Author: Leustean, M.C.
Paper Title Page
THP035 Production of a 1.3 GHz Niobium 9-cell TRIUMF-PAVAC Cavity for the ARIEL Project 978
 
  • V. Zvyagintsev, B. Amini, P.R. Harmer, P. Kolb, R.E. Laxdal, Y. Ma, B.S. Waraich, Z.Y. Yao
    TRIUMF, Canada's National Laboratory for Particle and Nuclear Physics, Vancouver, Canada
  • R. Edinger, M.C. Leustean, R. Singh
    PAVAC, Richmond, B.C., Canada
 
  A nine-cell 1.3 GHz superconducting niobium cavity has been fabricated for the ARIEL project at TRIUMF. The cavity is intended to accelerate a beam current of 10 mA at an accelerating gradient of 10 MV/m. The beam loaded RF power of 100 kW is supplied through two opposed fundamental power couplers. The electromagnetic design was done by TRIUMF. The cavity final design and fabrication procedure have been developed in collaboration between TRIUMF and PAVAC Industries Inc. Several innovations in the cavity fabrication process were developed at PAVAC. Since the most important weld is at the equator this weld is done first to form a ‘smart-bell’ as the basic unit as opposed to welding first at the iris to form ‘dumb-bell’ units. Each half cell is pressed with a male die into a plastic forming surface to produce half-cells with less shape distortion and material dislocations. The cavity fabrication sequence including the frequency tuning steps and RF frequency modelling methods will be discussed.