Wang, J.Q.

Paper Title Page
MOACH02 The Second Phase Commissioning of BEPCII 5
 
  • J.Q.Wang, L.Ma and C.Zhang
    IHEP, CAS
 
  BEPCII is the upgrade project of Beijing Electron-Positron Collider (BEPC), which will operate in the beam energy region of 1-2.1 GeV with the design luminosity of 1*10e33 cm-2s-1 at 1.89 GeV. From Nov. 2006 to Aug. 2007, the phase one beam commissioning of BEPCII storage rings was carried out with the so called backup scheme which adopted conventional magnets in the IR instead of the superconducting insertion magnets (SIM). After the SIM was installed into the interaction region, the second phase commissioning began in Oct. 2007. The tuning method for high luminosity but low background has been extensively studied, and the beam current reached more than 1/2 of the design of 0.91 A, with the luminosity higher than 1*10e32 cm-2s-1, which is 10 times of BEPC. In addition, beam was delivered to SR users for about 1 month at 2.5GeV with maximum current over 250mA.  
slides icon Transparencies  
   
MOACH03 Beam Dynamics Studies in the BEPCII Storage Rings 9
 
  • Q.Qin, N. Huang, W.B. Liu, Y.D. Liu, Y.M. Peng, J. Qiu, D. Wang, X.H. Wang, N. Wang, J.Q. Wang, Y.Y. Wei, X.M. Wen, J. Xing, G. Xu, C.H. Yu, C. Zhang, Y. Zhang, Z. Zhao, D.M. Zhou
    IHEP, CAS
 
  As an upgrade project of the Beijing Electron Positron Collider (BEPCII), the commissioning of the storage rings for both collision and synchrotron radiation modes started in Nov. 2006. Besides the normal commissioning on luminosity and beam performance, beam dynamics studies are being carried on as well. Some results on beam parameters determination, single and multi-bunch effect, and beam instabilities of two rings are given in this paper.  
slides icon Transparencies  
   
TUACH08 Experimental Background Study in the BEPCII/BESIII 49
 
  • C.Zhang, D.P. Jin, N. Huang, S.M. Yang, J. Xing, J.S. Cao, X.Y. Zhao, Q.J. Zhang, Q.B. Wu, Q. Qin, G. Xu, Y.Z. Wu, W.G. Li, Y.F. Wang, C. Zhang, J.Q. Wang, L. Ma, Y.N. Guo,
    IHEP, CAS
 
  Experimental beam-related background study is intro-duced with the BEijing Spectrometor (BESIII) off the interaction region (IR) of the BEPCII [2]. Only safety issues are studied carefully so far for the not good enough detectors’ accuracy. Various experiments are carried out and effective ways to reduce the doses to the IR are found. The results show that the BESIII is safe enough when it is pulled to the IR.  
slides icon Transparencies