MO405Construction and Commissioning of KEKB Superconducting Crab Cavities63
 
  • K. Hosoyama, K. Hara, A. Honma, A. Kabe, Y. Kojima, Y. Morita, H. Nakai, K. Nakanishi, K. Akai, K. Ebihara, T. Furuya, S. Mitsunobu, M. Ono, Y. Yamamoto
    KEK
  • K. Okubo, K. Sennyu, H. Hara, T. Yanagisawa
    MHI Kobe
 
 The superconducting crab cavities for KEKB were constructed and installed into KEKB electron-positron collider in January 2007. After cool-down of the crab cavities, the commissioning of the crab cavities started in February 2007 and continued until end of June. Effective head on collision of electron and positron has been achieved successfully for the first time during this spring operation of the KEKB. A luminosity of above 10^34/cm2/sec could be obtained at high beam currents operation (1.3A in the low energy positron and 0.7A in high energy electron). 