Author: Arinaga, M.
Paper Title Page
MOAL03 Beam Commissioning of SuperKEKB Rings at Phase 1 6
 
  • M. Tobiyama, M. Arinaga, J.W. Flanagan, H. Fukuma, H. Ikeda, H. Ishii, K. Mori, E. Mulyani, M. Tejima
    KEK, Ibaraki, Japan
  • G. Bonvicini
    Wayne State University, Detroit, Michigan, USA
  • E. Mulyani
    Sokendai, Ibaraki, Japan
  • G.S. Varner
    University of Hawaii, Honolulu,, USA
 
  The Phase 1 commissioning of SuperKEKB rings with-out superconducting final focus magnets or Belle-II de-tector began in Feb., 2016. A total of 1010 mA (LER) and 870 mA (HER) stored beam has been achieved close to the design emittance and x-y coupling. Most of the beam diagnostics, including new systems such as gated turn-by-turn monitors and X-ray beam size monitors, have been commissioned with beam and proved to be essential to the success of machine commissioning. The results of the beam commissioning, including the evaluation and diffi-culties of the beam diagnostics are shown.  
slides icon Slides MOAL03 [9.607 MB]  
DOI • reference for this paper ※ DOI:10.18429/JACoW-IBIC2016-MOAL03  