TU6PFP090 High-Intensity Demonstrations in the J-PARC 3-GeV RCS 1504
 
  • H. Hotchi, N. Hayashi, Y. Hikichi, S. Hiroki, J. Kamiya, K. Kanazawa, M. Kawase, M. Kinsho, M. Nomura, N. Ogiwara, R. Saeki, P.K. Saha, A. Schnase, T. Shimada, Y. Shobuda, K. Suganuma, H. Suzuki, H. Takahashi, T. Takayanagi, O. Takeda, F. Tamura, N. Tani, T. Togashi, T. Ueno, M. Watanabe, Y. Watanabe, K. Yamamoto, M. Yamamoto, Y. Yamazaki, H. Yoshikawa, M. Yoshimoto
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
  • A. Ando
    LASTI, Hyogo
  • H. Harada
    Hiroshima University, Graduate School of Science, Higashi-Hiroshima
  • K. Hasegawa, Y. Irie, C. Ohmori, M. Yoshii
    KEK, Ibaraki
  • K. Satou, Y. Yamazaki
    J-PARC, KEK & JAEA, Ibaraki-ken
 
 

The beam commissioning of the J-PARC 3-GeV RCS started in October 2007. The initial machine parameter tuning and underlying beam studies were completed in February 2008 through various beam dynamics measurements, such as optical functions, turn-by-turn beam positions, and transverse and logitudinal beam profiles. Now the RCS is in transition from the first commissioning phase to the next challenging stage and our efforts hereafter will be focused on higher beam power operations. In this paper, we describe experimental results obtained in the high intensity demonstrations in October 2008, together with the corresponding simulation results.

 
WE4GRC01 Beam Diagnostics at the First Beam Commissioning of the J-PARC MR 1964
 
  • T. Toyama, D.A. Arakawa, A. Arinaga, Y. Hashimoto, S. Hiramatsu, S. Igarashi, S. Lee, H. Matsumoto, J.-I. Odagiri, M. Tejima, M. Tobiyama, N. Yamamoto
    KEK, Ibaraki
  • K. Hanamura, S. Hatakeyama
    MELCO SC, Tsukuba
  • H. Harada
    JAEA, Ibaraki-ken
  • N. Hayashi, K. Yamamoto
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
  • K. Satou
    J-PARC, KEK & JAEA, Ibaraki-ken
 
 

Beam commissioning of the J-PARC MR has been going on from May 2008. The beam was one bunch of 4·1011 protons, nearly one hundredth of the design value. Here describe performances of the beam diagnostic devices: DCCT's, BPM's, BLM's, profile monitors and tune meters. Diagnostic design for the design intensity will be also included.

 

slides icon

Slides

 
TU6PFP091 Performance of the Bump System for the Painting Injection at J-PARC 1507
 
  • T. Takayanagi, H. Harada, H. Hotchi, Y. Irie, J. Kamiya, M. Kinsho, P.K. Saha, T. Togashi, T. Ueno, M. Watanabe, M. Yoshimoto
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
  • K. Satou
    J-PARC, KEK & JAEA, Ibaraki-ken
 
 

The painting injection of the 3-GeV RCS in J-PARC has been tested since May in 2008. The shift bump-magnets, which give a constant bump field in a horizontal plane during injection, comprise four magnets connected in series. However, the total integrated magnetic field over the four magnets is not zero because of the magnetic field interferences with the neighboring quadrupole magnets. So the gap of each magnet was adjusted by inserting thin insulators into the splitting plane of the side yoke so that the field integration becomes zero. The thickness was determined experimentally. The closed orbit distortion due to the field imbalances was then confirmed to be less than 1 mm. Another four paint bump-magnets are also necessary to give time-dependent fields. They are connected to their own power supplies, separately. The excitation of each magnet is calibrated by using the beam so that the created bump orbit satisfies the position and inclination at the injection point, and there are no orbit distortions outside the injection area. As for a vertical plane, a vertical paint magnet is located pi-radian upstream of the injection point to control the vertical angle of the beam.