William Roybal (Los Alamos National Laboratory)
TUPM050
Study on Switching from H- to H+ Beam Delivery to the Proton Radiography and Ultra Cold Neutron Facilities at the Los Alamos Neutron Science Center (LANSCE)
The Los Alamos Neutron Science Center (LANSCE) is a highly versatile H-/H+ 800-MeV linear accelerator that serves five distinct user facilities. Currently, H+ is accelerated through the drift tube linac down a stub line for the Isotope Production Facility at 100 MeV. The other four user facilities at LANSCE use the H- beam accelerated to 800 MeV. The H+ beam had historically been accelerated to 800 MeV for Area A operations but has not done so for over two decades. There are potential benefits to accelerating the H+ beam to 800 MeV to serve the Proton Radiography and Ultra-cold Neutron facilities in terms of potentially higher peak currents, improved emittance, higher ion source reliability, etc. A study was commissioned this year to conduct a cost/schedule/benefit analysis of converting from H- operations to H+ operations for these two facilities. The status of that study will be discussed.
  • C. Taylor, E. Espinoza, G. Rouleau, H. Watkins, J. O'Hara, J. Bradley III, L. Neukirch, M. Gulley, T. Ito, W. Barkley, W. Roybal
    Los Alamos National Laboratory
Cite: reference for this paper using: BibTeX, LaTeX, Text/Word, RIS, EndNote
THPA106
Los Alamos National Laboratory Fast Kicker Upgrade 2022
The Los Alamos Neutron Science Center’s proton storage ring (PSR) extraction kicker systems consist of two thyratron switched blumlein modulators. The operating parameters of the PSR have changed over the years and the flattop voltage of the modulator outputs has become a limiting factor in the length of the beam pulse able to be extracted from the ring. The extraction voltage pulse travels upstream relative to the beam and thus needs to be longer than the beam pulse. A reanalysis of the voltage waveforms and the beam propagation times revealed that a longer pulse could reduce beam spill levels that have been seen during past run cycles. Reduced spill will allow operation at higher beam currents and thus increase the amount of beam current available for experimenters. We have upgraded the blumlein cables in both extraction kicker modulators with longer cables. We present test results of the modulator outputs and correlate their improvement with reduced beam losses at the PSR exit septum and improved beam delivery. LA-UR-22-21024
  • H. Gaus, W. Roybal
    Los Alamos National Laboratory
Cite: reference for this paper using: BibTeX, LaTeX, Text/Word, RIS, EndNote
THPA107
Development of the digital low level RF system for the LANSCE proton storage ring
4212
Abstract As part of the modernization of the Los Alamos Neu-tron Science Center (LANSCE), a digital low level RF (LLRF) control system for the LANSCE proton storage ring (PSR) is designed. The LLRF control system is im-plemented on a Field Programmable Gate Array (FPGA). The high resolution tunable 2.8MHz reference RF is gen-erated by a direct digital synthesizer (DDS) at the LANSCE front end and is transmitted to the PSR control system located half mile away. Since the digital LLRF control system is synthesized in the In-phase/Quadrature (I/Q) coordinate, the I/Q RF signals are generated by the Hilbert Transformer (HT) based finite impulse response (FIR) filter. For the stabilization of the cavity field, a Proportional-Integral (PI) feedback controller is imple-mented. In order to verify the performance of the LLRF control system before it is applied to the PSR, a FPGA based PSR cavity simulator is designed and its parame-ters are identified using the cavity field data obtained during the PSR beam operation. The low power LLRF testbench based on the simulator is constructed and the amplitude and phase stabilities of the digital LLRF sys-tem are verified.
  • S. Kwon, A. Archuleta, H. Gaus, L. Castellano, M. Prokop, P. Van Rooy, P. Torrez, W. Roybal
    Los Alamos National Laboratory
Paper: THPA107
DOI: reference for this paper: 10.18429/JACoW-IPAC2023-THPA107
About:  Received: 02 May 2023 — Revised: 10 May 2023 — Accepted: 16 Jun 2023 — Issue date: 26 Sep 2023
Cite: reference for this paper using: BibTeX, LaTeX, Text/Word, RIS, EndNote