TUPO114 Beam Dynamics Studies for the CSNS DTL Due to a Quadrupole Fault 573
 
  • J. Peng, M.T. Li, Y.D. Liu, X.H. Lu, X.B. Luo
    CSNS, Guangdong Province, People’s Republic of China
  • Y.W. An, S. Fu, L. Huang, M.Y. Huang, Y. Li, Z.P. Li, S. Wang, S.Y. Xu, Y. Yuan
    IHEP, Beijing, People’s Republic of China
 
  The China Spal­la­tion Neu­tron Source(CSNS) ac­cel­era-tor sys­tems is de­signed to de­liver a 1.6GeV, 100kW pro-ton beam to a solid metal tar­get for neu­tron scat­ter­ing re­search. It con­sists of a 50keV H Ion Source, a 3MeV Radio Fre­quency Quadru­pole (RFQ), an 80MeV Drift Tube Linac (DTL), and a 1.6GeV Rapid-cy­cling Syn­chro-tron (RCS). The DTL con­sists of four tanks. In 2017, three of four tanks have been com­mis­sioned suc­cess­fully, and beam has been ac­cel­er­ated to 61MeV with nearly 100% trans­mis­sion. How­ever, in July 2017, one quadru­pole con­tained in the drift tube was found fault, the beam trans­mis­sion de­creased to 80%. A new lat­tice has been de­signed and the 100% trans­mis­sion has re­cov­ered. In Jan­u­ary 2018, the last tank of the DTL has been com­mis­sioned and ac­cel­er­ated the H beam to the de­sign en­ergy of 80MeV for the first time. The com­mis­sion­ing progress and the mea­sure­ment re­sults be­fore and after lat­tice ad­just­ment will be pre­sented.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-LINAC2018-TUPO114  
About • paper received ※ 12 September 2018       paper accepted ※ 20 September 2018       issue date ※ 18 January 2019  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)