TUPAB07 Commissioning of Positron Damping Ring and the Beam Transport for SuperKEKB 152
 
  • N. Iida, Y. Funakoshi, H. Ikeda, T. Ishibashi, H. Kaji, T. Kamitani, M. Kikuchi, T. Kobayashi, H. Koiso, F. Miyahara, T. Mori, Y. Ohnishi, Y. Seimiya, H. Sugimoto, H. Sugimura, R. Ueki, Y. Yano, D. Zhou
    KEK, Ibaraki, Japan
 
  The Positron Damping Ring (DR) for SuperKEKB successfully started its operation in February 2018, and the commissioning was continued until the end of SuperKEKB Phase 2 in July without serious troubles. This paper describes achievements of the beam commissioning of injection and extraction lines (LTR and RTL) between the LINAC and DR. In the LTR commissioning, the positron beam with high emittance, wide energy spread, and high charge were transported and injected into the DR. In the RTL commissioning, special cares were necessary to preserve the low emittance. The observed emittance growth in the RTL was not a problem for Phase 2, but it should be resolved in the coming Phase 3. In this paper, brief results of the commissioning of the DR is also reported.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-eeFACT2018-TUPAB07  
About • paper received ※ 20 October 2018       paper accepted ※ 19 February 2019       issue date ※ 21 April 2019  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)