Author: Zhang, J.H.
Paper Title Page
THPO053 Status of the China Material Irradiation Facility RFQ 811
 
  • C.X. Li, W.L. Chen, W.P. Dou, Z. Gao, Y. He, G. Huang, C.L. Li, L. Lu, W. Ma, A. Shi, L.B. Shi, L.P. Sun, F.F. Wang, W.B. Wang, Z.J. Wang, Q. Wu, X.B. Xu, L. Yang, P.Y. Yu, B. Zhang, J.H. Zhang, P. Zhang, T.M. Zhu
    IMP/CAS, Lanzhou, People’s Republic of China
 
  Funding: Supported by the National Magnetic Confinement Fusion Science Program of China (Grant No.2014GB104001) and the National Natural Science Foundation of China (Grant No.91426303).
The pulsed high power test and beam test of the China Material Irradiation Facility RFQ have been implemented. Before this, the radio frequency measurements and tuning are performed. In this paper, the processes and results of the radio frequency measurements, tuning, pulsed high power test and beam test will be presented. The results of tests are in good agreement with the design.
 
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-LINAC2018-THPO053  
About • paper received ※ 12 September 2018       paper accepted ※ 21 September 2018       issue date ※ 18 January 2019  