A   B   C   D   E   F   G   H   I   J   K   L   M   N   O   P   Q   R   S   T   U   V   W   X   Y   Z  

Ohuchi, N.

Paper Title Page
MOPEB034 Progress of Design Study of Interaction Region Quadrupoles for the SuperKEKB 346
 
  • M. Tawada, Y. Funakoshi, M. Iwasaki, H. Koiso, A. Morita, Y. Ohnishi, N. Ohuchi, K. Oide, K. Tsuchiya, Z.G. Zong
    KEK, Ibaraki
 
 

KEK is studying the design of the interaction region quadrupoles for the SuperKEKB of which the two beams of 4GeV/7GeV for LER/HER have a crossing angle of 83 mrad. For each beam, the final beam focusing system consisting of superconducting and permanent magnets is studied. The superconducting quadrupoles close to the interaction point for each beam are located in the compensation superconducting solenoid which cancels the solenoid field by the particle detector, Belle. These magnet parameters are optimized to obtain higher luminosity. In this paper, the design progress of final focusing system and magnets will be reported.

 
MOPEB037 Development of Current Leads for the Superconducting Correctors in the SuperKEKB-IR 355
 
  • Z.G. Zong, N. Higashi, N. Ohuchi, M. Tawada, K. Tsuchiya
    KEK, Ibaraki
 
 

To supply the electrical power for the superconducting correctors in the interaction region of the proposed SuperKEKB, a kind of vapor cooled current leads is designed, which consists of 8 brass leads and can transport currents to 4 correctors simultaneously. The design current of the leads is about 50 A. The thermal and electrical behaviors have studied by the finite elements method and the cryogenic experiment is also planed to validate the performance. In this paper the design will be presented and the finite element model will be compared with the experimental data.

 
WEPEC016 Preparation Status of Cryomodule Tests of Tesla-like Cavities in S1-Global Project at KEK 2926
 
  • E. Kako, H. Hayano, S. Noguchi, N. Ohuchi, M. Satoh, T. Shishido, K. Watanabe, Y. Yamamoto
    KEK, Ibaraki
 
 

Cryomodule tests of four Tesla-like cavities is under preparation for S1-global project at KEK. An average maximum accelerating gradient (Eacc,max) of four cavities in the vertical tests at 2 K was reached to approximately 25 MV/m. Conditioning of four STF-2 input couplers was carried out at a high power test stand with a 5MW-pulsed klystron. Two types of frequency tuning system with a slide-jack tuner and a piezo tuner is installed at the center or end position of the He jacket. String asssembly of the four cavities will be started in March, and the first cool-down test of the cryomodule is scheduled in June, 2010.

 
WEOAMH02 Recent Progress of KEKB 2372
 
  • Y. Funakoshi, T. Abe, K. Akai, Y. Cai, K. Ebihara, K. Egawa, A. Enomoto, J.W. Flanagan, H. Fukuma, K. Furukawa, T. Furuya, J. Haba, T. Ieiri, N. Iida, H. Ikeda, T. Ishibashi, M. Iwasaki, T. Kageyama, S. Kamada, T. Kamitani, S. Kato, M. Kikuchi, E. Kikutani, H. Koiso, M. Masuzawa, T. Mimashi, T. Miura, A. Morita, T.T. Nakamura, K. Nakanishi, M. Nishiwaki, Y. Ogawa, K. Ohmi, Y. Ohnishi, N. Ohuchi, K. Oide, T. Oki, M. Ono, M. Satoh, Y. Seimiya, K. Shibata, M. Suetake, Y. Suetsugu, T. Sugimura, Y. Susaki, T. Suwada, M. Tawada, M. Tejima, M. Tobiyama, N. Tokuda, S. Uehara, S. Uno, Y. Yamamoto, Y. Yano, K. Yokoyama, M. Yoshida, S.I. Yoshimoto, D.M. Zhou, Z.G. Zong
    KEK, Ibaraki
 
 

KEKB is an e-/e+ collider for the study of B physics and is also used for machine studies for future machines. The peak luminosity of KEKB, which is the world-highest value, has been still increasing. This report summarizes recent progress at KEKB.

 

slides icon

Slides

 
WEPE008 Construction of the S1-Global Cryomodules for ILC 3356
 
  • N. Ohuchi, H. Hayano, N. Higashi, E. Kako, Y. Kondou, H. Nakai, S. Noguchi, T. Saeki, M. Satoh, M. Sawabe, T. Shidara, T. Shishido, A. Terashima, K. Tsuchiya, K. Watanabe, A. Yamamoto, Y. Yamamoto, K. Yokoya
    KEK, Ibaraki
  • T.T. Arkan, S. Barbanotti, H. Carter, M.S. Champion, R.D. Kephart, J.S. Kerby, D.V. Mitchell, Y. Orlov, T.J. Peterson, M.C. Ross
    Fermilab, Batavia
  • A. Bosotti, C. Pagani, R. Paparella, P. Pierini
    INFN/LASA, Segrate (MI)
  • D. Kostin, L. Lilje, A. Matheisen, W.-D. Möller, H. Weise
    DESY, Hamburg
 
 

In an attempt at demonstrating an average field gradient of 31.5 MV/m as per the design accelerating gradient for ILC, a program called S1-Global is in progress as an international research collaboration among KEK, INFN, FNAL, DESY and SLAC. The S1-Global cryomodule will contain eight superconducting cavities from FNAL, DESY and KEK. The cryomodule will be constructed by joining two half-size cryomodules, each 6 m in length. The module containing four cavities from FNAL and DESY has been constructed by INFN. The module for four KEK cavities is being modified at present. The assembly of the cryomodules is scheduled from January 2010, and the operation of the system is scheduled from June 2010 at the KEK-STF. In this paper, the construction of the S1-Global cryomodule will be presented.