TUB001 Accelerator Data Foundation: How It All Fits Together 61
 
  • R. Billen, P. Le Roux, M. Peryt, C. Roderick, Z. Zaharieva
    CERN, Geneva
 
  Since 2003, a coherent data management approach was envisaged for the needs of installing, commissioning, operating and maintaining the LHC. Data repositories in the distinct domains of physical equipment, installed components, controls configuration and operational data have been established to cater for these different aspects. The interdependencies between the domains have been implemented as a distributed database. This approach, based on a very wide data foundation, has been used for the LHC and is being extended to the CERN accelerator complex.  
slides icon Slides  
WEP061 The Control System for the Cryogenics in the LHC Tunnel [ First Experience and Improvements ] 519
 
  • P. Gomes, E. Blanco, J. Casas, C. Fluder, E. Fortescue-Beck, P. Le Roux, G. Penacoba, M. Pezzetti, M. Soubiran, A. Tovar, L. Zwalinski
    CERN, Geneva
 
  The Large Hadron Collider (LHC) has been commissioned and started operation with beams in 2008, at CERN. Several months of cryogenic operation in nominal conditions have triggered an optimisation of the cryogenic process functional analysis. This lead to a few revisions of the control logic, realised on-the-fly; and to a major rebuild of the logic, implemented during the 2008-9 shut-down. In order to improve the operability, availability and safety of the LHC cryogenics, the process control structure was reorganised; the logic of process phases, interlocks, regulators and templates for automatic code generators were modified; the hard-wired vacuum-quality signals were upgraded to provide more detailed information; the protection of current feed boxes was enhanced by the addition of new signals; a new tool for remote-reset of Profibus-IO was developed. The databases, containing all instruments and controls information, were rationalized; the automatic specification generators, which extract the parameters used in the control software, were simplified. This paper describes the main improvements applied during the 2008-09 shut-down, and suggests perspectives of further developments.  
poster icon Poster