WEPWA015 Progress in Construction of the 35 MeV Compact Energy Recovery Linac at KEK 2159
 
  • S. Sakanaka, S. Adachi, M. Akemoto, D.A. Arakawa, S. Asaoka, K. Enami, K. Endo, S. Fukuda, T. Furuya, K. Haga, K. Hara, K. Harada, T. Honda, Y. Honda, H. Honma, T. Honma, K. Hosoyama, K. Hozumi, E. Kako, Y. Kamiya, H. Katagiri, H. Kawata, Y. Kobayashi, Y. Kojima, Y. Kondou, T. Kume, T. Matsumoto, H. Matsumura, H. Matsushita, S. Michizono, T. Miura, T. Miyajima, S. Nagahashi, H. Nakai, H. Nakajima, N. Nakamura, K. Nakanishi, K. Nakao, K.N. Nigorikawa, T. Nogami, S. Noguchi, S. Nozawa, T. Obina, T. Ozaki, F. Qiu, H. Sagehashi, H. Sakai, S. Sasaki, K. Satoh, M. Satoh, T. Shidara, M. Shimada, K. Shinoe, T. Shioya, T. Shishido, M. Tadano, T. Takahashi, R. Takai, T. Takenaka, Y. Tanimoto, M. Tobiyama, K. Tsuchiya, T. Uchiyama, A. Ueda, K. Umemori, K. Watanabe, M. Yamamoto, Y. Yamamoto, Y. Yano, M. Yoshida
    KEK, Ibaraki, Japan
  • E. Cenni
    Sokendai, Ibaraki, Japan
  • R. Hajima, S.M. Matsuba, R. Nagai, N. Nishimori, M. Sawamura, T. Shizuma
    JAEA, Ibaraki-ken, Japan
  • H. Takaki
    ISSP/SRL, Chiba, Japan
 
  The 35-MeV Com­pact En­ergy Re­cov­ery Linac (the Com­pact ERL or cERL) is under con­struc­tion at the High En­ergy Ac­cel­er­a­tor Re­search Or­ga­ni­za­tion (KEK) in Japan. With the Com­pact ERL, we aim at es­tab­lish­ing cut­ting-edge tech­nolo­gies for the GeV-class ERL-based syn­chro­tron light source. To in­stall the ac­cel­er­a­tor com­po­nents of the cERL, we have con­structed a shield­ing room hav­ing an area of about 60 m x 20 m. We have then in­stalled a 500-kV DC pho­to­cath­ode gun, a 5-MV su­per­con­duct­ing (SC) cry­omod­ule for the in­jec­tor, a 30-MV SC cry­omod­ule for the main linac, and some of the other com­po­nents. High-power test on the main SC cry­omod­ule is un­der­way in De­cem­ber, 2012. High-power or high-volt­age tests on the in­jec­tor cry­omod­ule and on the DC gun are planned dur­ing Jan­u­ary to March, 2013. An in­jec­tor of the Com­pact ERL will be com­mis­sioned in April, 2013. We re­port the newest sta­tus of its con­struc­tion.