WEPOA15 Installation Progress at the PIP-II Injector Test at Fermilab 722
 
  • C.M. Baffes, M.L. Alvarez, R. Andrews, A.Z. Chen, J. Czajkowski, P. Derwent, J.P. Edelen, B.M. Hanna, B.D. Hartsell, K.R. Kendziora, D.V. Mitchell, L.R. Prost, V.E. Scarpine, A.V. Shemyakin, J. Steimel, T.J. Zuchnik
    Fermilab, Batavia, Illinois, USA
  • A.L. Edelen
    CSU, Fort Collins, Colorado, USA
 
  Funding: Fermilab is operated by Fermi Research Alliance, LLC under Contract No. De-AC02-07CH11359 with the United States Department of Energy
A CW-compatible, pulsed H superconducting linac 'PIP-II' is being planned to upgrade Fermilab's injection complex. To validate the concept of the front-end of such a machine, a test accelerator (The PIP-II Injector Test, formerly known as "PXIE") is under construction. The warm part of this accelerator comprises a 10 mA DC 30 keV H ion source, a 2m-long LEBT, a 2.1 MeV CW RFQ, and a 10-m long MEBT that is capable of creating a large variety of bunch structures. The paper will report on the installation of the RFQ and the first sections of the MEBT and related mechanical design considerations.
 
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-NAPAC2016-WEPOA15  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)