WE5RFP022 Status of SESAME Project 2315
 
  • A. Nadji
    SOLEIL, Gif-sur-Yvette
  • T.H. Abu-Hanieh, A. Al-Adwan, M.A. Al-najdawi, A. Amro, M. Attal, S. Budair, D.S. Foudeh, A. Hamad, A. Kaftoosian, T.A. Khan, F. Makahleh, S.A. Matalgah, M. Sbahi, M.M. Shehab, H. Tarawneh, S. Varnasseri
    SESAME, Allan
 
 

SESAME is a 3rd generation synchrotron light source facility under construction in Allan, Jordan, 30 km North-West of Amman. SESAME consists of a 2.5 GeV storage ring, a 22.5 MeV Microtron and an 800 MeV Booster. The Microtron was installed at its final position and its subsystems have been successfully tested. The commissioning with beam of the Microtron will start in March 2009. The installation of the Booster is expected to take place in summer 2009. Most of the storage ring subsystems are ready for call for tender. The progress of SESAME project including beamlines status will be reported in this paper.