MOPEC003 | Operational Experience during Initial Beam Commissioning of the LHC | 456 |
|
||
After the incident on the 19th September 2008 and more than one year without beam the commissioning of the LHC started again on November 20, 2009. Progress was rapid and collisions under stable beam conditions were established at 1.2 TeV within 3 weeks. In 2010 after qualification of the new quench protection system the way to 3.5 TeV was open and collisions were delivered at this energy after a month of additional commissioning. This paper describes the experiences and issues encountered during these first periods of commissioning with beam. |
||
MOPEC007 | Operational Experience during the LHC Injection Tests | 468 |
|
||
Following the LHC injection tests of 2008, two injection tests took place in October and November 2009 as preparation for the LHC restart on November 20, 2009. During these injection tests beam was injected through the TI2 transfer line into sector 23 of ring 1 and through TI8 into the sectors 78, 67 and 56 of ring 2. The beam time was dedicated to injection steering, optics measurements and debugging of all the systems involved. Because many potential problems were sorted out in advance, these tests contributed to the rapid progress after the restart. This paper describes the experiences and issues encountered during these tests as well as related measurement results. |