TU6RFP023 | Installation and Hardware Commissioning of the Multi-Turn Extraction at the CERN Proton Synchrotron | 1581 |
|
||
The implementation of new Multi-turn extraction at the CERN Proton Synchrotron required major hardware changes for the nearly 50-year old accelerator. The installation of new PFNs and refurbished kicker magnets for the extraction, new sextupole and octupole magnets, new power converters, together with an in-depth review of the machine aperture leading to the design of new vacuum chambers was required. As a result, a heavy programme of interventions had to be scheduled during the winter shut-down 2007-8. The newly installed hardware and its commissioning is presented and discussed in details. |