A   B   C   D   E   F   G   H   I   J   K   L   M   N   O   P   Q   R   S   T   U   V   W   X   Y   Z  

Meddahi, M.

Paper Title Page
TU6RFP026 Beam Commissioning of Injection into the LHC 1590
 
  • V. Mertens, I.V. Agapov, B. Goddard, M. Gyr, V. Kain, T. Kramer, M. Lamont, M. Meddahi, J.A. Uythoven, J. Wenninger
    CERN, Geneva
 
 

The LHC injection tests and first turn beam commissioning took place in late summer 2008, after detailed and thorough preparation. The beam commissioning of the downstream sections of the SPS-to-LHC transfer lines and the LHC injection systems is described. The details of the aperture measurements in the injection regions are presented together with the performance of the injection related equipment. The measured injection stability is compared to the expectations. The operational issues encountered are discussed.

 
TU6RFP027 Resonant Third-Integer Extraction from the PS2 1593
 
  • M. Gyr, W. Bartmann, M. Benedikt, B. Goddard, M. Meddahi
    CERN, Geneva
  • A. Koschik
    ETH, Zürich
  • D. Mayani Parás
    UNAM, México, D.F.
 
 

For the proposed PS2 accelerator several extraction systems are needed, including a slow third-integer resonant extraction. The requirements are presented together with the conceptual considerations for the sextupole locations and strengths, the separatrices at the extraction elements and the aperture implications for the overall machine. Calculations of the phase space separatrices have been computed with a new code for the physics of slow resonant extraction, which is briefly reviewed. Implications for the extraction equipment design and for the injection-extraction straight section optics are discussed.

 
TU6RFP030 Fast Injection into the PS2 1602
 
  • J.A. Uythoven, W. Bartmann, J. Borburgh, T. Fowler, B. Goddard, M. Meddahi
    CERN, Geneva
 
 

The conceptual considerations of a fast injection system for protons and ions in the proposed PS2 accelerator are presented. Initial design parameters of the injection septum and kicker systems are derived, taking into account rise and fall times, apertures and machine optics. The requirements for an injection dump used for failures are described. Possible limitations and technical issues are outlined.

 
WE6PFP017 LHC Abort Gap Cleaning with the Transverse Damper 2519
 
  • E. Gianfelice-Wendt
    Fermilab, Batavia
  • B. Goddard, W. Höfle, V. Kain, M. Meddahi, E.N. Shaposhnikova
    CERN, Geneva
  • A. Koschik
    ETH, Zurich
 
 

Funding: Work partly supported by Fermilab, operated by Fermi Research Alliance, LLC under Contract No. DE-AC02-07CH11359 with the United States Department of Energy


In the Large Hadron Collider –LHC, particles not captured by the RF system at injection or leaking out of the RF bucket may quench the superconducting magnets during beam abort. The problem, common to other superconducting machines, is particularly serious for the LHC due to the very large stored energy in the beam. For the LHC a way of removing the unbunched beam has been studied and it uses the existing damper kickers to excite resonantly the particles travelling along the abort gap. In this paper we describe the results of simulations performed with MAD-X for various LHC optics configurations, including the estimated multipolar errors.

 
TU6RFP024 Initial Results from Beam Commissioning of the LHC Beam Dump System 1584
 
  • B. Goddard, I.V. Agapov, E. Carlier, L. Ducimetière, E. Gallet, M. Gyr, L.K. Jensen, O.R. Jones, V. Kain, T. Kramer, M. Lamont, M. Meddahi, V. Mertens, T. Risselada, J.A. Uythoven, J. Wenninger, W.J.M. Weterings
    CERN, Geneva
 
 

Initial commissioning of the LHC beam dump system with beam took place in August and September 2008. The preparation, setting-up and the tests performed are described together with results of the extractions of beam into the dump lines. Analysis of the first detailed aperture measurements of extraction channels and kicker performance derived from dilution sweep shapes are presented. The performance of the other equipment subsystems is summarised, in particular that of the dedicated dump system beam instrumentation.

 
TH6PFP038 Determination of the Chromaticity of the TI 8 Transfer Line Based on Kick Response Measurements 3787
 
  • K. Fuchsberger, S.D. Fartoukh, B. Goddard, O.R. Jones, V. Kain, M. Meddahi, V. Mertens, J. Wenninger
    CERN, Geneva
 
 

The 3 km long TI 8 transfer line is used to transfer 450 GeV proton and ion beams from the SPS to LHC collider. As part of a detailed optics investigation program the chromaticity of the transfer line was measured. Kick response data of the transfer line was recorded for various extraction energy offsets in the SPS. The quadrupolar and sextupolar field errors over the whole transfer line dipoles, a systematic error of the main quadrupole strengths and the initial momentum error were estimated by a fit. Using the updated model, the chromaticity of the line was then calculated.

 
TH6PFP040 Machine Studies During Beam Commissioning of the SPS-to-LHC Transfer Lines 3793
 
  • M. Meddahi, I.V. Agapov, K. Fuchsberger, B. Goddard, W. Herr, V. Kain, V. Mertens, D.P. Missiaen, T. Risselada, J.A. Uythoven, J. Wenninger
    CERN, Geneva
  • E. Gianfelice-Wendt
    Fermilab, Batavia
 
 

Funding: Work partly supported by Fermilab, operated by Fermi Research Alliance, LLC under Contract No. DE-AC02-07CH11359 with the United States Department of Energy


Through May to September 2008, further beam commissioning of the SPS to LHC transfer lines was performed. For the first time, optics and dispersion measurements were also taken in the last part of the lines, and into the LHC. Extensive trajectory and optics studies were conducted, in parallel with hardware checks. In particular dispersion measurements and their comparison with the beam line model were analysed in detail and led to propose the addition of a “dispersion-free” steering algorithm in the existing trajectory correction program.

 
TH6PFP041 Beam Line Design for the CERN HiRadMat Test Facility 3796
 
  • C. Heßler, R.W. Assmann, B. Goddard, M. Meddahi, W.J.M. Weterings
    CERN, Geneva
 
 

The LHC phase II collimation project requires beam shock and impact tests of materials used for beam intercepting devices. Similar tests are also of great interest for other accelerator components such as beam entrance/exit windows and protection devices. For this purpose a dedicated High Radiation Material test facility (HiRadMat) is under study. This facility may be installed at CERN at the location of a former beam line. This paper describes the associated beam line which is foreseen to deliver a 450 GeV proton beam from SPS with an intensity of up to 3·1013 protons per shot. Different beam line designs will be compared and the choice of the beam steering and diagnostic elements will be discussed, as well as operational issues.

 
TH6PFP042 The 4 GeV H- Beam Transfer Line from the SPL to the PS2 3799
 
  • C. Heßler, M. Eshraqi, B. Goddard, A.M. Lombardi, M. Meddahi
    CERN, Geneva
 
 

The proposed new CERN injector chain LINAC4, SPL, PS2 will require the construction of new beam transfer lines. A preliminary design has been performed for the 4 GeV SPL to PS2 H- transfer line. The constraints, beam parameters and geometry requirements are summarised and a possible layout proposed, together with the magnet specifications. First considerations on longitudinal beam dynamics and on beam loss limitations from H- lifetime are presented.