A   B   C   D   E   F   G   H   I   K   L   M   O   P   Q   R   S   T   U   V   W    

beam-transport

Paper Title Other Keywords Page
MO1002 Commissioning and Initial Operating Experience with the SNS 1-GeV Linac linac, SNS, target, emittance 1
 
  • S. Henderson
    ORNL, Oak Ridge, Tennessee
  The Spallation Neutron Source accelerator complex consists of a 2.5 MeV H- front-end injector system, a 186 MeV normal-conducting linear accelerator, a 1 GeV superconducting linear accelerator, an accumulator ring and associated beam transport lines. The SNS linac was commissioned in five discrete runs, starting in 2002 and completed in 2005. The remainder of the accelerator complex was commissioned in early 2006. With the completed commissioning of the SNS accelerator, the linac has begun initial low-power operations. In the course of beam commissioning, most beam performance parameters and beam intensity goals were achieved at low duty factor. A number of beam dynamics measurements have been performed, including emittance evolution and sensitivity to mismatch of the input beam. The beam commissioning results, achieved beam performance and initial operating experience of the SNS linac will be presented.  
 
MOP018 Upgrading the CEBAF Accelerator to 12 GeV: Project Status controls, linac, acceleration, dipole 70
 
  • L. Harwood
    Jefferson Lab, Newport News, Virginia
  Jefferson Lab is preparing to upgrade its 6 GeV Continuous Electron Beam Accelerator Facility (CEBAF) to 12 GeV as part of the 12 GeV Upgrade project. The doubled energy will significantly extend the scientific reach of the three existing Halls with upgraded experimental equipment, and will make possible a new research program in exotic mesons in a newly constructed fourth Hall. The acceleration of the present linacs will be roughly doubled through the addition of ten new cryomodules with performance ~5 times the original specification for CEBAF. The 2K helium plant will be roughly doubled; new rf systems, including digital controls, will be installed for the new cryomodules. The beam transport system’s capability will be doubled by strongly leveraging existing hardware (without incurring significant saturation) but must be enhanced with some replacement magnets, new power supplies, one new recirculation arc, and a beamline to the new Hall. Critical Decision 1 was approved by DOE for this project in February 2006. Technical status for the accelerator systems including R&D will be presented as well as the status of the 12 GeV Upgrade Project as a whole.  
 
MOP023 Beam-Based Optics Correction for New Beam Transport Line from LINAC to Photon Factory in KEK linac, optics, luminosity, quadrupole 85
 
  • N. Iida, M. Kikuchi
    KEK, Ibaraki
  The e+/e- injector LINAC in KEK usually injects into four rings which are Low Energy Ring(LER) of KEKB(3.5GeV/e+), High Energy Ring (HER) of KEKB(8.0GeV/e-), Photon Factory(PF)(2.5GeV/e-) and Advanced Ring for pulse X-rays(PF-AR)(3.0GeV/e-). While LINAC continuously injects into LER and HER alternatively every about five minutes, both of KEKB rings usually storage almost full operating currents. Time for PF or PF-AR which includes switching time had taken about 20 minutes a several times in a day. This had made luminosity at KEKB lower. In summer of 2005, a part of transport line from LINAC to PF were renewed, in which a DC bending magnet only for PF apportions electron beam from the end of LINAC to the new line. We succeeded to reduce the occupancy time for PF injection to about five minutes and there is almost no affection to KEKB luminosity. In this paper optics of the new PF beam transport line is described. In practical performance there had been leakage magnetic field from ECS magnets in KEKB(e+) beam transport line neighboring the PF line. Furthermore we measured the horizontal dispersions along the line. We describe about the magnetic shielding and the optics correction.