A   B   C   D   E   F   G   H   I   J   K   L   M   N   O   P   Q   R   S   T   U   V   W   X   Y   Z  

Follin, F.

Paper Title Page
TU6RFP022 First Results for the Beam Commissioning of the CERN Multi-Turn Extraction 1578
 
  • S.S. Gilardoni, F. Arnold Malandain, E. Benedetto, T. Bohl, S. Cettour Cave, K. Cornelis, H. Damerau, F. Follin, T. Fowler, F. Franchi, P. Freyermuth, H. Genoud, R. Giachino, M. Giovannozzi, S. Hancock, Y. Le Borgne, D. Manglunki, G. Metral, L. Pereira, J.P. Ridewood, Y. Riva, M. Schokker, L. Sermeus, R.R. Steerenberg, B. Vandorpe, J. Wenninger
    CERN, Geneva
 
 

The Multi-Turn Extraction, a new type of extraction based on beam trapping inside stable islands in the horizontal phase space, has been commissioned during the 2008 run of the CERN Proton Synchrotron. Both single- and multi-bunch beams with a total intensity up to 1.4×1013 protons have been extracted with efficiencies up to 98%. Furthermore, injection tests in the CERN Super Proton Synchrotron were performed, with the beam then accelerated and extracted to produce neutrinos for the CERN Neutrino to Gran Sasso experiments. The results of the extensive measurement campaign are presented and discussed in details.

 
TH5RFP034 First Experience with the LHC Beam Loss Monitoring System 3522
 
  • B. Dehning, D. Bocian, T.T. Boehlen, E. Effinger, J. Emery, F. Follin, V. Grishin, E.B. Holzer, H. Ikeda, S. Jackson, D.K. Kramer, G. Kruk, P. Le Roux, J. Mariethoz, M. Misiowiec, L. Ponce, C. Roderick, M. Sapinski, M. Stockner, C. Zamantzas
    CERN, Geneva
  • A. Priebe
    Poznań University of Technology, Poznań
 
 

The LHC beam loss monitoring system (BLM) consists of about 4000 monitors observing losses at all quadrupole magnets and many other likely loss locations. At the first LHC operation in August and September 2008 all monitors were active and used to observe the losses during the initial beam steerings, at collimators, at the LHC dump and during aperture scans. The different loss patterns will be discussed and compared with the expectations originating from simulations. The observed signals of the BLM system will be analysed in terms of response time, sensitivity cross talk between channels and noise performance.