Paper | Title | Page |
---|---|---|
MOPEA060 | Reconstructions of the Control System for the Charge Exchange System at the 3GeV RCS in J-PARC | 214 |
|
||
The charge exchange device for 3GeV RCS in J-PARC, which require that a broken foil is exchanged for a new foil by remote control and automatically in vacuum. The control system's important task will be to control under the unified management of the vacuum system and foil driving system and to support EPICS. This device consists of the vacuum system using PLC (Programmable Logic Controller) and the foil driving system using MCU (Multi Control Unit). A workstation (WS) was required, and we developed control system which control under the unified management of 2 different type of system. The uniform management control system became complex system. In fact, therefore control system was unfinished system, it did not protect trouble such as the vacuum gate valve closed while transfer rod insert in the ring. Each algorithm of PLC, MCU and WS was reviewed, and the control system that was able to do the unified management was restructured. Each algorithm of PLC, MCU and WS was debugged so that this control system is made remote control using EPICS. We introduce the reconstruction of the control system for the charge exchange system at the RCS in J-PARC. |
||
MOPEC069 | Status and Progress of the J-PARC 3-GeV RCS | 627 |
|
||
The J-PARC 3-GeV rapid cycling synchrotron (RCS) has been operated for the neutron and MLF users program from December 23rd, 2008. The RCS operations not only in support of the MLF but also were providing beam to support commissioning of the MR. In parallel we are challenging to realize higher beam power operations with better stability. Before scheduled maintenance last summer beam power was limited by the front end of about 20 kW, after that maintenance the RCS has been operated the beam power of more than 100 kW for MLF users. After beam deliver operation to the MR and MLF, while the priority has been given to their beam tuning, the RCS also continues further beam studies toward higher beam intensity. On December 7th, 2009, the RCS achieved the beam power of more than 300kW to the neutron production target with 25Hz. This presentation will concentrate itself on the outcome of the J-PARC RCS commissioning program, including the discussion on the issues of the high-power operation. |
||
WEPD085 | Design of the Pulse Bending Magnet for Switching the Painting Area Between the MLF and MR in J-Parc 3-Gev Rcs | 3293 |
|
||
At the J-PARC 3-GeV injection, the injection painting area is designed to be different for supplying the MLF (Material Life Science Facility) and MR (50GeV Main Ring) beams. Along with the injection system in the ring, pulsed switching magnets which are installed in the injection beam-line should also have a function to control the beam orbit at 25Hz. The deflection angle ranges from 3 to 38 mrad to meet the user operation as well as the beam physics run. |
||
THPEB019 | First Step Analysis of Hybrid Type Boron-doped Carbon Stripper Foils For RCS of J-PARC | 3924 |
|
||
J-PARC requires thick carbon stripper foils to strip electrons from the H- beam supplied by the linac before injection into the Rapid Cycling Synchrotron (RCS). Foil thickness is about 200 μg/cm2 corresponding to conversion efficiency of 99.7% from the primary H- beams of 181MeV energy to H+. For this purpose, we have successfully developed hybrid type thick boron-doped carbon (HBC) stripper foils, which showed a drastic improvement not only with respect to the lifetime, but also with respect to thickness reduction and shrinkage at high temperature during long beam irradiation. We started to study carbon stripper foils microscopically why carbon foils have considerable endurance for the beam impact by boron-doped. At first, we made a comparison between nominal carbon and HBC by the electric microscope and ion-induced analysis. In this paper, we will introduce some results for characteristics of HBC foils. |
||
THPEB020 | Beam Study Results with HBC Stripping Foils at the 3-GeV RCS in J-PARC | 3927 |
|
||
The hybrid type thick boron-doped carbon (HBC) stripping foils are installed and used for the beam injection at the 3GeV RCS (Rapid Cycling Synchrotron) in J-PARC (Japan Proton Accelerator Research Complex). The HBC foils are developed by Sugai group in KEK, which improved the lifetime drastically. Up to now, the performance deterioration of the stripping foils can not be seen after the long beam irradiation for the 120kW user operation and 300kW high power beam demonstration at the RCS. In order to examine the characteristic of the HBC foils, various beam studies were carried out. The beam-irradiated spot at the foil was measured by scanning the foil setting position, the charge exchange efficiency was evaluated with various thickness foils, and the effect of the SiC fibers supporting the foil mounting was checked with different mounting foils. Beam study results obtained with using the HBC foils will be presented. In addition, the trends of outgas from the stripping foils and the deformations of the foils during the beam irradiation will be reported. |
||
THPEB021 | Improvements of the Charge Exchange System at the 3GeV RCS in J-PARC | 3930 |
|
||
At the 3GeV RCS (Rapid Cycling Synchrotron) in J-PARC (Japan Proton Accelerator Research Complex), the scheme of H- charge exchange injection using stripping foils is adopted. The charge exchange system is composed of three stripping foil devices. The first stripping foil device, which converts the H- beam from the 181MeV LINAC into the H+ beam, can replace the broken foil with new one in vacuum remotely and automatically. In September 2007, mechanical trouble with the first stripping foil device had occurred just before the RCS beam commissioning was started. The magnetic coupling of the transfer rod had been decoupled and the transfer rod had been broken which was caught in the vacuum gate valve. We studied the trouble cause, re-examined the structural design and the selection for the material, and then verified the specification from endurance tests with sample pieces. Then the improved device was installed in the ring in September 2008. In this presentation, we report the mechanical trouble and that countermeasure, including the improvements of the charge exchange system. |