Paper | Title | Other Keywords | Page |
---|---|---|---|
OPL02 | Status of J-PARC Commissioning | injection, linac, acceleration, betatron | 6 |
|
|||
The Japan Proton Accelerator Research Complex (J-PARC) consists of Linac, 3-GeV rapid cycling synchrotron (RCS) and 50-GeV main ring synchrotron (MR). The J-PARC has been beam-commissioned since November 2006. The Linac and RCS have recently completed initial tunings of the basic parameters, and are now in transition from commissioning to operation and also to the challenging phase for aiming at the higher current operation. The MR also has recently started initial tunings in the storage mode. In this talk, the current status of the J-PARC beam commissioning will be outlined together with experimental data obtained in the actual beam tuning procedures. |
|||
OPL03 | Intensity Upgrade Plans for CERN-LHC Injectors | injection, linac, emittance, impedance | 16 |
|
|||
With LHC coming into operation very soon an upgrade plan for the whole CERN accelerator complex has been proposed to allow full exploitation of the LHC potential in the future as well as giving increased support to traditional and possible new experiments at lower beam energies. This plan foresees replacing during the period 2011 - 2017 all the accelerators in the LHC injector chain (Linac2, Booster, PS) by new machines (Linac4, SPL and PS2) except for the last - the SPS. In this scenario the SPS should be able to reliably accelerate twice higher beam intensity than achieved so far and therefore significant improvements to the machine performance, in addition to the increased injection energy due to PS2, should be found and implemented at the same time scale. The present status of proposals and ongoing studies for all accelerator injector chain is described with main emphasis on the SPS challenges and upgrade plans. |
|||
|
|||
WGC04 | SNS Injection and Extraction Systems–Issues and Solutions | injection, target, scattering, beam-losses | 268 |
|
|||
Beam loss is higher than expected in the Ring injection section and in the injection dump beam line. The primary causes are fairly well understood, and we have made some equipment modifications to reduce the loss. In the ring extraction beam line the beam distribution exhibits cross-plane coupling (tilt), and the cause has been traced to a large skew-quadrupole component in the extraction Lambertson septum magnet. In this talk we will discuss the issues surrounding the ring injection and extraction systems, the solutions we have implemented to date, and our plans for future improvements. |
|||
|
|||
WGC05 | Experience with J-PARC RCS Injection and Extraction Systems | injection, beam-losses, septum, closed-orbit | 275 |
|
|||
The 3 GeV RCS(Rapid Cycling Synchrotron) of J-PARC(Japan Protron Accelerator Research Complex) is already in the beam commissioning stage and as designed working as an injector to the 50-GeV MR(Main Ring) as well as delivering stable beam to the spallation neutron target. The overall design strategy together with beam commissioning results of the injection and extraction will be presented. |
|||
|
|||
WGC14 | A Triplet Insertion Concept for the PS2 H- Injection | injection, optics, insertion, kicker | 326 |
|
|||
The PS2, foreseen as a replacement of the CERN PS, is designed as a racetrack shaped machine with two long straight sections (LSS) for injection/extraction and RF, respectively. Two injection and three extraction systems are required, and in the present study are designed to fit in either a six-cell FODO or a seven-cell DOFO insertion, with a central triplet in order to fit the complete H- injection in one long drift. This study covers the optimisation of the LSS optics and the arrangement and characteristics of the various insertion elements. The main focus lies on the H- injection embedded in the triplet cell with the design of the chicane and painting bump according to the limits of Lorentz-stripping, excited H0 behaviour and the focusing effects of the chicane dipoles on the overall optics. |
|||
WGD01 | Operation of the High Intensity Proton Beam Facility at PSI | cyclotron, target, beam-losses, proton | 329 |
|
|||
The cyclotron based high power proton accelerator facility at PSI drives a neutron spallation source and two Meson production targets with a CW proton beam at 590MeV kinetic energy. This talk concentrates on the operational and technical aspects specific to acceleration and transport of a high power beam. Furthermore a summary on upgrade plans to increase the beam power from presently 1.2MW to 1.8MW will be given. |
|||
|
|||
WGD11 | Beam Commissioning of J-PARC MR | injection, quadrupole, linac, cavity | 376 |
|
|||
Beam commissioning of J-PARC Main Ring (MR) has been started in May, 2008. The 3-GeV beams extracted from the rapid cycling synchrotron (RCS) are injected into the MR and captured by rf, and then extracted to a 3-GeV beam dump. In this paper, we present results of the first-stage commissioning run from May to June 2008. After five months shutdown for installation of fast extraction and slow extraction devices, the second-stage commissioning run will be started in December 2008. |
|||
WGD12 | The NumI Proton Beam at Fermilab: Successes and Challenges | proton, target, controls, beam-losses | 379 |
|
|||
The NuMI beam at Fermilab has delivered almost 5x10 20 120 GeV protons to the neutrino production target, since the start for MINOS physics operation in 2005. We will report on beam operation status, including successes and challenges to date with the beam and NuMI system technical components. Also covered will be the ongoing program of increasing NuMI beam power using slip stacking of beam in the Main Injector accelerator. |
|||
|
|||
WGE04 | The Superconducting SIS100 Synchrotron for High Intensity Proton and Heavy Ion Beams | ion, dipole, quadrupole, beam-losses | 393 |
|
|||
The double synchrotron complex SIS100 and SIS300 is the central part of the FAIR project. SIS100 is a fast ramped superconducting synchrotron optimized for high intensity, low-charge state heavy ion operation. However, similar to the existing heavy ion synchrotron SIS18, SIS100 will also be used to accelerate all other ion species down to protons, In order to enable such a flexible operation and to avoid transition energy crossing, a triplet structure with three independent power circuits has been chosen. For the low charge state operation, a new lattice design concept has been applied which provides an optimized separation of ionized beam particles. Low charge state operation is enabled by means of the cryopumping of the actively cooled, thin wall vacuum chambers. The stability of the residual gas pressure is an essential precondition for this operation. The project status and the status of the major device developments will be presented. |
|||
WGF07 | Beam Diagnostics at the RAL Front-End Test Stand First Results and New Ideas | diagnostics, ion-source, emittance, ion | 458 |
|
|||
In order to contribute to the development of high power proton accelerators in the MW range a front end test stand (FETS) is being constructed at the Rutherford Appleton Laboratory (RAL) in the UK. The aim of the FETS is to demonstrate the production of a 60 mA, 2 ms, 50 pps chopped beam at 3 MeV with sufficient beam quality. Therefore a comprehensive set of diagnostic tools have been developed or are in the design and construction phase. To improve the beam quality delivered by the Penning H- ion source using a slit extraction, a pepper pot emittance measurement device and a 2D-transversal profile scanner has been built and used on the ion source development rig and results of the beam measurements will be presented. As destructive diagnostic devices suffer from the high beam power deposited on the device surfaces, two new diagnostic devices based on the photo detachment principle are under construction: A laser wire scanner allowing the reconstruction of the full 2D-transversal density distribution using tomographic techniques and an emittance scanner device. The design and status of construction of both devices will be presented and new ideas for the data analyses discussed. |
|||
|
|||
WGF12 | NuMI Proton Beam Diagnostics and Control: Achieving 2 Megawatt Capability | beam-losses, controls, proton, target | 475 |
|
|||
The NuMI proton beam at Fermilab currently delivers 120 GeV protons to the neutrino production target at beam powers up to 320 kW, with design capability to 400 kW. We are preparing for upgrade to 700 kW, and are in planning stage for delivering 2.3 MW beam provided by the Project X accelerator upgrade. We will report on the system of beam diagnostics and control used in operation of the NuMI beam, and the experience to date. Also covered will be the steps to provide a robust system for transport and targeting beam of 2 MW and beyond. |
|||
|
|||
CPL03 | Summary Report for Working Group C: Accelerator System Design, Injection, Extraction, Collimation | injection, collimation, lattice, laser | 487 |
|
|||
The charge to this working group was the following:
|
|||
|