Ciavola, F. Maimone, D. Mascali
    INFN/LNS, Catania
 
 

During the last 10 years it was demonstrated that slight variations of microwave frequency used in ECRIS strongly influence their performances either for extracted current and for beam brightness and stability. Theoretical investigations put in evidence that such frequency tuning is linked to the electromagnetic field structure inside the resonant cavity. On this basis, we carried out PIC simulations, showing that the frequency tuning has a global influence on plasma properties and on beam brightness. Such analysis allowed the design of the optimum setup for plasma chamber dimensions and microwave injection, to achieve higher currents and better emittances. The magnetic field is based on the use of steep gradient but the cryogenics issues are simplified; the extraction system is designed to minimize the aberrations. The overall dimensions of the MISHA source (Multicharged Ion Source for HAdrontherapy) have been chosen as a compromise between the ideal size for microwave to plasma interaction, the need to get long ion confinement time and the request of getting a compact ECRIS. The description of the source design will be given, along with the expected performances.

 
MO6RFP064 Stacking Simulations for Compton Positron Sources of Future Linear Colliders positron, damping, septum, emittance 512
 
  • F. Zimmermann, Y. Papaphilippou, L. Rinolfi, A. Vivoli
    CERN, Geneva
  • F. Antoniou
    National Technical University of Athens, Zografou
  • R. Chehab
    IN2P3 IPNL, Villeurbanne
  • M. Kuriki
    HU/AdSM, Higashi-Hiroshima
  • T. Omori, J. Urakawa
    KEK, Ibaraki
  • A. Variola
    LAL, Orsay
  • V. Yakimenko
    BNL, Upton, Long Island, New York
 
 

The Compton positron source of a future linear collider must obtain the target bunch population by accumulating a large number of positron packets, arriving either in a number of bursts from a “Compton ring”, with intermediate damping of the scattering electron beam, or quasi-continually from a “Compton energy recovery linac”. We present simulation results for the longitudinal stacking of Compton positrons in the ILC damping ring and the CLIC pre-damping ring, reporting parameter optimization, stacking efficiency, possible further improvements, and outstanding questions.

 
TU1RAI02 Non-Scaling FFAG Magnet Challenges quadrupole, lattice, septum, extraction 619
 
  • N. Marks
    STFC/DL/ASTeC, Daresbury, Warrington, Cheshire
 
 

The latest initiatives to design and build non-scaling FFAGs have encountered novel technical challenges; the required DC combined function magnets (normal and superconducting) and fast pulsed magnets for injection and extraction present new problems. The talk will report on progress in meeting these challenges for the non-scaling machines, EMMA and PAMELA and will provide details of their current design status. With the main EMMA ring magnets now being delivered and the injection and extraction magnets being assembled in-house, practical engineering features of these systems will be presented.

 

slides icon

Slides

 
TU1PBI04 Application of the Reduction of Scale Range in a Lorentz Boosted Frame to the Numerical Simulation of Particle Acceleration Devices simulation, laser, electron, plasma 641
 
  • J.-L. Vay, E. Cormier-Michel, W.M. Fawley, C.G.R. Geddes
    LBNL, Berkeley, California
  • D.P. Grote
    LLNL, Livermore, California
 
 

Funding: Supported by the US DOE at LBNL and LLNL under contracts DE-AC02-05CH11231 and DE-AC52-07NA27344, LARP, SciDAC, and ComPASS. Computuational resources of the NERSC were employed.


It has been shown* that the ratio of longest to shortest space and time scales of a system of two or more components crossing at relativistic velocities is not invariant under Lorentz transformation. This implies the existence of a frame of reference minimizing an aggregate measure of the ratio of space and time scales. It was demonstrated that this translated into a reduction by orders of magnitude in computer simulation run times, using methods based on first principles (e.g., Particle-In-Cell), for particle acceleration devices and for problems such as: free electron laser, laser-plasma accelerator, and particle beams interacting with electron clouds. Since then, speed-ups ranging from 75 to more than four orders of magnitude have been reported for the simulation of either scaled or reduced models of the above-cited problems. In ** it was shown that to achieve full benefits of the calculation in a boosted frame, some of the standard numerical techniques needed to be revised. The theory behind the speed-up of numerical simulation in a boosted frame, latest developments of numerical methods, and example applications with new opportunities that they offer are all presented.


* J.-L. Vay, Phys. Rev. Lett. 98, 130405 (2007).
**J.-L. Vay, Phys. of Plasmas 14, 1 (2008).

 

slides icon

Slides

 
TU1GRC04 FFAG Designs for the International Design Study for the Neutrino Factory lattice, cavity, dynamic-aperture, extraction 657
 
  • J.S. Berg
    BNL, Upton, Long Island, New York
  • S. Machida
    STFC/RAL/ASTeC, Chilton, Didcot, Oxon
 
 

Funding: Work Supported by the United States Department of Energy, Contract No. DE-AC02-98CH10886.


The International Design Study for the Neutrino Factory (IDS-NF) aims to produce a design report for a neutrino factory. One component of that design is a linear non-scaling fixed-field alternating gradient accelerator (FFAG) that will accelerate to the final energy of 25~GeV. An FFAG is used to reduce the machine cost by maximizing the number of passes made through the RF cavities. We present some design options for this FFAG, individually optimized for cost. We study the addition of nonlinear magnets to the lattice to improve the performance of the lattice and consider the negative effects of doing so.

 

slides icon

Slides

 
TU3PBI01 Beam Dynamics and Low Loss Operation of the J-PARC Main Ring resonance, space-charge, coupling, emittance 714
 
  • A.Y. Molodozhentsev
    J-PARC, KEK & JAEA, Ibaraki-ken
 
 

For operation of the JPARC Main Ring, low loss of the high-intensity bunches during the injection and acceleration processes is crucial to avoid radiation damage of the machine. This requires identification and correction the most dangerous resonances, which should be done in combination with the collective effects, in particular, the low energy space charge effects. In frame of this talk we review the status of the Main Ring commissioning process and compare it with the simulation results for the low intensity beam. For the future operation of the Main Ring with the moderate beam power we review the status of the simulation work and discuss the budget of the beam losses.

 
TU3PBC06 Recent Development at the NSCL Small Isochronous Ring ion, simulation, extraction, space-charge 733
 
  • Y. Li, G. Machicoane, F. Marti, T.P. Wangler
    NSCL, East Lansing, Michigan
  • E. Pozdeyev
    BNL, Upton, Long Island, New York
 
 

Funding: this work is supported by National Science Foundation Grant PHY-0606007.


The Small Isochronous Ring (SIR) at the NSCL/MSU was built to study space charge effects in the isochronous regime. Results of experimental studies of the longitudinal beam dynamics in the ring showed a remarkable agreement with results of numerical simulations. Recently, we have designed and built an energy analyzer to accurately measure the beam energy spread. We will present results of energy spread measurements as well as simulations of the beam behavior based on the Vlasov formalism.

 

slides icon

Slides

 
TU3GRI03 NSLS-II Beam Diagnostics Overview diagnostics, photon, vacuum, storage-ring 746
 
  • O. Singh, R. Alforque, B. Bacha, A. Blednykh, P. Cameron, W.X. Cheng, L.R. Dalesio, A.J. Della Penna, L. Doom, R.P. Fliller, G. Ganetis, R. Heese, H.-C. Hseuh, E.D. Johnson, B.N. Kosciuk, S.L. Kramer, S. Krinsky, J. Mead, S. Ozaki, D. Padrazo, I. Pinayev, V. Ravindranath, J. Rose, T.V. Shaftan, S. Sharma, J. Skaritka, T. Tanabe, Y. Tian, F.J. Willeke, L.-H. Yu
    BNL, Upton, Long Island, New York
 
 

A new 3rd generation light source (NSLS-II project) is in the early stage of construction at Brookhaven National Laboratory. The NSLS-II facility will provide ultra high brightness and flux with exceptional beam stability. It presents several challenges in the diagnostics and instrumentation, related to the extremely small emittance. In this paper, we present an overview of all planned instrumentation systems, results from research & development activities; and then focus on other challenging aspects.

 

slides icon

Slides

 
TU5PFP019 Phase and Frequency Locked Magnetrons for SRF Sources feedback, solenoid, cathode, controls 852
 
  • M.L. Neubauer, R.P. Johnson
    Muons, Inc, Batavia
  • A. Moretti, M. Popovic
    Fermilab, Batavia
 
 

Funding: Supported in part by USDOE Contract. DE-AC05-84-ER-40150 and by FRA DOE contract number DE-AC02-07CH11359


Magnetrons are low-cost highly-efficient microwave sources, but they have several limitations, primarily centered about the phase and frequency stability of their output. When the stability requirements are low, such as for medical accelerators or kitchen ovens, magnetrons are the very efficient power source of choice. But for high energy accelerators, because of the need for frequency and phase stability–-proton accelerators need 1-2 degrees source phase stability, and electron accelerators need .1-.2 degrees of phase stability–-they have rarely been used. We describe a novel variable frequency cavity technique which will be utilized to phase and frequency lock magnetrons.

 
TU5RFP002 Alternate Hybrid Mode Bunch Patterns for the Advanced Photon Source sextupole, betatron, kicker, emittance 1084
 
  • L. Emery, K.C. Harkay, V. Sajaev
    ANL, Argonne
 
 

Funding: This work was supported by U.S. Department of Energy, Office of Science, Office of Basic Energy Sciences, under Contract No. DE-AC02-06CH11357.


The Advanced Photon Source is filled for five weeks per year in a special bunch (hybrid) pattern of one large 16-mA (74-nC) bunch in a gap of 3 microseconds, and the remaining 86 mA in 8 trains of 7 consecutive bunches, forming a 500-microsecond-long bunch train. We are developing variations of this bunch pattern, which might have 3 large bunches equally spaced in the 3-microsecond gap in a 4-mA, 16-mA, and 8-mA distribution. The 500-microsecond-long bunch train could be changed to 2 or 3 bunch trains of 7 bunches. We report on the difficulties in bringing these into future operations: impedance-driven injection losses, sextupoles in injection section, lifetime and topup injection limit, and beam diagnostics responses to the patterns.

 
TU5RFP004 Observation of Ion Induced Effects and their Impact on the Performance of the MLS Electron Storage Ring ion, coupling, quadrupole, electron 1090
 
  • J. Feikes, M.V. Hartrott, G. Wüstefeld
    BESSY GmbH, Berlin
  • A. Hoehl, R. Klein, C. Koschitzki, G. Ulm
    PTB, Berlin
 
 

Funding: Work funded by Physikalisch-Technische Bundesanstalt


The Metrology Light Source (MLS) [1] is in user operation since 2008 at operating energies ranging from 105 MeV up to 630 MeV and with multi bunch currents up to 200 mA. At the injection energy of 105 MeV as soon as the beam current exceeds a few mA, the beam is strongly blown up in all three spatial dimensions and strong oscillations at very different spectral frequencies can be observed. These effects are caused by the interaction of beam charge with ions present and their strength and characteristic time scales depend on several machine parameters. As ion effects can strongly deteriorate the performance of the MLS, we report on first investigations.

 
TU5RFP006 Beam Transport and Diagnostics for the NSLS-II Injection System booster, linac, diagnostics, sextupole 1096
 
  • R.P. Fliller, R. Alforque, R. Heese, R. Meier, J. Rose, T.V. Shaftan, O. Singh, N. Tsoupas
    BNL, Upton, Long Island, New York
 
 

The NSLS II is a state of the art 3 GeV synchrotron light source being developed at BNL. The injection system will consist of a 200 MeV linac and a 3GeVbooster synchrotron. The transport lines between the linac and booster (LtB) and the booster and storage ring (BtS) must satify a number of requirements. In addition to transporting the beam while mantaining the beam emittance, these lines must allow for commissioning, provide appropriate diagnostics, allow for the appropriate safety devices and and in the case of the BtS line, provide for a stable beam for top off injection. Appropriate diagnostics are also necessary in the linac and booster to complement the measurements in the transfer lines. In this paper we discuss the design of the transfer lines for the NSLSII along with the incorporated diagnostics and safety systems. Necessary diagnostics in the linac and booster are also discussed.

 
TU5RFP007 NSLS-II Booster Acceptance Studies booster, simulation, kicker, lattice 1099
 
  • R.P. Fliller, W. Guo, R. Heese, Y. Li, T.V. Shaftan
    BNL, Upton, Long Island, New York
 
 

The NSLS II is a state of the art 3 GeV synchrotron light source being developed at BNL. The injection system will consist of a 200 MeV linac and a 3GeV booster synchrotron. The injection system must supply 7.3nC every minute to satisfy the top off requirements. A large booster acceptance is neccessary to have a high booster injection efficiency and alleviate the requirements on linac gun. We also anticipate transverse stacking of bunches in the booster to increase the amount of charge that can be delivered. We present studies of the anticipated booster stay clear including lattice errors and the ramifications for injection efficiency and transverse stacking.

 
TU5RFP009 NSLS-II Pulsed Magnet Design Considerations booster, kicker, septum, extraction 1105
 
  • R. Heese, R.P. Fliller, R. Meier, B. Parker, M. Rehak, T.V. Shaftan, F.J. Willeke, P. Zuhoski
    BNL, Upton, Long Island, New York
  • E. Weihreter
    BESSY GmbH, Berlin
 
 

NSLS-II injection system contains 13 pulsed magnets and their power supplies for injection in and extraction from the booster and injection in the storage ring. Requirement of having injection process transparent for the NSLS-II users translates into challenging specifications for the pulsed magnet design. To keep the beam jitter within 10% of radiation source size, relative kicker mismatch must be kept on 10-5 level and residual vertical field must be below few gauss in amplitude. In this paper we discuss specifications for the pulsed magnets, their preliminary design and parameters' tolerances.

 
TU5RFP011 Top-Off Safety Analysis for NSLS-II simulation, dipole, electron, radiation 1111
 
  • Y. Li, W.R. Casey, R. Heese, H.-C. Hseuh, P.K. Job, S. Krinsky, B. Parker, T.V. Shaftan, S. Sharma
    BNL, Upton, Long Island, New York
 
 

Funding: Work supported by U.S. DOE, Contract No.DE-AC02-98CH10886


Top-off injection will be adopted in NSLS-II. To ensure no injected beam can pass into experimental beamlines with open photon shutters during top-off injection, simulation studies for possible machine fault scenarios are required. We compare two available simulation methods, backward (H. Nishimura-LBL) and forward tracking (A. Terebilo-SLAC). We also discuss the tracking settings, fault scenarios, apertures and interlocks considered in our analysis.

 
TU5RFP012 Alternative Designs of the NSLS-II Injection Straight Section kicker, septum, storage-ring, sextupole 1114
 
  • T.V. Shaftan, R.P. Fliller, R. Heese, E.D. Johnson, R. Meier, M. Rehak, F.J. Willeke
    BNL, Upton, Long Island, New York
  • E. Weihreter
    BESSY GmbH, Berlin
 
 

The NSLS-II is a state of the art 3 GeV synchrotron light source that is being developed at BNL. The 9.3 meter long injection straight section of NSLS-II storage ring currently fits a conventional injection set-up that consists of four kickers producing a closed bump together with a DC septum and a pulsed septum. In this paper we analyze alternative options based on: a) injection via a pulsed sextupole and b) injection with a Lambertson septum. We discuss dynamics of the injected and stored beams and, consequently, magnet specifications and tolerances. In conclusion we summarize advantages and drawbacks of each injection scheme.

 
TU5RFP025 A Full-Energy-Injector for the ANKA Storage Ring storage-ring, optics, dipole, quadrupole 1147
 
  • E. Huttel, I. Birkel, A.-S. Müller, N.J. Smale, K.G. Sonnad, P. Wesolowski
    FZK, Karlsruhe
 
 

The ANKA storage ring is filled at 0.5 GeV and then ramped to 2.5 GeV for regular user operation. A full-energy injection of the ANKA storage ring would have several advantages. The damping at a beam energy of 2.5 GeV is stronger, which will more efficiently fight instabilities during the injection, therefore allowing higher beam currents. With constant magnet settings, the orbit stability would improve significantly. The injection time would be reduced and topping- up operation would become possible. As a consequence, the optical elements of the user beamlines would see a constant power as a function of time which further enhances the overall stability. In this paper, a design for a full energy injector is proposed. The injector will be located inside the storage ring tunnel, similar to the SLS and ALBA design. The focusing is mainly provided by combined function magnets. The full energy injector has a design emittance of 40 nmrad and a circumference of 94.8 m. A modification of the existing storage ring is foreseen to house the necessary more powerful injection elements.

 
TU5RFP029 Cherenkov Fibers for Beam Diagnostics at the Metrology Light Source septum, electron, storage-ring, kicker 1159
 
  • J. Bahrdt, J. Feikes, W. Frentrup, A. Gaupp, M.V. Hartrott, M. Scheer, G. Wüstefeld
    HZB, Berlin
  • J. Kuhnhenn
    FhG, Euskirchen
  • G. Ulm
    PTB, Berlin
 
 

The 0.6 GeV storage ring Metrology Light Source (MLS) is in operation since April 2008. Recently, Cherenkov glass fibers have been installed for a temporal and spatial detection of electron beam losses. Based on this information the loss mechanisms can be studied in detail and the performance of the machine can be optimized. First experiments with this diagnostic tool will be presented.

 
TU5RFP031 Recent Progress of the Operation at PF-Ring and PF-AR undulator, feedback, linac, polarization 1165
 
  • Y. Kobayashi, T. Aoto, S. Asaoka, K. Ebihara, K. Haga, K. Harada, T. Honda, T. Ieiri, M. Izawa, T. Kageyama, T. Kasuga, M. Kikuchi, K. Kudo, H. Maezawa, K. Marutsuka, A. Mishina, T.M. Mitsuhashi, T. Miyajima, H. Miyauchi, S. Nagahashi, T.T. Nakamura, T. Nogami, T. Obina, K. Oide, M. Ono, T. Ozaki, C.O. Pak, H. Sakai, Y. Sakamoto, S. Sakanaka, H. Sasaki, Y. Sato, M. Shimada, T. Shioya, M. Tadano, T. Tahara, T. Takahashi, R. Takai, S. Takasaki, Y. Tanimoto, M. Tejima, K. Tsuchiya, T. Uchiyama, A. Ueda, K. Umemori, S. Yamamoto, Ma. Yoshida, S.I. Yoshimoto
    KEK, Ibaraki
 
 

Two synchrotron light sources of the Photon Factory storage ring (PF-ring) and the Photon Factory advanced ring (PF-AR) have been stably operated at KEK. PF-ring covers the photon-energy range from VUV to hard X-ray using a 2.5 GeV (sometimes 3.0 GeV) electron beam. PF-AR is mostly operated in a single-bunch mode of 6.5GeV to provide pulsed hard X-rays. Recently, the operation has progressed to realize a so-called top-up injection at PF-ring. In a single-bunch mode, the continuous injection to preserve a constant beam current of 51 mA has been carried out since February 2007. In addition, the injection with continuing the experiments has been successfully operated in a multi-bunch mode since October 2008. At PF-AR, sputter ion pumps have been extensively reinforced to prolong the beam lifetime and to reduce the frequency of sudden lifetime drops by substituting for distributed ion pumps, which are considered as one of the dust sources. In this conference, we present the recent progress of the operation at PF-ring and PF-AR including machine developments.

 
TU5RFP042 Commissioning and User Operation of the ALS in Top-Off Mode radiation, storage-ring, booster, emittance 1183
 
  • C. Steier, B.J. Bailey, K.M. Baptiste, W. Barry, A. Biocca, W.E. Byrne, P.W. Casey, M.J. Chin, R.J. Donahue, R.M. Duarte, M.P. Fahmie, J. Gath, S.R. Jacobson, J. Julian, J.-Y. Jung, A.M. Kritscher, S. Kwiatkowski, S. Marks, J.P. McKean, R.S. Müller, H. Nishimura, J.W. ONeill, G.J. Portmann, S. Prestemon, D. Robin, S.L. Rossi, F. Sannibale, T. Scarvie, D. Schlueter, B. Shuman, A.Z. Smith-Baumann, G.D. Stover, CA. Timossi, W. Wan, T. Warwick, J.M. Weber, R.P. Wells, E.C. Williams
    LBNL, Berkeley, California
 
 

Funding: This work was supported by the Director, Office of Science, U. S. Department of Energy under Contract No. DE-AC02-05CH11231.


The upgrade of the Advanced Light Source to enable top-off operation has been ongoing for the last four years. Activities over the last year have centered around radiation safety aspects, culminating in a systematic proof that top-off operation is equally safe as decaying beam operation, followed by commissioning and full user operations. Top-off operation at the ALS provides a very large increase in time-averaged brightness to ALS users (by about a factor of 10) as well as improvements in beam stability. The presentation will provide an overview of the radiation safety rationale, commissioning results, as well as experience in user operations.

 
TU5RFP044 An Optic with Small Vertical Beta Function for the CAMD Light Source lattice, quadrupole, wiggler, resonance 1189
 
  • V.P. Suller, P. Jines, D.J. Launey, T.A. Miller, Y. Wang
    LSU/CAMD, Baton Rouge, Louisiana
  • S. Wang
    CAEP/IFP, Mainyang, Sichuan
 
 

At the CAMD Light Source a new optic has been developed for the lattice having small vertical beta function in each of the 4 long straight sections. This optic will be necessary to operate the multipole wigglers with small vertical aperture which are planned to be installed in the near future. Results are presented of the tests which have been made with this optic, particularly in the critical area of injection, which is made low energy. The lattice functions have been characterized using LOCO software and the reduced vertical aperture confirmed with an adjustable scraper.

 
TU5RFP066 Multibunch Injection Scheme for the Duke Booster Synchrotron for Top-Off Injection booster, linac, kicker, storage-ring 1238
 
  • S.F. Mikhailov, J.Y. Li, V. Popov, P.W. Wallace, P. Wang, Y.K. Wu
    FEL/Duke University, Durham, North Carolina
  • O. Anchugov
    BINP SB RAS, Novosibirsk
 
 

Funding: This work is supported by the US DoE grant #DE-FG02-01ER41175


A booster-injector synchrotron has been recently built and commissioned at Duke University to provide for the top-off injection into the storage ring in the energy range of 0.24 - 1.2 GeV. Booster injection kicker was designed with a pulse length of 18 out of 19 booster separatrixes, assuming a long train of electron bunches to be injected from the existing linac. Such scheme required a major linac upgrade from single bunch photo emission mode to a multibunch thermionic mode. A major disadvantage of the latter was much higher radiation levels in the facility. Since commissioning, the booster could only operate with one or two bunches limited by both long kicker pulse and single bunch injection from the linac. The consequent limitation of the injection rate restricted the capability of production of the Compton gamma rays in the loss mode, i.e. production of gammas with energy above 20-25 MeV, to about 5*108 photons per sec. Update of the linac for the repetition rate of up to 10 Hz, and modification of the injection kicker for 15 nS pulse length allowed us to developed an alternative multibunch injection scheme with a significant increase of the injection rate into storage ring.

 
TU6PFP005 Status Report on the Centro Nazionale di Adroterapia Oncologica (CNAO) rfq, emittance, ion, diagnostics 1297
 
  • E. Bressi, M. Pullia
    CNAO Foundation, Milan
  • C. Biscari
    INFN/LNF, Frascati (Roma)
 
 

The Centro Nazionale di Adroterapia Oncologica (National Center for Oncological Hadrontherapy, CNAO) is the Italian center for deep hadrontherapy. It will deliver treatments with active scanning both with proton and carbon ion beams. The accelerator complex is based on a 25 m diameter synchrotron capable to accelerate carbon ions up to 400 MeV/u and protons up to 250 MeV. Four treatment lines, in three treatment rooms, are foreseen in a first stage. In one of the three rooms a vertical and a horizontal fixed beam lines are provided, while in the other two rooms the treatment will be administered with horizontal beams only. The injection chain is positioned inside the synchrotron ring itself, to save space and to better exploit the two non-dispersive regions in the synchrotron. The injection chain is made by a 8 keV/u Low Energy Beam Transfer line (LEBT), a RFQ accelerating the beam to 400 keV/u, a LINAC to reach the injection energy of 7 MeV/u and a Medium Energy Beam Transfer line (MEBT) to transport the beam to the synchrotron. This report describes the design and the performances of the CNAO complex, and reports about the status of the commissioning of the machine.

 
TU6PFP006 Conceptual Design of Carbon/Proton Synchrotron for Particle Beam Therapy synchrotron, extraction, proton, cavity 1300
 
  • F. Noda
    Hitachi, Ltd., Energy and Environmental Systems laboratory, Hitachi-shi, Ibaraki-ken
  • H. Akiyama
    Hitachi Ltd., Power & Industrial Systems, 1-1, Saiwai-cho, 3-chome
  • F. Ebina, F. Fujitaka, H. Hae, H. Hiramoto, H. Nishiuchi, K. Saito, M. Umezawa
    Hitachi, Ltd., Energy and Environmental System Laboratory, Hitachi-shi
 
 

Slow cycle synchrotron system for cancer therapy is presented to realize the pencil beam scanning with carbon and proton. The designed synchrotron’s circumference is 60m and the maximum beam energies are 480MeV/u for carbon and 250MeV for proton. These energies correspond to the beam range of 35cm in water. In the treatment system with the present synchrotron, the discrete spot scanning scheme for lateral irradiation is employed using fast beam ON/OFF that is characteristic of the RF driven slow beam extraction from the synchrotron. Distal dose distribution is controlled with energy stacking technique, which is superimposing various bragg peaks which are controlled with the energy of the beam accelerated by the synchrotron. Furthermore, respiratory-gated operation with high throughput will be realized by the variable flat top length and timing for the beam extraction.

 
TU6PFP008 Design Features of a 300 AMeV Superconducting Cyclotron for Hadron Therapy cyclotron, ion, extraction, cavity 1306
 
  • L.A.C. Piazza, L. Calabretta, M. Camarda, D. Campo, G. Gallo, D. Garufi, R. La Rosa, M.M. Maggiore, S. Passarello
    INFN/LNS, Catania
 
 

The study of the Superconducting Cyclotron named SCENT300 [1] was carried out by the accelerator R&D team of LNS-INFN of Catania in collaboration with the University of Catania and supported by IBA (Belgium). The new design features concerning the magnetic properties of the machine and the last results about the beam dynamic are presented.

 
TU6PFP026 Conceptual Design of Helium Ion FFAGs ion, extraction, closed-orbit, focusing 1343
 
  • H.L. Luo, H. Hao, X.Q. Wang, Y.C. Xu
    USTC/NSRL, Hefei, Anhui
 
 

Funding: Work supported by National Natural Science Foundation of China (No.10175062 & 10575100).


In recent years, Fixed Field Alternating Gradient (FFAG) accelerator is becoming a highlight in particle accelerator R&D area. This type of accelerator could accelerate ions with higher beam current than conventional strong focusing circular accelerator, which could be more useful for the study of radioactive material. In this paper, conceptual design of an FFAG with high Helium ion beam current and a few MeV energy which is dedicated to study the impact of Helium embitterment to fusion reactor envelope material is discussed, the periodic focusing structure model is given, following which the calculation result of magnetic field is also presented.

 
TU6PFP030 6D Acceleration Studies in Proton Fixed Field Alternating Gradient Accelerator Lattices lattice, proton, cyclotron, neutron 1354
 
  • S.C. Tygier
    Manchester University, Manchester
  • R.J. Barlow, H.L. Owen
    UMAN, Manchester
 
 

It has been proposed to use a proton Fixed Field Alternating Gradient (FFAG) accelerator to drive an Accelerator Driven Subcritical Reactor (ADSR) as they have the potential to provide high current beams to energies needed, 500 MeV to 1 GeV. This paper describes the results of 6D simulations of acceleration in possible lattice designs to explore longitudinal acceptance. This is needed to evaluate accelerator duty cycle and options for acceleration such as harmonic number jumping.

 
TU6PFP043 Design Study of an Accelerator Mass Spectrometer Based on a Cyclotron cyclotron, ion, ion-source, cavity 1381
 
  • J.-W. Kim
    NCC, Korea, Kyonggi
  • C.C. Yun
    SNU, Seoul
 
 

An accelerator mass spectrometer (AMS) based on a compact cyclotron has been studied for biomedical uses. The system will have the mass resolving power of over 4000 to analyze a few different kinds of isotopes for tracing or chronometric dating. High transmission efficiency is a major design goal to compete with a Tandem AMS. A compact magnet with high stability, a saw tooth harmonic buncher, and flat-topping rf system are the components needed to achieve the goal. The results of design study for the AMS cyclotron and its injection line will be presented as well as the results of model tests for the cavity and the buncher.

 
TU6PFP054 Simulations of Longitudinal Phase Space Painting for the CSNS RCS Injection beam-losses, simulation, synchrotron, proton 1403
 
  • L. Liu, J. Qiu, J. Tang, T. Wei
    IHEP Beijing, Beijing
 
 

China Spallation Neutron Source (CSNS) is a high power proton accelerator-based facility. Uncontrolled beam loss is a major concern in designing the high power proton accelerators to control the radio-activation level. For the Rapid Cycling Synchrotron (RCS) of the CSNS, the repetition frequency is too high for the longitudinal motion to be fully adiabatic. Significant beam loss happens during the RF capture and initial acceleration. To reduce the longitudinal beam loss, phase space painting is used in the RCS injection. This paper presents detailed simulation studies on the longitudinal motion in the RCS by using the ORBIT code, which include different beam chopping factors, momentum offsets, injection times and RF voltage patterns. With a trade-off between the longitudinal beam loss and transverse incoherent tune shift that will also result in beam losses, optimized longitudinal painting schemes are obtained.

 
TU6PFP055 An RF Scenario for Protons and Ions in the PS2 proton, ion, acceleration, emittance 1406
 
  • S. Hancock, M. Benedikt, C. Carli
    CERN, Geneva
 
 

The PS2 is proposed as a replacement for the ageing PS and will provide proton beams with kinetic energies up to 50 GeV. It must also deliver Pb54+ ions, for which the revolution frequency swing will be more than a factor of two. The favoured rf scenario considers a 40 MHz accelerating system and is motivated by the possibility of chopping at up to 40 MHz in the SPL, the proposed proton injector. Using the same principal rf system for ions implies pushing for an unprecedented tuning range and the introduction of a new rf system in LEIR, the existing ion source. We present a solution to the disparate requirements of protons and ions based on a 40 MHz rf system with switchable tuning ranges to cover the large frequency swing required.

 
TU6PFP056 Longitudinal Painting Schemes for H- Charge Exchange Injection into the PS2 simulation, synchrotron, bunching, linac 1409
 
  • C. Carli, M. Benedikt, S. Hancock
    CERN, Geneva
  • V. Knuenz, I. Vonderhaid
    TU Vienna, Wien
 
 

Minimization of direct space charge tune shift at injection into the PS2 is important for the reduction of beam losses. A determining parameter for the tune shift is the bunching factor, defined as mean current over peak current for one RF period. Various longitudinal painting schemes for PS2 injection, all based on synchrotron motion, have been studied with respect to the resulting bunching factors. In particular, schemes using the SPL high-frequency chopper and different energy-spreads and offsets of the incoming beam as well as SPL beam energy modulations on have been simulated with the ESME code.

 
TU6PFP057 Operational Experience with First Circulating Beam in the LHC optics, instrumentation, closed-orbit, controls 1412
 
  • M. Lamont, R. Alemany-Fernandez, R. Bailey, P. Collier, B. Goddard, V. Kain, A. Macpherson, L. Ponce, S. Redaelli, W. Venturini Delsolaro, J. Wenninger
    CERN, Geneva
 
 

Following a series of injection tests, the first attempts to pass beam around both directions of the LHC were successful and led rapidly to circulating beam in the counter clockwise direction (beam 2) and many turns of beam 1. Unfortunately the beam commissioning was curtailed by the incident in sector 34. However, measurements performed during this first commissioning period should that the magnet model of the machine had delivered optics close to nominal, and also very good performance of beam instrumentation and supporting software. Details of the machine set-up and the commissioning procedures are detailed. The measurements performed and the key results from this period are described.

 
TU6PFP058 A Hybrid Design of Project-X linac, SRF, proton, synchrotron 1415
 
  • W. Chou
    Fermilab, Batavia
 
 

Funding: Work supported by the Fermi Research Alliance, LLC under contract No. DE-AC02-07CH11359 with the U.S. Dept. of Energy.


Project-X is a leading candidate of the next major accelerator construction project at Fermilab. The mission need of Project-X is to establish an intensity frontier for particle physics research, or more precisely, to build a multi-MW proton source for neutrino and other particle studies. Coupled with an upgraded Main Injector (MI) and Recycler, an 8 GeV superconducting RF (SRF) H linac meets this need. However, a more cost effective approach would be a hybrid design, namely, a combination of a 2 GeV SRF linac and an 8 GeV rapid cycling synchrotron (RCS) in lieu of an 8 GeV SRF linac. This alternative design also meets the mission need but at a lower cost since a synchrotron is cheaper than a SRF linac. It retains the ability to use a 2 GeV SRF linac for ILC technology development. It reuses the existing Debuncher enclosure and Booster RF. The transport line of 2 GeV H particles is shorter than the present 8 GeV design. The requirement of a cryogenic beam screen can be eliminated. The efficiency of stripping foil is higher and injection loss (kJ) will be lower.


*W. Chou, “A Simple Transition-Free Lattice of an 8 GeV Proton Synchrotron,” this conference.

 
TU6PFP059 Numerical Studies of High-Intensity Injection Painting for Project X space-charge, proton, simulation, linac 1418
 
  • A.I. Drozhdin, D.E. Johnson, L.G. Vorobiev
    Fermilab, Batavia
 
 

Injection painting enables the mitigation of space charge and stability issues, and may be indispensable for the Project-X at Fermilab, delivering high-intensity proton beams to HEP experiments. Numerical simulations of multi-turn phase space painting have been performed for the FNAL Recycler Ring, including a self-consistent space charge model, lattice nonlinearities, H- stripping, particle loss and foil heating. Different painting waveforms were studied to build a uniform (KV-like distribution) and other phase space distributions.

 
TU6PFP060 Current and Future High Power Operation of Fermilab Main Injector kicker, booster, target, proton 1421
 
  • I. Kourbanis, P. Adamson, B.C. Brown, D. Capista, W. Chou, D.K. Morris, K. Seiya, G.H. Wu, M.-J. Yang
    Fermilab, Batavia
 
 

Funding: Work supported by Fermi Research Alliance, LLC under contract No. DE-AC02-07CH11359 with the United States Department of Energy.


Currently Main Injector delivers 330KW of beam power at 120 GeV by using multi-batch slip stacking. The beam power is expected to increase to 400KW after installing clearing gap kickers to eliminate the injection kicker gap loss. The plan to increase the beam power to 700KW for NOvA and the role of MI in Project-X (2.1MW operation) will be discussed.

 
TU6PFP061 Progress in Multi-Batch Slip Stacking in the Fermilab Main Injector and Future Plans kicker, booster, antiproton, target 1424
 
  • K. Seiya, B. Chase, J.E. Dey, P.W. Joireman, I. Kourbanis, J. Reid
    Fermilab, Batavia
 
 

The multi-batch slip stacking has been used for operation since January, 2008 and effectively increased proton intensity to the NuMI target by 50% in a MI cycle. The MI accepts 11 pulses at injection energy from the Booster and sends two pulses to Anti-proton production and nine to the NuMI beam line. The total beam power on a cycle was increased to 340 KW on average. We have been doing beam studies in order to increase the beam power to 400 kW and to control the beam loss. We also discuss 12 batch slip stacking scheme which is going to be used for future Neutrino experiments.

 
TU6PFP063 Synchrotron Operation with Intermediate Charge State Heavy Ion Beams ion, heavy-ion, beam-losses, electron 1430
 
  • P.J. Spiller, L.H.J. Bozyk, P. Puppel, J. Stadlmann
    GSI, Darmstadt
 
 

In order to achieve the goals of the FAIR project, the heavy ion beam intensities have to be increased by two orders of magnitude. Space charge limits and significant beam loss in stripper stages disable a continuation of the present high charge state operation. However, in the energy range of SIS18 and SIS100, the chosen intermediate charge state for uranium 28+, is lower than the equilibrium charge state. Thus ionisation processes due to collisions with rest gas atoms become the main issue with respect to potential beam loss. Therefore, the SIS100 design concept is focused on the goal to minimization the beam-rest gas interaction and consequently the beam loss by charge change: SIS100 is the first synchrotron which has been optimised for the acceleration of intermediate charge state heavy ion operation. Ionisation beam loss, desorption processes and pressure stabilization were the driving issues for the chosen system layout and for several technological approaches. Beside focusing the SIS100 design on this specific issue an extended upgrade program is actually being realized to accommodate SIS18 for the intermediate charge state booster operation.

 
TU6PFP065 Status of the J-PARC 3-GeV RCS neutron, cavity, beam-losses, scattering 1436
 
  • M. Kinsho
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
 
 

The J-PARC 3-GeV rapid cycling synchrotron (RCS) has been beam commissioned since October 2007 and it has been able to provide downstream facilities, the 50-GeV synchrotron (MR) and the Materials and Life Science Facility (MLF) with stable beam required from them. After beam deliver operation to the MR and MLF, while the priority ha s been given to their beam tuning, the RCS also continues further beam studies toward higher beam intensity. On September 18th, 2008, the RCS achieved the beam power of 210kW to beam dump with 25Hz. This presentation will concentrate itself on the outcome of the J-PARC RCS commissioning program, including the discussion on the issues of the high-power operation.

 
TU6PFP067 Beam Loss Issues Connected to the Foil Scattering: Estimation vs. Measurement at the RCS of J-PARC simulation, beam-losses, scattering, insertion 1442
 
  • P.K. Saha, N. Hayashi, H. Hotchi, K. Yamamoto, M. Yoshimoto
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
  • Y. Irie
    KEK, Ibaraki
  • T. Toyama
    J-PARC, KEK & JAEA, Ibaraki-ken
 
 

The beam loss issues connected to the nuclear scattering together with the multiple Coulomb scattering at the charge-exchange foil during the multi-turn injection has been studied in detail for the RCS (Rapid Cycling Synchrotron) of J-PARC (Japan Proton Accelerator Research Complex). Recently, during the beam commissioning of RCS, some experimental data related to such issue has been taken and thus a comparison of the measured beam loss to the estimated one is reported in this paper. When the beam loss from such a source is unavoidable, a realistic estimation is quite important for a fair design of the injection system and the vicinity in order to reduce especially, the uncontrolled beam loss.

 
TU6PFP068 Longitudinal Painting Studies in the J-PARC RCS bunching, simulation, cavity, beam-losses 1445
 
  • F. Tamura, K. Hasegawa, M. Nomura, A. Schnase, T. Shimada, H. Suzuki, M. Yamamoto
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
  • K. Hara, C. Ohmori, M. Tada, M. Yoshii
    KEK/JAEA, Ibaraki-Ken
 
 

In the J-PARC RCS, we employ the longitudinal painting methods, the momentum offset injection method and applying the second harmonic RF voltages, to increase the bunching factor so that the space-charge tune shift is reduced. By the dual-harmonic operation with wide-band MA loaded cavities, in which each single cavity is driven by a superposition of the fundamental and the second harmonic RF signals, we can generate a large amplitude second harmonic RF voltage without extra cavities for the second harmonic RF. We present the results of the beam tests for the longitudinal painting in the J-PARC RCS. Also, we present the beam behavior at very high beam power.

 
TU6PFP069 Physics Design of the PEFP RCS extraction, acceleration, linac, emittance 1448
 
  • J.-H. Jang, Y.-S. Cho, H.S. Kim, H.-J. Kwon
    KAERI, Daejon
  • Y.Y. Lee
    BNL, Upton, Long Island, New York
 
 

Funding: This work is supported by Ministry of Education, Science and Technology of the Korean government.


The proton engineering frontier project (PEFP) is designing the rapid cycling synchrotron (RCS) whose main purpose is the spallation neutron source. The PEFP 100-MeV linac will be the injector to the RCS. The output energy and beam power are 1 GeV and 60 kW at the initial stage. We studied the H- charge exchange injection with transverse and momentum painting schemes. In order to enhance the machine versatility, we studied the slow extraction options for the nuclear physics and medical research in addition to the single turn extraction for the spallation neutron source. This paper summarizes the present status of the physics design of the RCS.

 
TU6PFP086 LHC Beams from the CERN PS Booster emittance, proton, extraction, booster 1494
 
  • B. Mikulec, A. Blas, C. Carli, A. Findlay, K. Hanke, G. Rumolo, J. Tan
    CERN, Geneva
 
 

The CERN PS Booster (PSB) produces a variety of beam flavours for the LHC. While the nominal LHC physics beams require 6 Booster bunches with intensities up to 1.6·1012 protons per bunch, during the LHC commissioning single bunch beams with variable intensities as low as 5·109 protons have to be provided reproducibly. The final transverse and in many cases also the final longitudinal beam characteristics have to be achieved already in the PSB and can be very demanding in terms of beam brightness and stability. The optimized production schemes for the different LHC beam flavours in the PSB and the achieved machine performance are presented. Experience with the first beams sent to the LHC in September 2008 is discussed. An overview of the first measured results with a new production scheme of the nominal LHC beam using single instead of double-batch beam transfer from the PSB to the PS is also given.

 
TU6PFP087 High Intensity Beams from the CERN PS Booster resonance, space-charge, impedance, linac 1497
 
  • B. Mikulec, M. Chanel, A. Findlay, K. Hanke, D. Quatraro, G. Rumolo, J. Tan, R. Tomás
    CERN, Geneva
 
 

The CERN Proton Synchrotron Booster (PSB) has been running for more than 30 years. Originally designed to accelerate particles from 50 to 800 MeV, later upgraded to an energy of 1 GeV and finally 1.4 GeV, it is steadily being pushed to its operational limits. One challenge is the permanent demand for intensity increase, in particular for CNGS and ISOLDE, but also in view of LINAC4. As it is an accelerator working with very high space charge during the low energy part of its cycle, its operational conditions have to be precisely tuned. Amongst other things resonances must be avoided, stop band crossings optimized and the machine impedance minimized. Recently, an operational intensity record was achieved with >4.25·1013 protons accelerated. An orbit correction campaign performed during the 2007/2008 shutdown was a major contributing factor to achieving this intensity. As the PSB presently has very few orbit correctors available, the orbit correction has to be achieved by displacing and/or tilting some of the defocusing quadrupoles common to all 4 PSB rings. The contributing factors used to optimize performance will be reviewed.

 
TU6PFP090 High-Intensity Demonstrations in the J-PARC 3-GeV RCS beam-losses, space-charge, linac, simulation 1504
 
  • H. Hotchi, N. Hayashi, Y. Hikichi, S. Hiroki, J. Kamiya, K. Kanazawa, M. Kawase, M. Kinsho, M. Nomura, N. Ogiwara, R. Saeki, P.K. Saha, A. Schnase, T. Shimada, Y. Shobuda, K. Suganuma, H. Suzuki, H. Takahashi, T. Takayanagi, O. Takeda, F. Tamura, N. Tani, T. Togashi, T. Ueno, M. Watanabe, Y. Watanabe, K. Yamamoto, M. Yamamoto, Y. Yamazaki, H. Yoshikawa, M. Yoshimoto
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
  • A. Ando
    LASTI, Hyogo
  • H. Harada
    Hiroshima University, Graduate School of Science, Higashi-Hiroshima
  • K. Hasegawa, Y. Irie, C. Ohmori, M. Yoshii
    KEK, Ibaraki
  • K. Satou, Y. Yamazaki
    J-PARC, KEK & JAEA, Ibaraki-ken
 
 

The beam commissioning of the J-PARC 3-GeV RCS started in October 2007. The initial machine parameter tuning and underlying beam studies were completed in February 2008 through various beam dynamics measurements, such as optical functions, turn-by-turn beam positions, and transverse and logitudinal beam profiles. Now the RCS is in transition from the first commissioning phase to the next challenging stage and our efforts hereafter will be focused on higher beam power operations. In this paper, we describe experimental results obtained in the high intensity demonstrations in October 2008, together with the corresponding simulation results.

 
TU6PFP091 Performance of the Bump System for the Painting Injection at J-PARC power-supply, target, emittance, controls 1507
 
  • T. Takayanagi, H. Harada, H. Hotchi, Y. Irie, J. Kamiya, M. Kinsho, P.K. Saha, T. Togashi, T. Ueno, M. Watanabe, M. Yoshimoto
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
  • K. Satou
    J-PARC, KEK & JAEA, Ibaraki-ken
 
 

The painting injection of the 3-GeV RCS in J-PARC has been tested since May in 2008. The shift bump-magnets, which give a constant bump field in a horizontal plane during injection, comprise four magnets connected in series. However, the total integrated magnetic field over the four magnets is not zero because of the magnetic field interferences with the neighboring quadrupole magnets. So the gap of each magnet was adjusted by inserting thin insulators into the splitting plane of the side yoke so that the field integration becomes zero. The thickness was determined experimentally. The closed orbit distortion due to the field imbalances was then confirmed to be less than 1 mm. Another four paint bump-magnets are also necessary to give time-dependent fields. They are connected to their own power supplies, separately. The excitation of each magnet is calibrated by using the beam so that the created bump orbit satisfies the position and inclination at the injection point, and there are no orbit distortions outside the injection area. As for a vertical plane, a vertical paint magnet is located pi-radian upstream of the injection point to control the vertical angle of the beam.

 
TU6PFP096 Cold-Cathode Kiloampere Electron Gun with Secondary Emission at Relativistic Voltage gun, electron, cathode, high-voltage 1522
 
  • S.A. Cherenshchykov
    NSC/KIPT, Kharkov
 
 

Funding: The research was supported the STCU foundation in frame of the project 1968.


Magnetron Injection Gun with voltage up {10}00 kV and current more 1 kA was calculated, designed and manufactured. The gun was tested in nanosecond and microsecond operating modes. The application of nanosecond voltage pulses with amplitude up to 600 kV permitted to obtain the secondary-emission current up to 5 kA. The cathode testing in microsecond mode permitted to obtain beam pulse with amplitude up to 1.2 kA at voltage of 400 kV in magnetic field of 0.3 T. There were obtained beam traces on the copper plate. Traces had the form of rings with diameter of 125 mm and width of 5 mm. The secondary emission nature of the cathode current was established. The identification was held basing on considered features of the exciting and on the maintenance of the secondary emission current. However, there is the probability of the parasitic explosive emission at extremely high voltage values since 800 kV. The gun may be used for charge particle accelerators in injectors and RF power sources. Results of the work and prospects of the secondary emission gun development are discussed.

 
TU6RFP014 The EMI Reduction of Pulsed Magnets in NSRRC kicker, shielding, background, power-supply 1559
 
  • Y.-H. Liu, C.K. Chan, C.-H. Chang, J.-R. Chen, K.C. Kuo, C.-S. Yang
    NSRRC, Hsinchu
 
 

The purpose of this paper is to reduce the Electromagnetic Interference (EMI) from kicker and its pulsed power supply. Analysis of conducted and radiated EMI is the beginning mission. Different frequency range of radiated EMI was measured by different sensors. A hybrid shielding method was used to test reduction of radiated EMI. The copper and μ-metal enclosure was used on kicker magnet to prevent the radiated EMI. The reduction of electromagnetic field showed the effect of different material. Besides, the conducted EMI was also tested and eliminated by adding grounding routs. For decreasing grounding noise to other systems, the individual grounding bus was installed. The experimental results showed significant effect. In the future, TPS (Taiwan Photon Source) injection magnets will design higher performance, lower EMI than TLS (Taiwan Light Source). Therefore reducing and eliminating the interference of electromagnetic waves will be a very important issue. All the EMI prevention schemes will implement in the new project.

 
TU6RFP022 First Results for the Beam Commissioning of the CERN Multi-Turn Extraction extraction, proton, kicker, septum 1578
 
  • S.S. Gilardoni, F. Arnold Malandain, E. Benedetto, T. Bohl, S. Cettour Cave, K. Cornelis, H. Damerau, F. Follin, T. Fowler, F. Franchi, P. Freyermuth, H. Genoud, R. Giachino, M. Giovannozzi, S. Hancock, Y. Le Borgne, D. Manglunki, G. Metral, L. Pereira, J.P. Ridewood, Y. Riva, M. Schokker, L. Sermeus, R.R. Steerenberg, B. Vandorpe, J. Wenninger
    CERN, Geneva
 
 

The Multi-Turn Extraction, a new type of extraction based on beam trapping inside stable islands in the horizontal phase space, has been commissioned during the 2008 run of the CERN Proton Synchrotron. Both single- and multi-bunch beams with a total intensity up to 1.4×1013 protons have been extracted with efficiencies up to 98%. Furthermore, injection tests in the CERN Super Proton Synchrotron were performed, with the beam then accelerated and extracted to produce neutrinos for the CERN Neutrino to Gran Sasso experiments. The results of the extensive measurement campaign are presented and discussed in details.

 
TU6RFP024 Initial Results from Beam Commissioning of the LHC Beam Dump System kicker, extraction, diagnostics, instrumentation 1584
 
  • B. Goddard, I.V. Agapov, E. Carlier, L. Ducimetière, E. Gallet, M. Gyr, L.K. Jensen, O.R. Jones, V. Kain, T. Kramer, M. Lamont, M. Meddahi, V. Mertens, T. Risselada, J.A. Uythoven, J. Wenninger, W.J.M. Weterings
    CERN, Geneva
 
 

Initial commissioning of the LHC beam dump system with beam took place in August and September 2008. The preparation, setting-up and the tests performed are described together with results of the extractions of beam into the dump lines. Analysis of the first detailed aperture measurements of extraction channels and kicker performance derived from dilution sweep shapes are presented. The performance of the other equipment subsystems is summarised, in particular that of the dedicated dump system beam instrumentation.

 
TU6RFP025 Operational Considerations for the PSB H- Injection System emittance, linac, scattering, kicker 1587
 
  • W.J.M. Weterings, M. Aiba, J. Borburgh, C. Carli, T. Fowler, B. Goddard
    CERN, Geneva
 
 

For the LINAC4 project the PS Booster (PSB) injection system will be upgraded. The 160 MeV H- beam will be distributed to the 4 superimposed PSB synchrotron rings and horizontally injected by means of an H- charge-exchange system. Operational considerations for the injection system are presented, including expected beam losses from field stripping of H- and excited H0 and foil scattering, possible injection failure cases and expected stripping foil lifetimes. Loading assumptions for the internal beam dumps are discussed together with estimates of doses on various components.

 
TU6RFP026 Beam Commissioning of Injection into the LHC kicker, beam-losses, optics, controls 1590
 
  • V. Mertens, I.V. Agapov, B. Goddard, M. Gyr, V. Kain, T. Kramer, M. Lamont, M. Meddahi, J.A. Uythoven, J. Wenninger
    CERN, Geneva
 
 

The LHC injection tests and first turn beam commissioning took place in late summer 2008, after detailed and thorough preparation. The beam commissioning of the downstream sections of the SPS-to-LHC transfer lines and the LHC injection systems is described. The details of the aperture measurements in the injection regions are presented together with the performance of the injection related equipment. The measured injection stability is compared to the expectations. The operational issues encountered are discussed.

 
TU6RFP027 Resonant Third-Integer Extraction from the PS2 extraction, sextupole, quadrupole, resonance 1593
 
  • M. Gyr, W. Bartmann, M. Benedikt, B. Goddard, M. Meddahi
    CERN, Geneva
  • A. Koschik
    ETH, Zürich
  • D. Mayani Parás
    UNAM, México, D.F.
 
 

For the proposed PS2 accelerator several extraction systems are needed, including a slow third-integer resonant extraction. The requirements are presented together with the conceptual considerations for the sextupole locations and strengths, the separatrices at the extraction elements and the aperture implications for the overall machine. Calculations of the phase space separatrices have been computed with a new code for the physics of slow resonant extraction, which is briefly reviewed. Implications for the extraction equipment design and for the injection-extraction straight section optics are discussed.

 
TU6RFP028 Laser Stripping for the PS2 Charge-Exchange Injection System laser, resonance, emittance, dipole 1596
 
  • B. Goddard, W. Bartmann
    CERN, Geneva
  • V.V. Danilov
    ORNL, Oak Ridge, Tennessee
  • D.E. Johnson
    Fermilab, Batavia
 
 

Laser stripping for an H- injection system into the proposed PS2 accelerator could provide an attractive alternative to the use of a conventional stripping foil. In this paper possible concepts for a 4 GeV laser stripping system are outlined and compared, using either laser or magnetic initial stripping steps and a resonant excitation of the intermediate H0 atom, followed by a final magnetic stripping. Issues of laser power, overall efficiency and emittance growth are discussed.

 
TU6RFP030 Fast Injection into the PS2 kicker, vacuum, impedance, septum 1602
 
  • J.A. Uythoven, W. Bartmann, J. Borburgh, T. Fowler, B. Goddard, M. Meddahi
    CERN, Geneva
 
 

The conceptual considerations of a fast injection system for protons and ions in the proposed PS2 accelerator are presented. Initial design parameters of the injection septum and kicker systems are derived, taking into account rise and fall times, apertures and machine optics. The requirements for an injection dump used for failures are described. Possible limitations and technical issues are outlined.

 
TU6RFP031 LHC Beam Dump System - Consequences of Abnormal Operation simulation, kicker, extraction, beam-losses 1605
 
  • T. Kramer, B. Goddard, J.A. Uythoven
    CERN, Geneva
 
 

The LHC beam dump system is one of the most critical systems concerning machine protection and safe operation. It is used to dispose of high intensity beams between 450 GeV and 7 TeV. Studies into the consequences of abnormal beam dump actions have been performed. Different error scenarios have been evaluated using particle tracking in MAD-X, including an asynchronous dump action, and the impact of different orbit and collimator settings. Losses at locations in the ring and the beam dump transfer lines have been quantified as a function of different settings of the dump system protection elements. The implications for the setting up and operation of these protection elements are discussed.

 
TU6RFP040 Design of the TPS Injection System kicker, septum, vacuum, storage-ring 1632
 
  • C.K. Chan, C.-H. Chang, P.J. Chou, C.-S. Fann, G.-Y. Hsiung, Y.-H. Liu, C.-S. Yang
    NSRRC, Hsinchu
  • J.-R. Chen
    National Tsing Hua University, Hsinchu
 
 

The Taiwan Photon Source (TPS) is a new 3 GeV synchrotron light source to be built at the National Synchrotron Radiation Research Center (NSRRC) in Taiwan. The design of TPS is aimed to provide a low-emittance and high-brilliance beam with operation in the top-up mode. In this paper we present the design of the TPS injection section and the transport line from booster to storage ring. The specifications and parameters of the septa, kickers, and ceramic chambers are also described.

 
TU6RFP041 Physical Model of Hydrogen Ion Laser Stripping laser, proton, electron, ion 1635
 
  • T.V. Gorlov, V.V. Danilov, A.P. Shishlo
    ORNL, Oak Ridge, Tennessee
 
 

Funding: *SNS is managed by UT-Battelle, LLC, for the U. S. Department of Energy under Contract No. DE-AC05-00OR22725.


Thin carbon foils used as a charge strippers for H־ ions have a limited life time and produce uncontrolled beam loss. Thus, foil based injection is one of the factors limiting beam power in high intensity proton rings. There is a possibility to replace such foils by laser-assisted stripping of negative hydrogen ions, a method developed and demonstrated at the SNS accelerator in Oak Ridge. In this paper we present progress in the physics and computation of H־ laser stripping. We present a physical model which includes such factors as the Stark effect, the polarization of the laser field, and the spontaneous relaxation and autoionization of hydrogen atoms in a strong electro-magnetic field. The model formulates a quantum mechanical problem that can be solved numerically using a module created for the PyORBIT parallel code developed at SNS.

 
TU6RFP042 An Electron Beam SNS Foil Test Stand electron, proton, neutron, factory 1638
 
  • R.W. Shaw, D.P. Bontrager, M.A. Plum, L.L. Wilson
    ORNL, Oak Ridge, Tennessee
  • C.S. Feigerle
    University of Tennessee, Knoxville, Tennessee
  • C.F. Luck
    ORNL RAD, Oak Ridge, Tennessee
 
 

Funding: SNS is managed by UT-Battelle, LLC, for the U.S. DOE under contract DE-AC05-00OR22725.


Nanocrystalline diamond foils are now in use for injection stripping at the SNS. Typical dimensions are 17x25 mm x 300-350 ug/cm2 physical thickness. Corrugations of the foil help to maintain flatness, but after ca. 300 C of injected charge curling is observed. We continue to experiment with foil preparation techniques. To allow independent stripper foil testing without impacting SNS neutron production, we have assembled a 30 keV electron beam foil test facility to investigate foil lifetimes. At 30 keV acceleration, a 1.6 mA/mm2 electron beam imparts the same peak heating load to a carbon foil as the injected and circulating current of the 1.4 MW SNS. At this energy the electron stopping distance is approximately six-fold longer than the foil thickness. The electron gun is capable of 5 mA current in a focal spot less than 1 mm FWHM diameter. Two foil stations are available for sequential tests, and foils can be rotated relative to the beam to vary their effective thickness. A 6 us risetime optical pyrometer records instantaneous foil temperatures over the 60 Hz heating profile. A CCD camera captures foil images over time. Results using this test stand are described.

 
TU6RFP043 Optimization of the Booster to SPEAR Transport Line for Top-Off Injection optics, controls, booster, vacuum 1641
 
  • J.A. Safranek, W.J. Corbett, X. Huang, J.J. Sebek
    SLAC, Menlo Park, California
  • W.X. Cheng
    BNL, Upton, Long Island, New York
 
 

Funding: Work supported by the US Department of Energy, Office of Basic Energy Sciences.


In the past, SPEAR3 has had typically 50 to 70% injection efficiency. Much of the lost injected beam hit the small gap vacuum chambers at the insertion devices. We are now implementing injection with photon beamline shutters open, so these losses create Bremsstrahlung down the photon beamlines, increasing radiation levels on the photon experimental floor. In this paper, we describe work done to better control the booster to SPEAR (BTS) transport line beam so as to reduce losses during injection. We have used new BTS BPM electronics to control the transport line trajectory. The trajectory response on these BPMs has been used to correct the BTS optics. We use turn-by-turn BPM readings of the injected beam in SPEAR to optimize the BTS trajectory in all six transverse and longitudinal coordinates. We use turn-by-turn profile measurements of the injected beam to verify the BTS optics correction. The stainless steel windows have been removed from the BTS vacuum system to reduce the transverse dimensions of the injected beam.

 
TU6RFP045 Stored Beam Stability during Pulsed Sextupole Injection at the Photon Factory Storage Ring photon, dipole, factory, sextupole 1647
 
  • H. Takaki, N. Nakamura
    ISSP/SRL, Chiba
  • K. Harada, T. Honda, Y. Kobayashi, T. Miyajima, S. Nagahashi, T. Obina, M. Shimada, A. Ueda
    KEK, Ibaraki
 
 

We successfully demonstrated a new beam injection method using a single pulsed sextupole magnet (PSM). The PSM has a parabolic-shaped magnetic field, which is expected to provide an effective kick to the injected beam without little effects on the stored beam. We installed the PSM injection system at the Photon Factory storage ring (PF-ring) and succeeded in injecting the beam into PF-ring and storing the current up to 450 mA. This is the first demonstration of the PSM beam injection in electron storage rings. We also tested top-up injection and confirmed that dipole oscillation of the stored beam was sufficiently reduced compared with that generated by the conventional injection system. In this conference, we will present the experimental results and the advantages of the PSM beam injection.

 
TU6RFP053 Controlled Emittance Blow Up in the Tevatron proton, emittance, kicker, luminosity 1668
 
  • C.-Y. Tan, J. Steimel
    Fermilab, Batavia
 
 

Funding: Operated by Fermi Research Alliance, LLC under Contract No. DE-AC02-07CH11359 with the United States Department of Energy.


We have designed and commissioned a system which blows up the transverse emittance of the anti-proton beam without affecting the proton beam. It consists of a bandwidth limited noise source centered around the betatron tune, a power amplifier and a directional stripline kicker. The amount of blow up is controlled by the amount of energy delivered to the anti-protons betatron bands.

 
TU6RFP070 A Prototype of Pulsed Power Supply for CSNS/RCS Injection Painting Bump Magnets power-supply, feedback, controls, pulsed-power 1711
 
  • L. Shen, Y.L. Chi, C. Huang
    IHEP Beijing, Beijing
 
 

The prototype of pulsed power supply for injection painting bump magnets of CSNS/RCS is being developed. This pulsed power supply consists of IGBT H bridges in series and parallel. The pulse current of the prototype is 18000A, the voltage is about 3KV and the equivalent frequency is about 1MHz. This paper will introduce this prototype in detail.

 
TU6RFP071 Development of a Prototype Bump Magnet for CSNS/RCS Injection simulation, linac, synchrotron, target 1714
 
  • J.X. Song, Y. Hao, L.H. Huo, W. Kang, L. Wang
    IHEP Beijing, Beijing
 
 

China Spallation Neutron Source is a high intensity beam facility planed to build in future in China. It is composed of Linac, RCS and target station. Two sets of pulsed painting bump magnets, 4 magnets in each set , will be used in CSNS RCS to create a dynamic orbit bump for injection process. The design of these 8 bump magnets has been completed. One prototype bump magnet has been assembled and tested. In this paper, the magnetic field analysis, the eddy current and thermal consideration in the end plates of the prototype bump magnet are presented, and issues of the magnet development, construction and test are discussed.

 
TU6RFP077 Gap Clearing Kicker Magnet for Main Injector kicker, impedance, simulation, high-voltage 1729
 
  • C.C. Jensen, R.E. Reilly, I. Terechkine
    Fermilab, Batavia
 
 

Funding: Fermilab is operated by Fermi Research Alliance, LLC under Contract No. DE-AC02-07CH11359 with the United States Department of Energy.


A fast kicker magnet has been designed for use in Main Injector at Fermilab. The magnet will be used for controlled removal of unbunched beam created in the slip stacking process. The strength of each of the six magnets is 75 G·m at 500 A. The aperture is 11.4 cm wide x 5.3 cm high x 64 cm long. The field rise time from 3% to 97% of less than 57 ns has been achieved along with a flattop variation of less than ±3% variation. Results of simulation and measurements will be presented. The pulser is described in a companion paper.

 
TU6RFP080 Cold Cathode Thyratron Based High-Voltage Kicker System for the Duke Accelerators: Performance and Improvements kicker, booster, high-voltage, cathode 1736
 
  • V. Popov, S.F. Mikhailov, P.W. Wallace
    FEL/Duke University, Durham, North Carolina
  • O. Anchugov, Yu. Matveev, D.A. Shvedov
    BINP SB RAS, Novosibirsk
 
 

Funding: Supported by US DoE grant #DE-FG02-01ER41175


The Duke FEL/HIGS (Free electron laser/High Intensity Gamma-ray source) facility has recently undergone through a series of major upgrade. As a part of this upgrade, a kicker system was designed to provide reliable injection from the booster into the storage ring at any energy chosen from the range of 240 MeV to 1.2 GeV. Relatively new and not sufficiently studied switching device has been selected as a basic component to build a set of nanosecond resolution high-voltage generators. So called Pseudo-Spark Switch (PSS), also known as a cold cathode thyratron, has the same or slightly better jitter, reasonable range of switched high voltages and significantly lower heater power as compared to the traditional “hot” thyratrons. Despite of the fact that it requires more complicated triggering system, this device still seems very attractive as a driver for short pulse kickers. Almost three years of operation of the Duke FEL facility has revealed number of advantages and challenges related to the thyratrons of this type. In this paper we depict design features of the kicker system, discuss some accomplished improvements and summarize our three year experience.

 
TU6RFP082 Tests and Operational Experience with the DAΦNE Stripline Injection Kicker kicker, impedance, damping, simulation 1739
 
  • F. Marcellini, D. Alesini, S. Guiducci, P. Raimondi
    INFN/LNF, Frascati (Roma)
 
 

New injection stripline kickers are operating since December 2007 at the DAΦNE collider. They are designed to operate with very short pulse generators to perturb only the injected bunch and the two stored adjacent ones at 2.7 ns and are a test for the design of the fast kickers of the damping ring of the International Linear Collider (ILC). Stripline frequency response and impedance measurements have been performed to characterize the structure and are compared to the simulation results. Operational performances are also described, pointing out the problems occured and the flexibility of the stripline structure that worked with both the short and the old pulse generators and has been used as an additional damping kicker to improve the efficiency of the horizontal multibunch feedback system.

 
TU6RFP083 Measurement Results of the Characteristic of the Pulse Power Supply for the Injection Bump System in J-PARC 3-GeV RCS power-supply, linac, proton, synchrotron 1742
 
  • T. Takayanagi, Y. Irie, J. Kamiya, M. Kinsho, T. Togashi, T. Ueno, M. Watanabe, M. Yoshimoto
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
 
 

The main circuit of the switching power supplies for the injection bump system is composed of multiple-connection of the IGBT assemblies. The element of the IGBT assembly, which is the power supply of the shift bump-magnets, is a type of 3300V-1200A and 6 kHz in elementary frequency. The power supply has the output performance of 20 kA / 6.6 kV. The synthetic frequency of the multiple-connection assemblies is over 48 kHz and the tracking error less than 1 % is proved. The beam commissioning test of long-term operation for about three-week was performed. The deviation of the exciting current from the programmed current pattern has been confirmed less than 1%. The peculiar characteristic of the pulse power supply has been obtained by the analysis on the frequency response of the exciting current and the magnetic field. In the FFT analytical result of the magnetic field, the peaks of 48 kHz and its higher harmonics that are related to the switching frequency was observed. The ground loop current and the voltage were also measured.

 
TU6RFP091 Development of an Adder-Topology ILC Damping Ring Kicker Modulator damping, kicker, high-voltage, extraction 1760
 
  • T. Tang, C. Burkhart
    SLAC, Menlo Park, California
 
 

Funding: Work supported by the Department of Energy under contract No. DE-AC02-76SF00515


The injection and extraction kickers (50 Ω) for the ILC damping rings will require highly reliable modulators to deliver ±5 kV, 2 ns flattop (~1 ns rise and fall time) electrical pulses at up to 6 MHz*. An effort is underway at SLAC National Accelerator Laboratory to meet these requirements using a transmission line adder topology to combine the output of an array of ~1 kV modules. The modules employ an ultra-fast hybrid driver/MOSFET that can switch 33 A in 1.2 ns. Experimental results for a scale adder structure will be presented.


*ILC Reference Design Report, http://www.linearcollider.org/cms/?pid=1000437

 
WE1RAC05 Automated Operation of the MLS Electron Storage Ring controls, storage-ring, target, EPICS 1798
 
  • T. Birke, B. Franksen, M.V. Hartrott, G. Wüstefeld
    BESSY GmbH, Berlin
  • M. Abo-Bakr, J. Feikes
    HZB, Berlin
 
 

The Metrology Light Source (MLS) is in user operation since April 2008 working at energies ranging from {10}5 MeV up to 630 MeV, operating currents from a single electron up to 200 mA and different values for the momentum compaction factor. In parallel to machine commissioning, an automated finite state machine has been developed. This code knows, controls and coordinates a broad manifold of machine states and meanwhile has been evolved to an automated operator acting by itself on demand of a few high level commands. Actions range from plain device I/O to complex transactions including filesystem operations and multiple device I/O. The aim is to always keep machine and control system in a well-defined state. We describe the program and report on the experience with the automated operation using this application.

 

slides icon

Slides

 
WE1GRI01 Progress with MW-Class Operation of the Spallation Neutron Source beam-losses, linac, target, laser 1818
 
  • J. Galambos
    ORNL, Oak Ridge, Tennessee
 
 

Funding: ORNL/SNS is managed by UT-Battelle, LLC, for the U.S. Department of Energy under contract DE-AC05-00OR22725.


The Spallation Neutron Source (SNS) has operated at beam powers over 650 kW, and is expecting to approach 1 MW operation by the summer of 2009. Challenges in operating a proton accelerator at these power levels is reducing the uncontrolled beam loss to levels approaching 10-6/meter, and ensuring machine protection. Experience with beam tuning and safely handling the high power will be presented. Also the progress in beam loss reduction over the course of the power ramp-up will be reviewed.


On behalf of the SNS Team

 

slides icon

Slides

 
WE1GRI02 Beam Commissioning of the J-PARC Main Ring extraction, acceleration, power-supply, quadrupole 1823
 
  • H. Kobayashi
    KEK, Ibaraki
 
 

The J-PARC accelerator comprises a 400 MeV linac, a 3-GeV Rapid Cycling Synchrotron (RCS) and a Main Ring (MR). In the linac, an H- ion beam was successfully accelerated to 181 MeV, the design target for the first step in Phase I, on January 24, 2007. Subsequently, full beam energy of 3 GeV was achieved in the RCS on October 31, 2007. The first beam commissioning of the MR was carried out in May and June 2008. Injection, circulation with rf capture and extraction to the injection beam dump were successfully performed. Some other basic tunings such as COD correction and chromaticity correction were also done well. In the MR, there are two extraction sections. One is for the Hadron Experimental Facility for which slow extraction will be mainly used and the other for neutrino experiment, which requires fast beam extraction. After confirming the basic performance of beam injection and beam circulation with rf capture, we have installed all devices for these two extraction sections and have progressed fine-tuning of ramp-up patterns of power supplies. Beam acceleration will start from December 2008. The first result of beam acceleration and extraction will be reported.

 

slides icon

Slides

 
WE1GRI03 Design Optimization of PS2 extraction, proton, ion, kicker 1828
 
  • M. Benedikt, B. Goddard
    CERN, Geneva
 
 

The PS2 will replace the present CERN-PS as the LHC pre-injector. It will have twice the PS energy and twice the circumference. Extensive design optimization is presently ongoing with the aim of starting the PS2 construction around 2011 and delivering beams for physics in 2017. The talk describes the various PS2 design constraints, the optimization steps, and the path towards the final design.

 

slides icon

Slides

 
WE2PBC02 A New Mode for Operation with Insertion Devices at UVX wiggler, insertion, insertion-device, betatron 1852
 
  • L. Liu, R.H.A. Farias, X.R. Resende, P.F. Tavares
    LNLS, Campinas
 
 

UVX is a 1.37 GeV electron storage ring at the Brazilian Synchrotron Light Laboratory (LNLS). The ring is composed of a 6-fold symmetric double-bend achromat lattice with 4 sections reserved for insertion devices. The storage ring was commissioned in 1997 in a mode of operation with high (~12 m) vertical betatron functions in the insertion straights. However, the need for operation with reduced vertical aperture arose with the gradual installation of insertion devices over the years and is particularly important for operation with a 14 mm vertical aperture superconducting wiggler scheduled for installation in late 2009. To cope with this restricted aperture, a new mode with low (~0.8 m) vertical betatron function in all six long straights was deemed necessary and was implemented at the end of 2008. In this report we present the commissioning results of the low vertical beta mode and the advantages in operating in this mode with insertions.

 

slides icon

Slides

 
WE4RAI02 The CERN LHC - World's Largest Vacuum Systems vacuum, cryogenics, ion, collider 1936
 
  • J.M. Jimenez
    CERN, Geneva
 
 

With the successful circulation of beams in the Large Hadron Collider (LHC), its vacuum system becomes the World’s largest vacuum system under operation. This system is composed of 54 km of UHV vacuum for the two circulating beams and about 50 km of insulation vacuum around the cryogenic magnets and the liquid helium transfer lines. The LHC complex is completed by 7 km of high vacuum transfer lines for the injection of beams from the SPS and their dumping. Over the 54 km of UHV beam vacuum, 48 km are at cryogenic temperature (1.9 K), the remaining 6 km are at ambient temperature and use extensively non-evaporable getter (NEG) coatings, a technology that was born and industrialised at CERN. The cryogenic insulation vacuums, less demanding technically, impress by their size and volume: 50 km and 15000 m3. Once cooled at 1.9 K, the cryopumping allows reaching pressure in the 10-4 Pa range. This paper describes the LHC vacuum system, its behaviour in presence of beams as well as the detailed actions undertaken to recover its integrity after the electrical short which happened in a quadrupole bus-bar on 19th of September 2008.

 

slides icon

Slides

 
WE4RAC03 Fifteen Years Operation Experiences of TLS Vacuum System vacuum, photon, SRF, kicker 1941
 
  • G.-Y. Hsiung, C.K. Chan, C.-C. Chang, C.L. Chen, S-N. Hsu, C.Y. Yang
    NSRRC, Hsinchu
  • J.-R. Chen
    National Tsing Hua University, Hsinchu
 
 

The Taiwan Light Source (TLS), a third generation accelerator, has been operated successfully since 1993. It has been upgraded to increase the beam energy from 1.3 GeV to 1.5 GeV and the consequent capability of full energy injection afterwards. While the beam current has been increased from 200 mA to 300 mA after replacement of RF cavities with superconducting one. The vacuum pressure tends to decrease continuously after installations of 3 undulators and 4 wigglers as well as the new front ends. The accumulated beam dose increased faster up to > 14500 Ah after the routine operational top-up mode since 2006 with average pressure has been maintained below 0.13 nPa/mA. The beam life time of 6 hours at 300 mA has been kept with a limitation of Touschek life time at a stable beam with variation of photon flux < 0.05%. However, the photon absorbers of front ends have been replaced with new ones for subjecting the higher irradiation power after upgrading. The good dynamic pressure reflects the effective pumping performance. The experiences of components failures will be summarized in this paper.

 

slides icon

Slides

 
WE4RAC04 Power Supply System for SESAME Booster booster, kicker, dipole, septum 1944
 
  • S. Varnasseri, A. Nadji
    SESAME, Amman
 
 

The SESAME booster, with a circumference of 38 m, has several bending magnets, focussing quadrupoles and defocussing quadrupoles and also the injection and extraction septums and kickers. There wil be one ramping power converter which supplies a series of 12 dipole magnets. Also 12 focussing magnets family and 6 defocussing magnets family are supplied separately with two ramping power converters. Technical issues of all the ramping and pulsed power supplies needed for the SESAME booster are disussed in this paper.

 
WE4PBI01 EMMA, the World's First Non-Scaling FFAG Accelerator acceleration, cavity, diagnostics, extraction 1947
 
  • S.L. Smith
    STFC/DL/ASTeC, Daresbury, Warrington, Cheshire
 
 

EMMA, the Electron Model with Many Applications, was originally conceived as a model of a GeV-scale muon accelerator. The non-scaling (NS) properties of resonance crossing, small apertures, parabolic ToF and serpentine acceleration are novel, unproven accelerator physics and require "proof of principle". EMMA has metamorphosed from a simple "demonstration" objective to a sophisticated instrument for accelerator physics investigation with operational demands far in excess of the muon application that lead to technological challenges in magnet design, rf optimisation, injection and extraction, and beam diagnostics. Machine components procured in 2008 will be installed February-May 2009 leading to full system tests June-August and commissioning with electrons beginning September 2009.

 

slides icon

Slides

 
WE4PBC02 SNS Ring Operational Experience and Power Ramp Up Status target, beam-losses, space-charge, beam-transport 1952
 
  • M.A. Plum
    ORNL, Oak Ridge, Tennessee
 
 

Funding: SNS is managed by UT-Battelle, LLC, for the U.S. DOE under contract DE-AC05-00OR22725


The SNS Ring has now been operating for about 2.5 years, and our march continues to increase the beam power to the design value of 1.4 MW. The Ring is a loss-limited machine, and in general the radioactivation levels are good, but there are some unanticipated hot spots that we are working to relieve. Beam optics functions have been measured using the model independent and orbit response matrix methods, and our results will be compared to the ideal model. High-intensity beam profiles measurements show space-charge effects, and these will be compared to model calculations. We will also discuss the status of equipment upgrades that are now in progress in the high-energy beam transport momentum dump, the injection-dump beam line, and in the ring-to-target beam line.

 

slides icon

Slides

 
WE4GRC01 Beam Diagnostics at the First Beam Commissioning of the J-PARC MR proton, extraction, electron, beam-losses 1964
 
  • T. Toyama, D.A. Arakawa, A. Arinaga, Y. Hashimoto, S. Hiramatsu, S. Igarashi, S. Lee, H. Matsumoto, J.-I. Odagiri, M. Tejima, M. Tobiyama, N. Yamamoto
    KEK, Ibaraki
  • K. Hanamura, S. Hatakeyama
    MELCO SC, Tsukuba
  • H. Harada
    JAEA, Ibaraki-ken
  • N. Hayashi, K. Yamamoto
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
  • K. Satou
    J-PARC, KEK & JAEA, Ibaraki-ken
 
 

Beam commissioning of the J-PARC MR has been going on from May 2008. The beam was one bunch of 4·1011 protons, nearly one hundredth of the design value. Here describe performances of the beam diagnostic devices: DCCT's, BPM's, BLM's, profile monitors and tune meters. Diagnostic design for the design intensity will be also included.

 

slides icon

Slides

 
WE4GRC03 First Results from the LHC Beam Instrumentation Systems proton, instrumentation, beam-losses, quadrupole 1970
 
  • E. Bravin
    CERN, Geneva
 
 

During the 2008 LHC injection synchronisation tests and the subsequent days with circualting beam, the majority of the LHC beam instrumentation systems were capable of measuring their first beam parameters. This includes the two large, distributed, beam position and beam loss systems, as well as the scitillating and OTR screen systems, the fast and DC beam current transformer systems, the tune measurement system and the wire scanner system. The fast timing system was also extensively used to synchronise most of this instrumentation. This paper will comment on the results to date, some of the problems observed and improvements to be implemented before the next LHC run.

 

slides icon

Slides

 
WE4GRC05 Machine Protection for the Experiments of the LHC proton, dipole, beam-losses, interlocks 1976
 
  • R. Appleby, D. Macina
    CERN, Geneva
 
 

The LHC stored beam contains 362 MJ of energy at the top beam energy of 7 TeV, presenting a significant risk to the components of the machine and the detectors. In response to this threat, a sophisticated system of machine protection has been developed to minimize the danger, and detect potentially dangerous situations. In this paper, the protection of the experiments in the LHC from the machine is considered, focusing on pilot beam strikes on the experiments during injection and on the dynamics of hardware failure with a circulating beam, with detailed time-domain calculations performed for LHC ring power converter failures and magnet quenches. The prospects for further integration of the machine protection and experimental protection systems are considered,along with the risk to near-beam detectors from closed local bumps.

 

slides icon

Slides

 
WE4GRC06 ALS Top-Off Mode Beam Interlock System controls, radiation, interlocks, storage-ring 1979
 
  • K.M. Baptiste, M.O. Balagot, W. Barry, P.W. Casey, H.K. Chen, R.S. Müller, D. Robin, C. Steier, J.M. Weber
    LBNL, Berkeley, California
 
 

Funding: Supported by the U.S. Department of Energy under Contract No. DE-AC02-05CH11231.


ALS has been upgraded by adding Top-Off Mode, a new mode of operation to the existing modes of Fill and Stored Beam. The Top-Off Mode permits injection of 1.9GeV electron beam into the Storage Ring, with the safety shutters open, once certain strict conditions are met and maintained. Top-Off Mode enables User operation without an interruption caused by mode switching between the Stored Beam Mode when safety shutters are open, to the Fill Mode with the safety shutters closed and back. The conditions necessary to permit Top-Off Mode are; stored beam is present, the energies are matched between the injector and storage ring, a select set of storage ring lattice magnets are operating at the correct current levels, and radiation losses are minimized. If certain combinations of these conditions are not met, a potentially dangerous condition of injecting electrons down a users beam line can exist. Therefore a system of mode control, energy match, lattice match and stored beam interlocks are needed to control the injected beam prohibiting potentially dangerous conditions. In this paper we will present the Top-Off Mode Beam Interlock system requirements, design, and operational parameters.

 

slides icon

Slides

 
WE5PFP003 Higher Harmonic Voltages in J-PARC RCS Operation cavity, acceleration, LLRF, synchrotron 1988
 
  • A. Schnase, M. Nomura, F. Tamura, M. Yamamoto
    JAEA/J-PARC, Tokai-mura
  • E. Ezura
    KEK, Ibaraki
  • K. Hara, K. Hasegawa, C. Ohmori, T. Shimada, H. Suzuki, M. Tada, M. Yoshii
    KEK/JAEA, Ibaraki-Ken
 
 

The J-PARC Rapid Cycling Synchrotron (RCS) uses broadband magnetic alloy loaded cavities to create the acceleration voltages needed for rapid cycling at 25 Hz rate. Besides the desired second harmonic of the acceleration frequency, which is employed in the painting process of RCS injection, also unwanted harmonics can be found at the acceleration gaps of the cavities. Here, the effect of the vector sums of undesired harmonics during the acceleration process is estimated.

 
WE5PFP017 Processing and Breakdown Localization Results for an L-Band Standing-Wave Cavity cavity, positron, plasma, ion 2024
 
  • F. Wang, C. Adolphsen
    SLAC, Menlo Park, California
 
 

Funding: Work supported by the DOE under contract DE-AC02-76SF00515


An L-band (1.3 GHz), normal-conducting, five-cell, standing-wave cavity that was built as a prototype capture accelerator for the ILC is being high-power processed at SLAC. The goal is to demonstrate stable operation at 15 MV/m with 1 msec, 5 Hz pulses and the cavity immersed in a 0.5 T solenoidal magnetic field. This paper summarizes the performance that was ultimately achieved and describes a novel analysis of the modal content of the stored energy in the cavity after a breakdown to determine on which iris it occurred.

 
WE5PFP074 First Beam Commissioning of the 400 MHz LHC RF System cavity, pick-up, feedback, controls 2180
 
  • A.C. Butterworth, M. E. Angoletta, L. Arnaudon, P. Baudrenghien, J. Bento, T. Bohl, O. Brunner, E. Ciapala, F. Dubouchet, G. Hagmann, W. Höfle, T.P.R. Linnecar, P. Maesen, J.C. Molendijk, E. Montesinos, J. Noirjean, A.V. Pashnin, V. Rossi, J. Sanchez-Quesada, M. Schokker, E.N. Shaposhnikova, D. Stellfeld, J. Tuckmantel, D. Valuch, U. Wehrle, F. Weierud
    CERN, Geneva
  • R. Sorokoletov
    JINR, Dubna, Moscow Region
 
 

Hardware commissioning of the LHC RF system was successfully completed in time for first beams in LHC in September 2008. All cavities ware conditioned to nominal field, power systems tested and all Low level synchronization systems, cavity controllers and beam control electronics were tested and calibrated. Beam was successfully captured in ring 2, cavities phased, and a number of initial measurements made. These results are presented and tests and preparation for colliding beams in 2009 are outlined.

 
WE5PFP075 The New CERN PS Transverse Damper betatron, kicker, pick-up, damping 2183
 
  • A. Blas, J.M. Belleman, E. Benedetto, F. Caspers, D.C. Glenat, R. Louwerse, M. Martini, E. Métral, V. Rossi, J.P.H. Sladen
    CERN, Geneva
 
 

Since 1999 the PS has been operated without active transverse damping thanks to an increase of the coupling between the transverse planes and the reduction of injection steering errors. Although the LHC requirements are met by these means, a new transverse feedback system has been commissioned to reinforce the robustness of operation and avoid the blow-up generated by residual injection steering errors. This system could also allow the reduction of the chromaticity and reduce the slow incoherent losses during the long PS injection plateau. It could also stabilize the high energy instabilities that appear occasionally with the LHC nominal beam and may be a limiting factor for ultimate LHC beam. Highlights include a signal processing with an automatic delay adapting itself to the varying revolution frequency, a programmable betatron phase adjustment along the cycle, pick-ups that have been re-furbished with electronics covering the very low frequency of the first betatron line and a compact wideband high-power solid state amplifier that drives the strip-line kicker via an impedance matching transformer. The overall system is described together with experimental results.

 
WE5PFP084 Evaluation of LLRF Stabilities at STF cavity, controls, feedback, klystron 2207
 
  • T. Miura, S. Fukuda, H. Katagiri, T. Matsumoto, S. Michizono, Y. Yano
    KEK, Ibaraki
  • Y. Okada
    NETS, Fuchu-shi
 
 

In STF phass-1, four-cavities are operated with vector-sum feedback (FB) control. The FB control instabilities arising from passband of TM010 mode other than π mode with FB loop-delays were measured. Further, a feedforward (FF) table was used in combination with FB control, which improved the flatness of the flat-top region. A method for reduction of overshoot in FB + FF operation is also proposed. By electrically developing a quasi-beam, the response for quasi-beam injection was also measured, and the correction on beam-loading was performed.

 
WE5PFP090 Energy Saving Controller for the TLS Booster RF System booster, klystron, cathode, cavity 2222
 
  • M.-S. Yeh, L.-H. Chang, L.J. Chen, F.-T. Chung, K.T. Hsu, M.-C. Lin, C.H. Lo, Ch. Wang
    NSRRC, Hsinchu
 
 

The quasi-constant current operation is achieved in the NSRRC by periodically injecting electrons from the booster to the storage ring. It means the booster RF system keeps running during operation period, even the injection period occupies only a small portion of the total operation time. To benefit both the energy saving and klystron life, an energy saving controller has been developed and integrated into the TLS booster RF system. The cathode current of the klystron is decreased during the top-injection period. The energy consumption is thus dramatically reduced. A continuous record since the beginning of 2009 shows this controller can save about 78 percent of energy consumption of the booster RF system during normal operation. An overview of the control architecture and its functionality is presented herein.

 
WE5RFP002 Design Status of Transfer Lines in TPS booster, linac, storage-ring, simulation 2261
 
  • P.J. Chou, H.-P. Chang, C.-C. Kuo, W.T. Liu
    NSRRC, Hsinchu
 
 

The booster design of Taiwan Photon Source(TPS) has been significantly revised. Therefore, the transfer line from linac to booster(LTB) and the one from booster to storage ring(BTS) have been redesigned accordingly. The design of LTB transfer line has been simplified to reduce the number of magnets. The length of BTS transfer line has been greatly reduced. The design goal of transfer lines is to achieve high efficiency for beam injection. The status of current progress will be reported.

 
WE5RFP010 Low-Alpha Operation of the SLS Storage Ring synchrotron, storage-ring, lattice, radiation 2285
 
  • A. Streun, M. Böge, N. Milas, F. Müller, V. Schlott, H. Sigg
    PSI, Villigen
  • G.A. Amatuni, D. Gishyan, K. Manukyan, A. Sargsyan
    CANDLE, Yerevan
 
 

Recently tentative top-up operation of the Swiss Light Source (SLS) storage ring at low momentum compaction factor has been started. We will present an analysis of the longitudinal dynamics and simulations of the injection process, and explain our method to ensure closed orbit stability. First experimental results will be shown and compared to the model predictions.

 
WE5RFP020 Operational Advances at Elettra and its New Full Energy Injector booster, insertion, insertion-device, power-supply 2309
 
  • E. Karantzoulis, A. Carniel, S. Ferry, S. Krecic
    ELETTRA, Basovizza
 
 

A full energy injector consisting of a 100 MeV linac and an up to 2.5 GeV booster is in operation since March 2008 replacing the previous 1 GeV linac injector to be used after refurbishing and upgrade for the new fourth generation light source (FEL) currently under construction at Sincrotrone Trieste. The measurements on the new injector, problems and solutions employed to increase its efficiency, reproducibility and reliability, aiming towards top-up operations in the near future, and its impact on the Elettra storage ring are presented and discussed.

 
WE5RFP022 Status of SESAME Project vacuum, microtron, booster, storage-ring 2315
 
  • A. Nadji
    SOLEIL, Gif-sur-Yvette
  • T.H. Abu-Hanieh, A. Al-Adwan, M.A. Al-najdawi, A. Amro, M. Attal, S. Budair, D.S. Foudeh, A. Hamad, A. Kaftoosian, T.A. Khan, F. Makahleh, S.A. Matalgah, M. Sbahi, M.M. Shehab, H. Tarawneh, S. Varnasseri
    SESAME, Allan
 
 

SESAME is a 3rd generation synchrotron light source facility under construction in Allan, Jordan, 30 km North-West of Amman. SESAME consists of a 2.5 GeV storage ring, a 22.5 MeV Microtron and an 800 MeV Booster. The Microtron was installed at its final position and its subsystems have been successfully tested. The commissioning with beam of the Microtron will start in March 2009. The installation of the Booster is expected to take place in summer 2009. Most of the storage ring subsystems are ready for call for tender. The progress of SESAME project including beamlines status will be reported in this paper.

 
WE5RFP027 Simulation of Hefei Advanced Light Source (HALS) Injection System kicker, emittance, septum, electron 2324
 
  • S.C. Zhang, G. Feng, W. Li, L. Liu, L. Wang, C.-F. Wu, H. Xu
    USTC/NSRL, Hefei, Anhui
 
 

Funding: supported by National Natural Science Foundation of China (10705027)


Hefei Advanced Light Source(HALS) is a super low emittance storage ring and has a very poor beam life time. In order to run the ring stablely, Top-up injection will be necessary. Injection system will greatly affect the quality of beam. This article first give a physics design of injecting system. Then the injecting system is tracked under different errors. The responses of storage beam and injecting beam is given in the article.

 
WE6PFP005 IBS and Possible Luminosity Improvement for RHIC Operation below Transition Energy emittance, luminosity, simulation, cavity 2486
 
  • A.V. Fedotov
    BNL, Upton, Long Island, New York
 
 

Funding: Work supported by Brookhaven Science Associates, LLC under Contract No. DE-AC02-98CH10886 with the U.S. Department of Energy.


There is a strong interest in low-energy RHIC collisions in the energy range below present RHIC transition energy. These collisions will help to answer one of the key questions in the field of QCD about the existence and location of a critical point on the QCD phase diagram. For low-energy RHIC operation, particle losses from the RF bucket are of particular concern since the longitudinal beam size is comparable to the existing RF bucket at low energies. However, operation below transition energy allows us to exploit an Intra-beam Scattering (IBS) feature that drives the transverse and longitudinal beam temperatures towards equilibrium by minimizing the longitudinal diffusion rate using a high RF voltage. Simulation studies were performed with the goal to understand whether one can use this feature of IBS to improve luminosity of RHIC collider at low-energies. This paper presents results of simulations which show that additional luminosity improvement for low-energy RHIC project may be possible with high RF voltage from a 56 MHz superconducting RF cavity that is presently under development for RHIC.

 
WE6PFP009 RHIC Low Energy Tests and Initial Operations luminosity, sextupole, emittance, power-supply 2498
 
  • T. Satogata, L. A. Ahrens, M. Bai, J.M. Brennan, D. Bruno, J.J. Butler, K.A. Drees, A.V. Fedotov, W. Fischer, M. Harvey, T. Hayes, W. Jappe, R.C. Lee, W.W. MacKay, N. Malitsky, G.J. Marr, R.J. Michnoff, B. Oerter, E. Pozdeyev, T. Roser, F. Severino, K. Smith, S. Tepikian, N. Tsoupas
    BNL, Upton, Long Island, New York
 
 

Funding: Work supported by Brookhaven Science Associates, LLC under Contract No. DE-AC02-98CH10886 with the U.S. Department of Energy.


There is significant interest in RHIC heavy ion collisions at center of mass energies of 5-50 GeV/u, motivated by a search for the QCD phase transition critical point. The low end of this energy range is nearly a factor of four below the nominal RHIC injection center of mass energy of 19.6 GeV/u. There are several operational challenges in the low-energy regime, including harmonic number changes, longitudinal acceptance, magnet field quality, lattice control, and luminosity monitoring. We report on the results of beam tests with protons and gold in 2007–9, including first RHIC operations at {(sNN)=9.2} GeV and low-energy nonlinear field corrections at {(sNN)=5} GeV.

 
WE6PFP014 Chromatic LHC Optics Effects on Collimation Phase Space Cuts betatron, optics, insertion, collimation 2510
 
  • C. Bracco, R.W. Assmann
    CERN, Geneva
 
 

The different levels of LHC collimators must be set up by respecting a strict setting hierarchy in order to guarantee the required performance and protection during the different operational machine stages. The available margins are a fraction of a beam σ. Two different sub-systems establish betatron and momentum collimation for the LHC. Collimator betatronic phase space cuts are defined for a central on-momentum particle. However, due to the chromatic features of the LHC optics and energy deviations of particles, the different phase space cuts become coupled. Starting from the basic equation of the transverse beam dynamics, the influence of off-momentum beta-beat and dispersion on the effective collimator settings has been calculated. The results are presented, defining the allowed phase space regions from LHC collimation. The impacts on collimation-related setting tolerances and the choice of an optimized LHC optics are discussed.

 
WE6PFP016 Study of High Beta Optics Solution for TOTEM optics, quadrupole, insertion, scattering 2516
 
  • H. Burkhardt, Y.I. Levinsen, S.M. White
    CERN, Geneva
 
 

The TOTEM experiment requires special high beta optics solutions. We report on studies of optics for an intermediate beta* = 90 m, as well as a solutions for a very high beta* of 1540 m, which respect all known constraints. These optics are rather different from the normal physics optics and will require global tune changes or adjustments.

 
WE6PFP017 LHC Abort Gap Cleaning with the Transverse Damper luminosity, optics, emittance, kicker 2519
 
  • E. Gianfelice-Wendt
    Fermilab, Batavia
  • B. Goddard, W. Höfle, V. Kain, M. Meddahi, E.N. Shaposhnikova
    CERN, Geneva
  • A. Koschik
    ETH, Zurich
 
 

Funding: Work partly supported by Fermilab, operated by Fermi Research Alliance, LLC under Contract No. DE-AC02-07CH11359 with the United States Department of Energy


In the Large Hadron Collider –LHC, particles not captured by the RF system at injection or leaking out of the RF bucket may quench the superconducting magnets during beam abort. The problem, common to other superconducting machines, is particularly serious for the LHC due to the very large stored energy in the beam. For the LHC a way of removing the unbunched beam has been studied and it uses the existing damper kickers to excite resonantly the particles travelling along the abort gap. In this paper we describe the results of simulations performed with MAD-X for various LHC optics configurations, including the estimated multipolar errors.

 
WE6PFP019 First Beam-Based Aperture Measurements in the Arcs of the CERN Large Hadron Collider beam-losses, coupling, optics, alignment 2525
 
  • S. Redaelli, I.V. Agapov, B. Dehning, M. Giovannozzi, F. Roncarolo, R. Tomás
    CERN, Geneva
  • R. Calaga
    BNL, Upton, Long Island, New York
 
 

Various LHC injection tests were performed in August and early September 2008 in preparation for the circulating beam operation. These tests provided the first opportunity to measure with beam the available mechanical aperture in two LHC sectors (2-3 and 7-8). The aperture was probed by exciting free oscillations and local orbit bumps of the injected beam trajectories. Intensities of a few 109 protons were used to remain safely below the quench limit of superconducting magnets in case of beam losses. In this paper the methods used to measure the mechanical aperture, the available on-line tools, and beam measurements for both sectors are presented. Detailed comparisons with the expected results from the as-built aperture models are also presented. It is shown that the measurements results are in good agreement with the LHC design aperture.

 
WE6PFP021 First Beta-Beating Measurement in the LHC optics, coupling, quadrupole, simulation 2531
 
  • R. Tomás, M. Aiba, S.D. Fartoukh, F. Franchi, M. Giovannozzi, V. Kain, M. Lamont, G. Vanbavinckhove, J. Wenninger, F. Zimmermann
    CERN, Geneva
  • R. Calaga
    BNL, Upton, Long Island, New York
  • A. Morita
    KEK, Ibaraki
 
 

In 2008 beam successfully circulated in the LHC. Thanks to an excellent functioning of the BPM system and the related software, injection oscillations were recorded for the first 90 turns at all BPMs. The analysis of these data gives the unique opportunity of evaluating the periodic optics and inferring possible error sources.

 
WE6PFP076 CLIC Drive Beam Frequency Multiplication System Design dipole, linac, emittance, sextupole 2673
 
  • C. Biscari, D. Alesini, A. Ghigo, F. Marcellini
    INFN/LNF, Frascati (Roma)
  • J.B. Jeanneret
    CERN, Geneva
 
 

The CLIC drive beam current, produced by the 1 GHZ fully loaded Linac, will be multiplied by a factor of 24 by the frequency multiplication system, to generate the high power beam representing the CLIC power source. The frequency multiplication system is composed by one delay loop plus two combiner rings. All rings will be isochronous, will contain trajectory tuning wigglers, and all magnets will be normal conducting. The design of the rings, with special emphasis on the rf deflectors characteristics, is presented.

 
WE6PFP092 Feasibility of Injection/Extraction Systems for Muon FFAG Rings in the Neutrino Factory kicker, extraction, acceleration, septum 2718
 
  • J. Pasternak, M. Aslaninejad
    Imperial College of Science and Technology, Department of Physics, London
  • J.S. Berg
    BNL, Upton, Long Island, New York
  • D.J. Kelliher, S. Machida
    STFC/RAL/ASTeC, Chilton, Didcot, Oxon
  • J. Pasternak
    STFC/RAL, Chilton, Didcot, Oxon
 
 

Non-scaling FFAG rings have been proposed as a solution for muon acceleration in the Neutrino Factory. In order to achieve small orbit excursion and small time of flight variation, lattices with a very compact cell structure and short straight sections are required. The resulting geometry dictates very difficult constraints on injection/extraction systems. The feasibility of injection/extraction is discussed and various implementations focusing on minimization of kicker/septum strength are presented.

 
WE6PFP110 Pulse-to-Pulse Switching Injection to Three Rings of Different Energies from a Single Electron Linac at KEK linac, optics, target, electron 2769
 
  • N. Iida, K. Furukawa, M. Ikeda, T. Kamitani, M. Kikuchi, E. Kikutani, Y. Kobayashi, T. Mimashi, T.M. Mitsuhashi, T. Miura, Y. Ogawa, Y. Ohnishi, S. Ohsawa, M. Satoh, M. Suetake, T. Suwada, M. Tawada, A. Ueda, Y. Yano, K. Yokoyama, M. Yoshida
    KEK, Ibaraki
 
 

The e+/e- injector LINAC in KEK usually successively injects into four rings, which are Low Energy Ring (LER) of KEKB (3.5GeV/e+), High Energy Ring (HER) of KEKB (8.0GeV/e-), Photon Factory (PF) (2.5GeV/e-) and Advanced Ring for pulse X-rays (PF-AR) (3.0GeV/e-). While LINAC continuously injects into LER and HER alternatively every about five minutes, keeping both of KEKB rings almost their full operating currents. It takes about one minute to switch beam mode of LINAC. PF and PF-AR are injected a few times in a day. Time for PF or PF-AR including mode-switch had taken about 20 minutes for each other. For PF injection, the switching time was shortened in 2005 and the occupancy time is about 5 minutes. In 2008, we succeeded to make the switching time shorter, 2 seconds for HER/LER, and Pulse-to-pulse alternatively injection for PF/HER using an event system. Especially for KEKB, the short switching time is contributed to provide high currents and to improve luminosity at which beam lives are too short to keep the high currents. In 2009, we have a plan to inject also for LER/HER pulse-to-pulse alternatively.

 
WE6RFP017 Collimation Considerations for PS2 collimation, beam-losses, kicker, extraction 2817
 
  • J. Barranco
    UPC, Barcelona
  • W. Bartmann, M. Benedikt, Y. Papaphilippou
    CERN, Geneva
 
 

A main concern in high intensity rings is the evaluation of uncontrolled losses and their minimization using collimation systems. A two-stage systemis foreseen for the PS2. The fundamental design strategy for the collimation design is presented, including machine apertures and collimator materials. The dependence of the collimator system efficiency on the primary scraper length and the impact parameter of the particle is evaluated for different collimator locations. Beam loss maps are finally produced displaying the detailed power load deposited around the ring.

 
WE6RFP066 Optical Diagnostic for Off-Axis Electrons in a Laser Wakefield Accelerator laser, radiation, electron, wakefield 2948
 
  • M.H. Helle
    Georgetown University, Washington
  • D.F. Gordon, A. Ting
    NRL, Washington, DC
  • D. Kaganovich
    Icarus Research, Inc., Bethesda, Maryland
 
 

Funding: This work is supported by the Office of Naval Research and the Department of Energy


Theoretical work* on electro-optic shock produced from the interaction of intense laser radiation with ~1% critical plasma suggests that second harmonic radiation will be emitted at the Cherenkov angle. This radiation pattern is produced under similar conditions as when off-axis electrons** were observed. These electrons are of particular interest since they are well suited for external injection into a laser wakefield acceleration structure. Recent experimental results at the U.S. Naval Research Laboratory, using a 10 TW, 50 fs, Ti-Sapphire laser, have shown the existence of such a second harmonic ring. Characterization of this optical radiation and its relationship to off-axis electrons will be presented.


*D. F. Gordon et al., Phys. Rev. Lett. {10}1, 45004 (2008).
**D. Kaganovich et al. Phys. Rev. Lett. {10}0, 215002 (2008).

 
WE6RFP072 Density Transition Measurement for the Electron Injection in Laser Wakefield Accelerator electron, plasma, laser, wakefield 2961
 
  • J. Kim, J.-U. Kim, S.H. Yoo
    KERI, Changwon
 
 

The electron injection into the acceleration phase of the laser wakefield accelerator(LWFA) the key issues for the stable operation of the LWFA. For the controlled electron injection, a sharp downward electron density transition is one candidate. When the laser pulse pass the sharp electron density transition, the electron from the high density region is injected into the acceleration phase. For this injection scheme, a very sharp electron density transition, the distance of the density change must be shorter than the plasma wavelength, is needed. A shock structure of plamsa generated at the gas target is one candidate for such a sharp electron density tarnsition structure. To find out the feasible condition of the density structure, the electorn density was measured by an interferometer with different time. A 200 ps, 100 mJ laser was used to generated plasma. A frequency doubled femto-second laser was used as a probe beam. The measured electron density structure which is compared with a 2D PIC simulation, indicates that feasible condition can be generated 1.2 ns after the laser pulse. This electron density structure will be used for the laser wakefield acceleration experiments.

 
WE6RFP073 Controlled Injection in the Sharp Phase Mixing Region of LWFA electron, laser, plasma, simulation 2964
 
  • S.H. Yoo, J. Kim, J.-U. Kim
    KERI, Changwon
 
 

Funding: Korea Electrotechnology Research Institute (KERI)


To generate the good quality electron bunch, stable fast injection is very important issue in the laser wakefield accelerator(LWFA). One of the self-injection methods is the wave breaking*. In this scheme, the density transition scale length is much larger than plasma skin depth. After a new self-injection mechanism using the sharp density transition scheme was proposed**, the experiment for the generation of the plasma shock structure have been conducted***. In this scheme, while one can reduce the wave breaking, the electron can be injected effectively using a phase mixing. Thus, the sharp density transition scheme is promising candidate method for the more stable generation of good quality electron bunch. In this scheme, the main issue is that the finding optimum conditions in which the injected electrons only in the first period of laser wake wave are accelerated further. In this paper, optimum conditions of sharp density transition scheme have been studied using Particle-In-Cell simulations. And the transverse parabolic profile is used to increase the beam quality. Throughout the extensive simulation work, the optimum conditions for the experiments at KERI is presented.


*S. Bulanov, et. al., Phys. Rev. E, 58, R5257 (1998)
**H. Suk, et. al., Phys. Rev. Lett. 86, {10}11 (2001)
***J. U. Kim, et. al., 69, 026409 (2004)

 
TH1GRI01 HIRFL-CSR Facility ion, extraction, heavy-ion, accumulation 3048
 
  • J.W. Xia, Y. Liu, Y.J. Yuan
    IMP, Lanzhou
 
 

CSR is a new ion cooler-storage-ring system in China IMP, it consists of a main ring (CSRm) and an experimental ring (CSRe). The two existing cyclotrons of the Heavy Ion Research Facility in Lanzhou (HIRFL) are used as its injector system. The heavy ion beams from the cyclotrons are injected first into CSRm for accumulation with e-cooling and acceleration, finally extracted fast to CSRe for internal-target experiments and mass measurements of radioactive ion beams (RIBs), or extracted slowly for external-target experiments or cancer therapy. In 2005 the CSR construction was completed and the commissioning finished in the past three years. It includes stripping injection (STI), electron-cooling with hollow electron beam, C-beam stacking with the combination of STI and e-cooling, wide energy-range acceleration from 7 MeV/u to {10}00 MeV/u with the RF harmonic-number changing, multiple multi-turn injection (MMI) and beam accumulation with MMI and e-cooling for heavy-ion beams of Ar, Kr and Xe, fast and slow extraction from CSRm, the commissioning of CSRe with two lattice modes, and a RIB mass-spectrometer test with the isochronous mode in CSRe by the time-of-flight method.

 

slides icon

Slides

 
TH1GRI02 Status of the China Spallation Neutron Source Project power-supply, dipole, linac, rfq 3053
 
  • S. Fu, H. Chen, Y.W. Chen, Y.L. Chi, C.D. Deng, H. Dong, L. Dong, S.X. Fang, W. He, K.X. Huang, W. Kang, X.C. Kong, J. Li, H.F. Ouyang, Q. Qin, H. Qu, C. Shi, H. Sun, J. Tang, S. Wang, J. Wei, T. Wei, T.G. Xu, Z.X. Xu, X. Yin, J. Zhang, Z.H. Zhang
    IHEP Beijing, Beijing
 
 

CSNS accelerator mainly consists of an H- linac and a proton rapid cycling synchrotron. It is designed to accelerate proton beam pulses to 1.6 GeV kinetic energy at 25 Hz repetition rate, striking a solid metal target to produce spallation neutrons. The accelerator is designed to deliver a beam power of 120 kW with the upgrade capability up to 500 kW, The CSNS accelerator is the first large-scale, high-power accelerator project to be constructed in China and thus we are facing a lot of challenges in some key technologies. A series of R&D for major prototypes have being conducted since 2006, including an H- ion source, DTL tank, RF power supply for the linac, injection/extraction magnets and its pulse power supplies, dipole and quadrupole prototype magnets in the ring and its power supplies, ferrite-loaded RF prototype cavity, ceramic vacuum chamber, control and some beam diagnostics. This paper will briefly introduce the design and R&D status of the CSNS accelerator.

 

slides icon

Slides

 
TH4GAC03 PAMELA Overview: Design Goals and Principles proton, lattice, ion, cavity 3142
 
  • K.J. Peach, J.H. Cobb, S.L. Sheehy, H. Witte, T. Yokoi
    JAI, Oxford
  • M. Aslaninejad, M.J. Easton, J. Pasternak
    Imperial College of Science and Technology, Department of Physics, London
  • R.J. Barlow, H.L. Owen, S.C. Tygier
    UMAN, Manchester
  • C.D. Beard, P.A. McIntosh, S.L. Smith, S.I. Tzenov
    STFC/DL/ASTeC, Daresbury, Warrington, Cheshire
  • N. Bliss
    STFC/DL, Daresbury, Warrington, Cheshire
  • T.R. Edgecock, J.K. Pozimski, J. Rochford
    STFC/RAL, Chilton, Didcot, Oxon
  • R.J.L. Fenning, A. Khan
    Brunel University, Middlesex
  • M.A. Hill
    GIROB, Oxford
  • C. Johnstone
    Fermilab, Batavia
  • B. Jones, B. Vojnovic
    Gray Institute for Radiation Oncology and Biology, Oxford
  • D.J. Kelliher, S. Machida
    STFC/RAL/ASTeC, Chilton, Didcot, Oxon
  • R. Seviour
    Cockcroft Institute, Lancaster University, Lancaster
 
 

Funding: EPSRC EP/E032869/1


The PAMELA (Particle Accelerator for MEdicaL Applications) project is to design an accelerator for proton and light ion therapy using non-scaling Fixed Field Alternating Gradient (FFAG) accelerators, as part of the CONFORM project, which is also constructing the EMMA electron model of a non-scaling FFAG at Daresbury. This paper presents an overview of the PAMELA design, and a discussion of the design goals and the principles used to arrive at a preliminary specification of the accelerator.

 

slides icon

Slides

 
TH4GBC03 Longitudinal Density Tailoring for the Enhancement of Electron Beams in the Capillary-Discharge Laser-Guided Wakefield Accelerator laser, electron, plasma, acceleration 3154
 
  • A.J. Gonsalves, E. Esarey, C.G.R. Geddes, W. Leemans, C. Lin, K. Nakamura, D. Panasenko, C.B. Schroeder, C. Tóth
    LBNL, Berkeley, California
 
 

Funding: Funded by the U.S. DOE Office of Science HEP including contract DE-AC02-05CH11231, and by DARPA.


A key issue in laser wakefield accelerators (LWFAs) is injection of electrons into the accelerating region of the wake. Typically electron beams have been self-injected into the wake in a highly non-linear process, and at a higher plasma density than that for an optimized guiding and accelerating structure. This in turn limits the electron beam energy and quality that can be achieved. In this talk it is shown that this coupling of injection and acceleration can be addressed for LWFA in a capillary discharge waveguide with the use of a gas jet embedded into the capillary to longitudinally tailor the electron density profile. Previous experiments without a gas jet have shown self-trapping and acceleration of electrons with energy up to 1 GeV [Leemans et al., Nature Phys. Vol. 2, 696, 2006]. By adding a gas jet in the capillary it has been shown that electrons can be trapped and accelerated to high-energy using plasma densities in the capillary lower than in previous experiments, and that use of this technique improved electron beam properties.

 

slides icon

Slides

 
TH4PBC02 Recent Developments at Diamond Light Source beam-losses, storage-ring, vacuum, undulator 3169
 
  • R.P. Walker
    Diamond, Oxfordshire
 
 

Diamond Light Source, the UK's 3rd generation synchrotron light facility, became operational in 2007. We report here on a number of important recent developments, aimed at increasing its operational performance. In particular, we present our initial experience with regular top-up injection, which began at the end of October 2008, including its reliability and effect on beam stability. We also discuss the issues that have been faced in increasing the beam current to its design value of 300 mA. Diamond currently operates with 10 in-vacuum undulators with a specified initial minimum operating gap of 7 mm. We report on our efforts to understand and control the distribution of beam losses in the ring, in order to allow operation with gaps as small as the target value of 5 mm.


On behalf of the Diamond Machine Staff

 

slides icon

Slides

 
TH4PBC03 Major Upgrade Activity of the PLS in PAL: PLS-II linac, klystron, lattice, storage-ring 3172
 
  • S.H. Nam
    PAL, Pohang, Kyungbuk
 
 

The Pohang Accelerator Laboratory (PAL) celebrated its 20th anniversary this year. After the completion of the Pohang Light Source (PLS) construction in 1994, the PLS started user service with two beamlines in 1995. The PLS energy was 2.0 GeV. The first major upgrade of the PLS had been done from 2000 to 2002, in which operation energy of the PLS was increased from 2.0 GeV to 2.5 GeV. The number of beamlines has been steadily increased since the start of user service. The number of beamlines currently in service is 28. Three beamlines are under construction. Number of users and performed experiments in 2007 were respectively 2553 and 837. Average impact factor of published papers is over 3.0, which is one of the best among Korean research institutes. Based on such success, the PAL is pursuing the second upgrade plan, called the PLS-II. The PLS will be upgraded its energy from 2.5 GeV to 3.0 GeV. With the upgrade, it will be possible to construct ten more insertion devices. The brightness of the PLS-II will be more than a order higher compared to the current PLS. In this presentation, details of the PLS-II project will be introduced.


This work was supported by the MEST (Ministry of Education, Science and Technology) and the POSCO (POhang iron and Steel making COmpany) in Korea.

 

slides icon

Slides

 
TH5PFP002 Simulation of Electron Cloud Density Distributions in RHIC Dipoles at Injection and Transition and Estimates for Scrubbing Times electron, dipole, simulation, proton 3187
 
  • P. He, M. Blaskiewicz, W. Fischer
    BNL, Upton, Long Island, New York
 
 

In this report we summarize electron-cloud simulations for the RHIC dipole regions at injection and transition to estimate if scrubbing at injection would reduce the electron cloud density at transition. We simulate the horizontal electron cloud distribution in the RHIC dipoles for secondary electron yields (SEY) from 1.1 to 2.0 at injection (with a bunch intensity of 1.3x109) and at transition (with a bunch intensity of 1.2x109). Also, we unveil the sensitivity to rather small changes in bunch intensity from 1.0 x109 to 1.5x109 , when SEY keep at 1.4 and 1.5 both for injection and transition.

 
TH5PFP004 Final Design of the IFMIF-EVEDA Low Energy Beam Transport Line rfq, space-charge, simulation, solenoid 3190
 
  • N. Chauvin, O. Delferrière, R.D. Duperrier, R. Gobin, P.A.P. Nghiem, D. Uriot
    CEA, Gif-sur-Yvette
  • M. Comunian
    INFN/LNL, Legnaro (PD)
 
 

During the EVEDA (Engineering Validation and Engineering Design Activities) phase of the IFMIF (International Fusion Materials Irradiation Facility) project, a 125 mA/9 MeV accelerator prototype will be built, tested and operated in Rokkasho-Mura (Japan). The injector section of this accelerator is composed by an ECR source, delivering a 140 mA deuteron beam at 100 keV, and a low energy beam transport (LEBT) line required to match the beam for the RFQ injection. The proposed design for the LEBT is based on a dual solenoids focusing scheme. In order to takes into account the space charge compensation of the beam induced by the ionisation of the residual gas, a 3D particle-in-cell code (SOLMAXP) has been developed for the beam dynamics calculations. The LEBT parameters have been optimized in order to maximize the beam transmission through the RFQ. The final LEBT design, as well as the simulation results, are presented.

 
TH5PFP028 Longitudinal Particle Simulation for J-PARC RCS simulation, extraction, acceleration, bunching 3254
 
  • M. Yamamoto, K. Hasegawa, M. Nomura, A. Schnase, T. Shimada, H. Suzuki, F. Tamura
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
  • E. Ezura, K. Hara, C. Ohmori, M. Tada, A. Takagi, M. Yoshii
    KEK, Ibaraki
  • K. Horino
    Nippon Advanced Technology Co. Ltd., Ibaraki-prefecture
 
 

J-PARC RCS is in the beam commissioning period. Some longitudinal beam gymnastics and the acceleration has been successfully perfomed under the high intensity operation. We have developed a longitudinal particle tracking code, which includes beam loading and space charge effects. The comparison between the beam test result and the particle tracking simulation is described.

 
TH5PFP029 Optical Measurement System of Laser-Cooled Mg Ion Beam laser, ion, synchrotron, coupling 3257
 
  • M. Nakao, T. Ishikawa, A. Noda, H. Souda, M. Tanabe, H. Tongu
    Kyoto ICR, Uji, Kyoto
  • M. Grieser
    MPI-K, Heidelberg
  • K. Jimbo
    Kyoto IAE, Kyoto
  • H. Okamoto
    HU/AdSM, Higashi-Hiroshima
  • S. Shibuya
    AEC, Chiba
  • T. Shirai
    NIRS, Chiba-shi
  • A.V. Smirnov
    JINR, Dubna, Moscow Region
 
 

Funding: This work is supported by Advanced Accelerator Development Project of MEXT and the Global COE program "The Next Generation of Physics, Spun from Universality and Emergence".


Transverse laser cooling experiments of 24Mg+ beam have been carried out at S-LSR, which is a small ion storage and cooler ring. According to a simulation, it is expected that under such a condition as the difference of synchrotron and betatron tunes is near integer, synchro-betatron coupling occurs and transverse laser cooling will be achieved*. In order to confirm this situation, the horizontal beam size and momentum spread are measured optically with CCD camera and PAT (post acceleration tube), respectively**,***. CCD camera observes fluorescence from the beam at the laser cooling section. Typical measured horizontal beam size is 0.5mm (1 σ). In some condition, an increase of fluorescence strength is observed, which indicates the beam concentration to the center, where the beam and the laser can interact. PAT is utilized for measurement of a longitudinal beam velocity profile. By application of electric potential to the PAT, the beam velocity is slightly modified. Since only particles which have velocities in a certain region can interact with the laser, the time variation of the florescence during voltage sweep represents the longitudinal velocity profile of the beam.


*H. Okamoto, Phys. Rev. E 50, 4982 (1994)
**B. Wanner et al., Phys. Rev. A 58, 2242 (1998)
***T. Ishikawa, Master's thesis, Kyoto University (2008)

 
TH5PFP032 Status of Electron-Cloud Build-Up Simulations for the Main Injector dipole, simulation, electron, proton 3266
 
  • M.A. Furman
    LBNL, Berkeley, California
  • I. Kourbanis, R.M. Zwaska
    Fermilab, Batavia
 
 

Funding: Supported by the US DOE under contract DE-AC02-05CH11231 and by the Fermilab Main Injector upgrade effort.


We provide a brief status report on measurements and simulations of the electron-cloud in the Fermilab Main Injector. Areas of agreement and disagreement are spelled out, along with their possible significance.

 
TH5PFP067 Longitudinal Phase Space Tomography at J-PARC RCS synchrotron, simulation, proton, acceleration 3358
 
  • M. Yoshimoto, N. Hayashi, M. Kawase, F. Tamura, M. Yamamoto
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
  • M. Yoshii
    KEK/JAEA, Ibaraki-Ken
 
 

In order to observe two-dimensional beam profiles in the longitudinal phase space, the reconstruction techniques with the computer tomography algorithms can be adopted at the J-PARC RCS. On the assumption that the longitudinal profiles should not be disturbed for one period of the synchrotron oscillation, such two-dimensional profiles can be reconstructed easily from one-dimensional bunch beam profiles, which are measured for every turn by the wall current monitor. In this presentation, we introduce the experimental results and the comparison to the longitudinal beam tracking simulation, and we discuss the technical issues and applicability of this longitudinal tomography techniques.

 
TH5PFP082 Matrix Solution of Coupling Impedance in Multi-Layer Circular Cylindrical Structures impedance, coupling, vacuum, space-charge 3395
 
  • H. Hahn
    BNL, Upton, Long Island, New York
 
 

Funding: This work was supported by Brookhaven Science Associates, LLC under Contract No. DE-AC02-98CH10886 with the U.S. Department of Energy.


Continuing interest in computing the coupling impedance of cylindrical multi-layer beam tubes led to several recent publications. A novel matrix method is here presented in which radial wave propagation is treated in analogy to longitudinal transmission lines. Starting from the Maxwell equations the solutions for monopole and dipole electromagnetic fields are in each layer described respectively by a 2×2 and 4×4 matrix. Assuming isotropic material properties within one layer, the radially transverse field components at the inner boundary of a layer are uniquely determined by matrix transfer of the field components at its outer boundary. By imposing power flow constraints on the matrix, field matching between layers is enforced and replaced by matrix multiplication. The wall impedance is found as eigen solution to the scalar Helmholtz equation with the additional boundary condition that the longitudinal magnetic field vanishes at the inner beam tube wall. The matrix method is demonstrated via the example of the longitudinal impedance of a multi-layer HOM absorber, involving a ceramic tube with metal coating and an external ferrite layer.

 
TH5RFP003 Development of a Fiber-Optic Beam Loss Position Monitor for the Advanced Photon Source Storage Ring electron, radiation, photon, beam-losses 3438
 
  • J.C. Dooling, W. Berg, L. Emery, B.X. Yang
    ANL, Argonne
 
 

Funding: Work supported by the U.S. Department of Energy, Office of Science, Office of Basic Energy Sciences, under contract number DE-AC02-06CH11357.


An array of fused-silica, fiber optic bundles has been built to spatially monitor e-beam loss in the APS storage ring (SR). A prototype beam loss position monitor (BLPM) has been installed on unoccupied undulator straight sections. The BLPM allows for 6 fiber bundles, 3 above and 3 below the beam. The center bundles are aligned with the beam axis. Presently, 4 bundles are used, 3 above and one in the center position below the beam. Each bundle is 3 m in length and composed of 61 220-micron-diameter fibers for a total aperture of 2 mm. The first 30 cm of each bundle are aligned parallel to the beam in contact with the vacuum chamber. Light generated by fast electrons within the fibers is thought to come primarily from Cerenkov radiation. The rest of the fiber acts as a light pipe to transmit photons to shielded PMTs. Tests show good signal strength during stored-beam mode from Touschek scattering and deterministic losses that occur during top-up injection and beam dumps. Post-injection loss signals show spatial and temporal dynamics. Simulation work is expected to provide calibration for integrated losses that can be compared with progressive undulator demagnetization.

 
TH5RFP006 Bunch Current and Phase Detection for the APS PAR controls, linac, cavity, monitoring 3447
 
  • C. Yao, W.E. Norum
    ANL, Argonne
 
 

Funding: Work supported by U.S. Department of Energy, Office of Science, Office of Basic Energy Sciences, under Contract No. DE-AC02-06CH11357.


The Advanced Photon Source (APS) injector consists of a linac, a particle accumulator ring (PAR), and a booster synchrotron (booster). The PAR accumulates multiple linac bunches and compresses them into a single bunch for booster injection. Beam energy in the PAR is 325 MeV. Due to its low energy and relatively strong beam-loading effect, beam charge and phase (or timing ) monitoring is critical to the stable operations of rf control loops. We implemented a monitor system with an FPGA processor, which provides both current monitor and stripline fast waveforms. The system provides a bunch charge reading with a data rate of up to 1 MHz and a beam phase resolution of 200 ps, which are sufficient for the rf phase control loops. The system is currently used for beam tuning and diagnostics during normal operation. We are planning to build an upgraded version with fast data output and included it in the new rf control loops. We present a description of the system and the measurement results.

 
TH5RFP008 Upgrade of the Beam Position Monitors at the Brazilian Synchrotron Light Source vacuum, storage-ring, synchrotron, simulation 3453
 
  • S.R. Marques, O.R. Bagnato, R.H.A. Farias, F. R. Francisco, R.T. Neuenschwander, F. Rodrigues, A.L. Rosa, R.M. Seraphim, P.F. Tavares, M.M. Xavier
    LNLS, Campinas
 
 

We describe the development of a new button-type beam position monitor (BPM) for the Brazilian Synchrotron Light Source (LNLS) electron storage ring. One third of the storage ring stripline BPMs were replaced whit this new model, which counts on bellows, temperature stabilization and new support stands in order achieve improved mechanical stability. Finally, in-vacuum heat absorbers were installed at the upstream vacuum tubes of the bending magnets to minimize the vacuum chamber motion due to the high thermal load. We also present performance results.

 
TH5RFP016 Comparison of RF BPM Receivers for NSLS-II Project brilliance, kicker, electron, synchrotron 3476
 
  • I. Pinayev, O. Singh
    BNL, Upton, Long Island, New York
  • G. Decker
    ANL, Argonne
 
 

Funding: Work supported by U.S. Department of Energy, Office of Science, Office of Basic Energy Sciences, under Contracts DE-AC02-98CH10886 and DE-AC02-06CH11357.


The NSLS-II Light Source being built at Brookhaven National Laboratory requires submicron stability of the electron orbit in the storage ring in order to utilize fully very small emittances and electron beam sizes. This sets high stability requirements for beam position monitors and a program has been initiated for the purpose of characterizing RF beam position monitor (BPM) receivers in use at other light sources. Present state-of-the-art performance will be contrasted with more recently available technologies. The details of the program and preliminary results are presented.

 
TH5RFP034 First Experience with the LHC Beam Loss Monitoring System beam-losses, proton, controls, quadrupole 3522
 
  • B. Dehning, D. Bocian, T.T. Boehlen, E. Effinger, J. Emery, F. Follin, V. Grishin, E.B. Holzer, H. Ikeda, S. Jackson, D.K. Kramer, G. Kruk, P. Le Roux, J. Mariethoz, M. Misiowiec, L. Ponce, C. Roderick, M. Sapinski, M. Stockner, C. Zamantzas
    CERN, Geneva
  • A. Priebe
    Poznań University of Technology, Poznań
 
 

The LHC beam loss monitoring system (BLM) consists of about 4000 monitors observing losses at all quadrupole magnets and many other likely loss locations. At the first LHC operation in August and September 2008 all monitors were active and used to observe the losses during the initial beam steerings, at collimators, at the LHC dump and during aperture scans. The different loss patterns will be discussed and compared with the expectations originating from simulations. The observed signals of the BLM system will be analysed in terms of response time, sensitivity cross talk between channels and noise performance.

 
TH5RFP035 Energy Deposition Simulations and Measurements in an LHC Collimator and Beam Loss Monitors simulation, proton, beam-losses, collimation 3525
 
  • T.T. Boehlen, R.W. Assmann, C. Bracco, B. Dehning, S. Redaelli, Th. Weiler, C. Zamantzas
    CERN, Geneva
 
 

The LHC collimators are protected against beam caused damages by measuring the secondary particle showers with beam loss monitors. Downstream of every collimator an ionisation chamber and a secondary emission monitor are installed to determine the energy deposition in the collimator. The relation between the energy deposition in the beam loss monitor and the collimator jaw is based on secondary shower simulations. To verify the FLUKA simulations the prototype LHC collimator installed in the SPS was equipped with beam loss monitors. The results of the measurements of the direct impact of the 26 GeV proton beam injected in the SPS onto the collimator are compared with the predictions of the FLUKA simulations. In addition simulation results from parameter scans and for mean and peak energy deposition with its dependencies are shown.

 
TH5RFP061 Study of J-PARC Linac Beam Position Monitor as Phase Monitor linac, monitoring, cavity, acceleration 3591
 
  • S. Sato, K. Hasegawa, A. Miura, T. Morishita, H. Sako, A. Ueno, H. Yoshikawa
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
  • Z. Igarashi, M. Ikegami
    KEK, Ibaraki
  • T. Tomisawa
    JAEA/LINAC, Ibaraki-ken
 
 

In the J-PARC LINAC, BPMs with 4 strip lines (up, down, right, left) have been used to monitor the beam position by taking log ratio of signals on the opposite (facing) sides of stirp lines. We are studying possibility to monitor beam phase by measuring phase of summed signal of all four stlip lines. In this paper, status of the study is presented.

 
TH5RFP063 Longitudinal Beam Dynamics in the HDSM at MAMI linac, synchrotron, microtron, simulation 3594
 
  • M. Dehn, H. Euteneuer, A. Jankowiak
    IKP, Mainz
 
 

Funding: Work supported by DFG (CRC 443) and the German Federal State of Rheinland-Pfalz.


The 1.5GeV Harmonic Double Sided Microtron (HDSM)* as the fourth stage of the Mainz Microtron (MAMI) is now in routine operation for two and a half years**. Simulations predicted a wide range of applicable longitudinal parameters with which the machine can be run. Measurements of the longitudinal acceptance proved that. The reproducibility of different configurations is sufficient to support a fast and reliable set-up of the machine and to guarantee a stable long-term operation. But in order to optimise the configuration a reliable measurement of the phases and accelerating voltages in both linacs is essential. Each turn’s phase information is provided by low-Q-TM010 resonators at both linacs when operating the machine with 10ns diagnostic pulses. The HDSM’s four bending magnets are designed with a field gradient to compensate the vertical fringe defocusing. The decreasing field integral results in less synchronous energy gain per turn, automatically causing a change of the longitudinal phase. The calibration of the phase signals which in case of the RTMs could be easily done by exciting a synchrotron oscillation was improved to deliver precise phase data.


*K.-H. Kaiser et al., NIM A 593 (2008) 159 - 170, doi:10.{10}16/j.nima.2008.05.018
**A. Jankowiak et al., ID 2689, this conference

 
TH5RFP094 Beam Loss Monitors in the NSLS Storage Rings radiation, electron, septum, beam-losses 3672
 
  • S.L. Kramer, M.G. Fedurin
    BNL, Upton, Long Island, New York
 
 

Funding: Work supported by U.S. DOE, Contract No.DE-AC02-98CH10886


Beam loss monitors have been used for more than a decade in the VUV ring at the NSLS. These have proved useful for optimizing injection and operation of the ring. Recently similar monitors have been installed in the Xray ring and are being used to better understand injection as well as operation of the ring. These units have been compared with the Bergoz Beam Loss Monitors, which have been mostly useful for operating beam losses. The experience with these units have led to an improved detector that is being considered by NSLS-II as a beam containment verification monitor, as well as diagnostic for optimization of injection efficiency.

 
TH6PFP011 Beam Based Calibration of the LNLS UVX Storage Ring BPMs quadrupole, alignment, storage-ring, synchrotron 3717
 
  • L. Liu, R.H.A. Farias, X.R. Resende, P.F. Tavares
    LNLS, Campinas
 
 

The UVX electron storage ring at the Brazilian Synchrotron Light Laboratory (LNLS) was recently equipped with active current shunt circuits that allow for individual variation of the quadrupole magnet strengths. This allows us to apply the widely used technique of beam-based alignment (BBA) to calibrate the electrical center offset of the BPMs with respect to the magnetic center of the closest quadrupole. In this report we present the BBA experimental results and an analysis of the resolution of the method in the case of the LNLS UVX storage ring.

 
TH6PFP013 An Injection/Extraction Scenario for EMMA septum, kicker, extraction, lattice 3723
 
  • J.S. Berg
    BNL, Upton, Long Island, New York
 
 

Funding: Work Supported by the United States Department of Energy, Contract No. DE-AC02-98CH10886.


EMMA is an experiment to study beam dynamics in a linear non-scaling fixed-field alternating gradient accelerator (FFAG). It accelerates an electron beam from 10 to 20 MeV kinetic energy. To optimally perform these studies, one must be able to inject the beam at any energy within the machine's energy range. Furthermore, because we wish to study the behavior of large-emittance beams in such a machine, the injection systems must be able to inject the beam anywhere within a transverse phase space ellipse with a normalized acceptance of 3 mm, and the extraction systems must be able to extract from that same ellipse. I describe a computation of kicker and septum fields to achieve all of these requirements, and discuss how this interacts with the hardware constraints.

 
TH6PFP015 Minimizing Emittance Growth during H- Injection in the AGS Booster emittance, booster, optics, linac 3729
 
  • K.A. Brown, L. A. Ahrens, C.J. Gardner, D.M. Gassner, D. Raparia, D. Steski, P. Thieberger, K. Zeno
    BNL, Upton, Long Island, New York
 
 

Funding: Work supported by Brookhaven Science Associates, LLC under Contract No. DE-AC02-98CH10886 with the U.S. Department of Energy.


As part of the efforts to increase polarization and luminosity in RHIC during polarized proton operations we have modified the injection optics and stripping foil geometry in the AGS Booster in order to reduce the emittance growth during H- injection. In this paper we describe the modifications, the injection process, and present results from beam experiments.

 
TH6PFP033 Double Mini-Beta-Y Plus Virtual Focussing Optics for the Diamond Storage Ring optics, undulator, quadrupole, insertion 3772
 
  • B. Singh, R.T. Fielder, E.C. Longhi, I.P.S. Martin, C. Rau, U.H. Wagner
    Diamond, Oxfordshire
  • R. Bartolini
    JAI, Oxford
 
 

A proposal has been developed to modify a long insertion straight (~11.4 m long) of the DIAMOND storage ring. Additional quadrupoles provide two sections with small vertical beta-function values, in order to accommodate two canted in-vacuum undulators for the imaging and coherence branches of the I13 beam line. A further requirement was to provide a horizontal focussing of the emitted undulator radiation by means of a positive alpha-x in the second section. This optic is obtained using a small relaxation in the “pi–trick”, approximately preserving the on-momentum nonlinear dynamics of the ring. The effects of the optic on beam dynamics (i.e. beam lifetime, injection etc.) and possible compensation schemes are presented.

 
TH6PFP034 Study of Beam Losses at Injection in the CERN Proton Synchrotron optics, septum, emittance, radiation 3775
 
  • S. Aumon, S.S. Gilardoni, O. Hans, F.C. Peters
    CERN, Geneva
 
 

The maximum intensity the CERN PS has to deliver is continuously increasing. In particular, during the next years, one of the most intense beam ever produced in the PS, with up to 3000·1010 proton per pulse, should be delivered on a regular basis for the CNGS physics program. It is now known that the existing radiation shielding of the PS in some places is too weak and constitutes a major limitation due to large beam losses in specific locations of the machine. This is the case for the injection region: losses appear on the injection septum when the beam is injected in the ring and during the first turn, due also to an optical mismatch between the injection line and the PS. This paper presents the experimental studies and the simulations which have been made to understand the loss pattern in the injection region. Possible solutions to reduce the beam losses will be described, including the computation of a new injection optics.

 
TH6PFP036 Lattice Issues of the CERN PSB with H- Charge Exchange Injection Hardware lattice, quadrupole, linac, betatron 3781
 
  • C. Carli, M. Aiba, M. Chanel, B. Goddard, M. Martini, W.J.M. Weterings
    CERN, Geneva
 
 

The motivation for the construction of CERN Linac4 is to improve the performance of the PSB by raising the injection energy and implementing a new H- charge exchange multiturn injection scheme. Strategies to design the H- charge exchange injection hardware and, in particular, to mitigate perturbations of the lattice will be reported and the proposed geometry described.

 
TH6PFP038 Determination of the Chromaticity of the TI 8 Transfer Line Based on Kick Response Measurements optics, quadrupole, controls, multipole 3787
 
  • K. Fuchsberger, S.D. Fartoukh, B. Goddard, O.R. Jones, V. Kain, M. Meddahi, V. Mertens, J. Wenninger
    CERN, Geneva
 
 

The 3 km long TI 8 transfer line is used to transfer 450 GeV proton and ion beams from the SPS to LHC collider. As part of a detailed optics investigation program the chromaticity of the transfer line was measured. Kick response data of the transfer line was recorded for various extraction energy offsets in the SPS. The quadrupolar and sextupolar field errors over the whole transfer line dipoles, a systematic error of the main quadrupole strengths and the initial momentum error were estimated by a fit. Using the updated model, the chromaticity of the line was then calculated.

 
TH6PFP039 Beam Loss Control for the Unstripped Ions from the PS2 Charge Exchange Injection scattering, emittance, beam-losses, ion 3790
 
  • W. Bartmann, J. Barranco, M. Benedikt, B. Goddard, T. Kramer, Y. Papaphilippou, H. Vincke
    CERN, Geneva
 
 

Control of beam losses is an important aspect of the H- injection system for the PS2, a proposed replacement of the CPS in the CERN injector complex. H- ions may pass the foil unstripped or be partially stripped to excited H0 states which may be stripped in the subsequent strong-field chicane magnet. Depending on the choice of the magnetic field, atoms in the ground and first excited states can be extracted and dumped. The conceptual design of the waste beam handling is presented, including local collimation and the dump line, both of which must take into account the divergence of the beam from stripping in fringe fields. Beam load estimates and activation related requirements of the local collimators and dump are briefly discussed.

 
TH6PFP040 Machine Studies During Beam Commissioning of the SPS-to-LHC Transfer Lines alignment, optics, quadrupole, coupling 3793
 
  • M. Meddahi, I.V. Agapov, K. Fuchsberger, B. Goddard, W. Herr, V. Kain, V. Mertens, D.P. Missiaen, T. Risselada, J.A. Uythoven, J. Wenninger
    CERN, Geneva
  • E. Gianfelice-Wendt
    Fermilab, Batavia
 
 

Funding: Work partly supported by Fermilab, operated by Fermi Research Alliance, LLC under Contract No. DE-AC02-07CH11359 with the United States Department of Energy


Through May to September 2008, further beam commissioning of the SPS to LHC transfer lines was performed. For the first time, optics and dispersion measurements were also taken in the last part of the lines, and into the LHC. Extensive trajectory and optics studies were conducted, in parallel with hardware checks. In particular dispersion measurements and their comparison with the beam line model were analysed in detail and led to propose the addition of a “dispersion-free” steering algorithm in the existing trajectory correction program.

 
TH6PFP042 The 4 GeV H- Beam Transfer Line from the SPL to the PS2 quadrupole, linac, beam-losses, simulation 3799
 
  • C. Heßler, M. Eshraqi, B. Goddard, A.M. Lombardi, M. Meddahi
    CERN, Geneva
 
 

The proposed new CERN injector chain LINAC4, SPL, PS2 will require the construction of new beam transfer lines. A preliminary design has been performed for the 4 GeV SPL to PS2 H- transfer line. The constraints, beam parameters and geometry requirements are summarised and a possible layout proposed, together with the magnet specifications. First considerations on longitudinal beam dynamics and on beam loss limitations from H- lifetime are presented.

 
TH6PFP044 Linear Optics Design of Negative Momentum Compaction Lattices for PS2 optics, quadrupole, resonance, dipole 3805
 
  • Y. Papaphilippou, J. Barranco, W. Bartmann, M. Benedikt, C. Carli, B. Goddard
    CERN, Geneva
  • R. De Maria, S. Peggs, D. Trbojevic
    BNL, Upton, Long Island, New York
 
 

In view of the CERN Proton Synchrotron proposed replacement with a new ring (PS2), a detailed optics design as been undertaken following the evaluation of several lattice options. The basic arc module consists of cells providing negative momentum compaction. The straight section is formed with a combination of FODO and quadrupole triplet cells, to accommodate the injection and extraction systems, in particular the H- injection elements. The arc is matched to the straight section with a dispersion suppressor and matching module. Different lattices are compared with respect to their linear optics functions, tuning flexibility and geometrical acceptance properties.

 
TH6PFP054 Beam Dynamics Design of Debuncher System for J-PARC Linac Energy Upgrade linac, cavity, simulation, controls 3829
 
  • M. Ikegami
    KEK, Ibaraki
  • T. Morishita, H. Sako
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
  • T. Ohkawa
    MHI, Kobe
 
 

The output energy of J-PARC linac is planned to be upgraded from 181 MeV to 400 MeV by adding an ACS (Annular Coupled Structure linac) section. The debuncher system for J-PARC linac is also replaced in this energy upgrade. The new debuncher system will consist of two 972-MHz debuncher cavities with the separate-function configuration. In this configuration, the momentum jitter is corrected with the first debuncher, whereas the momentum spread is controlled with the second debuncher. This configuration is advantageous in simplifying the tuning procedure, and it is also beneficial in reducing the nonlinear effects of the debuncher cavities. In this paper, the beam dynamics design of the debuncher system is presented with some simulation results.

 
TH6PFP073 Controlled Transverse Emittance Blow-Up in the CERN SPS emittance, feedback, octupole, controls 3871
 
  • E. Métral, G. Arduini, F. Arnold Malandain, W. Höfle, D. Manglunki
    CERN, Geneva
 
 

For several years, a large variety of beams have been prepared in the LHC injectors, such as single-bunch and multi-bunch beams, with 25 ns, 50 ns and 75 ns bunch spacings, nominal and intermediate intensities per bunch. As compared to the nominal LHC beam (i.e. with nominal bunch intensity and 25 ns spacing) the other beams can be produced with lower transverse emittances. Beams of low transverse emittances are of interest during the commissioning phase for aperture considerations and because of the reduced long-range beam-beam effects. On the other hand machine protection considerations might lead to prefer nominal transverse emittances for safe machine operations. The purpose of this paper is to present the results of controlled transverse emittance blow-ups using the transverse feedback and octupoles. The procedures tested in the SPS in 2008 allow to tune the transverse emittances up to nominal values at SPS extraction.

 
TH6PFP086 Single Particle Dynamics in the University of Maryland Electron Ring electron, lattice, simulation, space-charge 3904
 
  • E.W. Nissen, B. Erdelyi
    Northern Illinois University, DeKalb, Illinois
  • S. Bernal, D.F. Sutter
    UMD, College Park, Maryland
 
 

We undertake a study of the single particle dynamics in a model of the University of Maryland Electron Ring. This accelerator uses a low energy electron beam to study the effects of space charge on beam dynamics. However, due to this low energy, other effects that are seldom taken into account in high energy accelerators become important to the single particle dynamics of the beam. The simulation is performed using COSY Infinity, which has the effects of the earth’s magnetic field added to it. When the simulated trajectories are compared to measured beam positions there is good agreement through the ninth section of the ring, at which point the difference between predicted and observed diverges. A method of calculating map elements corresponding to the measured data will be used to determine where issues with the ring that could cause these problems might be found.

 
TH6PFP094 SPEAR3 Nonlinear Dynamics Measurements kicker, optics, synchrotron, betatron 3928
 
  • J.A. Safranek, W.J. Corbett, X. Huang, J.J. Sebek, A. Terebilo
    SLAC, Menlo Park, California
 
 

Funding: Work supported by the US Department of Energy, Office of Basic Energy Sciences.


We present nonlinear dynamics measurements and tracking for the SPEAR3 storage ring. SPEAR3 does not have a vertical pinger magnet, so we have developed a method of measuring (x, y) frequency maps by exciting vertical oscillations using a strip line driven with a swept frequency. When the vertical oscillations reach the desired amplitude, the drive is cut, and an injection kicker excites horizontal oscillations. The subsequent free horizontal and vertical betatron oscillations are digitized turn-by-turn. We have used measured and tracked frequency maps in (x, y) and (x, energy) to characterize and optimize the dynamic aperture, injection and lifetime of the SPEAR3 low emittance optics.

 
TH6REP002 Independent Component Analysis for the Turn by Turn Beam Position Measurement in the TLS betatron, synchrotron, diagnostics, septum 3950
 
  • P.C. Chiu, K.T. Hsu, K.H. Hu, C.H. Kuo, C.Y. Wu
    NSRRC, Hsinchu
 
 

After commissioning of new BPM system in the TLS, it would support functionality of turn by turn data which can be applied in independent component analysis (ICA). This data analysis method is a special case of blind source separation to separate multivariable signal and additive noise and shown to be a useful diagnostic tool in acceleration application. In this paper, we use the ICA method to analyze experimental BPM turn by turn data of the TLS storage ring, measure betatron tunes, and identify abnormal BPM signals. Other possible applications have been also further studied continuously.

 
TH6REP003 Orbit Stability Observation of the Taiwan Light Source power-supply, septum, feedback, kicker 3953
 
  • P.C. Chiu, K.T. Hsu, K.H. Hu, C.H. Kuo, C.Y. Wu
    NSRRC, Hsinchu
 
 

Since the diagnostic system built with the new BPM system upgrade in TLS, we can observe and analyze the orbit stability more clearly and systematically. The disturbances to cause orbit fluctuation mainly come from power supply ripple, ground vibration, ID effects and etc. Removing the disturbed source is a straight, effective but inactive solution. Orbit feedback system is therefore adopted to suppress the remaining noise. In this report, we will evaluate the orbit stability in TLS and present the efforts we have done to improve the orbit stability.

 
TH6REP006 Correlation Study between Beam Behaviour Observed by Electron BPMs and Photon Monitors photon, electron, kicker, septum 3959
 
  • K.H. Hu, Y.-T. Chang, J. Chen, Y.-S. Cheng, P.C. Chiu, K.T. Hsu, C.H. Kuo, C.Y. Wu
    NSRRC, Hsinchu
 
 

Beam qualities include orbit stability and multi-bunch instability plays a crucial role for the operation of a synchrotron light source. To improve and to keep high beam quality, intensive correlation analysis is performed between data taken by electron BPMs and photon monitors. Efforts of this study will be summary in this report.

 
TH6REP032 Fast-Gated Camera Measurements in SPEAR3 optics, diagnostics, kicker, betatron 4015
 
  • W.X. Cheng, W.J. Corbett, A.S. Fisher, X. Huang, J.A. Safranek, A. Terebilo
    SLAC, Menlo Park, California
  • W.Y. Mok
    Life Imaging Technology, Palo Alto, California
 
 

Funding: Work sponsored by U.S. Department of Energy Contract DE-AC03-76SF00515 and Office of Basic Energy Sciences, Division of Chemical Sciences.


An intensified, fast-gated CCD camera was recently installed on the visible diagnostic beam line in SPEAR3. The ~2nS electronic gate capability, ability to make multiple-exposure images and to acquire sequences of images provides good diagnostic potential. Furthermore, the addition of a rotating mirror just upstream of the photocathode provides the ability to optically ‘streak’ multiple images across the photocathode. In this paper, we report on several fast-gated camera studies including (1) resonant excitation of vertical bunch motion, (2) imaging of the injected beam with and without emittance-spoiling windows in the upstream transfer line, (3) injection kicker tuning to minimize perturbations to the stored beam and (4) images of short-bunch ‘bursting’ in the low momentum-compaction mode of operation.

 
TH6REP046 Reduction of Systematic Errors in Diagnostic Receivers through the Use of Balanced Dicke-Switching and Y-Factor Noise Calibrations diagnostics, radiation, coupling, instrumentation 4057
 
  • J. Musson, T.L. Allison, R. J. Flood, J. Yan
    JLAB, Newport News, Virginia
 
 

Receivers designed for diagnostic applications range from those having moderate sensitivity to those possessing large dynamic range. Digital receivers have a dynamic range which are a function of the number of bits represented by the ADC and subsequent processing. If some of this range is sacrificed for extreme sensitivity, noise power can then be used to perform two-point load calibrations. Since load temperatures can be precisely determined, the receiver can be quickly and accurately characterized; minute changes in system gain can then be detected, and systematic errors corrected. In addition, using receiver pairs in a balanced approach to measuring X+, X-, Y+, Y-, eliminates systematic offset errors from non-identical system gains, and changes in system performance. This paper describes and demonstrates a balanced BPM-style diagnostic receiver, employing Dicke-switching to establish and maintain real-time system calibration. Benefits of such a receiver include wide bandwidth, solid absolute accuracy, improved position accuracy, and phase-sensitive measurements. System description, static and dynamic modeling, and measurement data are presented.

 
TH6REP067 Preliminary Investigations for a Digital Multi-Bunch Feedback System for the LNLS feedback, pick-up, synchrotron, kicker 4108
 
  • S.R. Marques, R.H.A. Farias, L. Sanfelici, P.F. Tavares
    LNLS, Campinas
 
 

The main facility of the Brazilian Synchrotron Light Laboratory is a 1.37 GeV Synchrotron Light Source. The accelerator ring can be filled with up to 148 electron bunches and the initial current of 250 mA decreases down to 150 mA at the end of the user’s shifts. The beam energy is ramped down to 500 MeV, the current is refilled and the energy is ramped up again to 1.37 GeV for a new shift. Coupled-bunch instabilities excited by different sources can negatively impact the light source performance either lowering the brilliance of the beam or causing beam losses in the energy ramps. The upcoming new insertion devices and beamlines are pushing up the beam stability requirements even more. We present the current status of a digital feedback system that is being designed for controlling transversal and longitudinal beam instabilities.

 
TH6REP072 DAΦNE Horizontal Feedback Upgrade feedback, damping, kicker, positron 4123
 
  • A. Drago
    INFN/LNF, Frascati (Roma)
 
 

In this paper the horizontal feedback upgrade for the positron DAΦNE ring is presented. After having completed the analysis of the e+ current limit behavior, a feedback upgrade has been turned out necessary. For the success of the crab waist experiment in the 2008 year, a fast solution to implement the upgrade has been necessary. It has been considered if a simple power increase would be the best solution. The lack of power combiners and of space for other two power amplifiers has brought to a different approach, doubling the entire feedback system. The advantages of this implementation respect to a more traditional power amplifier doubling are evident: two feedback kicks every revolution turns, better use of the power amplifiers, greater reliability, and less coherent noise in the system. Measurements of the two feedbacks have shown a perfect equivalence of the new and the old system: in fact the resulting damping rate is exactly the double of each system taken individually. A description of the implementation is presented together with the performance of the system.

 
TH6REP082 Experiment of Transverse Feedback System at HLS feedback, damping, octupole, controls 4147
 
  • J.H. Wang, Y.B. Chen, W. Li, L. Liu, M. Meng, B. Sun, L. Wang, Y.L. Yang, Z.R. Zhou
    USTC/NSRL, Hefei, Anhui
  • J. Cao, J. Yue
    IHEP Beiing, Beijing
  • D.K. Liu
    SINAP, Shanghai
  • L. Ma
    IHEP Beijing, Beijing
  • K.R. Ye
    SSRF, Shanghai
 
 

In this paper, we introduce the BxB transverse feedback systems at Hefei Light Source (HLS), which employ an analog system and a digital system. The construction and commissioning for two feedback systems, as well as the instability analysis of beam and the experiment result of the feedback system in HLS are also presented in this paper.

 
TH6REP083 Commissioning of the HLS Analog TFB System feedback, damping, status, controls 4150
 
  • Y.L. Yang, Y.B. Chen, W. Li, L. Liu, M. Meng, B. Sun, J.H. Wang, L. Wang, Z.R. Zhou
    USTC/NSRL, Hefei, Anhui
 
 

As low injection energy and multi-turn injection at HLS, the task of diagnosing and curing coupled-bunch instabilities becomes ever harder. The transverse analog feedback system has been redeveloped to improve effect, recently. In this paper, the new improved designs are described and new system's commissioning results are discussed. The transverse coupled bunch instability at 200MeV injection status is also experimentally studied.

 
TH6REP084 Commissioning of the Digital Transverse Bunch-by-Bunch Feedback System for the HLS feedback, octupole, damping, storage-ring 4153
 
  • Z.R. Zhou, Y.B. Chen, M. Meng, B. Sun, J.H. Wang, L. Wang, Y.L. Yang
    USTC/NSRL, Hefei, Anhui
  • K. Kobayashi, T. Nakamura
    JASRI/SPring-8, Hyogo-ken
 
 

Hefei Light Source (HLS) is an 800MeV storage ring with bunch rate of 204 MHz, the harmonics of 45, and circumference of 66 meters. HLS injection works at 200MeV, where the multi-bunch instabilities limit the maximum stored current. A digital transverse bunch-by-bunch feedback system has recently been commissioned at HLS to suppress the multi-bunch instabilities during injection. We employ the SPring-8 FPGA based feedback processor and modified it at NSRL to process horizontal and vertical oscillation signals, independently and simultaneously by one single processor. The design of the digital transverse feedback system and the experiment results are presented in this paper.

 
TH6REP098 Preinjector Gun Upgrade, Timing and Synchronization and Preparation for the Top-Up Injection in Elettra booster, gun, controls, storage-ring 4183
 
  • A. Carniel, S. Bassanese, M. Ferianis, E. Karantzoulis, C. Scafuri, A. Vascotto
    ELETTRA, Basovizza
 
 

Elettra is the third generation light source in operation in Trieste since 1993,upgraded with a full energy booster injector last year. Top-up operation is on schedule in the near future but already the new timing system and gun are ready to operate in this mode. The paper describes all tasks and requirements needed to satisfy top-up injection include custom made hardware, interaction with controls and radiation protection system.

 
FR1GRC04 AGS Polarized Proton Operation in Run 2009 resonance, polarization, emittance, betatron 4251
 
  • H. Huang, L. A. Ahrens, M. Bai, K.A. Brown, C.J. Gardner, J.W. Glenn, F. Lin, A.U. Luccio, W.W. MacKay, T. Roser, V. Schoefer, S. Tepikian, N. Tsoupas, K. Yip, A. Zelenski, K. Zeno
    BNL, Upton, Long Island, New York
  • H.M. Spinka, D.G. Underwood
    ANL, Argonne
 
 

Funding: Work supported by Brookhaven Science Associates, LLC under Contract No. DE-AC02-98CH10886 with the U.S. Department of Energy.


After installation of two partial snakes in the Brookhaven Alternating Gradient Synchrotron (AGS), a polarized proton beam with 1.5*1011 intensity and 65% polarization has been achieved. There are residual polarization losses due to horizontal resonances over the whole energy ramp and some polarization loss due to vertical intrinsic resonances. Many efforts have been put in to reduce the emittances coming into the AGS and to consequently reduce polarization loss. This paper presents the accelerator setup and preliminary results from run-9 operations.

 

slides icon

Slides

 
FR1GRC05 The LHC Injection Tests instrumentation, controls, quadrupole, proton 4254
 
  • M. Lamont, R. Alemany-Fernandez, R. Bailey, P. Collier, B. Goddard, V. Kain, A. Macpherson, L. Ponce, S. Redaelli, W. Venturini Delsolaro, J. Wenninger
    CERN, Geneva
 
 

A series of LHC injection tests was performed in August and September 2008. The first saw beam injected into sector 23; the second into sectors 78 and 23; the third into sectors 78-67 and sectors 23-34-45. The fourth, into sectors 23-34-45, was performed the evening before the extended injection test on the 10th September which saw both beams brought around the full circumference of the LHC. The tests enabled the testing and debugging of a number of critical control and hardware systems; testing and validation of instrumentation with beam for the first time; deployment, and validation of a number of measurement procedures. Beam based measurements revealed a number of machine configuration issues that were rapidly resolved. The tests were undoubtedly an essential precursor to the successful start of LHC beam commissioning. This paper provides an outline of preparation for the tests, the machine configuration and summarizes the measurements made and individual system performance.

 

slides icon

Slides

 
FR5PFP010 Using Novel Injection Schemes for Enhanced Storage Ring Performance lattice, brightness, insertion, insertion-device 4326
 
  • D. Robin, C. Steier, L. Yang
    LBNL, Berkeley, California
 
 

Funding: Supported by DOE BES contract DE-AC03-76SF00098.


Recently there has been a proposal to use pulsed high order multipole elements for injection. One of the advantages of this proposed injection scheme would be that it would be less disruptive to the stored beam and thus advantageous for Top-off operation. In addition to Top-off, such novel injectors might open the door to operating storage rings in more desirable lattice settings. In this paper we will explore some of the possibilities for taking advantage of high order multipole pulsed kick injection.

 
FR5PFP015 An Achromatic Mass Separator Design for Ions from the EBIT Charge Breeder at the NSCL ion, quadrupole, emittance, simulation 4341
 
  • M. Portillo, G. Bollen, S. Chouhan, O.K. Kester, G. Machicoane, J. Ottarson, S. Schwarz, A. Zeller
    NSCL, East Lansing, Michigan
 
 

Funding: This work was supported by Michigan State University and the National Science Foundation under grant PHY-0110253.


The NSCL at Michigan State University (MSU) is implementing a system called the ReA3 to reaccelerate rare isotope beams from projectile fragmentation to energies of about 3 MeV/u. The re-acceleration system uses an Electron Beam Ion Trap (EBIT) to provide a compact and cost efficient system. We discuss the design parameters for a m/q separator that is to be used to separate highly charged ions from an EBIT type charge breeder. The separator is designed to accept ions at 12 keV/u with mass to charge ratios in the range of m/q = 2.5 to 5 amu. The goal is to separate selected rare isotope species from any residual ions before injecting them into the ReA3 linear accelerator system. Using ray tracing simulations with SIMION*, as well as higher order map calculations with COSY INFINITY**, the performance of the separator has been evaluated in terms of the expected mass resolution and overall acceptance. The separator consists of a magnetic sector and a series of electrostatic devices to obtain a first order achromatic tune. For comparison, similar performance values will be derived as those for a similar separator constructed at REX-ISOLDE***.


*D.A. Dahl, Int. J. Mass Spectrom. Ion Processes 200, 3 (2000) .
**K. Makino and M. Berz, Nucl. Instr. and Meth. A 558, 346 (2005)
***R. Rao et. al., EPAC-98, Stockholm, Sweden, 2132-2134 (1998).

 
FR5PFP018 Experimental Studies of Random Error Effects in High-Intensity Accelerators Using the Paul Trap Simulator Experiment (PTSX) quadrupole, focusing, plasma, ion 4344
 
  • M. Chung
    Fermilab, Batavia
  • M. Chung, R.C. Davidson, P. Efthimion, E.P. Gilson, R. M. Majeski
    PPPL, Princeton, New Jersey
 
 

Funding: Research supported by the U.S. Department of Energy.


Understanding the effects of random errors in machine components such as quadrupole magnets and RF cavities is essential for the optimum design and stable operation of high-intensity accelerators. The effects of random errors have been studied theoretically, but systematic experimental studies have been somewhat limited due to the lack of dedicated experimental facilities. In this paper, based on the compelling physics analogy between intense beam propagation through a periodic focusing quadrupole magnet system and pure ion plasma confined in a linear Paul trap, experimental studies of random error effects have been performed using the Paul Trap Simulator Experiment (PTSX). It is shown that random errors in the quadrupole focusing strength continuously produce a non-thermal tail of trapped ions, and increases the rms radius and the transverse emittance almost linearly with the amplitude and duration of the noise. This result is consistent with 2D WARP PIC simulations. In particular, it is observed that random error effect can be further enhanced in the presence of beam mismatch.

 
FR5PFP030 Cyclotron Matching Injection Optics Optimization cyclotron, space-charge, TRIUMF, focusing 4372
 
  • R.A. Baartman
    TRIUMF, Vancouver
 
 

Injection from an external ion source into a cyclotron results in unavoidable emittance growth when the cyclotron's pole gap is not small compared with the first turn radius. In such a congested geometry, the injected beam first has the two transverse directions coupled on entering the axial magnetic field of the cyclotron, then transverse and longitudinal phase spaces are coupled by the inflector. Generally, to avoid loss, the beam is focused tightly through the inflector. It thus arrives at the first turn strongly mismatched because the vertical focusing in such a cyclotron is rather weak (vertical tune < 0.3). Space charge exacerbates the mismatch because it depresses the vertical tune further. Emittance growth from all these effects can be calculated using the full Sacherer 6D envelope formalism. We develop the technique to include cyclotrons and in particular the transverse optics of the rf gaps, and apply it in particular to the re-design of the TRIUMF 300 keV vertical injection line.

 
FR5PFP046 Longitudinal Dynamics Studies for ISIS Upgrades space-charge, simulation, longitudinal-dynamics, synchrotron 4411
 
  • R.E. Williamson, B.G. Pine, C.M. Warsop
    STFC/RAL/ISIS, Chilton, Didcot, Oxon
 
 

ISIS is the pulsed neutron and muon source based at the Rutherford Appleton Laboratory in the UK. Operation is centred on a loss-limited 50 Hz proton synchrotron which accelerates ~3·1013 protons per pulse from 70 MeV to 800 MeV, corresponding to mean beam powers of 0.2 MW. A number of ISIS upgrades are currently under study. One option replaces the linac for higher energy injection into the existing ring, potentially increasing beam current through reduction in space charge. The other main option adds a new 3 GeV RCS, boosting the energy of the beam to provide higher beam power. For both these upgrade routes, longitudinal dynamics of the existing and proposed new rings play a crucial role in achieving high intensity with low loss. This paper outlines longitudinal beam dynamics studies in the rings for both these cases, including development of a new longitudinal space charge code, comparison of different algorithms and codes and treatment of the key beam dynamics issues for each case. The influence of non-space charge impedances is also considered.

 
FR5PFP061 Matching and Injection of Beams with Space Charge into the University of Maryland Electron Ring (UMER) solenoid, lattice, quadrupole, emittance 4449
 
  • R.A. Kishek, B.L. Beaudoin, S. Bernal, M. Cornacchia, I. Haber, P.G. O'Shea, M. Reiser, D.F. Sutter, J.C.T. Thangaraj, C. Wu
    UMD, College Park, Maryland
  • D. Stratakis
    BNL, Upton, Long Island, New York
 
 

Funding: This work is funded by the US Dept. of Energy Offices of High Energy Physics and High Energy Density Physics, and by the US Dept. of Defense Office of Naval Research and Joint Technology Office


Beam matching is critical for avoiding envelope mismatch oscillations that can lead to emittance growth and halo formation, especially if the beam has significant space charge. The University of Maryland Electron Ring (UMER) is a research storage ring that is designed for scaled studies that are applicable to many larger machines. Using 10 keV electron beams at relatively high current (0.6 – 100 mA), space charge forces are relatively strong. Matching of the UMER beam is rendered difficult by the space charge, the crowdedness of the lattice, and especially the unique injection scheme where an offset oversized quadrupole is shared between the ring and the injector. In this paper we discuss several schemes for optimizing the matching at injection, both analytical and beam-based, which we test using particle-in-cell simulations with the code, WARP. Comparison to UMER experimental data is provided where available.

 
FR5RFP018 Laser Wakefield Simulation Using a Speed-of-Light Frame Envelope Model simulation, laser, wakefield, plasma 4569
 
  • B.M. Cowan, D.L. Bruhwiler, P. Messmer, K. Paul
    Tech-X, Boulder, Colorado
  • E. Cormier-Michel, E. Esarey, C.G.R. Geddes
    LBNL, Berkeley, California
 
 

Funding: Work supported by Department of Energy contracts DE-AC02-05CH11231 (LBNL), DE-FC02-07ER41499 (SciDAC), and DE-FG02-04ER84097 (SBIR).


Simulation of laser wakefield accelerator (LWFA) experiments is computationally highly intensive due to the disparate length scales involved. Current experiments extend hundreds of laser wavelengths transversely and many thousands in the propagation direction, making explicit PIC simulations enormously expensive. We can substantially improve the performance of LWFA simulations by modeling the envelope modulation of the laser field rather than the field itself. This allows for much coarser grids, since we need only resolve the plasma wavelength and not the laser wavelength, and this also allows larger timesteps. Thus an envelope model can result in savings of several orders of magnitude in computational resources. By propagating the laser envelope in a Galilean frame moving at the speed of light, dispersive errors can be avoided and simulations over long distances become possible. Here we describe the model and its implementation. We show rigorous studies of convergence and discretization error, as well as benchmarks against explicit PIC. We also demonstrate efficient, fully 3D simulations of downramp injection and meter-scale acceleration stages.

 
FR5RFP026 All-Optical Compton Gamma-Ray Source electron, plasma, laser, cavity 4589
 
  • K. Koyama, A. Yamazaki
    UTNL, Ibaraki
  • T. Hosokai
    RLNR, Tokyo
  • A. Maekawa, M. Uesaka
    The University of Tokyo, Nuclear Professional School, Ibaraki-ken
  • M. Miyashita
    SUT, Noda-shi, Chiba
 
 

An all-optical inverse Compton gamma-ray source is enable us to make a tabletop monochromatic gamma-ray source that might be applied to measure an amount of nuclear material, etc. An intense laser pulse excites a very nonlinear plasma wave and accelerate electron bunch up to several-hundreds MeV within a length of a few millimeters. The key to success is stabilization of the laser-plasma accelerators. We are developing the artificial injection technique of initial electrons in to the plasma wave and guiding of the intense laser pulse by the preformed plasma channel.

 
FR5RFP072 Stabilization of Beam Instability due to Space-Charge Effects at J-PARC space-charge, kicker, impedance, simulation 4701
 
  • Y. Shobuda
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
  • Y.H. Chin, M. Ikegami, T. Toyama
    KEK, Ibaraki
 
 

Kicker magnets are ones of dominant sources of impedances in the 3GeV Rapid Cycling Synchrotron (RCS) at Japan Proton Accelerator Research Complex (J-PARC). They may be limiting factors in achieving high intensity beams. Recently, the 300kW beam was accomplished at 3GeV RCS, while no instability was observed. In this paper, the space-charge effects are studied as beam stabilization effects.

 
FR5RFP073 Estimation of the Electron Emission from the RCS Collimator electron, proton, beam-losses, synchrotron 4704
 
  • K. Yamamoto
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
  • T. Toyama
    J-PARC, KEK & JAEA, Ibaraki-ken
 
 

The RCS of J-PARC accelerator complex has been commissioned since September 2007. By a study of one year, we were able to demonstrate more than 200kW operation. In such high intensity operation, the electron cloud effect may have an important roll for the accelerator limitation. we estimated the electron emission from the collimator surface of RCS by a simulation.

 
FR5RFP093 BTF Simulations for Tevatron and RHIC with Resistive Wall Wake Field wakefield, simulation, emittance, impedance 4755
 
  • V.H. Ranjbar, A.V. Sobol
    Tech-X, Boulder, Colorado
  • H.J. Kim, T. Sen, C.-Y. Tan
    Fermilab, Batavia
 
 

Funding: This work was supported by the US DOE Office of Science, Office of Nuclear Physics, under Grant No.DE-FG02-08ER85183


Recent improvements to BBSIM permit detailed simulations of collective effects due to resistive wall wake fields. We compare results of beam transfer measurements (BTF) in the Tevatron and RHIC with and without the effects of resistive wall wake fields. These are then compared to actual BTF measurements made in both machines and the impact of intensity on our measurements. We also investigate the impact of resistive wall wake fields on various chromaticity measurement approaches.

 
FR5REP007 Final Implementation and Performance of the LHC Collimator Control System controls, collimation, insertion, betatron 4788
 
  • S. Redaelli, R.W. Assmann, R. Losito, A. Masi
    CERN, Geneva
 
 

The 2008 collimation system of the CERN Large Hadron Collider (LHC) included 80 movable collimators for a total of 316 degrees of freedom. Before beam operation, the final controls implementation was deployed and commissioned. The control system enabled remote control and appropriate diagnostics of the relevant parameters. The collimator motion is driven with time-functions, synchronized with other accelerator systems, which allows controlling the collimator jaw positions with a micrometer accuracy during all machine phases. The machine protection functionality of the system, which also relies on function-based tolerance windows, was also fully validated. The collimator control challenges are reviewed and the final system architecture is presented. The results of the remote system commissioning and the operational experience are discussed. The system tests performed for the 2009 beam operation are also reviewed.

 
FR5REP010 Event-Based Timing and Control System for Fast Beam-Mode Switching at KEK 8-GeV Linac controls, linac, EPICS, electron 4797
 
  • K. Furukawa, M. Satoh, T. Suwada
    KEK, Ibaraki
  • A. Kazakov
    Sokendai, Ibaraki
  • T. Kudou, S. Kusano
    MELCO SC, Tsukuba
  • L.Y. Zhao
    SINAP, Shanghai
 
 

The 8-GeV linac at KEK provides electrons and positrons to several accelerator facilities. A 50-Hz beam-mode switching system has been constructed to realize simultaneous top-up injections for Photon Factory and the KEKB high- and low-energy rings, which require different beam characteristics. An event-based timing and control system was built to change the parameters of various accelerator components within 20 ms. The components are spread over a 600-m linac and require changes to a total of 100 timing and control parameters. The system has been operated successfully since the autumn of 2008 and has been improved upon as beam operation experience has been accumulated. It is expected to enhance the quality of the experiments at KEKB and PF. We describe the details of this new and improved control system and present status of the accelerator operation.

 
FR5REP015 ALS Control System Upgrade in C# EPICS, controls, booster, linac 4803
 
  • H. Nishimura, M.J. Beaudrow, W.E. Byrne, C.M. Ikami, G.J. Portmann, CA. Timossi, M.E. Urashka
    LBNL, Berkeley, California
 
 

Funding: Supported by the U.S. Department of Energy under Contract No. DE-AC02-05CH11231.


The high-level software for the ALS injector control system is being rewritten synchronizing with the low-level hardware migration to the EPICS system*. New programs are all written in C# for the use on the new operator consoles that are Windows Vista PCs. We use SCA. NET for the channel access, WCF for IPC, and XML for configurations. GUI is currently in WinForm but moving to WPF. We will be reporting the result of the first release of the system from the aspect of the software development.


*The progress was reported at PCaPAC 2008 as http://users.cosylab.com/~mpelko/PCaPAC08/papers/mow02.pdf,and
http://users.cosylab.com/~mpelko/PCaPAC08/papers/tup018.pdf

 
FR5REP029 A Novel Beam Steering Algorithm with Orbit Response Matrix closed-orbit, controls, dipole, space-charge 4829
 
  • C. Wu, E.H. Abed, B.L. Beaudoin, S. Bernal, K. Fiuza, I. Haber, R.A. Kishek, P.G. O'Shea, M. Reiser, D.F. Sutter
    UMD, College Park, Maryland
 
 

Funding: This work is funded by the US Dept. of Energy Offices of High Energy Physics and High Energy Density Physics, and by the US Dept. of Defense Office of Naval Research and Joint Technology Office.


Beam centroid control is an important method for optimizing the performance for accelerators, including the University of Maryland Electron Ring (UMER), which is a scaled low-energy (10KeV) storage ring. The conventional response matrix and singular value decomposition approach do not work well on the UMER because of the unique ring structure. One of the purposes of this work is to verify that the beam centroid could be controlled in the presence of very strong space charge. In this paper, we present a novel algorithm which is based on the singular value decomposition, but uses a different response matrix, which is computed from the closed equilibrium orbit and beam positions up to the first four turns in the multi-turn beam circulation. Other issues like strong coupling between the horizontal steering dipoles and vertical steering dipoles in the beam injection section will be addressed. Implementation of this algorithm leads to significant improvement on the beam positions and multi-turn operation.

 
FR5REP031 ALS FPGA-Based Extraction Trigger Inhibit Interlock System for Top-Off Mode extraction, controls, status, interlocks 4835
 
  • J.M. Weber, K.M. Baptiste, R.S. Müller
    LBNL, Berkeley, California
 
 

Funding: Supported by the U.S. Department of Energy under Contract No. DE-AC02-05CH11231.


The Advanced Light Source (ALS) is a third generation synchrotron light source that has been operating since 1993 at Berkeley Lab. Recently, the ALS was upgraded to achieve Top-Off Mode, which allows injection of 1.9GeV electron beam into the Storage Ring approximately every 30 seconds. The ALS Top-Off Mode Beam Current Interlock System was installed to prevent the potential hazard of injected electrons propagating down user beam lines. One of the requirements of this interlock system is a fast response time from detected event to injection trigger inhibit. Therefore, solid state devices, not electro-mechanical relays typically used in accelerator safety systems, must be used to implement the trigger inhibit logic. An FPGA-based solution was selected for this function. Since commercial FPGAs are not rated for high reliability or fail-safe operation, some of the logic resources were used to perform system self-checking to reduce the time to detect system failures and increase reliability. The implementation and self-checking functions of the Extraction Trigger Inhibit Interlock System will be discussed.

 
FR5REP044 Layout of an Electrostatic Storage Ring at KACST storage-ring, ion, quadrupole, lattice 4866
 
  • M.O.A. El Ghazaly
    KUK, Abha
  • M.H. Al-Malki, M.O.A. El Ghazaly
    KACST, Riyadh
  • A.I. Papash
    MPI-K, Heidelberg
  • C.P. Welsch
    Cockcroft Institute, Warrington, Cheshire
 
 

A state-of-the-art fixed energy electrostatic storage ring that will allow for precision experiments with most different kinds of ions in the energy range of up to 30 keV will be constructed and operated at the National Center for Mathematic and Physics (NCMP) at the King Abdulaziz City for Science and Technology (KACST). The ring is planed to be the central machine of a unique and highly flexible experimental platform. The lattice design therefore has to cover the different experimental techniques that the ring will be equipped with, such as e.g. electron-ion crossed-beams and ion-laser/ion-ion/ion-neutral merged-beams techniques. This paper presents the technical and particle optical design of this novel machine, explains the particular challenges in its layout, and reports on the general project status.

 
FR5REP052 Construction Status of Linac4 linac, klystron, booster, DTL 4884
 
  • F. Gerigk, C. Carli, R. Garoby, K. Hanke, A.M. Lombardi, R. Maccaferri, S. Maury, S. Ramberger, C. Rossi, M. Vretenar
    CERN, Geneva
 
 

The civil engineering works of the Linac4 linear accelerator at CERN started in October 2008 and regular machine operation is foreseen for 2013. Linac4 will accelerate H- ions to an energy of 160 MeV for injection into the PS Booster (PSB). It will thus replace the ageing Linac2, which presently injects at 50 MeV into the PSB, and it will also represents the first step in the injector upgrade for the LHC aiming at increasing its luminosity. This paper reports on the status of the design and construction of the main machine elements, which will be installed in the linac tunnel from the beginning of 2012 onwards, on the progress of the civil engineering and on the ongoing activities at the Linac4 test stand.

 
FR5REP055 Linac4 Beam Characterisation before Injection into the CERN PS Booster linac, emittance, diagnostics, proton 4893
 
  • B. Mikulec, G. Bellodi, M. Eshraqi, K. Hanke, T. Hermanns, S. Lanzone, A.M. Lombardi, U. Raich
    CERN, Geneva
 
 

Construction work for the new CERN linear accelerator, Linac4, started in October 2008. Linac4 will replace the existing Linac2 and provide an H- beam at 160 MeV (as opposed to the present 50 MeV proton beam) for injection into the CERN PS Booster (PSB). The charge-exchange H- injection combined with the higher beam energy will allow for an increase in beam brightness required for reaching the ultimate LHC luminosity. Commissioning of Linac4 and of the transfer line to the PSB is planned for the last quarter of 2012. Appropriate beam instrumentation is foreseen to provide transverse and longitudinal beam characterization at the exit of Linac4 and in two dedicated measurement lines located before injection into the PSB. A detailed description of the diagnostics set, especially of spectrometer and emittance meter, and the upgrade of the measurement lines for Linac4 commissioning and operation is presented.

 
FR5REP077 Performance Analysis and Improvement of the 50 MeV Linac for the Taiwan Light Source controls, linac, booster, gun 4956
 
  • C.Y. Wu, Y.-T. Chang, J. Chen, Y.-S. Cheng, K.T. Hsu, K.H. Hu, D. Lee
    NSRRC, Hsinchu
 
 

Operation performance of the linear accelerator is crucial to satisfy stringent requirements for the top-up operation of the Taiwan Light Source. The performance of linear accelerator affects injector stability directly. Efforts to improve diagnostics and develop control applications for performance characterization are on going. Enhance operation performance of 50 MeV linac is also under way. Efforts for the improvement of the linac to provide better top-up injection performance will be summary in this report.

 
FR5REP093 Coupled Particle Motion in the CIAE CRM Pulsed Injection line emittance, solenoid, quadrupole, cyclotron 4996
 
  • S. An, S.M. Wei, T.J. Zhang
    CIAE, Beijing
  • K. Bongardt
    FZJ, Jülich
 
 

The 10 mA, 40keV H- pulsed injection line for the CIAE 10 MeV CRM cyclotron has two main operation modes for bunched beams: delivering 5 mA CW beam or chopped pulse with more than 100uA. Chopped pulse is achieved by placing behind the 70.5 MHz bunching cavity a sinusoidal transverse deflecting cavity with frequency of 2.2 MHz, 1/32 of the bunching frequency. Particles outside the wanted ±3° phase width @ 2.2 MHz, corresponding to ±90° @ 70.5 MHz, are either absorbed in a 50cm drift after chopper or at round slit1, 1cm aperture. Time dependence of sinusoidal chopping field causes RMS emittance increase by a factor 3 and changes twiss parameter alpha by a factor 2 before the round slit1. Solenoid couples motion in transversal planes, but equalizes both RMS emittances. Particle tracking results are presented for the chopped pulse, showing longitudinal-transverse coupling in the deflector and equalization of RMS emittances in the solenoid. Optimised focusing strength leads to about 1 % transmission efficiency for the chopped pulse. The CRM inflector receives 2.4 ns long pulse at about 4.4 MHz repetition rate, 1/16 of the RF frequency.

 
FR5REP094 Tracking Periodic Parameters in the Measured Magnetic Field Maps of a Spiral FFAG closed-orbit, dipole, lattice, extraction 4999
 
  • F. Méot
    CEA, Gif-sur-Yvette
  • F. Forest, M.J. Leray
    Sigmaphi, Vannes
  • J. Pasternak
    Imperial College of Science and Technology, Department of Physics, London
 
 

Funding: Agence Nationale de la Recherche, France, contract NT05-1_41853


A prototype of a spiral lattice FFAG magnet has been constructed in the frame of the RACCAM project*. THis magnet is subject to extensive field measurements and 3-dimensional field map measurements. The properties and qualities of the magnet are assessed directly from ray-tracing, using stepwise integration, for deriving lattice parameters as tunes, chromaticities, dynamic paertures, etc. Reporting on this is the subject of the poster.


*http://lpsc.in2p3.fr/service_accelerateurs/raccam.htm

 
FR5REP099 Status of the FLNR JINR Cyclotrons ion, cyclotron, ECR, ion-source 5011
 
  • I.V. Kalagin, S.N. Dmitriev, B. Gikal, G.G. Gulbekyan
    JINR, Dubna, Moscow Region
 
 

The current status of the JINR FLNR cyclotrons and plans of their modernization are reported. At present time, four isochronous cyclotrons: U400, U400M, U200 and IC100 are under operation at the JINR FLNR. The U400 and the U400M are the basic cyclotrons that are under operation about 6000 and 3000 hours per year correspondingly. Both the accelerators are used in DRIBS experiments to produce and accelerate exotic very neutron-rich isotopes of light elements such as 6He and 8He. The U400 (pole diameter of D=4 m) is designed to accelerate ion beams of atomic masses from 4 to 209 to maximum energy of 26 MeV/u for synthesis of the new super heavy elements and other physical experiments. The U400M cyclotron (D=4 m) is used to accelerate ions of elements from Li to Ar up to 50 MeV/u and heavier ions such as 48Ca, Kr,Xe, up to 6 MeV/u after recent modernization. The U200 cyclotron (D=2 m) is used to produce isotopes by using He ions with energies about 9 MeV/u, modernization of the cyclotron injection is planned. Modernized IC100 accelerator (D=1m) is used to produce track membranes and carrying out experiments in solid-state physics by using Ar, Kr and Xe ions at energies of 1.2 MeV/u.

 
FR5REP100 Coupling Resonance Qx-Qy=0 and Its Correction in Axial Injection Channel of the Cyclotron emittance, resonance, cyclotron, ion 5014
 
  • N.Yu. Kazarinov
    JINR, Dubna, Moscow Region
 
 

In axial injection channels of FLNR JINR cyclotrons the axial symmetric ion beam is formed just after the analyzing bending magnet. This gives an opportunity to use for beam focusing at vertical part of the channel solenoidal magnetic lenses only. During the motion of intense axial symmetric beam in the longitudinal magnetic field of solenoids and cyclotron the transverse tunes Qx, Qy coincide. In this case the small disturbance of beam axial symmetry leads to excitation of coupling resonance Qx-Qy=0 due to beam self-fields. The influence of the resonance results in significant asymmetry of the transverse beam emittances. The magnitude of this asymmetry is evaluated within the framework of moments method and is in a good agreement with one obtained in the macro-particles simulation. The correction of resonance by means of the normal quadrupole lens is proposed.

 
FR5REP101 Screening of Optical Elements in C400 Axial Injection Beam Line cyclotron, shielding, ion, ion-source 5017
 
  • N.Yu. Kazarinov, V. Aleksandrov, V. Shevtsov, A. Tuzikov
    JINR, Dubna, Moscow Region
  • Y. Jongen
    IBA, Louvain-la-Neuve
 
 

C400 is compact superconducting cyclotron for hadron therapy. The permissible level of the transverse magnetic field at the horizontal part of axial injection beam line of a cyclotron is about 10 Gauss. At the same time the C400 magnetic field is about 500 Gauss in magnitude at the places of the ion sources, vertical bending magnet and quadrupole lens location. Thereby the screening of these beam-line elements is needed. The 3D OPERA model of the cyclotron and channel elements is used for this purpose.

 
FR5REP102 Axial Injection Beam Line of C400 Superconducting Cyclotron for Carbon Therapy ion, cyclotron, ion-source, solenoid 5020
 
  • N.Yu. Kazarinov, V. Aleksandrov, V. Shevtsov, A. Tuzikov
    JINR, Dubna, Moscow Region
  • Y. Jongen
    IBA, Louvain-la-Neuve
 
 

C400 is compact superconducting isochronous cyclotron for carbon beam therapy designed by IBA, Louvain-La-Neuve (Belgium) in collaboration with JINR, Dubna (Russia). The cyclotron can accelerate all ions with charge to mass ratio 0.5. Protons are accelerated as single charge 2H+ molecules and extracted by stripping at 270 MeV. All other ions are extracted by an electrostatic deflector at 400 MeV/u. The final layout of the axial injection beam line of C400 cyclotron is given. Two ion sources for production of 12C6+ ions and Alphas beams are located at the horizontal part of the channel before both side of the combination vertical magnet. The third ion source for the production of 2H+ is placed in straight line on the vertical axis. The rotational symmetry of the beam is reestablished with the help of one quadrupole lens placed just after analyzing magnet. The beam focusing at the vertical part of the channel is provided by three solenoidal lenses instead of four quadrupoles used in the previous version of beam line. The results of simulation of ion beams transport in the axial injection channel are presented.

 
FR5REP107 Modelling the ALICE Electron Beam Properties through the EMMA Injection Line Tomography Section space-charge, diagnostics, quadrupole, extraction 5023
 
  • D.J. Holder
    Cockcroft Institute, Warrington, Cheshire
  • B.D. Muratori
    STFC/DL/ASTeC, Daresbury, Warrington, Cheshire
 
 

EMMA (Electron Machine with Many Applications) is a prototype non-scaling electron FFAG currently under construction at Daresbury Laboratory. The energy recovery linac prototype ALICE will operate as its injector, at a reduced the energy of 10 to 20 MeV, compared to its nominal energy of 35 MeV. An injection line has been designed which consists of a dogleg to extract the beam from ALICE, a matching section, a tomography section and some additional dipoles and quadrupoles to transport and match the beam to the entrance of EMMA. This injection line serves both as a diagnostic to measure the properties of the beam being injected into EMMA and also a useful diagnostic tool for ALICE operation. This paper details the simulations undertaken of the electron beam passing through the matching and tomography sections of the EMMA injection line, including the effect of space charge. This will be an issue in the energy range at which this diagnostic is being operated when combined with high bunch charge. A number of different scenarios have been modelled and an attempt made to compensate for the effects of space charge in the matching and tomography sections.

 
FR5REP108 EMMA Diagnostic Line extraction, dipole, diagnostics, septum 5026
 
  • B.D. Muratori, J.K. Jones, S.L. Smith, S.I. Tzenov
    STFC/DL/ASTeC, Daresbury, Warrington, Cheshire
 
 

EMMA (Electron Machine with Many Applications) is a prototype non-scaling electron FFAG to be hosted at Daresbury Laboratory. NS-FFAGs related to EMMA have an unprecedented potential for medical accelerators for carbon and proton hadron therapy. It also represents a possible active element for an ADSR (Accelerator Driven Sub-critical Reactor). This paper will summarize the design of the extraction / diagnostic transfer line of the NS-FFAG. In order to operate EMMA, the energy recovery linac ALICE shall be used as injector and the energy will range from 10 to 20 MeV. Because this would be the first non-scaling FFAG, it is important that as many of the bunch properties are studied as feasible, both at injection and at extraction. To do this, a complete diagnostic line was designed consisting of a tomography module together with several other diagnostic devices including the possibility of using a transverse deflecting cavity. Details of the diagnostics are also presented.

 
FR5REP109 EMMA Commissioning extraction, diagnostics, controls, emittance 5029
 
  • B.D. Muratori, J.K. Jones, Y.M. Saveliev, S.L. Smith, S.I. Tzenov
    STFC/DL/ASTeC, Daresbury, Warrington, Cheshire
  • J.S. Berg
    BNL, Upton, Long Island, New York
  • C. Johnstone
    Fermilab, Batavia
  • S.R. Koscielniak
    TRIUMF, Vancouver
 
 

EMMA (Electron Machine with Many Applications) is a prototype non-scaling electron FFAG to be hosted at Daresbury Laboratory. NS-FFAGs related to EMMA have an unprecedented potential for medical accelerators for carbon and proton hadron therapy. It also represents a possible active element for an ADSR (Accelerator Driven Sub-critical Reactor). This paper summarises the commissioning plans for this machine together with the major steps and experiments involved along the way. A description of how the 10 to 20 MeV beam is achieved within ALICE is also given, as well as extraction from the EMMA ring to the diagnostics line and then dump.