TPPT017 Fabrication and Test of the Drift Tubes for PEFP 20 MeV DTL 1552
 
  • Y.-H. Kim, Y.-S. Cho, H.-J. Kwon, M.-Y. Park
    KAERI, Daejon
 
  Funding: This work is supported by the 21C Frontier R&D program in the Ministry of Science and Technology of the Korean government.

Drift tubes of PEFP (Proton Engineering Frontier Project) 20MeV DTL contain electro-quadrupole magnet composed of commercial enamel wire cooled with water coolant. Those were fabricated through the process of brazing, assembling, electron-beam welding, and post-machining. During the e-beam welding, temperature increase was kept under 50 degree to protect the EQM wire from thermal damage. We performed several tests such as vacuum leak test, hydraulic test, and electrical test. EQM properties such as effective length, magnetic saturation, and offset between magnetic center and geometric center of DT were measured and recorded also.

 
TPPT018 Tuning of 20MeV PEFP DTL 1598
 
  • M.-Y. Park, Y.-S. Cho, H.-S. Kim, H.-J. Kwon, K.T. Seol, Y.G. Song
    KAERI, Daejon
 
  Funding: This work is supported by the 21C Frontier R&D program in the Ministry of Science and Technology of the Korean government.

The PEFP (Proton Engineering Frontier Project) 20 MeV DTL have been constructing in KAERI site. The tuning goals for PEFP DTL are achieving the tank frequency as ± 5 kHz of designed resonant frequency and 1% of field profile through a tank. To tune the tank frequency 8 low power slug tuners per tank are fabricated and the tuning range is ±125 kHz per a tuner. Post couplers with tap to stabilize the field against the perturbation also are fabricated and will be installed every 3rd (1st tank) and 2nd (2,3,4th tank) drift tubes. We set up the bead perturbation measurement equipment as measuring the phase shift of a tank using network analyzer and LabView program. We are finalizing the tuning procedures and also the data calculation program. In this presentation we will show the overall features of the PEFP DTL tuning and discuss the measurement results.

 
WPAT012 Status and Test Results of HPRF System for PEFP 1288
 
  • K.T. Seol, Y.-S. Cho, H.-S. Kim, H.-J. Kwon, M.-Y. Park, Y.G. Song
    KAERI, Daejon
 
  Funding: This work is supported by the 21C Frontier R&D program in the Ministry of Science and Technology of the Korean government.

The PEFP 20MeV proton accelerator is composed of 3MeV RFQ and 20MeV DTL and two sets of 1MW, 350MHz RF system are required for each accelerating structure. The high power RF system for 3MeV RFQ was already installed and operated to drive the RFQ. The klystron was tested up to 600kW itself and operated in pulse routinely. The HPRF system for 20MeV DTL which consists of 4 tanks was installed, and the RF test for 4 tanks has been carried out. The ridge-loaded power coupler was designed and installed to drive RFQ and DTL. In this paper, the status and test results of the RF system for 20MeV proton accelerator are discussed.

 
FPAE044 Test Results of the PEFP 3MeV RFQ Upgrade 2842
 
  • Y.-S. Cho, S.-H. Han, J.-H. Jang, H.-S. Kim, Y.-H. Kim, H.-J. Kwon, M.-Y. Park, K.T. Seol
    KAERI, Daejon
 
  Funding: This work is supported by the 21C Frontier R&D program in the Ministry of Science and Technology of the Korean government.

A 3MeV RFQ upgrade for 100MeV proton accelerator has been fabricated at PEFP (Proton Engineering Frontier Project). The tuning of the cavity was carried out before and after the brazing to meet the condition that the quadrupole field profile is within 1% of design value and dipole component is less than 1% of quadrupole one. The ancillary system such as high power RF including klystron power supply and cooling system were already tested up to operating level. Therefore, the main issues of the tests were cavity conditioning up to full power level and low duty beam test. After the completion of the beam test of RFQ itself, the 20MeV DTL which has been tested independently will be carried out. In this paper, the test results of the PEFP 3MeV RFQ upgrade including high power conditioning and low duty beam acceleration are presented.

 
FPAE046 Initial Test of the PEFP 20MeV DTL 2917
 
  • H.-S. Kim, Y.-S. Cho, S.-H. Han, J.-H. Jang, Y.-H. Kim, H.-J. Kwon, M.-Y. Park, K.T. Seol
    KAERI, Daejon
  • Y.-S. Hwang
    SNU, Seoul
 
  Funding: This work is supported by the 21C Frontier R&D program in the Ministry of Science and Technology of the Korean government.

A conventional 20MeV drift tube linac (DTL) for the Proton Engineering Frontier Project (PEFP) has been developed as a low energy section of 100MeV accelerator. The machine consists of four tanks with 152 cells supplied with 900kW RF power from 350MHz klystron through the ridge-loaded waveguide coupler. We assembled the fabricated accelerator components and aligned each part with care. We have also prepared the subsystems for the test of the DTL such as RF power delivery system, high voltage DC power supply, vacuum system, cooling system, measurements and control system and so on. The detailed description of the initial test setup and preliminary test results will be given in this paper.