Author: Varela, R.
Paper Title Page
TU2A04 Progress Report on LIPAC 308
 
  • M. Sugimoto, T. Akagi, T. Ebisawa, Y. Hirata, R. Ichimiya, A. Kasugai, K. Kondo, S. Maebara, K. Sakamoto, T. Shinya
    QST, Aomori, Japan
  • P. Abbon, N. Bazin, B. Bolzon, N. Chauvin, S. Chel, R. Gobin, J. Marroncle, B. Renard
    CEA/IRFU, Gif-sur-Yvette, France
  • L. Antoniazzi, L. Bellan, D. Bortolato, M. Comunian, E. Fagotti, F. Grespan, M. Montis, A. Palmieri, A. Pisent, F. Scantamburlo
    INFN/LNL, Legnaro (PD), Italy
  • P.-Y. Beauvais, H. Dzitko, D. Gex, R. Heidinger, A. Jokinen, I. Moya, G. Phillips
    Fusion for Energy, Garching, Germany
  • P. Cara
    IFMIF/EVEDA, Rokkasho, Japan
  • D. Gavela, D. Jiménez-Rey, I. Kirpitchev, J. Mollá, P. Méndez, I. Podadera, D. Regidor, R. Varela, M. Weber
    CIEMAT, Madrid, Spain
  • J. Knaster
    F4E, Barcelona, Spain
  • G. Pruneri
    Consorzio RFX, Associazione Euratom-ENEA sulla Fusione, Padova, Italy
 
  International Fusion Materials Irradiation Facility (IFMIF) is the neutron source for simulating fusion reactor environment using two 40 MeV/125 mA CW D+ beams. LIPAc facility is under construction in Rokkasho for validating 9 MeV/125 mA CW linac technology as a prototype of the IFMIF accelerator. Commissioning of 5 MeV CW RFQ is underway after the completion of installation of RFQ, MEBT, diagnostic plate. low power beam dump, RF power system and their auxiliaries. As the first step, high power RF conditioning is planned to complete in early 2018 and beam commissioning will start with stepwise approach at the same time. The status of LIPAc construction for preparing 9 MeV acceleration and results of RFQ beam commissioning are presented.  
slides icon Slides TU2A04 [9.651 MB]  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-LINAC2018-TU2A04  
About • paper received ※ 12 September 2018       paper accepted ※ 21 September 2018       issue date ※ 18 January 2019  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)