TU5RFP042 Commissioning and User Operation of the ALS in Top-Off Mode 1183
 
  • C. Steier, B.J. Bailey, K.M. Baptiste, W. Barry, A. Biocca, W.E. Byrne, P.W. Casey, M.J. Chin, R.J. Donahue, R.M. Duarte, M.P. Fahmie, J. Gath, S.R. Jacobson, J. Julian, J.-Y. Jung, A.M. Kritscher, S. Kwiatkowski, S. Marks, J.P. McKean, R.S. Müller, H. Nishimura, J.W. ONeill, G.J. Portmann, S. Prestemon, D. Robin, S.L. Rossi, F. Sannibale, T. Scarvie, D. Schlueter, B. Shuman, A.Z. Smith-Baumann, G.D. Stover, CA. Timossi, W. Wan, T. Warwick, J.M. Weber, R.P. Wells, E.C. Williams
    LBNL, Berkeley, California
 
 

Funding: This work was supported by the Director, Office of Science, U. S. Department of Energy under Contract No. DE-AC02-05CH11231.


The upgrade of the Advanced Light Source to enable top-off operation has been ongoing for the last four years. Activities over the last year have centered around radiation safety aspects, culminating in a systematic proof that top-off operation is equally safe as decaying beam operation, followed by commissioning and full user operations. Top-off operation at the ALS provides a very large increase in time-averaged brightness to ALS users (by about a factor of 10) as well as improvements in beam stability. The presentation will provide an overview of the radiation safety rationale, commissioning results, as well as experience in user operations.