Pasky, S.J.

Paper Title Page
WPAE070 Injector Power Supplies Reliability Improvements at the Advanced Photon Source 3804
 
  • A.L. Hillman, S.J. Pasky, N. Sereno, R. Soliday, J. Wang
    ANL, Argonne, Illinois
 
  Funding: *Work supported by U.S. Department of Energy, Office of Basic Energy Sciences, under Contract No. W-31-109-ENG-38.

Operational goals for the APS facility include 97% availability and a mean time between unscheduled beam losses (faults) of 70 hours, with more than 5000 user hours of scheduled beam per year. To meet this objective, our focus has changed to maximizing the mean time between faults (MTBF). We have made various hardware and software improvements to better operate and monitor the injector power supply systems. These improvements have been challenging to design and implement in light of the facility operating requirements but are critical to maintaining maximum reliability and availability of beam for user operations. This paper presents actions taken as well as future plans to continue improving injector power supply hardware and software to meet APS user operation goals.