Paper | Title | Other Keywords | Page |
---|---|---|---|
MOPMB065 | Design Status of BCC Cryomodule for LCLS-II HE | cryomodule, cavity, simulation, cryogenics | 263 |
|
|||
Funding: This manuscript has been authored by Fermi Research Alliance, LLC under Contract No. DE-AC02-07CH11359 with the U.S. Department of Energy, Office of Science, Office of High Energy Physics. A Buncher or Capture Cavity (BCC) Cryomodule is currently in development at Fermilab for use in a second injector for LCLS-II-HE. The BCC Cryomodule is designed to contain one 1.3 GHz cavity and one solenoid magnet as part of a 100MeV low emittance injector. The design considerations for the Cryomodule are similar to the LCLS-II cryomodule with additional requirements to account for additional vacuum loading at the end of this vessel due to the termination of the insulating vacuum. To accomplish this design, the cryomodule is being developed using the experience gained during the development of the LCLS-II cryomodule. The design, analysis, and status of the Cryomodule will be discussed. |
|||
DOI • | reference for this paper ※ doi:10.18429/JACoW-SRF2023-MOPMB065 | ||
About • | Received ※ 18 June 2023 — Revised ※ 23 June 2023 — Accepted ※ 26 June 2023 — Issue date ※ 13 July 2023 | ||
Cite • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | ||
TUPTB027 | Cleanroom Assembly of the LIPAc Cryomodule | SRF, cavity, cryomodule, pick-up | 452 |
|
|||
In complement to the development activities for fusion reactors (JT-60SA & ITER), Fusion for Energy contributes to the R&D for material characterisation facilities. LIPAc is the technical demonstrator for the production and acceleration of a D+ beam that will be used for neutron production by nuclear stripping reaction on a liquid Li target. Since its first beam in 2014, the LIPAc construction and commissioning continues and will be concluded with the cryomodule installation, aiming for beam validation at nominal power. The cryomodule assembly, started in March 2019, was paused due to welding issues on the solenoid bellows. The slow pumping group used for the cleanroom assembly also needed improvement to overcome helium contamination. Two and half years were devoted to the pumping improvement and, repair, cold tests and high pressure rinsing of the solenoids. In August 2022, the cleanroom assembly resumed with the mounting of all power couplers to the SRF cavities. Despite good progress, the assembly had to be paused again to fix leaks on different vacuum components and a solenoid BPM port. This paper presents the issues faced and their solutions along the cold mass assembly. | |||
![]() |
Poster TUPTB027 [2.384 MB] | ||
DOI • | reference for this paper ※ doi:10.18429/JACoW-SRF2023-TUPTB027 | ||
About • | Received ※ 15 June 2023 — Revised ※ 24 June 2023 — Accepted ※ 29 June 2023 — Issue date ※ 16 July 2023 | ||
Cite • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | ||
TUPTB031 | Operational Consideration in the LIPAc SRF with Potential Solenoid Failure Modes | SRF, simulation, operation, cryomodule | 467 |
|
|||
The commissioning of LIPAc (Linear IFMIF Prototype Accelerator) is ongoing at Rokkasho institute of QST for the engineering validation of the accelerator system up to 9 MeV/125 mA. Several SRF cryomodules will be required for IFMIF to accelerate deuterons from 5 MeV to 40 MeV. The prototype of the first of these cryomodules has been manufactured and will be installed and tested on the LIPAc. It holds the eight HWRs (Half Wave Resonator) and RF couplers to accelerate the beam and the eight superconducting solenoids to focus it. During the solenoid HPR process, carried out after fixing welding issues on the solenoid beam line bellows, some concerns appeared about the integrity of two solenoids. The examination with CT scanning of the solenoids revealed that one screw and a few pins had leaved their socket. Although it should be no critical problem, we tried the beam simulation with PIC code TraceWin to determine the location of solenoids whose impact will be minimized to manage in case of failure of solenoid as mitigation action. This paper presents the recommended locations of the suspicious solenoids in the cryomodule and resultant beam conditions through the beam dynamics study. | |||
DOI • | reference for this paper ※ doi:10.18429/JACoW-SRF2023-TUPTB031 | ||
About • | Received ※ 28 June 2023 — Revised ※ 29 June 2023 — Accepted ※ 07 July 2023 — Issue date ※ 16 July 2023 | ||
Cite • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | ||
WEPWB066 | Final Design of the Production SSR1 Cryomodule for PIP-II Project at Fermilab | vacuum, cryomodule, cavity, alignment | 736 |
|
|||
Funding: Work supported by Fermi Research Alliance, LLC under Contract No. DEAC02- 07CH11359 with the United States Department of Energy, Office of Science, Office of High Energy Physics. This contribution reports the design of the production Single Spoke Resonator Type 1 Cryomodule (SSR1 CM) for the PIP-II project at Fermilab. The innovative design is based on a structure, the strongback, which supports the coldmass from the bottom, stays at room temperature during operations, and can slide longitudinally with respect to the vacuum vessel. The Fermilab style cryomodule developed for the prototype Single Spoke Resonator Type 1 (pSSR1), the prototype High Beta 650 MHz (pHB650), and preproduction Single Spoke Resonator Type 2 (ppSSR2) cryomodules is the baseline of the present design. The focus of this contribution is on the results of calculations and finite element analyses performed to optimize the critical components of the cryomodule: vacuum vessel, strongback, thermal shield, and magnetic shield. |
|||
DOI • | reference for this paper ※ doi:10.18429/JACoW-SRF2023-WEPWB066 | ||
About • | Received ※ 17 June 2023 — Revised ※ 24 June 2023 — Accepted ※ 28 June 2023 — Issue date ※ 15 July 2023 | ||
Cite • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | ||
WEPWB075 | Impact of Solenoid Induced Residual Magnetic Fields on the Prototype SSR1 CM Performance | cavity, cryomodule, focusing, SRF | 760 |
|
|||
Funding: This manuscript has been authored by Fermi Research Alliance, LLC, under Contract No. DE-AC02-07CH11359 with the U.S. Department of Energy, Office of Science, Office of High Energy Physics. A prototype cryomodule containing eight Single Spoke Resonators type-1 (SSR1) operating at 325 MHz and four superconducting focusing lenses was successfully assembled, cold tested, and accelerated beam in the framework of the PIP-II project at Fermilab. The impact of induced residual magnetic fields from the solenoids on performance of cavities is presented in this contribution. In addition, design optimizations for the production cryomodules as a result of this impact are highlighted. |
|||
![]() |
Poster WEPWB075 [2.429 MB] | ||
DOI • | reference for this paper ※ doi:10.18429/JACoW-SRF2023-WEPWB075 | ||
About • | Received ※ 26 June 2023 — Revised ※ 27 June 2023 — Accepted ※ 28 June 2023 — Issue date ※ 11 July 2023 | ||
Cite • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | ||
WEPWB083 | Basic Design and Consideration of Li-Vapor Contamination for A-FNS SRF | SRF, cavity, linac, operation | 773 |
|
|||
The Advanced Fusion Neutron Source (A-FNS) project is in progressing in Japan, QST Rokkasho institute. A-FNS will demonstrate a performance of the DEMO DT fusion reactor material. In order to perform the test, a high intensity deuteron beam accelerator will be used to produce a high flux neutron field which is similar to the 14 MeV DT neutron. The Superconducting Radio-Frequency linear accelerator (SRF) is one component of the A-FNS accelerator system. Although the A-FNS accelerator system design is based on the IFMIF design, the improvement of some subsystem has been considering by taking into account the lessons learnt from the LIPAc project. In order to keep a high stability and availability of the SRF performance, we plan to increase the number of SRF cavities and cryomodules considering the trouble or degradation of the cavity performance and modify the engineering design of some components. In addition, changing of the beam transport line design and Li vapor contamination study of SRF cavity are conducting. In this presentation, the progress of the SRF design and related activities for A-FNS in QST will be presented. | |||
DOI • | reference for this paper ※ doi:10.18429/JACoW-SRF2023-WEPWB083 | ||
About • | Received ※ 28 June 2023 — Revised ※ 29 June 2023 — Accepted ※ 30 June 2023 — Issue date ※ 17 August 2023 | ||
Cite • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | ||
FRIBA05 | Automation of FRIB SRF Cavities and SC Solenoids Turn-on/off | cavity, cryomodule, SRF, linac | 999 |
|
|||
The superconducting driver Linac for the Facility for Rare Isotope Beams (FRIB) is a heavy ion accelerator that accelerate ions to 200 MeV per nucleon. The Linac has 46 cryomodules that contain 324 superconducting radio frequency (SRF) cavities and 69 superconducting (SC) solenoid packages. For operation of all cryomodules with high efficiency and reliability, automation for SRF cavity and SC solenoid fast turn-on/off is essentially. Based on cryomodule commissioning results and expert experience, all manual cavity and solenoid turn-on/off procedures and steps have been replaced by automatic programs for FRIB linac operation. This allows the operators to turn the systems on and off without expert-level training. Automation reduces the risk of human error, speeds up beam recovery after user access to experimental areas, and increases beam availability. The cavity turn-on procedure makes sure that the cavity can operate at low field with expected read backs, ramps up the field, and makes sure that the RF amplitude and phase are stable. The design, implementation, and operating experience with automation will be presented. | |||
![]() |
Slides FRIBA05 [3.503 MB] | ||
DOI • | reference for this paper ※ doi:10.18429/JACoW-SRF2023-FRIBA05 | ||
About • | Received ※ 29 June 2023 — Revised ※ 16 August 2023 — Accepted ※ 21 August 2023 — Issue date ※ 21 August 2023 | ||
Cite • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | ||