TUPMA102 Installation and Radiation Maintanance Scenario for J-PARC 50 GeV Synchrotron 247
 
  • M. Yoshioka, T. Fujino, Y. Hori, K. Ishii, H. Kobayashi, T. Kubo, H. Matsumoto, H. Oki, T. Oogoe, Y. Saito, Y. Sato, M. Shimamoto, M. J. Shirakata, Y. Takeuchi, M. Uota, Y. Watanabe
    KEK, Ibaraki
  • M. HOSOKAWA
    THK CO., LTD, Hitachinaka
  • Y. Kuniyasu
    MELCO SC, Tsukuba
 
  Installation and assembling of accelerator components for J-PARC 50 GeV Synchrotron are now underway. Off-beam commissioning will be carried out between December 2007 and April 2008, and the full commissioning of J-PARC accelerator complex, which is consisted of an injector linac, a 3 GeV rapid cycling synchrotron and the 50 GeV Synchrotron, will be started from May 2008. This paper describes the status, schedule and method of installation and assembling of accelerator components. Radiation maintenance scenario will be also described.