RPPE002 Installation and Radiation Maintenance Scenario for J-PARC 50 GeV Synchrotron 835
 
  • M. Yoshioka, H. Kobayashi, T. Oogoe, Y. Takeuchi, Y. Watanabe
    KEK, Ibaraki
  • Y. Kuniyasu
    MELCO SC, Tsukuba
  • H. Oki, Y. Takiyama
    ,
 
  Funding: Ministry of Education, Culture, Science and Technology, Japan

J-PARC comprises a 400 MeV linac (181 MeV at the first stage), a 3 GeV rapid-cycling synchrotron and a 50 GeV synchrotron (Main Ring), which will provide high power proton beam to the material and life science facility, the neutrino facility and the nuclear and particle physics experimental hall. The installation of the accelerator components for the Main Ring will be started on mid. 2005 and the beam commissioning is scheduled in end of 2007. This paper describes the installation scenario of the accelerator components into the main ring tunnel and the development of radiation maintenance scenario for the beam injection and ejection systems.