Author: de Oliveira, H.G.P.
Paper Title Page
MOPE08 The LNLS Metrology Building 17
 
  • H.G.P. de Oliveira, C. Esper Neto, P.T. Fonseca, R.R. Geraldes, B.C. Meyer, M.A. Pereira, G.L.M.P. Rodrigues, L. Sanfelici, L.G. da Silva
    LNLS, Campinas, Brazil
  • L. Buccianti, M.H.A. Costa
    Biotec Controle Ambiental, São José dos Campos, SP, Brazil
  • C. Prudente
    Prudente Engenharia Ltda., Uberlândia, Minas Gerais, Brazil
 
  Funding: Brazilian Ministry of Science, Technology, Innovation and Communication.
The increasing demands of instrumentation projects for SIRIUS require more sensitive equipment to be devel-oped and characterized in theμand nanometer scale. To achieve this level of precision it is necessary to work within a controlled environment, minimizing instabilities and disturbance effects such as temperature variation and vibrations. Based on metrology labs as those at BESSY, ESRF, DLS and others, a new facility is currently under final construction stage at the LNLS, which will be dedi-cated to high precision optical and mechanical metrolo-gies. This work describes in detail the project of the new LNLS Metrology Building.
 
poster icon Poster MOPE08 [2.829 MB]  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-MEDSI2016-MOPE08  
About • paper received ※ 09 September 2016       paper accepted ※ 15 September 2016       issue date ※ 22 June 2017  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
WEPE06 High Heat Load Front Ends for Sirius 324
 
  • L.M. Volpe, H.F. Canova, P.T. Fonseca, P.P.S. Freitas, A. Gilmour, A.S. Rocha, G.L.M.P. Rodrigues, L. Sanfelici, M. Saveri Silva, H. Westfahl Jr., H.G.P. de Oliveira
    LNLS, Campinas, Brazil
 
  Funding: Brazilian Ministry of Science, Technology, Innovation and Communication (MCTIC)
Currently under construction on Brazilian Synchrotron Light Laboratory Campus, Campinas/SP, Sirius is a 3GeV, 4th Generation Synchrotron Light Source. In this paper we describe the Front End that has been designed to transmit the intense synchrotron radiation generated by the insertion devices that will generate the most critical thermal stress, with a peak power density of 55.7 kW/mrad² and a total power of 9.3kW at 500mA in the storage ring. The functions of the main components and their location in the layout are described. Computational fluid dynamics (CFD) and structural simulations, that have been carried out to verify the performance under the high heat loads generated by Sirius, are also detailed along with the limits of temperature and stress that have been employed in the design.
 
poster icon Poster WEPE06 [1.415 MB]  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-MEDSI2016-WEPE06  
About • paper received ※ 11 September 2016       paper accepted ※ 19 September 2016       issue date ※ 22 June 2017  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)