WE1A05 |
SwissFEL Linac Commissioning Status, Current Performance and Future Plans |
605 |
|
- P. Craievich
PSI, Villigen PSI, Switzerland
|
|
|
SwissFEL, the hard x-ray free-electron laser facility at PSI, is in an advanced commissioning phase. The commissioning of the 5.8 GeV Linac started in 2016 and the first FEL pilot-experiments were performed at a reduced beam energy in the end of 2017. In 2018, it is foreseen to progressively increase the electron beam energy and photon energy up to the maximum design values, interleaved by several FEL pilot experiments. This paper gives an overview of the commissioning progress including the achieved machine performance and first operational experience.
|
|
|
Slides WE1A05 [10.370 MB]
|
|
DOI • |
reference for this paper
※ https://doi.org/10.18429/JACoW-LINAC2018-WE1A05
|
|
About • |
paper received ※ 18 September 2018 paper accepted ※ 09 October 2018 issue date ※ 18 January 2019 |
|
Export • |
reference for this paper using
※ BibTeX,
※ LaTeX,
※ Text/Word,
※ RIS,
※ EndNote (xml)
|
|
|
THPO115 |
Consolidation and Extension of the High-gradient LINAC RF Technology at PSI |
937 |
|
- P. Craievich, M. Bopp, H.-H. Braun, A. Citterio, H. Fitze, T. Garvey, T. Kleeb, F. Löhl, F. Marcellini, M. Pedrozzi, J.-Y. Raguin, L. Rivkin, K. Rolli, R. Zennaro
PSI, Villigen PSI, Switzerland
|
|
|
For SwissFEL a novel production process for high-gradient, high-precision C-band accelerating structures had been developed at PSI and was implemented for series production in collaboration with industry. The copper parts of the structures are machined and brazed relying on a ultra-high precision manufacturing process and tight mechanical tolerances; no RF tuning methods are applied during or after production. So far none of the structures of the series production failed during RF power conditioning and operation in the SwissFEL facility. After completing the series production for SwissFEL PSI started collaborations with CERN, ELETTRA and DESY for applying the production process and related know-how to other frequencies, namely S-band (3 GHz) and X-band (12 GHz). This paper gives an overview on the ongoing and planned R\&D activities and results obtained so far.
|
|
DOI • |
reference for this paper
※ https://doi.org/10.18429/JACoW-LINAC2018-THPO115
|
|
About • |
paper received ※ 11 September 2018 paper accepted ※ 19 September 2018 issue date ※ 18 January 2019 |
|
Export • |
reference for this paper using
※ BibTeX,
※ LaTeX,
※ Text/Word,
※ RIS,
※ EndNote (xml)
|
|
|