Paper | Title | Page |
---|---|---|
MOPEB045 | Commissioning of the LHC Magnet Powering System in 2009 | 376 |
|
||
On 19th September 2008 the Large Hadron Collider (LHC) experienced a serious incident, caused by a bad electrical joint, which stopped beam operation just a few days after its beginning. During the following 14 months the damage was repaired, additional protection systems were installed and the measures to avoid a similar incident were taken (i.e. new layer of the Magnet Quench Protection System [nQPS], more efficient He release valves). As a consequence, a large number of powering tests had to be repeated or carried out for the first time. The re-commissioning of the already existing systems as well as the commissioning of the new ones has been carefully studied, then performed taking into account the history of each of the eight LHC sectors (warm-up, left at floating temperature,'). Moreover, a campaign of measurements of the bus-bar splice resistances has been carried out with the nQPS in order to spot out non conformities, thus assessing the risk of the LHC operation for the initial energy level. This paper discusses how the guidelines for the LHC 2009 re-commissioning were defined, providing a general principle to be used for the future re-commissioning. |
||
MOPEC003 | Operational Experience during Initial Beam Commissioning of the LHC | 456 |
|
||
After the incident on the 19th September 2008 and more than one year without beam the commissioning of the LHC started again on November 20, 2009. Progress was rapid and collisions under stable beam conditions were established at 1.2 TeV within 3 weeks. In 2010 after qualification of the new quench protection system the way to 3.5 TeV was open and collisions were delivered at this energy after a month of additional commissioning. This paper describes the experiences and issues encountered during these first periods of commissioning with beam. |
||
MOPEC007 | Operational Experience during the LHC Injection Tests | 468 |
|
||
Following the LHC injection tests of 2008, two injection tests took place in October and November 2009 as preparation for the LHC restart on November 20, 2009. During these injection tests beam was injected through the TI2 transfer line into sector 23 of ring 1 and through TI8 into the sectors 78, 67 and 56 of ring 2. The beam time was dedicated to injection steering, optics measurements and debugging of all the systems involved. Because many potential problems were sorted out in advance, these tests contributed to the rapid progress after the restart. This paper describes the experiences and issues encountered during these tests as well as related measurement results. |