A   B   C   D   E   F   G   H   I   J   K   L   M   N   O   P   Q   R   S   T   U   V   W   X   Y   Z  

Redaelli, S.

Paper Title Page
TU6PFP057 Operational Experience with First Circulating Beam in the LHC 1412
 
  • M. Lamont, R. Alemany-Fernandez, R. Bailey, P. Collier, B. Goddard, V. Kain, A. Macpherson, L. Ponce, S. Redaelli, W. Venturini Delsolaro, J. Wenninger
    CERN, Geneva
 
 

Following a series of injection tests, the first attempts to pass beam around both directions of the LHC were successful and led rapidly to circulating beam in the counter clockwise direction (beam 2) and many turns of beam 1. Unfortunately the beam commissioning was curtailed by the incident in sector 34. However, measurements performed during this first commissioning period should that the magnet model of the machine had delivered optics close to nominal, and also very good performance of beam instrumentation and supporting software. Details of the machine set-up and the commissioning procedures are detailed. The measurements performed and the key results from this period are described.

 
WE6PFP012 LHC Cleaning Efficiency with Imperfections 2504
 
  • C. Bracco, R.W. Assmann, S. Redaelli, Th. Weiler
    CERN, Geneva
 
 

The performance reach of the LHC depends on the magnitude of beam losses and the achievable cleaning efficiency of its collimation system. The ideal performance reach for the nominal Phase 1 collimation system is reviewed. However, unavoidable imperfections affect any accelerator and can further deteriorate the collimation performance. Multiple static machine and collimator imperfections were included in the LHC tracking simulations. Error models for collimator jaw flatness, collimator setup accuracy, the LHC orbit and the LHC aperture were set up, based to the maximum extent possible on measurements and results of experimental beam tests. It is shown that combined "realistic" imperfections can reduce the LHC cleaning efficiency by about a factor 11 on average.

 
WE6PFP013 Beam Commissioning Plan for LHC Collimation 2507
 
  • C. Bracco, R.W. Assmann, S. Redaelli, Th. Weiler
    CERN, Geneva
 
 

The Large Hadron Collider extends the present state-of-the-art in stored beam energy by 2-3 orders of magnitude. A sophisticated system of collimators is implemented along the 27 km ring and mainly in two dedicated cleaning insertions, to intercept and absorb unavoidable beam losses which could induce quenches in the superconducting magnets. 88 collimators per beam are initially installed for the so called Phase 1. An optimized strategy for the commissioning of this considerable number of collimators has been defined. This optimized strategy maximizes cleaning efficiency and tolerances available for operation, while minimizing the required beam time for collimator setup and ensuring at all times the required passive machine protection. It is shown that operational tolerances from collimation can initially significantly relaxed.

 
WE6PFP019 First Beam-Based Aperture Measurements in the Arcs of the CERN Large Hadron Collider 2525
 
  • S. Redaelli, I.V. Agapov, B. Dehning, M. Giovannozzi, F. Roncarolo, R. Tomás
    CERN, Geneva
  • R. Calaga
    BNL, Upton, Long Island, New York
 
 

Various LHC injection tests were performed in August and early September 2008 in preparation for the circulating beam operation. These tests provided the first opportunity to measure with beam the available mechanical aperture in two LHC sectors (2-3 and 7-8). The aperture was probed by exciting free oscillations and local orbit bumps of the injected beam trajectories. Intensities of a few 109 protons were used to remain safely below the quench limit of superconducting magnets in case of beam losses. In this paper the methods used to measure the mechanical aperture, the available on-line tools, and beam measurements for both sectors are presented. Detailed comparisons with the expected results from the as-built aperture models are also presented. It is shown that the measurements results are in good agreement with the LHC design aperture.

 
WE6RFP021 Beam Loss Predictions for the UA9 Crystal Collimation Experiment 2829
 
  • V.P. Previtali, R.W. Assmann, S. Redaelli
    CERN, Geneva
  • V.P. Previtali
    EPFL, Lausanne
  • I.A. Yazynin
    IHEP Protvino, Protvino, Moscow Region
 
 

The UA9 experiment at the SPS aims at testing bent crystals for usage as collimators with high energy stored proton and heavy ion beams. The experiments will try to establish crystal-based cleaning efficiency with slowly diffusing beam halo. One method for evaluating efficiency relies on Roman Pots and is described elsewhere. An alternative method relies on observing the beam loss signals around the ring. Comparisons of losses escaping from standard collimators and bent crystals will allow determination of cleaning efficiency, equivalent to the definition used for the LHC collimation design. This alternative method is described and simulations with LHC collimation tracking tools for UA9 are discussed. The predicted beam losses along the SPS ring are presented for different orientations and amorphous layer thicknesses of the crystal. The effect of different diffusion speeds for the beam are discussed.

 
WE6RFP022 Simulations of Crystal Collimation for the LHC 2832
 
  • V.P. Previtali, R.W. Assmann, S. Redaelli
    CERN, Geneva
  • V.P. Previtali
    EPFL, Lausanne
  • I.A. Yazynin
    IHEP Protvino, Protvino, Moscow Region
 
 

Bent crystals are promised to provide a path towards significant improvement of cleaning efficiency for high power collimation systems. In this paper a possible implementation of a crystal-enhanced collimation system is evaluated for the LHC. Simulation studies were performed with the same state-of the art tracking codes as used for the design of the conventional LHC collimation system. The numerical models are described and predictions for the local and global cleaning efficiency with a crystal-based LHC collimation system are presented. Open issues and further work towards a crystal collimation design for the LHC are discussed.

 
WE6RFP023 Operational Experience with a LHC Collimator Prototype in the CERN SPS 2835
 
  • S. Redaelli, O. Aberle, R.W. Assmann, C. Bracco, B. Dehning, M. Jonker, R. Losito, A. Masi, M. Sapinski, Th. Weiler, C. Zamantzas
    CERN, Geneva
 
 

A full scale prototype of the Large Hadron Collider (LHC) collimator was installed in 2004 in the CERN Super Proton synchrotron (SPS). During three years of operation the prototype has been used extensively for beam tests, for control tests and also to benchmark LHC simulation tools. This operational experience has been extremely valuable in view of the final LHC implementation as well as for estimating the LHC operational scenarios, most notably to establish procedures for the beam-based alignment of the collimators with respect to the circulating beam. This was made possible by installing in the SPS a first prototype of the LHC beam loss monitoring system. The operational experience gained at the SPS, lessons learnt for the LHC operation and various accelerator physics effects that could limit the efficiency of the collimator alignment procedures are presented.

 
WE1GRC05 Crystal Collimation Studies at the Tevatron (T-980) 1836
 
  • N.V. Mokhov, G. Annala, A. Apyan, R.A. Carrigan, A.I. Drozhdin, T.R. Johnson, A.M. Legan, R.E. Reilly, V.D. Shiltsev, D.A. Still, R. Tesarek, J.R. Zagel
    Fermilab, Batavia
  • R.W. Assmann, V.P. Previtali, S. Redaelli, W. Scandale
    CERN, Geneva
  • Y.A. Chesnokov, I.A. Yazynin
    IHEP Protvino, Protvino, Moscow Region
  • V. Guidi
    INFN-Ferrara, Ferrara
  • Yu.M. Ivanov
    PNPI, Gatchina, Leningrad District
  • S. Peggs
    BNL, Upton, Long Island, New York
  • M. Prest
    Università dell'Insubria & INFN Milano Bicocca, Como
  • S. Shiraishi
    Enrico Fermi Institute, University of Chicago, Chicago, Illinois
 
 

Funding: Work supported by Fermi Research Alliance, LLC, under contract No. DE-AC02-07CH11359 with the U.S. Department of Energy.


Bent-crystal channeling is a technique with a potential to increase the beam-halo collimation efficiency at high-energy colliders. First measurements at the Tevatron in 2005 have shown that using a 5-mm silicon crystal to deflect the proton beam halo onto a secondary collimator improves the system performance by reducing the machine impedance, beam losses in the collider detectors and irradiation of the superconducting magnets, all in agreement with simulations. Recent results, obtained with substantially improved goniometer and enhanced beam diagnostics, are reported showing channeling collimation of the ~1-TeV circulating proton beam halo at the Tevatron collider. Comprehensive results of computer modeling are presented which allow further developments of the T-980 experiment towards a robust system compatible with requirements to high-efficient collimation at the Tevatron and LHC hadron colliders.

 

slides icon

Slides

 
TH5PFP009 Studies on Combined Momentum and Betatron Cleaning in the LHC 3205
 
  • R.W. Assmann, G. Bellodi, C. Bracco, V.P. Previtali, S. Redaelli, Th. Weiler
    CERN, Geneva
 
 

Collimation and halo cleaning for the LHC beams are performed separately for betatron and momentum losses, requiring two dedicated insertions for collimation. Betatron cleaning is performed in IR7 while momentum cleaning is performed in IR3. A study has been performed to evaluate the performance reach for a combined betatron and momentum cleaning system in IR3. The results are presented.

 
TH5RFP035 Energy Deposition Simulations and Measurements in an LHC Collimator and Beam Loss Monitors 3525
 
  • T.T. Boehlen, R.W. Assmann, C. Bracco, B. Dehning, S. Redaelli, Th. Weiler, C. Zamantzas
    CERN, Geneva
 
 

The LHC collimators are protected against beam caused damages by measuring the secondary particle showers with beam loss monitors. Downstream of every collimator an ionisation chamber and a secondary emission monitor are installed to determine the energy deposition in the collimator. The relation between the energy deposition in the beam loss monitor and the collimator jaw is based on secondary shower simulations. To verify the FLUKA simulations the prototype LHC collimator installed in the SPS was equipped with beam loss monitors. The results of the measurements of the direct impact of the 26 GeV proton beam injected in the SPS onto the collimator are compared with the predictions of the FLUKA simulations. In addition simulation results from parameter scans and for mean and peak energy deposition with its dependencies are shown.

 
FR1GRC05 The LHC Injection Tests 4254
 
  • M. Lamont, R. Alemany-Fernandez, R. Bailey, P. Collier, B. Goddard, V. Kain, A. Macpherson, L. Ponce, S. Redaelli, W. Venturini Delsolaro, J. Wenninger
    CERN, Geneva
 
 

A series of LHC injection tests was performed in August and September 2008. The first saw beam injected into sector 23; the second into sectors 78 and 23; the third into sectors 78-67 and sectors 23-34-45. The fourth, into sectors 23-34-45, was performed the evening before the extended injection test on the 10th September which saw both beams brought around the full circumference of the LHC. The tests enabled the testing and debugging of a number of critical control and hardware systems; testing and validation of instrumentation with beam for the first time; deployment, and validation of a number of measurement procedures. Beam based measurements revealed a number of machine configuration issues that were rapidly resolved. The tests were undoubtedly an essential precursor to the successful start of LHC beam commissioning. This paper provides an outline of preparation for the tests, the machine configuration and summarizes the measurements made and individual system performance.

 

slides icon

Slides

 
FR5REP007 Final Implementation and Performance of the LHC Collimator Control System 4788
 
  • S. Redaelli, R.W. Assmann, R. Losito, A. Masi
    CERN, Geneva
 
 

The 2008 collimation system of the CERN Large Hadron Collider (LHC) included 80 movable collimators for a total of 316 degrees of freedom. Before beam operation, the final controls implementation was deployed and commissioned. The control system enabled remote control and appropriate diagnostics of the relevant parameters. The collimator motion is driven with time-functions, synchronized with other accelerator systems, which allows controlling the collimator jaw positions with a micrometer accuracy during all machine phases. The machine protection functionality of the system, which also relies on function-based tolerance windows, was also fully validated. The collimator control challenges are reviewed and the final system architecture is presented. The results of the remote system commissioning and the operational experience are discussed. The system tests performed for the 2009 beam operation are also reviewed.