Paper | Title | Page |
---|---|---|
WE4GRC04 | The Alignment of the LHC | 1973 |
|
||
The Large Hadron Collider (LHC) has been aligned using classical and non-standard techniques. The results have been seen on September 10th, 2008, the day when the beam made several turns in the machine with very few correctors activated. The paper will present the different steps of the alignment, from the metrological measurements done during the phase of the magnets assembly to the alignment itself in the tunnel as well as the techniques used to obtain the accuracy required by the physicists. The correlation of the results of this alignment with the position of the beam seen on the BPMs by the operation team during the days the beam has circulated will be presented. |
||
|
||
TH5RFP082 | Propagation Error Simulations Concerning the CLIC Active Prealignment | 3639 |
|
||
The CLIC components will have to be pre-aligned within a tolerance of 10 microns over a sliding window of 200m all along the linacs, before injecting the first beam. Such tolerance is about 30 times more demanding than for the existing machines as the SPS and LHC; it is a technical challenge and a key issue for the CLIC feasibility. In order to define the CLIC alignment strategy from the survey and beam dynamics point of view, simulations have been undertaken concerning the propagation error due to the measurement uncertainties of the pre-alignment systems. The uncertainties of measurement, taken as hypotheses for the simulations, are based on the data obtained on several dedicated facilities. This paper introduces the facilities and the latest results obtained, as well as the simulations performed. |
||
TH6PFP040 | Machine Studies During Beam Commissioning of the SPS-to-LHC Transfer Lines | 3793 |
|
||
Funding: Work partly supported by Fermilab, operated by Fermi Research Alliance, LLC under Contract No. DE-AC02-07CH11359 with the United States Department of Energy Through May to September 2008, further beam commissioning of the SPS to LHC transfer lines was performed. For the first time, optics and dispersion measurements were also taken in the last part of the lines, and into the LHC. Extensive trajectory and optics studies were conducted, in parallel with hardware checks. In particular dispersion measurements and their comparison with the beam line model were analysed in detail and led to propose the addition of a “dispersion-free” steering algorithm in the existing trajectory correction program. |