Paper | Title | Page |
---|---|---|
TU3GRC05 | Commissioning and Performance of LCLS Cavity BPMs | 754 |
|
||
Funding: Work supported by U.S. Department of Energy under Contract Nos. DE-AC02-06CH11357 and DE-AC02-76SF00515. We present the performance of the cavity beam position monitor (BPM) system for the LCLS undulator. The construction and installation phase of 34 BPMs for the undulator and 2 for the transport line have been completed. The X-band cavity BPM employs a TM010 monopole reference cavity and a TM110 dipole cavity designed to operate at a center frequency of 11.384 GHz. The signal processing electronics features a low-noise single-stage three-channel heterodyne receiver that has selectable gain and a phase locking local oscillator. The approximately 40 MHz IF is digitized by a 120M sample/second four-channel 16-bit digitizer. System requirements include sub-micron position resolution for a single-bunch beam charge of 200 pC. We discuss the system specifications and commissioning results. |
||
|