MOMPR008 |
SharePoint for HEPS Technical Systems and Project Management |
site, database, MMI, interface |
175 |
|
- X.H. Wu, L. Bai, C.P. Chu
IHEP, Beijing, People’s Republic of China
|
|
|
High Energy Photon Source is the latest planned synchrotron light source in China which is designed for ultra-low emittance and high brightness. The accelerator and beamlines contains tens of thousands of devices which require systematic management. It is also necessary to capture project management information systematically. HEPS chooses the Microsoft SharePoint as the document tool for the project and all technical systems. Additionally, Microsoft Project Server on top of SharePoint is used for the project management. Utilizing the SharePoint and Project software can facilitate a lot of daily work for the HEPS project. This paper describes the SharePoint and Project setup and various applications been developed so far.
|
|
DOI • |
reference for this paper
※ https://doi.org/10.18429/JACoW-ICALEPCS2019-MOMPR008
|
|
About • |
paper received ※ 01 October 2019 paper accepted ※ 09 October 2019 issue date ※ 30 August 2020 |
|
Export • |
reference for this paper using
※ BibTeX,
※ LaTeX,
※ Text/Word,
※ RIS,
※ EndNote (xml)
|
|
|
WEMPL008 |
The MAX IV Way of Agile Project Management for the Control System |
controls, software, feedback, synchrotron |
1020 |
|
- V.H. Hardion, M. Lindberg, D.P. Spruce
MAX IV Laboratory, Lund University, Lund, Sweden
|
|
|
Projects management of synchrotron is both complicated and complex. Building scientific facilities are resource consuming although largely made out of standard and well known components. The industrial approach of project management resolves this complication by requiring analysis and planning to facilitate the execution of tasks. The complexity comes by all the research making unique the accelerators, the beamlines and its usage. Known unknown requires experiments which evolve continuously causing the development path to be naturally iterative. Agile project management has come a long way since its definition in 2001. Nowadays this method is ubiquitous in the software development industry following different implementation like Scrum or XP and started to evolve at a bigger scale (i.e Scaled Agile) applied within an entire organization. The versatility of the Agile method has been applied to a Scientific technical development program such as the MAX IV Laboratory control system. This article describes the experience of 7 years of Agile project management and the use of Lean Management principles to develop and maintain the control system.
|
|
|
Slides WEMPL008 [1.834 MB]
|
|
|
Poster WEMPL008 [0.959 MB]
|
|
DOI • |
reference for this paper
※ https://doi.org/10.18429/JACoW-ICALEPCS2019-WEMPL008
|
|
About • |
paper received ※ 30 September 2019 paper accepted ※ 09 October 2019 issue date ※ 30 August 2020 |
|