WGF11 Beam Diagnostic System of the Main Ring Synchrotron of J-PARC 472
 
  • K. Satou
    J-PARC, KEK&JAEA, Ibaraki-ken
  • D.A. Arakawa, A. Arinaga, Y. Hashimoto, S. Igarashi, M. Tejima
    KEK, Ibaraki
  • N. Hayashi, K. Yamamoto
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
  • T. Toyama
    J-PARC, KEK & JAEA, Ibaraki-ken
 
 

The beam commissioning of the J-PARC Main Ring synchrotron (MR) has been started from May of this year. A single bunch beam from 3 GeV Rapid Cycling Synchrotron (RCS) was injected to the ring through 3-50 beam transporting (3-50BT) and then was extracted to the beam dump after 1000 turns (typically) without acceleration. The beam intensity was 4·1011 ppb that is 2 orders of magnitude smaller than that of the design intensity. The beam diagnostic system was used to establish the beam operational parameters. The system includes the instrumentations as follows; 3 types of Current Transformers (CTs), DCCT, fast CT (FCT), and Wall Current Monitor (WCM); Beam Position Monitors (BPMs); proportional counter type Beam Loss Monitors (BLMs) at each quadropole magnet; horizontal and vertical tune monitors with exciter systems; and 3 types of beam profile monitors, Multi Wire Profile Monitors (MWPMs) at 3-50BT and downstream of injection septa, a horizontal Flying Wire Profile Monitor (FWPM) and a vertical residual gas Ionization Profile Monitor (IPM) in the ring. At the workshop, the present status of the system will be presented.

 

slides icon

Slides