TUYRA02 | Challenges and Solutions for J-PARC Commissioning and Early Operation | 1304 |
|
||
The J-PARC accelerator facility consists of a 400 MeV H- linac, a 3-GeV RCS, a 50-GeV MR (Main Ring) and related experimental facilities. Beam commissioning of the facility is started from the upstream accelerators while construction of the downstream accelerators and experimental facilities is in progress. The beam commissioning of MR, MLF(Materials and Life science experimental Facility) and Hadron experimental facility started in JFY 2008. In this presentation, we present an overview of the J-PARC commissioning status. Recent progress of MR commissioning will be described in more detail. The talk will focus on the issues, challenges, solutions, and lessons learned during the commissioning and early operations of J-PARC. |
||
|
||
TUPEA051 | Application of Digital Narrow Band Noise to J-PARC Main Ring | 1446 |
|
||
Applying narrow band longitudinal noise to the beam in J-PARC Main Ring in flattop, while the acceleration voltage is off might help to counteract the effect of ripple on the slow extraction. For this purpose, a complex noise sequence output by DSP modulates a custom made DDS synthesizer to create single side spectra without carrier. The noise is calculated starting from a description in frequency domain. Then an algorithm creates narrow band spectra with optimized behavior in time domain. Frequency domain data is transformed to time domain, and the amplitude is smoothed. The smoothed data is transformed back to frequency domain, and the spectral shape is restored. This process repeats until the amplitude in time domain has converged, while the desired spectrum shape is preserved. Noise generated in this way can be tailored for different requirements. We show the signal properties, the hardware, and preliminary beam test results, when the noise is applied to the MR RF system. |
||
WEPEB005 | Magnet Pattern Control System of the J-PARC Main Ring | 2692 |
|
||
In the J-PARC Main Ring (MR), the bending, quadrupole, sextupole, and steering magnets can be controlled on the operating interfaces (OPI). The optics parameters for all magnets are calculated by using SAD, and are converted to BL tables (ex: 2000 points for a steering magnet) for each power supplies. The BL tables are made from the parameters of optics, pattern timing, and beam energy at flat bottom and flat top. For MR beam studies, the BL tables are adjustable with offset and factor. This system is useful for COD correction, beta function measurement, aperture survey, and slow extraction. In this proceeding, the structure of the magnet control system and OPIs for beam studies will be shown. |
||
THPEB014 | Status and Upgrade Plan of Slow Extraction from the J-PARC Main Ring | 3912 |
|
||
High power protons from the J-PARC main ring is slowly extracted using the third integer resonance and delivered to the experimental hall for various nuclear and particle physics experiments. The slow extraction device comprises two electro static septa (ESS),ten magnetic septa, four bump magnets, eight resonant sextupole magnets and their power supply. One of the critical issue of the slow extraction is radiation caused by the beam loss during the slow extraction. We have developed the electrostatic and magnetic septa with thin septum thickness. A unique scheme with large step size and small angular spread of the extracted beam enables hit rate on the ESS less than 1% level. In January 2009, first 30 GeV proton beam has been successfully delivered to the fixed target. Quadrupole magnets and a DSP feedback control system to obtain a uniform beam spill structure were implemented in 2009 summer shutdown period. We will report the extraction efficiency, extracted beam profiles and spill structure obtained by the beam commissioning so far. We will also mention a upgrade plan based on some new ideas to aim a higher performance. |
||
THPEB015 | Beam Injection Tuning of the J-PARC Main Ring | 3915 |
|
||
The beam commissioning of J-PARC (Japan Proton Accelerator Research Complex) MR (Main Ring) was started from May 2008 and is in progress. As usual, injection tuning is in the first stage and strongly related to other tuning items. Starting with design schemes, making adjustment due to leakage field influence from injection septum, doing envelope matching considering dilution of beam profile in Main Ring are reported in this paper. The 'Without bump' scheme was got on June 15th 2008, while 'With bump' scheme on February 15th 2009. Beam orbit betatron oscillation to the MR close orbit which cause by injection error is less than 1 mm both in horizontal and vertical direction. Meanwhile, Beam Optics matching for 3 GeV beam from 350BT to MR has been well done too, which is also very important. * T. Koseki, Challenges and Solutions for J-PARC Commissioning and Early Operation, in these proceedings |
||
THPEB016 | Beam Fast Extraction Tuning of the J-PARC Main Ring | 3918 |
|
||
The beam commissioning of J-PARC/MR has been started from May 2008 and is in progress*. One key purpose of MR commissioning is the 30 GeV beam fast extraction to Neutrino beam line, which reflect the overall commissioning result. In the MR, the third straight section is assigned for the fast extraction. 5 kickers and 8 septa were installed there, which can give beam a bipolar kick to inside or outside of MR. Inside kick means beam to Neutrino Oscillation Experiment, while outside kick means beam dumped to abort line. However before commissioning, the measured magnetic field distribution of each septa shows non-linear profile along the horizontal direction. In order to find the influence, a simulation with these measured field has been performed. Depends on this study and some OPI (Operation Interface) made by code SAD for orbit modification online, fast extraction of 30 GeV beam to Neutrino line has been achieved on April 23rd 2009. Beam orbit have been tuned to less than 0.5 mm and 0.1 mrad in both horizontal and vertical at the beginning of Neutrino line, which is also the end of MR fast extraction. And so far, 100 kW continual operation to neutrino line have been achieved, too. * T. Koseki, "Challenges and Solutions for J-PARC Commissioning and Early Operation", in these proceedings |
||
TUPD009 | Study of the Beam Dynamics for the 'Fast Extraction' Operating Scenario of the J-PARC Main Ring | 1937 |
|
||
During the early J-PARC Main Ring commissioning and the machine operation with the moderate beam power the 'fast extraction' bare working point has been chosen to provide the machine operation in the safe regime. We discuss main experimental results obtained so far and compare with the results of the computational model of the machine, including the first experimental approach to minimize the effect of the 'sum' linear coupling resonance. The strategy to increase the beam power without changing the operational working point is presented by keeping the moderate space-charge detuning. The advantage of the second harmonic MR RF cavity, including the estimation of the beam losses during the injection and acceleration processes, is discussed. |
||
THPE068 | Effects of the Field Leakage of the Slow Extraction Septum Magnets of the J-PARC Main Ring | 4674 |
|
||
During the early J-PARC Main Ring commissioning the emittance growth at the injection energy, caused by the field leakage of the slow extraction septums, has been observed. By using the measured field data in the J-PARC Main Ring computational model we perform the analysis of the resonance excitation for the 'bare' working points around the 3rd order horizontal resonance, used for the slow extraction of the accelerated beam. The space charge effects of the low energy beam with the moderate beam power are taken into this analysis. Some possible ways to reduce the transverse emittance dilution and the particle losses during the machine operation for the 'hadron' experiments are discussed. |