JACoW logo

Joint Accelerator Conferences Website

The Joint Accelerator Conferences Website (JACoW) is an international collaboration that publishes the proceedings of accelerator conferences held around the world.


RIS citation export for THPAF019: Initial Performance of the Magnet System in the Splitter/Combiner Section of the Cornell-Brookhaven Energy-Recovery Linac Test Accelerator

TY - CONF
AU - Crittenden, J.A.
AU - Bartnik, A.C.
AU - Bass, R.M.
AU - Berg, J.S.
AU - Burke, D.C.
AU - Dobbins, J.
AU - Gulliford, C.M.
AU - Jusic, D.
AU - Li, Y.
AU - Sagan, D.
AU - Smolenski, K.W.
AU - Turco, Turco, J.
ED - Koscielniak, Shane
ED - Satogata, Todd
ED - Schaa, Volker RW
ED - Thomson, Jana
TI - Initial Performance of the Magnet System in the Splitter/Combiner Section of the Cornell-Brookhaven Energy-Recovery Linac Test Accelerator
J2 - Proc. of IPAC2018, Vancouver, BC, Canada, April 29-May 4, 2018
C1 - Vancouver, BC, Canada
T2 - International Particle Accelerator Conference
T3 - 9
LA - english
AB - The Cornell-Brookhaven Energy-recovery Linac Test Accelerator is a four-pass, 150-MeV electron accelerator with a six-cell 1.3 GHz superconducting-RF linear accelerator and a fixed-field alternating-gradient (FFAG) return loop made up of Halbach-style quadrupole magnets. The optics matching between the linear accelerator and the return loop is achieved with a conventional magnet system comprised of 50 dipole magnets and 64 quadrupole magnets in four beamlines at each end of the linac. The 42-, 78-, 114- and 150-MeV electron beams are separated into independent vacuum chambers in order to allow for the path-length adjustment required by energy recovery. We report on the first beam tests of the initial installation of the splitter/combiner section at the exit of the linac. The vacuum system of the 42-MeV S1 line was installed during the first week of April. Nine dipole and four quadrupole magnets were installed and surveyed into position the following week, and the water cooling system was commissioned. A 6-MeV beam passed through the line on April~11 with no need for adjusting pre-set magnet excitation currents. One week later, time-of-flight measurements were used to calibrate and phase the individual superconducting RF cavities. The S1 magnet settings were then scaled up to achieve 5-cavity, 42-MeV operation through the first nine FFAG permanent-magnet quadrupoles. This initial Fractional Arc Test will conclude on May 18, when the installation of the remaining seven splitter/combiner lines and the return loop will begin. CBETA operations are scheduled to begin in early 2019.
PB - JACoW Publishing
CP - Geneva, Switzerland
SP - 2986
EP - 2989
KW - linac
KW - quadrupole
KW - dipole
KW - cavity
KW - optics
DA - 2018/06
PY - 2018
SN - 978-3-95450-184-7
DO - 10.18429/JACoW-IPAC2018-THPAF019
UR - http://jacow.org/ipac2018/papers/thpaf019.pdf
ER -