WEPPC047 | Operational Experience with 55 MeV Pulsed RTM | 538 |
|
||
Operational experience with 55 MeV RTM * is reported. After RTM commissioning described in * it was installed in specially built bunker with 60-80 cm thick barite concrete walls placed in accelerator hall in order to protect detector equipment from parasitic radiation. New equipment was installed at RTM including new pulsed modulator, high power vacuum window and circulator, new cooling system, additional steering coils. Control system software based on LabView was also modified to make RTM tuning easier. Introduced changes made RTM operation more stable, beam transmission through RTM was improved. After re-commissioning RTM is used for experiments in nuclear physics, in PET isotope production research, in explosive detection experiments etc.
*A.I.Karev, A.N.Lebedev, V.G.Raevsky, A.N.Ermakov, A.N.Kamanin, V.V.Khankin, N.I.Pahomov, V.I.Shvedunov, etc., 55 MeV special purpose race-track microtron commissioning, in Proc. RuPAC-2010, p.316-318 |
||