TUPB066 Preliminary Test of the Bunch-by-Bunch Transverse Feedback System for TPS Storage Ring 502
 
  • Y.-S. Cheng, P.C. Chiu, K.T. Hsu, S.Y. Hsu, H.P. Hsueh, K.H. Hu, C.Y. Liao
    NSRRC, Hsinchu, Taiwan
 
  Commissioning of the Taiwan Photon Source (TPS) is in progress and divided into two phases. The storage ring equips with two five-cell PETRA RF cavities and without insertion devices installed for Phase-I commission to confirm correctness of everything, to do preliminary vacuum clearing, and wait available of cryogenic system available. After finished the Phase I commissioning in March, 2015, installation of two superconducting RF cavities and 10 sets of insertion devices are ongoing. The commissioning is planned to start around in August. There is a prototype vertical stripline kicker installed in 2014. One horizontal stripline kicker and two vertical stripline kickers were installed in May. Commercial available feedback processor was selected for the feedback system integration. Preliminary feedback loop closed have been tested during Phase-I beam commissioning in early 2015 with prototype vertical kicker. Beam commissioning with new kickers is scheduled when beam stored in Phase-II beam commissioning which will started soon. Final check before beam test is under way.  
Export • reference for this paper to ※ BibTeX, ※ LaTeX, ※ Text, ※ RIS/RefMan, ※ EndNote (xml)  
 
TUPB067 Synchrotron Radiation Measurement at Taiwan Photon Source 507
 
  • C.Y. Liao, Y.-S. Cheng, P.C. Chiu, K.T. Hsu, S.Y. Hsu, H.P. Hsueh, K.H. Hu, C.K. Kuan, C.Y. Wu
    NSRRC, Hsinchu, Taiwan
 
  The synchrotron radiation light produced from a dipole magnet is widely used to characterize beam parameters in synchrotron light source (photon synchrotron). The synchrotron radiation monitor (SRM) systems were implemented for the booster synchrotron and the storage ring at Taiwan Photon Source (TPS). The beam parameters of the booster were recorded during the energy ramping process through the CCD camera and streak camera. The beam size measurement and beam behavior observed of the storage ring were performed by X-ray pinhole camera and streak camera respectability. The results are summarized in this report.  