Khodzhibagiyan, H.G.

Paper Title Page
MOPEB040 Superconducting Magnets for the NICA Facility at JINR: Status of the Design and Construction Plans 361
 
  • A.D. Kovalenko, N.N. Agapov, V.D. Kekelidze, H.G. Khodzhibagiyan, I.N. Meshkov, V.A. Mikhaylov, V.A. Petrov, A.N. Sissakian, A. Sorin, G.V. Trubnikov
    JINR, Dubna, Moscow Region
 
 

NICA (Nuclotron-based Ion Collider fAcility) is the new accelerator complex currently under construction at JINR. The facility is aimed to provide collider experiments with heavy ions up to uranium (gold at the beginning stage) with a centre of mass energy up to 11 GeV/u and an average luminosity up to 1027 cm-2 s-1. The collisions of polarized deuterons and protons are foreseen also. The accelerator complex includes two injector linacs, a superconducting booster synchrotron, a 6 GeV/u superconducting synchrotron (existing Nuclotron) and a collider consisting of two storage rings. Different modifications of superferric magnets based on a hollow composite NbTi cable operating at 4.5 K is proposed to be used for the NICA booster and collider rings. The twin-aperture collider dipole consists of two vertically assembled cold masses placed inside a common thermal shield and a common cryostat. The dipole good field aperture is fixed to 60 mm. The 2 T option, which design is very similar to the Nuclotron's one, was fixed as basis for the collider of 350 m long. R&D work on a curved 4 T Cosine(θ)-dipoles based on a hollow Nuclotron-type cable is proposed to be continued.

 
MOPD007 Design of the Nuclotron Booster in the NICA Project 681
 
  • A.O. Sidorin, N.N. Agapov, A.V. Eliseev, V. Karpinsky, H.G. Khodzhibagiyan, A.D. Kovalenko, G.L. Kuznetsov, I.N. Meshkov, V.A. Mikhaylov, V. Monchinsky, A.V. Smirnov, G.V. Trubnikov, B. Vasilishin
    JINR, Dubna, Moscow Region
  • A.V. Butenko
    JINR/LHE, Moscow
 
 

The main goal of the Nuclotron booster construction are following: accumulation up to 4·10+9 Au32+ ions; acceleration of the ions up to energy of 600 MeV/u that is sufficient for stripping of the ions to the bare nucleus state; simplification of the requirements to the vacuum conditions in the Nuclotron; forming of the required beam emittance at the energy of 100 MeV/u with electron cooling system. The features of this booster, the requirement to the main synchrotron systems and their parameters are presented.

 
MOPD008 Status of the Nuclotron. 'Nuclotron-M' project 684
 
  • A.O. Sidorin, N.N. Agapov, V. Batin, A.V. Butenko, D.E. Donets, A.V. Eliseev, A. Govorov, V. Karpinsky, V.D. Kekelidze, H.G. Khodzhibagiyan, A. Kirichenko, O.S. Kozlov, I.N. Meshkov, V.A. Mikhaylov, V. Monchinsky, S. Romanov, V. Shevtsov, A.N. Sissakian, I. Slepnev, V. Slepnev, G.V. Trubnikov, B. Vasilishin, V. Volkov
    JINR, Dubna, Moscow Region
  • V. Alexandrov
    BINP SB RAS, Protvino, Moscow Region
  • O.I. Brovko, A.D. Kovalenko
    JINR/LHE, Moscow
 
 

The 'Nuclotron-M' project started in 2007 is considered as the key point of the first stage of the NICA/MPD project. General goal of the 'Nuclotron-M' project is to prepare all the systems of the Nuclotron for its long and reliable operation as a part of the NICA collider injection chain. Additionally the project realization will increase the Nuclotron ability for realization of its current experimental program. Results of the last runs of the Nuclotron operation are presented.