Paper |
Title |
Page |
TOAB02 |
Current Status of the Control System for J-PARC Accelerator Complex
|
62 |
|
- M. Adachi, S. F. Fukuta, S. H. Hatakeyama, M. T. Tanaka
MELCO SC, Tsukuba
- A. Akiyama, N. Kamikubota, T. Katoh, K. Kudo, T. Matsumoto, H. Nakagawa, J.-I. Odagiri, Y. Takeuchi, N. Yamamoto
KEK, Ibaraki
- H. Ikeda, T. Suzuki, N. T. Tsuchiya
JAEA, Ibaraki-ken
- Y. I. Itoh, Y. Kato, M. Kawase, H. Sakaki, H. Sako, G. B. Shen, H. Takahashi
JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
- S. Motohashi, M. Takagi, S. Y. Yoshida
Kanto Information Service (KIS), Accelerator Group, Ibaraki
- S. S. Sawa
Total Support Systems Corporation, Tokai-mura, Naka-gun, Ibaraki
- M. S. Sugimoto
Mitsubishi Electric Control Software Corp, Kobe
- H. Yoshikawa
KEK/JAEA, Ibaraki-Ken
|
|
|
J-PARC accelerator complex consists of a proton linac (LINAC), > a Rapid Cycle Synchrotron (RCS), and a Main Ring synchrotron (MR). The commissioning of LINAC already started in November 2006, while the commissioning of Main Ring synchrotron (MR) is scheduled in May 2008. Most of the machine components of MR have been installed in the tunnel. Introduction of electronic modules and wiring will be made by the end of 2007. For the control of MR, the J-PARC accelerator control network was extended to include the MR related parts in March 2007. IOC computers (VME-bus computers) for MR will be introduced in 2007. In addition, more server computers for application development will be also introduced in 2007. This paper reports the status of development for the J-PARC MR control system.
|
|
|
Slides
|
|
ROAA04 |
XAL Online Model Enhancements for J-PARC Commissioning and Operation
|
494 |
|
- H. Ikeda
Visual Information Center, Inc., Ibaraki-ken
- M. Ikegami
JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
- T. Ohkawa, H. Sako, G. B. Shen
JAEA, Ibaraki-ken
- A. Ueno
JAEA/LINAC, Ibaraki-ken
- C. K. Allen
LANL, Los Alamos, New Mexico
|
|
|
The XAL application development environment has been installed as a part of the control system for the Japan Proton Accelerator Research Complex (J-PARC) in Tokai, Japan. XAL was initially developed at SNS and has been described at length in previous conference proceedings (e.g., Chu et. al. APAC07, Galambos et. al. PAC05, etc.). We outline the upgrades and enhancements to the XAL online model necessary for accurate simulation of the J-PARC linac. For example, we have added permanent magnet quadrupoles and additional space charge capabilities such as off-centered and rotated beams and bending magnets with space charge. In addition significant architectural refactoring was performed in order to incorporate the current, and past, upgrades into a robust framework capable of supporting future control operations. The architecture and design of XAL is as important as its function, as such, we also focus upon the revised architecture and how it supports a component-based, software engineering approach.
|
|
|
Slides
|
|
ROPB04 |
Beam Commissioning Software and Database for J-PARC LINAC
|
698 |
|
- C. K. Allen
LANL, Los Alamos, New Mexico
- H. Ikeda
Visual Information Center, Inc., Ibaraki-ken
- H. Sakaki, G. B. Shen, H. Takahashi, H. Yoshikawa
JAEA, Ibaraki-ken
- H. Sako
JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
|
|
|
A beam commissioning software system based on a relational database (RDB) has been developed for the J-PARC LINAC. We developed two high-level software frameworks, JCE and XAL. JCE (Java Commissioning Environment) based on a scripting language SAD script has been developed in Java with device control, monitoring, online modelling and data analysis functions. XAL has been developed initially by SNS and developed for J-PARC. A commissioning database system has been developed to configure commonly these two frameworks, for model geometry, EPICS control, and calibration parameters. A server for unit conversion of magnet power supplies has also developed for the commissioning software. Commissioning applications for RF tuning, transverse matching, orbit correction, beam-based calibration, beam monitor controls have been developed using the two framework and successfully applied for beam tuning. We report on the status of development for the commissioning software system.
|
|
|