A   B   C   D   E   F   G   H   I   J   K   L   M   N   O   P   Q   R   S   T   U   V   W   X   Y   Z  

Goddard, B.

Paper Title Page
TU6PFP057 Operational Experience with First Circulating Beam in the LHC 1412
 
  • M. Lamont, R. Alemany-Fernandez, R. Bailey, P. Collier, B. Goddard, V. Kain, A. Macpherson, L. Ponce, S. Redaelli, W. Venturini Delsolaro, J. Wenninger
    CERN, Geneva
 
 

Following a series of injection tests, the first attempts to pass beam around both directions of the LHC were successful and led rapidly to circulating beam in the counter clockwise direction (beam 2) and many turns of beam 1. Unfortunately the beam commissioning was curtailed by the incident in sector 34. However, measurements performed during this first commissioning period should that the magnet model of the machine had delivered optics close to nominal, and also very good performance of beam instrumentation and supporting software. Details of the machine set-up and the commissioning procedures are detailed. The measurements performed and the key results from this period are described.

 
TU6RFP024 Initial Results from Beam Commissioning of the LHC Beam Dump System 1584
 
  • B. Goddard, I.V. Agapov, E. Carlier, L. Ducimetière, E. Gallet, M. Gyr, L.K. Jensen, O.R. Jones, V. Kain, T. Kramer, M. Lamont, M. Meddahi, V. Mertens, T. Risselada, J.A. Uythoven, J. Wenninger, W.J.M. Weterings
    CERN, Geneva
 
 

Initial commissioning of the LHC beam dump system with beam took place in August and September 2008. The preparation, setting-up and the tests performed are described together with results of the extractions of beam into the dump lines. Analysis of the first detailed aperture measurements of extraction channels and kicker performance derived from dilution sweep shapes are presented. The performance of the other equipment subsystems is summarised, in particular that of the dedicated dump system beam instrumentation.

 
TU6RFP025 Operational Considerations for the PSB H- Injection System 1587
 
  • W.J.M. Weterings, M. Aiba, J. Borburgh, C. Carli, T. Fowler, B. Goddard
    CERN, Geneva
 
 

For the LINAC4 project the PS Booster (PSB) injection system will be upgraded. The 160 MeV H- beam will be distributed to the 4 superimposed PSB synchrotron rings and horizontally injected by means of an H- charge-exchange system. Operational considerations for the injection system are presented, including expected beam losses from field stripping of H- and excited H0 and foil scattering, possible injection failure cases and expected stripping foil lifetimes. Loading assumptions for the internal beam dumps are discussed together with estimates of doses on various components.

 
TU6RFP026 Beam Commissioning of Injection into the LHC 1590
 
  • V. Mertens, I.V. Agapov, B. Goddard, M. Gyr, V. Kain, T. Kramer, M. Lamont, M. Meddahi, J.A. Uythoven, J. Wenninger
    CERN, Geneva
 
 

The LHC injection tests and first turn beam commissioning took place in late summer 2008, after detailed and thorough preparation. The beam commissioning of the downstream sections of the SPS-to-LHC transfer lines and the LHC injection systems is described. The details of the aperture measurements in the injection regions are presented together with the performance of the injection related equipment. The measured injection stability is compared to the expectations. The operational issues encountered are discussed.

 
TU6RFP027 Resonant Third-Integer Extraction from the PS2 1593
 
  • M. Gyr, W. Bartmann, M. Benedikt, B. Goddard, M. Meddahi
    CERN, Geneva
  • A. Koschik
    ETH, Zürich
  • D. Mayani Parás
    UNAM, México, D.F.
 
 

For the proposed PS2 accelerator several extraction systems are needed, including a slow third-integer resonant extraction. The requirements are presented together with the conceptual considerations for the sextupole locations and strengths, the separatrices at the extraction elements and the aperture implications for the overall machine. Calculations of the phase space separatrices have been computed with a new code for the physics of slow resonant extraction, which is briefly reviewed. Implications for the extraction equipment design and for the injection-extraction straight section optics are discussed.

 
TU6RFP028 Laser Stripping for the PS2 Charge-Exchange Injection System 1596
 
  • B. Goddard, W. Bartmann
    CERN, Geneva
  • V.V. Danilov
    ORNL, Oak Ridge, Tennessee
  • D.E. Johnson
    Fermilab, Batavia
 
 

Laser stripping for an H- injection system into the proposed PS2 accelerator could provide an attractive alternative to the use of a conventional stripping foil. In this paper possible concepts for a 4 GeV laser stripping system are outlined and compared, using either laser or magnetic initial stripping steps and a resonant excitation of the intermediate H0 atom, followed by a final magnetic stripping. Issues of laser power, overall efficiency and emittance growth are discussed.

 
TU6RFP029 Experience with the LHC Beam Dump Post-Operational Checks System 1599
 
  • J.A. Uythoven, J. Axensalva, V. Baggiolini, E. Carlier, E. Gallet, B. Goddard, V. Kain, M. Lamont, N. Magnin
    CERN, Geneva
 
 

After each beam dump in the LHC automatic post-operational checks are made to guarantee that the last beam dump has been executed correctly and that the system can be declared to be 'as good as new' before the next injection is allowed. The analysis scope comprises the kicker waveforms, redundancy in kicker generator signal paths and different beam instrumentation measurements. This paper describes the implementation and the operational experience of the internal and external post-operational checks of the LHC beam dumping system during the commissioning of the LHC without beam and during the first days of beam operation.

 
TU6RFP030 Fast Injection into the PS2 1602
 
  • J.A. Uythoven, W. Bartmann, J. Borburgh, T. Fowler, B. Goddard, M. Meddahi
    CERN, Geneva
 
 

The conceptual considerations of a fast injection system for protons and ions in the proposed PS2 accelerator are presented. Initial design parameters of the injection septum and kicker systems are derived, taking into account rise and fall times, apertures and machine optics. The requirements for an injection dump used for failures are described. Possible limitations and technical issues are outlined.

 
TU6RFP031 LHC Beam Dump System - Consequences of Abnormal Operation 1605
 
  • T. Kramer, B. Goddard, J.A. Uythoven
    CERN, Geneva
 
 

The LHC beam dump system is one of the most critical systems concerning machine protection and safe operation. It is used to dispose of high intensity beams between 450 GeV and 7 TeV. Studies into the consequences of abnormal beam dump actions have been performed. Different error scenarios have been evaluated using particle tracking in MAD-X, including an asynchronous dump action, and the impact of different orbit and collimator settings. Losses at locations in the ring and the beam dump transfer lines have been quantified as a function of different settings of the dump system protection elements. The implications for the setting up and operation of these protection elements are discussed.

 
WE1GRI03 Design Optimization of PS2 1828
 
  • M. Benedikt, B. Goddard
    CERN, Geneva
 
 

The PS2 will replace the present CERN-PS as the LHC pre-injector. It will have twice the PS energy and twice the circumference. Extensive design optimization is presently ongoing with the aim of starting the PS2 construction around 2011 and delivering beams for physics in 2017. The talk describes the various PS2 design constraints, the optimization steps, and the path towards the final design.

 

slides icon

Slides

 
WE6PFP017 LHC Abort Gap Cleaning with the Transverse Damper 2519
 
  • E. Gianfelice-Wendt
    Fermilab, Batavia
  • B. Goddard, W. Höfle, V. Kain, M. Meddahi, E.N. Shaposhnikova
    CERN, Geneva
  • A. Koschik
    ETH, Zurich
 
 

Funding: Work partly supported by Fermilab, operated by Fermi Research Alliance, LLC under Contract No. DE-AC02-07CH11359 with the United States Department of Energy


In the Large Hadron Collider –LHC, particles not captured by the RF system at injection or leaking out of the RF bucket may quench the superconducting magnets during beam abort. The problem, common to other superconducting machines, is particularly serious for the LHC due to the very large stored energy in the beam. For the LHC a way of removing the unbunched beam has been studied and it uses the existing damper kickers to excite resonantly the particles travelling along the abort gap. In this paper we describe the results of simulations performed with MAD-X for various LHC optics configurations, including the estimated multipolar errors.

 
TH6PFP036 Lattice Issues of the CERN PSB with H- Charge Exchange Injection Hardware 3781
 
  • C. Carli, M. Aiba, M. Chanel, B. Goddard, M. Martini, W.J.M. Weterings
    CERN, Geneva
 
 

The motivation for the construction of CERN Linac4 is to improve the performance of the PSB by raising the injection energy and implementing a new H- charge exchange multiturn injection scheme. Strategies to design the H- charge exchange injection hardware and, in particular, to mitigate perturbations of the lattice will be reported and the proposed geometry described.

 
TH6PFP038 Determination of the Chromaticity of the TI 8 Transfer Line Based on Kick Response Measurements 3787
 
  • K. Fuchsberger, S.D. Fartoukh, B. Goddard, O.R. Jones, V. Kain, M. Meddahi, V. Mertens, J. Wenninger
    CERN, Geneva
 
 

The 3 km long TI 8 transfer line is used to transfer 450 GeV proton and ion beams from the SPS to LHC collider. As part of a detailed optics investigation program the chromaticity of the transfer line was measured. Kick response data of the transfer line was recorded for various extraction energy offsets in the SPS. The quadrupolar and sextupolar field errors over the whole transfer line dipoles, a systematic error of the main quadrupole strengths and the initial momentum error were estimated by a fit. Using the updated model, the chromaticity of the line was then calculated.

 
TH6PFP039 Beam Loss Control for the Unstripped Ions from the PS2 Charge Exchange Injection 3790
 
  • W. Bartmann, J. Barranco, M. Benedikt, B. Goddard, T. Kramer, Y. Papaphilippou, H. Vincke
    CERN, Geneva
 
 

Control of beam losses is an important aspect of the H- injection system for the PS2, a proposed replacement of the CPS in the CERN injector complex. H- ions may pass the foil unstripped or be partially stripped to excited H0 states which may be stripped in the subsequent strong-field chicane magnet. Depending on the choice of the magnetic field, atoms in the ground and first excited states can be extracted and dumped. The conceptual design of the waste beam handling is presented, including local collimation and the dump line, both of which must take into account the divergence of the beam from stripping in fringe fields. Beam load estimates and activation related requirements of the local collimators and dump are briefly discussed.

 
TH6PFP040 Machine Studies During Beam Commissioning of the SPS-to-LHC Transfer Lines 3793
 
  • M. Meddahi, I.V. Agapov, K. Fuchsberger, B. Goddard, W. Herr, V. Kain, V. Mertens, D.P. Missiaen, T. Risselada, J.A. Uythoven, J. Wenninger
    CERN, Geneva
  • E. Gianfelice-Wendt
    Fermilab, Batavia
 
 

Funding: Work partly supported by Fermilab, operated by Fermi Research Alliance, LLC under Contract No. DE-AC02-07CH11359 with the United States Department of Energy


Through May to September 2008, further beam commissioning of the SPS to LHC transfer lines was performed. For the first time, optics and dispersion measurements were also taken in the last part of the lines, and into the LHC. Extensive trajectory and optics studies were conducted, in parallel with hardware checks. In particular dispersion measurements and their comparison with the beam line model were analysed in detail and led to propose the addition of a “dispersion-free” steering algorithm in the existing trajectory correction program.

 
TH6PFP041 Beam Line Design for the CERN HiRadMat Test Facility 3796
 
  • C. Heßler, R.W. Assmann, B. Goddard, M. Meddahi, W.J.M. Weterings
    CERN, Geneva
 
 

The LHC phase II collimation project requires beam shock and impact tests of materials used for beam intercepting devices. Similar tests are also of great interest for other accelerator components such as beam entrance/exit windows and protection devices. For this purpose a dedicated High Radiation Material test facility (HiRadMat) is under study. This facility may be installed at CERN at the location of a former beam line. This paper describes the associated beam line which is foreseen to deliver a 450 GeV proton beam from SPS with an intensity of up to 3·1013 protons per shot. Different beam line designs will be compared and the choice of the beam steering and diagnostic elements will be discussed, as well as operational issues.

 
TH6PFP042 The 4 GeV H- Beam Transfer Line from the SPL to the PS2 3799
 
  • C. Heßler, M. Eshraqi, B. Goddard, A.M. Lombardi, M. Meddahi
    CERN, Geneva
 
 

The proposed new CERN injector chain LINAC4, SPL, PS2 will require the construction of new beam transfer lines. A preliminary design has been performed for the 4 GeV SPL to PS2 H- transfer line. The constraints, beam parameters and geometry requirements are summarised and a possible layout proposed, together with the magnet specifications. First considerations on longitudinal beam dynamics and on beam loss limitations from H- lifetime are presented.

 
TH6PFP044 Linear Optics Design of Negative Momentum Compaction Lattices for PS2 3805
 
  • Y. Papaphilippou, J. Barranco, W. Bartmann, M. Benedikt, C. Carli, B. Goddard
    CERN, Geneva
  • R. De Maria, S. Peggs, D. Trbojevic
    BNL, Upton, Long Island, New York
 
 

In view of the CERN Proton Synchrotron proposed replacement with a new ring (PS2), a detailed optics design as been undertaken following the evaluation of several lattice options. The basic arc module consists of cells providing negative momentum compaction. The straight section is formed with a combination of FODO and quadrupole triplet cells, to accommodate the injection and extraction systems, in particular the H- injection elements. The arc is matched to the straight section with a dispersion suppressor and matching module. Different lattices are compared with respect to their linear optics functions, tuning flexibility and geometrical acceptance properties.

 
FR1GRC05 The LHC Injection Tests 4254
 
  • M. Lamont, R. Alemany-Fernandez, R. Bailey, P. Collier, B. Goddard, V. Kain, A. Macpherson, L. Ponce, S. Redaelli, W. Venturini Delsolaro, J. Wenninger
    CERN, Geneva
 
 

A series of LHC injection tests was performed in August and September 2008. The first saw beam injected into sector 23; the second into sectors 78 and 23; the third into sectors 78-67 and sectors 23-34-45. The fourth, into sectors 23-34-45, was performed the evening before the extended injection test on the 10th September which saw both beams brought around the full circumference of the LHC. The tests enabled the testing and debugging of a number of critical control and hardware systems; testing and validation of instrumentation with beam for the first time; deployment, and validation of a number of measurement procedures. Beam based measurements revealed a number of machine configuration issues that were rapidly resolved. The tests were undoubtedly an essential precursor to the successful start of LHC beam commissioning. This paper provides an outline of preparation for the tests, the machine configuration and summarizes the measurements made and individual system performance.

 

slides icon

Slides