Author: Schalwat, M.
Paper Title Page
MOP040 Industrialization of European XFEL Preparation Cycle “Final EP ” at Research Instruments Company 201
 
  • A. Matheisen, N. Krupka, M. Schalwat, A. Schmidt, M. Schmökel, W. Singer, B. van der Horst
    DESY, Hamburg, Germany
  • P. Michelato, L. Monaco
    INFN/LASA, Segrate (MI), Italy
  • M. Pekeler
    RI Research Instruments GmbH, Bergisch Gladbach, Germany
 
  In the Specification for XFEL Cavity preparation (R1) two different preparation sequences are presented. Research Instruments Company as one of the two companies contracted for XFEL cavity production and preparation has chosen the so called “final EP” cycle. Major infrastructure components like EP facility and the BCP facility were pre- qualified. This existing and the new set up areas like the cleanroom are distributed over the ground area of the industrial park Bergisch Gladbach. The process flow given in the DESY specification needed adaptation to this scenario. Additional infrastructure beside the once specified needed to be set up to ensure the same quality of processes even with a changed work flow. The general lay out of the facility, matched work flow of preparation and test results of resonators processed by RI company in their infrastructure will be reported.
(R1) Series Surface and acceptance test preparation of superconducting cavities for the European Xfel (XFEL/A - D) JUNE 30, 2009
 
 
MOP047 Set up of Production Line for EXFEL Beam Position Monitor and Quadrupol Units for Cavity String Assembly at CEA 224
 
  • M. Schalwat, M. Koepke, A. Matheisen, H. Weitkämper
    DESY, Hamburg, Germany
 
  The super conducting (s.c.) accelerator models of the EXFEL consist of eight s.c. resonators, one s.c. quadrupol magnet and one beam position monitor. These components are connected inside ISO 4 cleanroom at CEA Saclay to a so called cavity string under the guidance of the XFEL WP 09 activities. The eight s.c. cavities are handed from DESY to CEA for string assembly after successful RF test. The beam- position monitor and Quadrupol units (BQU) are assembled and cleaned in the DESY cleanroom at DESY Hamburg to the same standard’s of cleanliness as requested for s.c. Cavities. The completed BQU units are handed over to CEA IRFU / WP 9 in “ready for installation to cavity string“ status. The setup of infrastructure, the qualification of processes and transport as well as the ramp up to a delivery rate of 1 BQU per week will be presented.  
 
TUP056 Industrialization of European XFEL Preparation Cycle “BCP Flash” at Ettore Zanon Company 547
 
  • A. Matheisen, N. Krupka, M. Schalwat, A. Schmidt, W. Singer, N. Steinhau Kühl, B. van der Horst
    DESY, Hamburg, Germany
  • G. Corniani
    Ettore Zanon S.p.A., Schio, Italy
  • P. Michelato, L. Monaco
    INFN/LASA, Segrate (MI), Italy
 
  In the Specification for XFEL Cavity preparation (R1) two different preparation sequences are presented. Ettore Zanon Company as one of the two companies contracted for XFEL cavity production and preparation has chosen the so called BCP flash cycle. To fulfill the requested work flow and quality of infrastructure and processes, the company set up a complete new infrastructure in refurbished fabrication halls. The layout of the facility, set up of work flow of preparation and test results of resonators processed by E.Zanon in their infrastructure will be reported.
(R1) Series Surface and acceptance test preparation of superconducting cavities for the European Xfel (XFEL/A - D) JUNE 30, 2009